IR 05000400/2009301: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 May 1, 2009
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION


Mr. Christopher Vice President Carolina Power & Light Company Shearon Harris Nuclear Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 SUBJECT: SHEARON HARRIS NUCLEAR POWER PLANT - NRC OPERATOR LICENSE EXAMINATION REPORT 05000400/2009301
==REGION II==
May 1, 2009
 
==SUBJECT:==
SHEARON HARRIS NUCLEAR POWER PLANT - NRC OPERATOR LICENSE EXAMINATION REPORT 05000400/2009301


==Dear Mr. Burton:==
==Dear Mr. Burton:==
Line 27: Line 31:
Seven Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. One RO applicant failed the written examination. There were four post-administration comments concerning the operating and written examinations. These comments, and the NRC resolution of these comments, are summarized in Enclosure 2. A Simulator Fidelity Report is included in this report as Enclosure 3.
Seven Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. One RO applicant failed the written examination. There were four post-administration comments concerning the operating and written examinations. These comments, and the NRC resolution of these comments, are summarized in Enclosure 2. A Simulator Fidelity Report is included in this report as Enclosure 3.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room).
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room).


CP&L 2 If you have any questions concerning this letter, please contact me at (404) 562-4550.
CP&L   2 If you have any questions concerning this letter, please contact me at (404) 562-4550.


Sincerely,
Sincerely,
/RA/
/RA/
Malcolm Widmann, Chief Operations Branch Division of Reactor Safety  
Malcolm Widmann, Chief Operations Branch Division of Reactor Safety Docket No: 50-400 License No. NPF-63
 
Docket No: 50-400 License No. NPF-63  


===Enclosures:===
===Enclosures:===
1. Report Details 2. Facility Comments and NRC Resolution 3. Simulator Fidelity Report  
1. Report Details 2. Facility Comments and NRC Resolution 3. Simulator Fidelity Report (
 
(


REGION II==
REGION II==
Docket No.: 05000400 License No.: NPF-63 Report No.: 05000400/2009301 Licensee: Carolina Power & Light Company (CP&L)
Facility: Shearon Harris Nuclear Power Plant Location: 5413 Shearon Harris Road New Hill, NC 27562 Dates: Operating Test - March 9-18, 2009 Written Examination - March 20, 2009 Examiners: F. Ehrhardt, Chief Examiner, Sr. Operations Engineer R. Monk, Senior Resident Inspector (Examiner Certified)
M. Riches, Operations Engineer Approved by: M. Widmann, Chief Operations Branch Division of Reactor Safety Enclosure 1


Docket No.: 05000400 License No.: NPF-63
=SUMMARY OF FINDINGS=
ER 05000400/2009301; March 9-18, 2009 & March 20; Shearon Harris Nuclear Power Plant;


Report No.: 05000400/2009301
Operator License Examinations.


Licensee: Carolina Power & Light Company (CP&L)
Nuclear Regulatory Commission (NRC) examiners conducted an initial examination in accordance with the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." This examination implemented the operator licensing requirements identified in 10 CFR §55.41, §55.43, and §55.45, as applicable.
Facility: Shearon Harris Nuclear Power Plant


Location: 5413 Shearon Harris Road New Hill, NC 27562 Dates: Operating Test - March 9-18, 2009 Written Examination - March 20, 2009
The NRC developed the written examination outline. Members of the Shearon Harris Nuclear Power Plant staff developed both the operating tests and the written examination.


Examiners: F. Ehrhardt, Chief Examiner, Sr. Operations Engineer R. Monk, Senior Resident Inspector (Examiner Certified)
The NRC administered the operating tests during the period March 9-13 and March 17-18, 2009. Members of the Shearon Harris Nuclear Power Plant training staff administered the written examination on March 20, 2009. Seven Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants passed both the operating test and written examination.
M. Riches, Operations Engineer Approved by: M. Widmann, Chief Operations Branch Division of Reactor Safety Enclosure 1


=SUMMARY OF FINDINGS=
One Reactor Operator failed the written examination. Eight applicants were issued licenses commensurate with the level of examination administered. One SRO applicant and one RO applicant were issued letters stating that they passed both the written and operating examinations and that their licenses will be issued pending receipt of additional information.
ER 05000400/2009301; March 9-18, 2009 & March 20; Shearon Harris Nuclear Power Plant; Operator License Examinations.
 
Nuclear Regulatory Commission (NRC) examiners conducted an initial examination in accordance with the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors."  This examination implemented the operator licensing requirements identified in 10 CFR §55.41, §55.43, and §55.45, as applicable.
 
