ML12248A047: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 40: Line 40:


_________________________              G SUNSI REVIEW COMPLETE OFFICE              RII:RDP        RII:DRP SIGNATURE          TXL /RA/        FJE /RA/
_________________________              G SUNSI REVIEW COMPLETE OFFICE              RII:RDP        RII:DRP SIGNATURE          TXL /RA/        FJE /RA/
NAME                TLighty        FEhrhardt DATE                  08/24/2012      08/28/2012 E-MAIL COPY?          YES        NO  YES        NO YES      NO  YES      NO  YES      NO  YES      NO  YES  NO
NAME                TLighty        FEhrhardt DATE                  08/24/2012      08/28/2012 E-MAIL COPY?          YES        NO  YES        NO YES      NO  YES      NO  YES      NO  YES      NO  YES  NO T. Lynch                                3 cc w/encl:                                Mark Williams C. Russ Dedrickson                        Commissioner Fleet Support Supervisor                  Georgia Department of Natural Resources Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution B. D. McKinney, Jr.
 
T. Lynch                                3 cc w/encl:                                Mark Williams C. Russ Dedrickson                        Commissioner Fleet Support Supervisor                  Georgia Department of Natural Resources Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution B. D. McKinney, Jr.
Cheryl A. Gayheart                        Regulatory Response Manager Plant Manager                              Southern Nuclear Operating Company, Inc.
Cheryl A. Gayheart                        Regulatory Response Manager Plant Manager                              Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant            Electronic Mail Distribution Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant            Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Latest revision as of 13:24, 6 February 2020

Mid Cycle Assessment Letter Farley 2012
ML12248A047
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 09/04/2012
From: Croteau R
Division Reactor Projects II
To: Lynch T
Southern Nuclear Operating Co
References
IR-12-006
Download: ML12248A047 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 4, 2012 Mr. Tom A. Lynch Site Vice President - Farley Southern Nuclear Operating Company, Inc.

7388 North State Highway 95 Columbia, AL 36319

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - JOSEPH M.

FARLEY NUCLEAR PLANT (NRC INSPECTION REPORT 05000348, 364/2012006)

Dear Mr. Lynch:

On August 14, 2012, the NRC completed its performance review of Joseph M. Farley Nuclear Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011, through June 30, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at Farley Unit 1 and Unit 2 during the most recent quarter was within the Regulatory Response Column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because of one or more greater-than-green Security Cornerstone inputs as described in inspection report 0500348, 364/2011202 sent on January 10, 2012. As described in our letter to you dated July 30, 2012, this change in the Action Matrix from the end-of-cycle assessment is due to the integration of the security cornerstone into the ROP performance assessment program governed by IMC 0305, Operating Reactor Assessment Program.

On May 21, 2012, your staff notified the NRC of your readiness for it to conduct a supplemental inspection to review the actions taken to address performance issues. NRC inspectors completed this supplemental inspection in August 2012 and you will be notified of the results of this inspection via separate correspondence.

The enclosed inspection plan lists the inspections scheduled through December 2013. Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, consistent with the Agencys actions related to Fukushima, the NRC will perform TI-187, Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns and TI-188 Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns. The NRC also plans to conduct Initial Operator License Examinations, and TI-182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

T. Lynch 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Frank Ehrhardt at (404) 997-4611 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Richard Croteau, Director Division of Reactor Projects Docket No.: 50-348, 50-364 License No.: NPF-2, NPF-8

Enclosure:

Farley Inspection/Activity Plan (09/01/2012 - 12/31/2013) cc w/encl: (See page 3)

_________________________ G SUNSI REVIEW COMPLETE OFFICE RII:RDP RII:DRP SIGNATURE TXL /RA/ FJE /RA/

NAME TLighty FEhrhardt DATE 08/24/2012 08/28/2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO T. Lynch 3 cc w/encl: Mark Williams C. Russ Dedrickson Commissioner Fleet Support Supervisor Georgia Department of Natural Resources Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution B. D. McKinney, Jr.

Cheryl A. Gayheart Regulatory Response Manager Plant Manager Southern Nuclear Operating Company, Inc.

Joseph M. Farley Nuclear Plant Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution D. W. Daughhetee Licensing Engineer S. Kuczynski Southern Nuclear Operating Company, Inc.

Chairman, President and CEO Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution T. D. Honeycutt Regulatory Response Supervisor Leigh Perry Southern Nuclear Operating Company, Inc.

