IR 05000400/2019001

From kanterella
Jump to navigation Jump to search
Nuclear Regulatory Commission Integrated Inspection Report 05000400/2019001
ML19130A153
Person / Time
Site: Harris 
Issue date: 05/10/2019
From: Lundy Pressley
NRC/RGN-II/DRP/RPB4
To: Hamilton T
Duke Energy Progress
References
IR 2019001
Download: ML19130A153 (16)


Text

May 10, 2019

SUBJECT:

SHEARON HARRIS UNIT 1 - NUCLEAR REGULATORY COMMISSION INTEGRATED INSPECTION REPORT 05000400/2019001

Dear Ms. Hamilton:

On March 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Shearon Harris Unit 1. On April 10, 2019, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

However, inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC resident inspector at the Shearon Harris Nuclear Power Plant. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Lundy F. Pressley, Acting Chief Reactor Projects Branch 4 Division of Reactor Projects Docket No.: 05000400 License No.: NPF-63

Enclosure:

Inspection Report 05000400/2019001

Inspection Report

Docket Number:

05000400

License Number:

NPF-63

Report Number:

05000400/2019001

Enterprise Identifier: I-2019-001-0025

Licensee:

Duke Energy Progress, LLC

Facility:

Shearon Harris, Unit 1

Location:

New Hill, NC 27562

Inspection Dates:

January 01, 2019 to March 31, 2019

Inspectors:

J. Zeiler, Senior Resident Inspector

A. Patz, Resident Inspector

S. Downey, Senior Reactor Inspector (Section 71152.2)

Approved By:

Lundy F. Pressley, Acting Chief

Reactor Projects Branch 4

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a quarterly inspection at Harris, Unit 1 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. Findings and violations being considered in the NRCs assessment are summarized in the table below. A licensee-identified non-cited violation is documented in report section 7115

List of Findings and Violations

No findings were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPE

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown (IP Section 02.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) A boric acid transfer system during B boric acid transfer pump unavailability on January 3, 2019 (2)

'B' emergency service water (ESW) pump and 'B' ESW booster pump while 'A' ESW pump and 'A' ESW booster pump was out-of-service for preventive maintenance on January 15, 2019 (3)

'A' containment spray (CS) pump while 'B' CS pump was out-of-service for preventive maintenance on February 5, 2019

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) ESW intake structure and yard area (fire zones 12-I-ESWPA, 12-I-ESWPA-BAL, 12-I-ESWPB, 12-I-ESWPB-BAL, and 12-I-ESW-BAL) on January 15, 2019
(2) Reactor auxiliary building (RAB) 190' elevation 'A' residual heat removal (RHR)and CS pump room (fire zone 1-A-1-PA) on February 5, 2019
(3) RAB 216' elevation mechanical penetration room, south corridor, and ESW pipe tunnel (fire zones 1-A-2-MP, 1-A-2-COR, and 1-A-2-PT) on February 6, 2019
(4) RAB 286' elevation 'B' electrical switchgear and ventilation rooms (fire zones 1-A-SWGRB and 1-A-5-HVB) on February 13, 2019
(5) RAB 236' elevation chemical and volume control system (CVCS) area (fire zone 1-A-3-COMB) on February 15, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the RAB 216' elevation on February 14, 2019.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

The inspectors observed and evaluated licensed operator performance in the control room during 'A' train reactor trip breaker and solid state protection system testing on March 18, 2019.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

The inspectors observed and evaluated a simulator scenario for operator requalification training involving a small-break loss-of-coolant accident on February 19, 2019.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Containment ventilation isolation radiation monitor 3561C failed to alarm when tested on November 7, 2018
(2) Loose fan belts on 'A' RHR/CS pump room air handler system resulting in fan speed below minimum requirements on December 31, 2018

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Elevated (Green) risk during planned unavailability of the 'A' ESW pump and 'A' ESW booster pump for preventive maintenance on January 15, 2019
(2) Elevated (Green) risk during planned unavailability of the 'B' CS pump for seal water piping inspections on February 5, 2019
(3) Elevated (Green) risk during emergent repair of power range nuclear instrument channel NI-41 following inoperability due to anomalous upper detector high current on February 11, 2019
(4) Elevated (Green) risk during planned unavailability of the 'B' emergency safeguards sequencer for relay calibration and replacement on February 13, 2019
(5) Elevated (Green) risk during planned unavailability of the 'A' motor driven auxiliary feedwater (AFW) pump for preventive maintenance on February 19, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determinations and Functionality Assessments Sample (IP Section 02.01) (4 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Leakage of diaphragm valves in the emergency core cooling system (ECCS)recirculation flow path on January 15, 2019 (nuclear condition reports (NCRs) 02252508 and 02252515)
(2) Increased levels of particulate found in oil of 'A' component cooling water (CCW)pump inboard bearing on January 31, 2019 (NCR 02255195)
(3) Gas voids found in piping upstream of 'B' CS pump discharge containment isolation valve 1CT-88 on February 20, 2019 (NCR 02258496)