The NRC developed the written examination outline. Members of the Shearon Harris Nuclear Power Plant staff developed both the operating tests and the written examination.
 
The NRC administered the operating tests during the period March 9-13 and March 17-18, 2009. Members of the Shearon Harris Nuclear Power Plant training staff administered the written examination on March 20, 2009. Seven Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. One Reactor Operator failed the written examination. Eight applicants were issued licenses commensurate with the level of examination administered. One SRO applicant and one RO applicant were issued letters stating that they passed both the written and operating examinations and that their licenses will be issued pending receipt of additional information.


There were four post-examination comments.
There were four post-examination comments.


No findings of significance were identified.
No findings of significance were identified.
1


=REPORT DETAILS=
=REPORT DETAILS=
Line 78: Line 71:


====a. Inspection Scope====
====a. Inspection Scope====
The NRC developed the written examination outline. Members of the Shearon Harris Nuclear Power Plant staff developed both the operating tests and the written examination. All examination material was developed in accordance with the guidelines contained in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRC examination team reviewed the proposed examination. Examination changes agreed upon between the NRC and the licensee were made per NUREG-1021 and incorporated into the final version of the examination materials.
The NRC developed the written examination outline. Members of the Shearon Harris Nuclear Power Plant staff developed both the operating tests and the written examination. All examination material was developed in accordance with the guidelines contained in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRC examination team reviewed the proposed examination. Examination changes agreed upon between the NRC and the licensee were made per NUREG-1021 and incorporated into the final version of the examination materials.


The NRC reviewed the licensee's examination security measures while preparing and administering the examinations in order to ensure compliance with 10 CFR §55.49, "Integrity of examinations and tests."
The NRC reviewed the licensees examination security measures while preparing and administering the examinations in order to ensure compliance with 10 CFR §55.49, Integrity of examinations and tests.


The NRC examiners evaluated eight Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants using the guidelines contained in NUREG-1021. The examiners administered the operating tests during the period March 9-13 and March 17-18. Members of the Shearon Harris Nuclear Power Plant training staff administered the written examination on March 20, 2009. Evaluations of applicants and reviews of associated documentation were performed to determine if the applicants, who applied for licenses to operate the Shearon Harris Nuclear Power Plant, met the requirements specified in 10 CFR Part 55, "Operators' Licenses."
The NRC examiners evaluated eight Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants using the guidelines contained in NUREG-1021. The examiners administered the operating tests during the period March 9-13 and March 17-18. Members of the Shearon Harris Nuclear Power Plant training staff administered the written examination on March 20, 2009. Evaluations of applicants and reviews of associated documentation were performed to determine if the applicants, who applied for licenses to operate the Shearon Harris Nuclear Power Plant, met the requirements specified in 10 CFR Part 55, Operators Licenses.


====b. Findings====
====b. Findings====
No findings of significance were identified. The NRC determined, using NUREG-1021 that the licensee's operating test and written examination submittals were both within the range of acceptability expected for a proposed examination.
No findings of significance were identified. The NRC determined, using NUREG-1021 that the licensees operating test and written examination submittals were both within the range of acceptability expected for a proposed examination.


Seven Senior Reactor Operator (SRO) applicants and three Reactor Operator (RO)applicants passed both the written and operating examinations. One RO applicant failed the written examination. Issuance of two licenses, one for an RO applicant and one for an SRO applicant, have been delayed pending receipt of additional information. Details concerning the need for additional information have been sent to the individual applicants and the facility licensee.
Seven Senior Reactor Operator (SRO) applicants and three Reactor Operator (RO)applicants passed both the written and operating examinations. One RO applicant failed the written examination. Issuance of two licenses, one for an RO applicant and one for an SRO applicant, have been delayed pending receipt of additional information. Details concerning the need for additional information have been sent to the individual applicants and the facility licensee.
Line 91: Line 84:
Copies of all individual examination reports were sent to the facility Training Manager for evaluation of weaknesses and determination of appropriate remedial training.
Copies of all individual examination reports were sent to the facility Training Manager for evaluation of weaknesses and determination of appropriate remedial training.


The licensee submitted two post-examination comments concerning the operating test and two comments concerning the written examination. A copy of the final written examination and answer key, with all changes incorporated, and the licensee's post-examination comments may be accessed in the ADAMS system (ADAMS Accession Number(s) ML091170441, ML091170423, and ML091170432).
The licensee submitted two post-examination comments concerning the operating test and two comments concerning the written examination. A copy of the final written examination and answer key, with all changes incorporated, and the licensees post-examination comments may be accessed in the ADAMS system (ADAMS Accession Number(s) ML091170441, ML091170423, and ML091170432).