SVP & General Counsel-Ops & SNC Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution L. Mike Stinson Vice President D. G. Bost Fleet Operations Support Chief Nuclear Officer Southern Nuclear Operating Company, Inc.

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution Electronic Mail Distribution N. J. Stringfellow Dennis R. Madison Licensing Manager Vice President Southern Nuclear Operating Company, Inc.

Edwin I. Hatch Nuclear Plant Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution L. P. Hill Licensing Supervisor Paula Marino Southern Nuclear Operating Company, Inc.

Vice President Electronic Mail Distribution Engineering Southern Nuclear Operating Company, Inc. L. L. Crumpton Electronic Mail Distribution Administrative Assistant, Sr.

Southern Nuclear Operating Company, Inc.

T. E. Tynan Electronic Mail Distribution Site Vice President Vogtle Electric Generating Plant William D. Oldfield Southern Nuclear Operating Company, Inc. Principal Licensing Engineer Electronic Mail Distribution Joseph M. Farley Nuclear Plant Electronic Mail Distribution M. J. Ajluni Nuclear Licensing Director (cc w/encl continued next page)

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution

T. Lynch 4 (cc w/encl continued) Chuck Mueller Manager Todd L. Youngblood Policy and Radiation Program Vice President Georgia Department of Natural Resources Fleet Oversight Electronic Mail Distribution Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution John G. Horn Site Support Manager Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Mark Culver Chairman Houston County Commission P. O. Box 6406 Dothan, AL 36302 James L. McNees, CHP Director Office of Radiation Control Alabama Dept. of Public Health P. O. Box 303017 Montgomery, AL 36130-3017 Donald E. Williamson State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 30317 Montgomery, AL 36130-3017

T. Lynch 5 Letter to Tom A. Lynch from Frank Ehrhardt dated September 4, 2012.

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - JOSEPH M.

FARLEY NUCLEAR PLANT (NRC INSPECTION REPORT 05000348, 364/2012006)

Distribution w/encl:

C. Evans, RII L. Douglas, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMFarley Resource ROP Assessment Institute of Nuclear Power Operations (INPO)

Page 1 of 1 Farley 09/04/2012 08:17:35 Inspection / Activity Plan Report 22 09/01/2012 - 12/31/2013 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site PSB1-RP - RP PUBLIC RAD SAFETY BASELINE 3 1, 2 01/14/2013 01/18/2013 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 01/14/2013 01/18/2013 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 01/14/2013 01/18/2013 IP 71151 Performance Indicator Verification MODS - PERM MODS 50.59 INSPECTION 6 1, 2 02/25/2013 03/01/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 1, 2 03/11/2013 03/15/2013 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications EP - EP PROGRAM INSPECTION 1 1, 2 03/18/2013 03/22/2013 IP 7111402 Alert and Notification System Testing 1, 2 03/18/2013 03/22/2013 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 03/18/2013 03/22/2013 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 03/18/2013 03/22/2013 IP 71151 Performance Indicator Verification PSB1-RP - RAD HAZARDS ANALYSIS AND TRANSPORTATION 2 1, 2 04/15/2013 04/19/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 04/15/2013 04/19/2013 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2 04/15/2013 04/19/2013 IP 71151 Performance Indicator Verification ISI - UNIT 2 INSERVICE INSPECTION 1 2 04/22/2013 04/26/2013 IP 7111108P Inservice Inspection Activities - PWR OL EXAM - INITIAL EXAM PREP 3 1 05/27/2013 05/31/2013 V23407 FARLEY/JUNE 2013 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 1 3 1 06/17/2013 06/21/2013 V23407 FARLEY/JUNE 2013 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL EXAM - WEEK 2 3 1 06/24/2013 06/28/2013 V23407 FARLEY/JUNE 2013 INITIAL EXAM AT POWER FACILITIES ISI - UNIT 1 INSERVICE INSPECTION 1 1 10/07/2013 10/11/2013 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 1 SG INSERVICE INSPECTION 1 1 10/14/2013 10/18/2013 IP 7111108P Inservice Inspection Activities - PWR PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 5 1, 2 11/04/2013 11/09/2013 IP 71152B Problem Identification and Resolution 1, 2 11/18/2013 11/22/2013 IP 71152B Problem Identification and Resolution Comments:

This report does not include INPO and OUTAGE activities. Enclosure This report shows only on-site and announced inspection procedures.