(4)

'A' train emergency diesel generator auxiliary lube oil pump tripped after starting on March 21, 2019 (NCR 02264131)

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modification:

(1) Installation of wireless electronic equipment in the nuclear plant power block including control room

71111.19 - Post Maintenance Testing

Post Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post maintenance tests:

(1) Operations surveillance test (OST)-1214, ESW System Operability Train A Quarterly Interval Modes 1-2-3-4-5-Defueled, following scheduled preventive maintenance on the 'A' ESW pump and 'A' ESW booster pump on January 15, 2019
(2) OST-1122, Train A 6.9 kV Emergency Bus Undervoltage Trip Actuating Device Operational Test and Contact Check, following corrective replacement of the turbine driven AFW pump governor positioner on January 19, 2019
(3) Technical Procedure Testing (OPT)-1512, Train B Essential Chilled Water Turbopak Units Quarterly Inspection and Checks, following preventive maintenance on the B essential services chilled water (ESCW) chiller on January 29, 2019
(4) OST-1119, Containment Spray Operability Train B Quarterly Interval Modes 1-4, following scheduled preventive maintenance on the 'B' CS pump on February 5, 2019
(5) OST-1211, Auxiliary Feedwater Pump 1A-SA Operability Test Quarterly Interval Modes 1-4, and OST-1077, Auxiliary Feedwater Valves Operability Test Quarterly Interval Mode 4-5-6, following scheduled preventive maintenance on the 'A' motor driven AFW pump motor and discharge pressure control valve on February 19, 2019
(6) Operating Procedure (OP)-145, Component Cooling Water, for operating the 'B' CCW pump following pump inrush current testing on March 4, 2019

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

FLEX Testing (IP Section 03.02)

Work orders (WO) 20281145-02 and 20281145-03, Perform quarterly functional tests of FLEX diesel generators 1FLX-E042 and 1FLX-E043, on March 6, 2019

In Service Testing (IST) (IP Section 03.01) (1 Sample)

OST-1093, CVCS/Safety Injection System Operability Train B Quarterly Interval Modes 1-4, on January 3, 2019

Reactor Coolant System (RCS) Leak Detection (IP Section 03.01) (1 Sample)

OST-1026, Reactor Coolant System Leakage Evaluation, Computer Calculation, Daily Interval, Modes 1-4, on March 22, 2019

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) OST-1076, Auxiliary Feedwater Pump 1B-SB Operability Test Quarterly Interval Modes 1-4, on January 7, 2019
(2) OPT-1538, Emergency Safeguards Sequencer System Test - Train B Quarterly Interval Modes 1-6, on February 13,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

Unit 1 (January 1, 2018 - December 31, 2018)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)

Unit 1 (January 1, 2018 - December 31, 2018)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

Unit 1 (January 1, 2018 - December 31, 2018)

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) TS 3.0.3 entered for both trains of containment vacuum relief rendered inoperable during maintenance on containment ventilation isolation radiation monitors (NCR 02244746)
(2) Operating experience smart sample (OpESS) 2018/01, 10 CFR Part 21 notification of the potential existence of defects related to control rod drive mechanism (CRDM)thermal sleeves (NCRs 02220429, 02208989)

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71152 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a Non-Cited Violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Technical Specification (TS) 3.6.5, Vacuum Relief System, requires two containment vacuum relief trains shall be operable in Modes 1, 2, 3, and 4. The associated action statement for TS 3.6.5 with one inoperable containment vacuum relief train requires the inoperable train to be restored to operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least hot standby within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. Since there is no TS action statement addressing inoperability of both containment vacuum relief trains, the limiting condition for operation associated with TS 3.0.3 applies. TS 3.0.3 requires, within one hour, action shall be initiated to place the unit in a mode in which (TS 3.6.5) does not apply and be in hot standby within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, hot shutdown within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and cold shutdown within the subsequent 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Contrary to the above, on November 20, 2018, while in Mode 1, the licensee failed to follow the action requirements of TS 3.0.3, in that, within one hour of entering TS 3.0.3, after both containment vacuum relief trains were rendered inoperable, actions were not initiated to place the unit in a mode in which TS 3.6.5 did not apply. TS 3.0.3 was exited 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> and 18 minutes from the time both containment vacuum relief valves were initially rendered inoperable. Both containment vacuum relief trains were rendered inoperable during planned maintenance to replace the electrical breakers to containment ventilation isolation radiation monitors 3561A and 3561C. When both radiation monitors were de-energized for this planned work, a containment ventilation isolation signal (CVIS) was generated as designed, which prevents opening containment ventilation systems, including both A and B train containment vacuum relief valves. While reviewing procedural guidance for returning the radiation monitors to service and resetting CVIS after the work was completed, the operators realized that the containment vacuum relief system had been impacted and TS 3.0.3 had been applicable.