{{a|4OA6}}
{{a|4OA6}}
Line 100: Line 93:
On March 18, 2009 the NRC examination team discussed generic issues associated with the operating test with Mr. Chris Burton, Shearon Harris Vice President, and members of the Shearon Harris Nuclear Power Plant staff. The examiners asked the licensee if any of the examination material was proprietary. No proprietary information was identified.
On March 18, 2009 the NRC examination team discussed generic issues associated with the operating test with Mr. Chris Burton, Shearon Harris Vice President, and members of the Shearon Harris Nuclear Power Plant staff. The examiners asked the licensee if any of the examination material was proprietary. No proprietary information was identified.


KEY POINTS OF CONTACT Licensee personnel
KEY POINTS OF CONTACT Licensee personnel C. Burton, Vice President Harris Plant K. Henderson, General Manager Harris Plant W. Gurganious, Director - Fleet Nuclear Training G. Kilpatrick, Manager - Training T. Toler, Superintendent - Operations Training K. Bailey, Supervisor - Operations Continuing Training A. Lucky, Senior Nuclear Operations Training Instructor T. Craig, Senior Operations Instructor R. Bright, Simulator Support W. Saunders, Manager - Operations W. Gunter, Manager - Shift Operations M. Weber, Superintendent - Operations Support M. Christopherson, Control Room Supervisor M. Fulks, Senior Reactor Operator D. Cortlett, Supervisor - Licensing/Regulatory Programs M. Wallace, Senior Specialist - Licensing NRC personnel J. Austin, Senior Resident Inspector
 
C. Burton, Vice President Harris Plant K. Henderson, General Manager Harris Plant W. Gurganious, Director - Fleet Nuclear Training G. Kilpatrick, Manager - Training T. Toler, Superintendent - Operations Training K. Bailey, Supervisor - Operations Continuing Training A. Lucky, Senior Nuclear Operations Training Instructor T. Craig, Senior Operations Instructor R. Bright, Simulator Support W. Saunders, Manager - Operations W. Gunter, Manager - Shift Operations M. Weber, Superintendent - Operations Support M. Christopherson, Control Room Supervisor M. Fulks, Senior Reactor Operator D. Cortlett, Supervisor - Licensing/Regulatory Programs M. Wallace, Senior Specialist - Licensing NRC personnel J. Austin, Senior Resident Inspector  


=FACILITY POST-EXAMINATION COMMENTS AND NRC RESOLUTIONS=
=FACILITY POST-EXAMINATION COMMENTS AND NRC RESOLUTIONS=


A complete text of the licensee's post-examination comments can be found in ADAMS under Accession Number ML091170441.
A complete text of the licensees post-examination comments can be found in ADAMS under
Item Administrative Topic "a." - Determine Rod Misalignment Using Thermocouples (RO A1-1 and SRO A1-1)
Accession Number ML091170441.
Comment The licensee recommended that a corrected copy of the JPM guide be used when grading the applicants' performance.
Item
The corrected copy supplied by the licensee modified the task standards for performance step 5  
Administrative Topic a. - Determine Rod Misalignment Using Thermocouples (RO A1-1 and
(a critical step in RO A1-1 and SRO A1-1) and performance step 6 (a critical step in SRO A1-1) to be correct with respect to the thermocouple data that was provided to the applicants as part of the initiating cue during administration of the JPM.
SRO A1-1)
Comment
The licensee recommended that a corrected copy of the JPM guide be used when grading the
applicants performance.
The corrected copy supplied by the licensee modified the task standards for performance step 5
(a critical step in RO A1-1 and SRO A1-1) and performance step 6 (a critical step in SRO A1-1)
to be correct with respect to the thermocouple data that was provided to the applicants as part
of the initiating cue during administration of the JPM.
NRC Resolution
NRC Resolution
The licensee's recommendation was accepted.
The licensees recommendation was accepted.
The task standards for performance steps 5 and 6 in the "as administered" JPMs are not correct for the thermocouple data provided to applicants. The task standards contained in the corrected
The task standards for performance steps 5 and 6 in the as administered JPMs are not correct
copy of the JPM guide provided by the licensee are correct with respect to thermocouple data provided to the applicants.
for the thermocouple data provided to applicants. The task standards contained in the corrected
Item Administrative Topic "b." - Perform a Manual Shutdown Margin Calculation (RO A1-2)
copy of the JPM guide provided by the licensee are correct with respect to thermocouple data
provided to the applicants.
Item
Administrative Topic b. - Perform a Manual Shutdown Margin Calculation (RO A1-2)
Comment
Comment
The licensee recommended that a corrected copy of the JPM guide be used when grading the applicants' performance.
The licensee recommended that a corrected copy of the JPM guide be used when grading the
The task standards associated with performance steps within the JPM guide were written for use of OST-1036, Shutdown Margin Calculation Modes 1-5 (Cycle 15). During administration of this JPM, all applicants were provided with OST-1036, Shutdown Margin Calculation Modes 1-5 (Cycle 13). The corrected copy of the exam guide modifies all task standards to be correct assuming use of OST-1036, Shutdown Margin Calculation Modes 1-5 (Cycle 13).
applicants performance.
The task standards associated with performance steps within the JPM guide were written for
use of OST-1036, Shutdown Margin Calculation Modes 1-5 (Cycle 15). During administration
of this JPM, all applicants were provided with OST-1036, Shutdown Margin Calculation Modes
1-5 (Cycle 13). The corrected copy of the exam guide modifies all task standards to be correct
assuming use of OST-1036, Shutdown Margin Calculation Modes 1-5 (Cycle 13).
NRC Resolution
NRC Resolution
The licensees recommendation was accepted.


