ML18099A232

From kanterella
Jump to navigation Jump to search

Correction of an Error in the Renewed Facility Operating License No. DPR-66 Associated with License Amendment No. 301 CAC No. MF3301; EPID L-2013-LLF-0001)
ML18099A232
Person / Time
Site: Beaver Valley
Issue date: 04/18/2018
From: Jennifer Tobin
Plant Licensing Branch 1
To: Bologna R
FirstEnergy Nuclear Operating Co
Tobin J, NRR/DORL/LPL1, 415-2328
References
CAC MF3301, EPID L-2013-LLF-0001
Download: ML18099A232 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 18, 2018 Mr. Richard D. Bologna Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SSB P.O. Box 4, Route 168 Shippingport, PA 15077

SUBJECT:

BEAVER VALLEY POWER STATION, UNIT NO. 1 - CORRECTION OF AN ERROR IN THE RENEWED FACILITY OPERATING LICENSE NO. DPR-66, ASSOCIATED WITH LICENSE AMENDMENT NO. 301 (CAC NO. MF3301; EPID L-2013-LLF-0001)

Dear Mr. Bologna:

By letter dated January 22, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17291A081), the U.S. Nuclear Regulatory Commission (NRC) issued Amendment No. 301 to Renewed Facility Operating License No. DPR-66 for Beaver Valley Power Station, Unit No. 1. The amendment revised the license to establish and maintain a risk-informed, performance-based fire protection program in accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Section 50.48(c).

Subsequent to the issuance of this amendment, the NRC was notified by e-mail dated February 23, 2018 (ADAMS Accession No. ML180588072), by FirstEnergy Nuclear Operating Company that an administrative error was made in the license condition page involving an incorrect reference. Specifically, the Transition License Condition 5.(c).3 referenced Unit 1 instead of Unit 2.

The NRC staff has determined that this error was made inadvertently. The correction does not change any of the conclusions associated with the issuance of Amendment No. 301 and does

R. Bologna not affect the associated notice to the public. The replacement license condition page associated with this change is enclosed.

If you have any questions, please contact me at 301-415-2328 or Jennifer.Tobin@nrc.gov.

Sincerely, Jennifer Tobin, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-334

Enclosure:

Corrected Page 6 of Renewed Facility Operating License No. DPR-66 for Amendment 301 cc: Listserv

ENCLOSURE Corrected Page 6 of Renewed Facility Operating License No. DPR-66 for Amendment No. 301 FirstEnergy Nuclear Operating Company Beaver Valley Power Station, Unit No. 1 Docket No. 50-334

2. Fire Protection Program Changes that Have No More than Minimal Risk Impact Prior NRC review and approval are not required for changes to the licensee's fire protection program that have been demonstrated to have no more than a minimal risk impact.

The licensee may use its screening process as approved in the NRC SE dated January 22, 2018, to determine that certain fire protection program changes meet the minimal criterion.

The licensee shall ensure that fire protection defense-in-depth and safety margins are maintained when changes are made to the fire protection program.

(c) Transition License Conditions

1. Before achieving full compliance with 10 CFR 50.48( c ), as specified by (2) below, risk-informed changes to the licensee's fire protection program may not be made without prior NRC review and approval unless the change has been demonstrated to have no more than a minimal risk impact, as described in (2) above.
2. The licensee shall implement the Unit 1 modifications to its facility, as described in Attachment S, Table S-2, "Plant Modifications Committed," in FENOC letter L-17-122, dated April 21, 2017, to complete the transition to full compliance with 10 CFR 50.48(c), by the completion of the second Unit 1 refueling outage after issuance of the safety evaluation. The licensee shall maintain appropriate compensatory measures in place until completion of these modifications.
3. The licensee shall implement the items listed in Attachment S, Table S-3, "Implementation Items," of FENOC letter L-17-268, dated August 22, 2017, by 12 months after issuance of the safety evaluation (with the exception of Items BV1-1633, BV1-2974, BV1-3060, BV1-3108, BV1-3109, BV2-1580, BV2-1622, BV2-1623, and BV2-1750, which are to be completed by the end of the second Unit 2 refueling outage after issuance of the safety evaluation).

(6) Systems Integrity FENOC shall implement a program to reduce leakage from systems outside containment that would or could contain highly radioactive fluids during a serious transient or accident to as low as practical levels. This program shall include the following:

1. Provisions establishing preventive maintenance and periodic visual inspection requirements, and
2. Integrated leak test requirements for each system at a frequency not to exceed refueling cycle intervals.

Amendment No. 301 Beaver Valley Unit 1 Renewed Operating License OPR-66

R. Bologna

SUBJECT:

BEAVER VALLEY POWER STATION, UNIT NO. 1 - CORRECTION OF AN ERROR IN THE RENEWED FACILITY OPERATING LICENSE NO. DPR-66, ASSOCIATED WITH LICENSE AMENDMENT NO. 301 (CAC NO. MF3301; EPID L-2013-LLF-0001) DATED APRIL 18, 2018 DISTRIBUTION:

PUBLIC RidsACRS_MailCTR Resource RidsRgn1 MailCenter Resource RidsNrrPMBeaverValley Resource RidsNrrDorlLpl1 Resource RidsNsirDprResource RidsNrrDraAplb Resource RidsNrrLAIBetts Resource RidsNrrDorl RidsNrrOd JRobinson, NRR ADAMS A ccess1on Nos.: PKG ML18099A257 L ett er: ML18099A232 *b>Ye-ma, OFFICE NRR/DORL/LPL 1/PM NRR/DORL/LPL 1/LA NRR/DRA/APLB NRR/DORL/LPL 1/BC NRR/DORL/LPL 1/PM NAME JTobin IBetts JRobinson JDanna JTobin DATE 04/9/2018 04/11/2018 3/26/2018 04/13/2018 04/18/2018 OFFICIAL RECORD COPY