APPENDIX D ADDITIONAL CONDITIONS OPERATING LICENSE NO. NPF-73 FirstEnergy Nuclear Operating Company and FirstEnergy Nuclear Generation, LLC shall comply with the following conditions on the schedules noted below:
APPENDIX D ADDITIONAL CONDITIONS OPERATING LICENSE NO. NPF-73 FirstEnergy Nuclear Operating Company and FirstEnergy Nuclear Generation, LLC shall comply with the following conditions on the schedules noted below:
Amendment        Additional Condition                                                Implementation Number                                                                                Date 187            Based on the Commission's Order dated April 14, 2017,                The amendment regarding the direct transfer from Ohio Edison Company (OE) and      shall be The Toledo Edison Company (TE) to FirstEnergy Nuclear                implemented Generation, LLC (FENGen), FENOC and FENGen shall comply              within 90 days with the following conditions noted Below.                          from June 1, 2017 A. By June 1, 2017, OE and TE shall initiate the transfer to FENGen the accumulated decommissioning funds held by OE and TE for Beaver Valley Unit 2. All such funds shall be deposited and held in the FENGen nuclear decommissioning trust for Beaver Valley Unit 2 along with other funds maintained by FENGen for Beaver Valley Unit 2 and shall be maintained in such trust outside of FENGen's administrative control and in accordance with the requirements of 1O CFR 50.75(h)(1 ).
Amendment        Additional Condition                                                Implementation Number                                                                                Date 187            Based on the Commission's Order dated April 14, 2017,                The amendment regarding the direct transfer from Ohio Edison Company (OE) and      shall be The Toledo Edison Company (TE) to FirstEnergy Nuclear                implemented Generation, LLC (FENGen), FENOC and FENGen shall comply              within 90 days with the following conditions noted Below.                          from June 1, 2017 A. By June 1, 2017, OE and TE shall initiate the transfer to FENGen the accumulated decommissioning funds held by OE and TE for Beaver Valley Unit 2. All such funds shall be deposited and held in the FENGen nuclear decommissioning trust for Beaver Valley Unit 2 along with other funds maintained by FENGen for Beaver Valley Unit 2 and shall be maintained in such trust outside of FENGen's administrative control and in accordance with the requirements of 10 CFR 50.75(h)(1 ).
Such transfer of the accumulated decommissioning funds by OE and TE shall be completed within a reasonable period of time.
Such transfer of the accumulated decommissioning funds by OE and TE shall be completed within a reasonable period of time.
B. The Support Agreement in the amount of $400 million from FirstEnergy Solutions Corp. (FES) described in the application dated June 24, 2016 shall be effective and consistent with the representations in the application. FENGen shall take no action to void, cancel, or modify the Support Agreement without the prior written consent of the NRC staff. FENGen shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, no later than 10 working days after any funds are provided to FENGen by FES under the terms of the Support Agreement.
B. The Support Agreement in the amount of $400 million from FirstEnergy Solutions Corp. (FES) described in the application dated June 24, 2016 shall be effective and consistent with the representations in the application. FENGen shall take no action to void, cancel, or modify the Support Agreement without the prior written consent of the NRC staff. FENGen shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, no later than 10 working days after any funds are provided to FENGen by FES under the terms of the Support Agreement.

Latest revision as of 11:35, 10 November 2019

Correction to Conforming Amendment No. 187 Order to Transfer License
ML17157B284
Person / Time
Site: Beaver Valley
Issue date: 06/07/2017
From: Booma Venkataraman
Plant Licensing Branch 1
To: Richey M
FirstEnergy Nuclear Operating Co
Venkataraman B
References
CAC MF8066
Download: ML17157B284 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 7, 2017 Mr. Marty L. Richey, Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077

SUBJECT:

BEAVER VALLEY POWER STATION, UNIT 2-CORRECTION TO CONFORMING AMENDMENT NO. 187 RE: ORDER TO TRANSFER LICENSE (CAC NO. MF8066)

Dear Mr. Richey:

On May 30, 2017, the U.S. Nuclear Regulatory Commission (NRG) issued Conforming Amendment No. 187 to Renewed Facility Operating License No. NPF-73, for Beaver Valley Power Station, Unit 2 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML17115A123). The conforming amendment was issued relative to the April 14, 2017, order approving the direct transfer of Toledo Edison Company's 18.26 percent leased interest and Ohio Edison Company's 21.66 percent leased interest in Beaver Valley Power Station, Unit 2, to FirstEnergy Nuclear Generation, LLC (ADAMS Accession No. ML17081A433).

On June 2, 2017, FirstEnergy Corporation staff notified NRG staff that one of the license pages (Appendix D, page D-6) revised by Conforming Amendment No. 187 was missing the new amendment number (187) in the left hand column under "Amendment Number." The corrected Appendix D, page D-6, is enclosed.

Please replace Appendix D, page D-6, of Renewed Facility Operating License No. NPF-73 with the enclosed page. The NRG staff apologizes for any inconvenience this may have caused.

If you have any questions, please contact me at 301-415-2934 or Booma.Venkataraman@nrc.gov.

Sincerely,

,i~:~7" O'~

Booma Venkataraman, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-412

Enclosure:

Corrected Appendix D, page D-6 cc w/encl: Distribution via Listserv

ENCLOSURE CORRECTED APPENDIX D, PAGE D-6

APPENDIX D ADDITIONAL CONDITIONS OPERATING LICENSE NO. NPF-73 FirstEnergy Nuclear Operating Company and FirstEnergy Nuclear Generation, LLC shall comply with the following conditions on the schedules noted below:

Amendment Additional Condition Implementation Number Date 187 Based on the Commission's Order dated April 14, 2017, The amendment regarding the direct transfer from Ohio Edison Company (OE) and shall be The Toledo Edison Company (TE) to FirstEnergy Nuclear implemented Generation, LLC (FENGen), FENOC and FENGen shall comply within 90 days with the following conditions noted Below. from June 1, 2017 A. By June 1, 2017, OE and TE shall initiate the transfer to FENGen the accumulated decommissioning funds held by OE and TE for Beaver Valley Unit 2. All such funds shall be deposited and held in the FENGen nuclear decommissioning trust for Beaver Valley Unit 2 along with other funds maintained by FENGen for Beaver Valley Unit 2 and shall be maintained in such trust outside of FENGen's administrative control and in accordance with the requirements of 10 CFR 50.75(h)(1 ).

Such transfer of the accumulated decommissioning funds by OE and TE shall be completed within a reasonable period of time.

B. The Support Agreement in the amount of $400 million from FirstEnergy Solutions Corp. (FES) described in the application dated June 24, 2016 shall be effective and consistent with the representations in the application. FENGen shall take no action to void, cancel, or modify the Support Agreement without the prior written consent of the NRC staff. FENGen shall inform the Director of the Office of Nuclear Reactor Regulation, in writing, no later than 10 working days after any funds are provided to FENGen by FES under the terms of the Support Agreement.

Beaver Valley Unit 2 D-6 Amendment No. 187

ML171578284 OFFICE NRR/DORL/LPL 1/PM NRR/DORL/LPL 1/LA NRR/DORL/LPL 1/BC NRR/DORL/LPL 1/PM NAME BVenkataraman LRonewicz JDanna BVenkataraman DATE 06/06/2017 06/06/2017 06/06/2017 06/07/2017