The licensee's recommendation was accepted.
The task standards for the performance steps within the as administered JPM are not correct
Enclosure 2
for the reference material (Cycle 15) supplied to the applicants. The task standards contained
The task standards for the performance steps within the "as administered" JPM are not correct for the reference material (Cycle 15) supplied to the applicants. The task standards contained in the corrected copy of the JPM guide provided by the licensee are correct with respect to the reference material used by all applicants (Cycle 13).
in the corrected copy of the JPM guide provided by the licensee are correct with respect to the
Item SRO Question 83, K/A 061AG2.4.41
reference material used by all applicants (Cycle 13).
Comment The licensee recommends that choices 'C' and 'D' both be accepted as correct answers.
Item
Insufficient information is provided in the stem to differentiate whether or not a pathway for fission products to escape containment exists. For the containment radiation levels given in the question a Containment Ventilation Isolation Signal would have occurred. With no indication of equipment or component malfunctions related to the Containment Ventilation Isolation provided
SRO Question 83, K/A 061AG2.4.41
in the stem, a pathway would not exist for fission products to escape containment (containment would be intact). However, the stem also states that Plant Vent Stack #1 WRGM Effluent radiation levels are rising, indicating that a pathway exists for fission products to escape to the environment via containment and the plant vent stack (containment breached). Additionally, only one (Charging Pump 1B Room Area Radiation Monitor) of seven Fuel Breach Area
Comment
Radiation Monitors was listed in the stem as alarming, vice multiple monitors that would be expected to be in alarm for a fuel breach, indicating that a leak existed in the associated charging pump room (containment breached).
The licensee recommends that choices C and D both be accepted as correct answers.
Insufficient information is provided in the stem to differentiate whether or not a pathway for
fission products to escape containment exists. For the containment radiation levels given in the
question a Containment Ventilation Isolation Signal would have occurred. With no indication of
equipment or component malfunctions related to the Containment Ventilation Isolation provided
in the stem, a pathway would not exist for fission products to escape containment (containment
would be intact). However, the stem also states that Plant Vent Stack #1 WRGM Effluent
radiation levels are rising, indicating that a pathway exists for fission products to escape to the
environment via containment and the plant vent stack (containment breached). Additionally,
only one (Charging Pump 1B Room Area Radiation Monitor) of seven Fuel Breach Area
Radiation Monitors was listed in the stem as alarming, vice multiple monitors that would be
expected to be in alarm for a fuel breach, indicating that a leak existed in the associated
charging pump room (containment breached).
NRC Resolution
NRC Resolution
The licensee's recommendation was accepted. The stem did not provide all necessary information to unambiguously distinguish between choices 'C' and 'D.' In order to answer the question based on the information provided in the stem, an applicant must either: 1. Assume that Containment Ventilation Isolation operated correctly (containment intact) and ignore contradictory rising Plant Vent Stack #1 WRGM Effluent and Charging Pump 1B Room Area radiation levels, or 2. Assume that Containment Ventilation Isolation did not operate correctly (no information provided in stem to support the assumption) and consider rising Plant Vent Stack #1 WRGM Effluent and Charging Pump 1B Room Area radiation levels (containment
The licensees recommendation was accepted. The stem did not provide all necessary
information to unambiguously distinguish between choices C and D. In order to answer the
question based on the information provided in the stem, an applicant must either:
1. Assume that Containment Ventilation Isolation operated correctly (containment intact)
and ignore contradictory rising Plant Vent Stack #1 WRGM Effluent and Charging Pump
1B Room Area radiation levels, or
2. Assume that Containment Ventilation Isolation did not operate correctly (no information
provided in stem to support the assumption) and consider rising Plant Vent Stack #1
WRGM Effluent and Charging Pump 1B Room Area radiation levels (containment
breached.)
breached.)
Because answers 'C' and 'D' do not contain conflicting information, both are accepted as correct. Item
Because answers C and D do not contain conflicting information, both are accepted as
correct.
Item
SRO Question 87, K/A 012A2.01
SRO Question 87, K/A 012A2.01
Comment The licensee recommends that the question be deleted from the examination.
Comment
Enclosure 2
The licensee recommends that the question be deleted from the examination.
There is no correct answer listed for the question. With OWP-RP-02 in place for Pressurizer Pressure Channel II (PT-476), channel II OTT bistables are tripped. The actions of Answer D (original correct answer) would allow the plant to remain in a condition contrary to Tech Specs for 7 hours. All other answer choices are still incorrect.
 
