March 1, 2007
SUBJECT:
ANNUAL ASSESSMENT LETTER - SHEARON HARRIS NUCLEAR POWER PLANT (NRC INSPECTION REPORT 05000400/2007001)
Dear Mr. Duncan:
On February 07, 2007, the NRC technical staff completed its performance review of the Shearon Harris Power Plant for the period from January 1 through December 31, 2006. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and the enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and a resultant inspection plan.
Overall, Shearon Harris operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for Shearon Harris Unit 1 for the most recent quarter, as well as the first three quarters of the assessment cycle, was in the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan on conducting several non-ROP inspections which include the license renewal inspection and the containment emergency recirculation sump blockage temporary instruction.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through September 30, 2008. The inspection plan is provided to minimize the resource impact on your staff and to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last twelve months of the inspection plan are tentative and may be revised at the mid-cycle review meeting.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 562-4603 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.:
50-400 License No.:
NPF-63 Enclosure: Harris Inspection/Activity Plan cc w/encl: (See page 3)
_________________________
OFFICE RII:DRP RII:DRP SIGNATURE RAM SON NAME RMusser:rcm SNinh DATE 03/01/2007 02/23/2007 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
cc w/encl:
Chris L. Burton, Manager Performance Evaluation and Regulatory Affairs CPB 9 Carolina Power & Light Company Electronic Mail Distribution Robert II Director of Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Eric McCartney Plant General Manager--Harris Plant Progress Energy Carolinas, Inc.
Shearon Harris Nuclear Power Plant Electronic Mail Distribution J. Wayne Gurganious Training Manager-Harris Plant Progress Energy Carolinas, Inc.
Harris Energy & Environmental Center Electronic Mail Distribution Christos Kamilaris, Manager Support Services Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution David H. Corlett, Supervisor Licensing/Regulatory Programs Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution David T. Conley Associate General Counsel - Legal Department Progress Energy Service Company, LLC Electronic Mail Distribution John H. O'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Beverly Hall, Chief, Radiation Protection Section N. C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution Public Service Commission State of South Carolina P. O. Box 11649 Columbia, SC 29211 Chairman of the North Carolina Utilities Commission c/o Sam Watson, Staff Attorney Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Herb Council, Chair Board of County Commissioners of Wake County P. O. Box 550 Raleigh, NC 27602 Tommy Emerson, Chair Board of County Commissioners of Chatham County Electronic Mail Distribution
Report to R. from Randall A. Musser dated March 1, 2007, SUBJECT:
ANNUAL ASSESSMENT LETTER - SHEARON HARRIS NUCLEAR POWER PLANT (NRC INSPECTION REPORT 05000400/2007001)
C. Patel, NRR C. Evans (Part 72 Only)
L. Slack, RII EICS RIDSNRRDIRS OE Mail (email address if applicable)
RIDSNRRDIRSIPAB INPO PUBLIC