Significance: Green. The inspectors assessed the significance of the finding using IMC 0609, Appendix A, Significance Determination Process for Findings At-Power, dated June 19, 2012. The finding was screened using Exhibit 3, Barrier Integrity Screening Questions, since it was associated with a degraded containment pressure control system. The finding was determined to be of very low safety significance (Green) because it did not represent an actual open pathway in the physical integrity of containment or partial failure of containment isolation systems or containment heat removal components; and Harris does not have hydrogen igniters.

Corrective Action Reference: NCR

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 10, 2019, the inspectors presented the quarterly resident inspector inspection results to Ms. Tanya Hamilton, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Procedures

OP-107

Chemical and Volume Control

Revision 117

OP-112

Containment Spray System

Revision 46

OP-139

Service Water System

Revision 136

71111.05Q Fire Plans

CSD-HNP-PFP-

RAB-190-216

Reactor Auxiliary Building Elevations 190 and 216 Pre-Fire

Plan

Revision 1

CSD-HNP-PFP-

RAB-236

Reactor Auxiliary Building Elevation 236 Pre-Fire Plan

Revision 2

CSD-HNP-PFP-

SEC

Out Building Pre-Fire Plan

Revision 4

CSD-HNP-RAB-

286

Reactor Auxiliary Building Elevation 286 Pre-Fire Plan

Revision 1

Miscellaneous

Fire Protection

Permit and

Impairment Log

Entries

Procedures

AD-EG-ALL-1520

Transient Combustible Control

Revision 11

FPP-001

Fire Protection Program Manual

Revision 44

FPP-013

Fire Protection - Minimum Requirements, Mitigation Actions

and Surveillance Requirements

Revision 99

71111.06

Calculations

PRA-F-E-004

Reactor Auxiliary Building Unit 1 Elevation 190' & 216'

Internal Flooding Analysis

Revision 8

71111.11Q Procedures

AD-OP-All-0106

Conduct of Infrequently Performed Test or Evolution

Revision 4

AD-OP-ALL-1000

Conduct of Operations

Revision 15

AD-TQ-ALL-0420

Conduct of Simulator Training and Evaluation

Revision 14

AOP-025

Loss of One Emergency AC Bus (6.9kV) or One Emergency

DC Bus (125V)

Revision 42

AP-002

Plant Conduct of Operations

Revision 73

EOP-E-0

Reactor Trip or Safety Injection

Revision 12

MST-I0001

Train A Solid State Protection System Actuation Logic &

Master Relay Test

Revision 38

OMM-001

Operations Administrative Requirements

Revision 114

OMM-014

Operation of the Work Coordination Center

Revision 73

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-104

Rod Control System

Revision 43

Work Orders

WO 20281152

Conduct SSPS Testing on 'A' Train

71111.12

Calculations

HNP-F/PSA-0020

HNP PRA Evaluation of Risk Significant SSCs for

Maintenance Rule

Revision 1

HNP-F/PSA-0065

HNP PRA - System Notebooks

Revision 8

Corrective Action

Documents

NCR 02241966

Containment ventilation isolation radiation monitor 3561C

failed to alarm when tested

NCR 02250497

Loose fan belts on 'A' RHR/CS pump room air handler

system

Miscellaneous

NUMARC 93-01

Industry Guideline for Monitoring the Effectiveness of

Maintenance at Nuclear Power Plants

Revision 4A

Procedures

AD-EG-ALL-1210

Maintenance Rule Program

Revision 1

EOP-E-1

Reactor Trip Response

Revision 5

OWP-RM

Radiation, Effluent, and Explosive Gas Monitoring

Revision 45

Work Orders

WO 20287202

Perform MST-I0347 to determine cause of electronic spikes

on RM-01CR-3561ASA

WO 20303302

Repair loose belts on 'A' RHR/CS pump room air handler

71111.13

Procedures

AD-NF-ALL-0501

Electronic Risk Assessment Tool (ERAT)