There is no correct answer listed for the question. With OWP-RP-02 in place for Pressurizer
Pressure Channel II (PT-476), channel II OTT bistables are tripped. The actions of Answer D
(original correct answer) would allow the plant to remain in a condition contrary to Tech Specs
for 7 hours. All other answer choices are still incorrect.
NRC Resolution
NRC Resolution
The licensee's recommendation was accepted.
The licensees recommendation was accepted.
Initial conditions given in the stem of the question impose contradictory requirements that make all of the possible answer choices incorrect. Therefore the question was deleted from the exam per NUREG 1021 ES-403 d.1.b.
Initial conditions given in the stem of the question impose contradictory requirements that make
all of the possible answer choices incorrect. Therefore the question was deleted from the exam
per NUREG 1021 ES-403 d.1.b.
SIMULATOR FIDELITY REPORT
SIMULATOR FIDELITY REPORT
Facility Licensee: Shearon Harris Nuclear Power Plant
Facility Licensee: Shearon Harris Nuclear Power Plant
Facility Docket No.: 05000400
Facility Docket No.: 05000400
Operating Test Administered: March 9-18, 2009
Operating Test Administered: March 9-18, 2009
This form is to be used only to report observations. These observations do not constitute audit or inspection findings and, without further verification and review in accordance with Inspection
This form is to be used only to report observations. These observations do not constitute audit
Procedure 71111.11 are not indicative of noncompliance with 10 CFR 55.46. No licensee action is required in response to these observations.
or inspection findings and, without further verification and review in accordance with Inspection
Procedure 71111.11 are not indicative of noncompliance with 10 CFR 55.46. No licensee
action is required in response to these observations.
While conducting the simulator portion of the operating test, examiners observed the following:
While conducting the simulator portion of the operating test, examiners observed the following:
Item Description
Item                                                         Description
 
C RCP                       C Reactor Coolant Pump radial bearing and seal water injection
"C" RCP "C" Reactor Coolant Pump radial bearing and seal water injection temperatures did not respond as expected during a simulated #1 seal failure. Malfunction RCS14C was inserted at a value of 35%, resulting in a #1 seal high leak off flow alarm and seal leak off flow indication pegged high (> 10 gpm) as expected. However, radial
temperatures did not respond as expected during a simulated #1
bearing and seal water injection temperatures lowered a few degrees and then remained stable for greater than 15 minutes, which was not expected. Expected response was that radial bearing and seal injection temperatures would rise due to hotter RCS water flowing up through the thermal barrier heat exchanger.
seal failure. Malfunction RCS14C was inserted at a value of 35%,
The licensee generated Simulator Service Request number 09-101 to track this item.
resulting in a #1 seal high leak off flow alarm and seal leak off flow
indication pegged high (> 10 gpm) as expected. However, radial
bearing and seal water injection temperatures lowered a few
degrees and then remained stable for greater than 15 minutes,
which was not expected. Expected response was that radial
bearing and seal injection temperatures would rise due to hotter
RCS water flowing up through the thermal barrier heat exchanger.
The licensee generated Simulator Service Request number 09-
101 to track this item.


ML091210151_ X   SUNSI REVIEW COMPLETE OFFICE RII:DRS RII:DRS RII:DRS RII:DRS   SIGNATURE /RA via email/ /RA/ /RA via email/ /RA/ /   NAME Craig Kontz Mark Riches Frank Erdhardt Malcolm Widmann   DATE 4/30/2009 4/30/2009 4/30/2009 5/     /2009 5/     /2009 5/     /2009 5/     /2009 E-MAIL COPY?     YES NO   YES NO   YES NO   YES NO     YES
ML091210151_                 X SUNSI REVIEW COMPLETE
N YES NO   YES NO
OFFICE             RII:DRS         RII:DRS         RII:DRS         RII:DRS
SIGNATURE         /RA via email/   /RA/             /RA via email/   /RA/           /
NAME               Craig Kontz     Mark Riches     Frank Erdhardt   Malcolm Widmann
DATE                   4/30/2009       4/30/2009       4/30/2009       5/ /2009     5/   /2009   5/ /2009     5/ /2009
E-MAIL COPY?         YES         NO YES         NO YES         NO YES       NO   YES       N YES       NO YES       NO
}}
}}

Latest revision as of 06:30, 14 November 2019

Er 05000400-09-301, on March 9-18, 2009 & March 20, Shearon Harris Nuclear Power Plant, Operator License Examinations
ML091210151
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 05/01/2009
From: Widmann M
NRC/RGN-II/DRS/OLB
To: Burton C
Carolina Power & Light Co
References
ER-09-301
Download: ML091210151 (13)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

May 1, 2009

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - NRC OPERATOR LICENSE EXAMINATION REPORT 05000400/2009301

Dear Mr. Burton:

During the period March 9-13 and March 17-18, 2009, the Nuclear Regulatory Commission (NRC) administered operating tests to employees of your company who had applied for licenses to operate the Shearon Harris Nuclear Power Plant. At the conclusion of the tests, the examiners discussed preliminary findings related to the operating tests with those members of your staff identified in the enclosed report. The written examination was administered by your staff on March 20, 2009.

Seven Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. One RO applicant failed the written examination. There were four post-administration comments concerning the operating and written examinations. These comments, and the NRC resolution of these comments, are summarized in Enclosure 2. A Simulator Fidelity Report is included in this report as Enclosure 3.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm.adams.html (the Public Electronic Reading Room).

CP&L 2 If you have any questions concerning this letter, please contact me at (404) 562-4550.

Sincerely,

/RA/

Malcolm Widmann, Chief Operations Branch Division of Reactor Safety Docket No: 50-400 License No. NPF-63

Enclosures:

1. Report Details 2. Facility Comments and NRC Resolution 3. Simulator Fidelity Report (

REGION II==

Docket No.: 05000400 License No.: NPF-63 Report No.: 05000400/2009301 Licensee: Carolina Power & Light Company (CP&L)

Facility: Shearon Harris Nuclear Power Plant Location: 5413 Shearon Harris Road New Hill, NC 27562 Dates: Operating Test - March 9-18, 2009 Written Examination - March 20, 2009 Examiners: F. Ehrhardt, Chief Examiner, Sr. Operations Engineer R. Monk, Senior Resident Inspector (Examiner Certified)

M. Riches, Operations Engineer Approved by: M. Widmann, Chief Operations Branch Division of Reactor Safety Enclosure 1

SUMMARY OF FINDINGS

ER 05000400/2009301; March 9-18, 2009 & March 20; Shearon Harris Nuclear Power Plant;

Operator License Examinations.

Nuclear Regulatory Commission (NRC) examiners conducted an initial examination in accordance with the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." This examination implemented the operator licensing requirements identified in 10 CFR §55.41, §55.43, and §55.45, as applicable.

The NRC developed the written examination outline. Members of the Shearon Harris Nuclear Power Plant staff developed both the operating tests and the written examination.

The NRC administered the operating tests during the period March 9-13 and March 17-18, 2009. Members of the Shearon Harris Nuclear Power Plant training staff administered the written examination on March 20, 2009. Seven Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants passed both the operating test and written examination.

One Reactor Operator failed the written examination. Eight applicants were issued licenses commensurate with the level of examination administered. One SRO applicant and one RO applicant were issued letters stating that they passed both the written and operating examinations and that their licenses will be issued pending receipt of additional information.

There were four post-examination comments.

No findings of significance were identified.