Revision 3

AD-OP-ALL-0201

Protected Equipment

Revision 5

AD-OP-ALL-1000

Conduct of Operations

Revision 15

AD-WC-ALL-

200

On-Line Work Management

Revision 13

AD-WC-ALL-

240

On-Line Risk Management Process

Revision 1

AD-WC-ALL-

0410

Work Activity Integrated Risk Management

Revision 7

OMM-001

Conduct of Operations

Revision 114

Work Orders

WO 10622005

Lubrication of 'A' ESW booster pump coupling

WO 12296955

Tighten seal water piping connection on 'A' containment

spray pump

WO 20193828

AFW pump motor 1A-SA testing

WO 20237424

Preventive maintenance on 'A' ESW stuffing box and seal

water cooling system

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WO 20266256

Replace actuator oil in 'A' AFW discharge control valve

WO 20311779

Repair emergent issue with N-41 upper detector reading

high

WOs 20181791,

266115, and

266116

'B' train sequencer relay calibrations and replacement

71111.15

Corrective Action

Documents

NCR 01959624

Copper detected in CCW pump bearing oil sample

NCR 02203899

Oil sample particulate results for the 'A' CCW pump

Procedures

AD-OP-ALL-0105

Operability Determinations and Functionality Assessments

Revision 4

AD-OP-ALL-0202

Aggregate Operator Impact Assessment

Revision 2

DBD-103

Chemical and Volume Control System

Revision 24

DBD-106

Containment Spray System

Revision 17

DBD-131

Component Cooling Water System

Revision 17

DBD-201

Emergency Diesel Generator System

Revision 18

OST-1013

1A-SA Emergency Diesel Generator Operability Test

Monthly Interval Modes 1-6

Revision 43

OST-1107

ECCS/Containment Spray Flow Path and Piping Filled

Verification Monthly Interval Modes 1-6

Revision 36

PM-M0102

3/8 - 6 Inch Diaphragm Valve Nonmetallic Component

Replacement

Revision 6

Work Orders

WO 20179904

Evaluate gas voids

71111.18

Engineering

Changes

EC 413085

Non-Controlled Plant Equipment Wireless Emitting Device

Installation

Revision 1

EC 414212

Electromagnetic Interference Proximity for Transceivers

Revision 3

Miscellaneous

NEI 96-07

Guidelines for 10 CFR 50.59 Evaluations Endorsed by

Regulatory Guide 1.187

Revision 1

Regulatory Guide 1.187

Guidance for Implementation of 10 CFR 50.59, dated

November 2000

Procedures

AD-EG-ALL-1110

Design Review Requirements

Revision 6

AD-EG-ALL-1130

Activation of Engineering Changes

Revision 2

AD-EG-ALL-1132

Preparation and Control of Design Change Engineering

Changes

Revision 13

AD-EG-ALL-1137

Engineering Change Product Selection

Revision 5

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AD-LS-ALL-0008

CFR 50.59 Review Process

Revision 0

Work Orders

WO 20288719

Install wireless emitting device and hardware for main control

room

71111.19

Procedures

PLP-400

Post Maintenance Testing

Revision 64

Work Orders

WO 10622005

Lubrication of 'A' ESW booster pump coupling

WO 12296955

Tighten seal water piping connection on 'A' containment

spray pump

WO 20191986

Obtain one set of inrush current data

WO 20193828

AFW pump motor 1A-SA testing

WO 20237424

Preventive maintenance on 'A' ESW stuffing box and seal

water cooling system

WO 20266256

Replace actuator oil in 'A' AFW discharge control valve

WO 20285410

VMS-2, Determine available adjustment for future

modification

WO 20307647

TDAFW pump tripped while starting during OST-1044

71111.22

Procedures

CSD-EG-HNP-

8888

Flexible Response to Extended Loss of ALL AC Power

Revision 0

ISI-800

Inservice Testing of Pumps

Revision 30

OST-1093

Completed procedures on January 14, 2015, and January

2, 2017

PD-OP-ALL-0500

Diverse and Flexile Coping Strategies FLEX Program

Revision 1

71151

Miscellaneous

2018 Licensee

Event Reports

2018 Operator

Log Entries

NEI 99-02

Regulatory Assessment Performance Indicator Guideline

Procedures

AD-LS-ALL-0004

NRC Performance Indicators and Monthly Operating Report

Revision 3

71152

Engineering

Changes

2571

HNP RFO-21 Thermal Sleeve Flange Upper Flange Wear

Inspection Results

Revision 0

Procedures

AD-LS-ALL-0006

Notification/Reportability Evaluation

Revision 1

AD-PI-ALL-0100

Corrective Action Program

Revision 20

AD-PI-ALL-0102

Apparent Cause Evaluation

Revision 4

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AD-PI-ALL-0104

Prompt Investigation Response Team

Revision 4

AD-PI-ALL-0106

Cause Investigation Checklists

Revisions 2

and 3

AD-PI-ALL-0108

Performance Analysis

Revision 0

DBD-136

Containment Ventilation & Cooling Systems

Revision 12

OWP-RM

Radiation, Effluent, and Explosive Gas Monitoring

Revisions 44

and 45

Work Orders

WO 20191928

Replace breaker to radiation monitor RM-3561A

WO 20191929

Replace breaker to radiation monitor RM-3561C