REPORT DETAILS

OTHER ACTIVITIES

4OA5 Operator Licensing Examinations

a. Inspection Scope

The NRC developed the written examination outline. Members of the Shearon Harris Nuclear Power Plant staff developed both the operating tests and the written examination. All examination material was developed in accordance with the guidelines contained in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRC examination team reviewed the proposed examination. Examination changes agreed upon between the NRC and the licensee were made per NUREG-1021 and incorporated into the final version of the examination materials.

The NRC reviewed the licensees examination security measures while preparing and administering the examinations in order to ensure compliance with 10 CFR §55.49, Integrity of examinations and tests.

The NRC examiners evaluated eight Reactor Operator (RO) and three Senior Reactor Operator (SRO) applicants using the guidelines contained in NUREG-1021. The examiners administered the operating tests during the period March 9-13 and March 17-18. Members of the Shearon Harris Nuclear Power Plant training staff administered the written examination on March 20, 2009. Evaluations of applicants and reviews of associated documentation were performed to determine if the applicants, who applied for licenses to operate the Shearon Harris Nuclear Power Plant, met the requirements specified in 10 CFR Part 55, Operators Licenses.

b. Findings

No findings of significance were identified. The NRC determined, using NUREG-1021 that the licensees operating test and written examination submittals were both within the range of acceptability expected for a proposed examination.

Seven Senior Reactor Operator (SRO) applicants and three Reactor Operator (RO)applicants passed both the written and operating examinations. One RO applicant failed the written examination. Issuance of two licenses, one for an RO applicant and one for an SRO applicant, have been delayed pending receipt of additional information. Details concerning the need for additional information have been sent to the individual applicants and the facility licensee.

Copies of all individual examination reports were sent to the facility Training Manager for evaluation of weaknesses and determination of appropriate remedial training.

The licensee submitted two post-examination comments concerning the operating test and two comments concerning the written examination. A copy of the final written examination and answer key, with all changes incorporated, and the licensees post-examination comments may be accessed in the ADAMS system (ADAMS Accession Number(s) ML091170441, ML091170423, and ML091170432).

4OA6 Meetings, Including Exit

Exit Meeting Summary

On March 18, 2009 the NRC examination team discussed generic issues associated with the operating test with Mr. Chris Burton, Shearon Harris Vice President, and members of the Shearon Harris Nuclear Power Plant staff. The examiners asked the licensee if any of the examination material was proprietary. No proprietary information was identified.

KEY POINTS OF CONTACT Licensee personnel C. Burton, Vice President Harris Plant K. Henderson, General Manager Harris Plant W. Gurganious, Director - Fleet Nuclear Training G. Kilpatrick, Manager - Training T. Toler, Superintendent - Operations Training K. Bailey, Supervisor - Operations Continuing Training A. Lucky, Senior Nuclear Operations Training Instructor T. Craig, Senior Operations Instructor R. Bright, Simulator Support W. Saunders, Manager - Operations W. Gunter, Manager - Shift Operations M. Weber, Superintendent - Operations Support M. Christopherson, Control Room Supervisor M. Fulks, Senior Reactor Operator D. Cortlett, Supervisor - Licensing/Regulatory Programs M. Wallace, Senior Specialist - Licensing NRC personnel J. Austin, Senior Resident Inspector

FACILITY POST-EXAMINATION COMMENTS AND NRC RESOLUTIONS

A complete text of the licensees post-examination comments can be found in ADAMS under

Accession Number ML091170441.

Item

Administrative Topic a. - Determine Rod Misalignment Using Thermocouples (RO A1-1 and

SRO A1-1)

Comment

The licensee recommended that a corrected copy of the JPM guide be used when grading the

applicants performance.

The corrected copy supplied by the licensee modified the task standards for performance step 5

(a critical step in RO A1-1 and SRO A1-1) and performance step 6 (a critical step in SRO A1-1)

to be correct with respect to the thermocouple data that was provided to the applicants as part

of the initiating cue during administration of the JPM.

NRC Resolution

The licensees recommendation was accepted.

The task standards for performance steps 5 and 6 in the as administered JPMs are not correct

for the thermocouple data provided to applicants. The task standards contained in the corrected

copy of the JPM guide provided by the licensee are correct with respect to thermocouple data

provided to the applicants.

Item

Administrative Topic b. - Perform a Manual Shutdown Margin Calculation (RO A1-2)

Comment

The licensee recommended that a corrected copy of the JPM guide be used when grading the

applicants performance.

The task standards associated with performance steps within the JPM guide were written for

use of OST-1036, Shutdown Margin Calculation Modes 1-5 (Cycle 15). During administration

of this JPM, all applicants were provided with OST-1036, Shutdown Margin Calculation Modes

1-5 (Cycle 13). The corrected copy of the exam guide modifies all task standards to be correct

assuming use of OST-1036, Shutdown Margin Calculation Modes 1-5 (Cycle 13).

NRC Resolution

The licensees recommendation was accepted.

The task standards for the performance steps within the as administered JPM are not correct

for the reference material (Cycle 15) supplied to the applicants. The task standards contained

in the corrected copy of the JPM guide provided by the licensee are correct with respect to the

reference material used by all applicants (Cycle 13).

Item

SRO Question 83, K/A 061AG2.4.41

Comment

The licensee recommends that choices C and D both be accepted as correct answers.

Insufficient information is provided in the stem to differentiate whether or not a pathway for

fission products to escape containment exists. For the containment radiation levels given in the

question a Containment Ventilation Isolation Signal would have occurred. With no indication of

equipment or component malfunctions related to the Containment Ventilation Isolation provided

in the stem, a pathway would not exist for fission products to escape containment (containment

would be intact). However, the stem also states that Plant Vent Stack #1 WRGM Effluent

radiation levels are rising, indicating that a pathway exists for fission products to escape to the

environment via containment and the plant vent stack (containment breached). Additionally,

only one (Charging Pump 1B Room Area Radiation Monitor) of seven Fuel Breach Area

Radiation Monitors was listed in the stem as alarming, vice multiple monitors that would be

expected to be in alarm for a fuel breach, indicating that a leak existed in the associated

charging pump room (containment breached).

NRC Resolution

The licensees recommendation was accepted. The stem did not provide all necessary

information to unambiguously distinguish between choices C and D. In order to answer the

question based on the information provided in the stem, an applicant must either:

1. Assume that Containment Ventilation Isolation operated correctly (containment intact)

and ignore contradictory rising Plant Vent Stack #1 WRGM Effluent and Charging Pump

1B Room Area radiation levels, or

2. Assume that Containment Ventilation Isolation did not operate correctly (no information

provided in stem to support the assumption) and consider rising Plant Vent Stack #1

WRGM Effluent and Charging Pump 1B Room Area radiation levels (containment

breached.)

Because answers C and D do not contain conflicting information, both are accepted as

correct.

Item

SRO Question 87, K/A 012A2.01

Comment

The licensee recommends that the question be deleted from the examination.

There is no correct answer listed for the question. With OWP-RP-02 in place for Pressurizer

Pressure Channel II (PT-476), channel II OTT bistables are tripped. The actions of Answer D

(original correct answer) would allow the plant to remain in a condition contrary to Tech Specs

for 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />. All other answer choices are still incorrect.

NRC Resolution

The licensees recommendation was accepted.

Initial conditions given in the stem of the question impose contradictory requirements that make

all of the possible answer choices incorrect. Therefore the question was deleted from the exam

per NUREG 1021 ES-403 d.1.b.

SIMULATOR FIDELITY REPORT

Facility Licensee: Shearon Harris Nuclear Power Plant

Facility Docket No.: 05000400

Operating Test Administered: March 9-18, 2009

This form is to be used only to report observations. These observations do not constitute audit

or inspection findings and, without further verification and review in accordance with Inspection

Procedure 71111.11 are not indicative of noncompliance with 10 CFR 55.46. No licensee

action is required in response to these observations.

While conducting the simulator portion of the operating test, examiners observed the following:

Item Description

C RCP C Reactor Coolant Pump radial bearing and seal water injection

temperatures did not respond as expected during a simulated #1

seal failure. Malfunction RCS14C was inserted at a value of 35%,

resulting in a #1 seal high leak off flow alarm and seal leak off flow

indication pegged high (> 10 gpm) as expected. However, radial

bearing and seal water injection temperatures lowered a few

degrees and then remained stable for greater than 15 minutes,

which was not expected. Expected response was that radial

bearing and seal injection temperatures would rise due to hotter

RCS water flowing up through the thermal barrier heat exchanger.

The licensee generated Simulator Service Request number 09-

101 to track this item.

ML091210151_ X SUNSI REVIEW COMPLETE

OFFICE RII:DRS RII:DRS RII:DRS RII:DRS

SIGNATURE /RA via email/ /RA/ /RA via email/ /RA/ /

NAME Craig Kontz Mark Riches Frank Erdhardt Malcolm Widmann

DATE 4/30/2009 4/30/2009 4/30/2009 5/ /2009 5/ /2009 5/ /2009 5/ /2009

E-MAIL COPY? YES NO YES NO YES NO YES NO YES N YES NO YES NO