Letter Sequence Other |
---|
EPID:L-2020-LLM-0000, Firstenergy Nuclear Operating Company - Letter, Order, SE Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley, Units 1 and 2, Davis-Besse, Unit 1, and Perry, Unit 1 (Approved, Closed) |
|
MONTHYEARML19193A0022019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Letter, Order, SE Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley, Units 1 and 2, Davis-Besse, Unit 1, and Perry, Unit 1 Project stage: Request ML20030A4402020-02-27027 February 2020 Issuance of Amendment Nos. 304, 194, 299, and 187; Order Approving Transfers of Facility Operating Licenses and Independent Spent Fuel Storage Installation General Licenses and Conforming Amendments Project stage: Approval L-20-086, Submittal of Indemnity Agreements2020-03-12012 March 2020 Submittal of Indemnity Agreements Project stage: Other ML20080H7112020-03-23023 March 2020 Correction Letter for Conforming License Amendments Nos. 304 and 194, Order Approving Transfer of Licenses and Conforming License Amendments Project stage: Other ML21302A0642021-10-29029 October 2021 and Big Rock Point - Supplement to Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments Project stage: Supplement ML22021B6702022-01-21021 January 2022 and Big Rock Point - Supplement to Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments Project stage: Supplement ML22096A3042022-05-0909 May 2022 and Big Rock Point Plant - New Information Regarding Order Approving Transfer of Licenses (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) Project stage: Other ML22173A1772022-06-23023 June 2022 Enclosure 3 - Big Rock Point Amendment to Indemnity Agreement No. B-22 - Amendment No. 20 Project stage: Other ML22173A1782022-06-23023 June 2022 Enclosure 4 - Palisades Amendment to Indemnity Agreement No. B-40 - Amendment No. 13 Project stage: Other ML22173A1792022-06-23023 June 2022, 28 June 2022 Conforming Amendments for License Transfer to Holtec (L-2022-LLM-0002 and L-2020-LLM-0003) Project stage: Request ML22178A0772022-06-24024 June 2022 (HDI) Satisfactory Documentary Evidence Required Before the Planned Closing Date of the Purchase and Sale Transaction of Palisades Nuclear Plant and Big Rock Point Plant Project stage: Request PNP 2022-019, & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals2022-06-24024 June 2022 & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals Project stage: Request ML22179A0752022-06-28028 June 2022 E-mail from Entergy Dated June 28, 2022, Notification of Palisades and Big Rock Point License Transfer (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) Project stage: Other ML22173A1762022-06-28028 June 2022 Enclosure 2 - Holtec Palisades, LLC and Holtec Decommissioning International, LLC - Palisades Nuclear Plant Amendment to Renewed Facility Operating License Project stage: Other ML22173A1752022-06-28028 June 2022 Enclosure 1 - Holtec Palisades, LLC and Holtec Decommissioning International, LLC - Big Rock Point Plant Amendment to Facility Operating License Project stage: Other ML22173A1732022-06-28028 June 2022 and Big Rock Point Plant - Issuance of Amendment Nos. 129 and 273 Order Approving Transfer of Licenses and Conforming License Amendments (EPIDs L-2022-LLM-0002 and L-2020-LLM-0003) Project stage: Approval 2021-10-29
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) IR 05000334/20240102024-08-20020 August 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010 L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-158, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 L-24-157, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations L-24-114, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation L-24-115, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 the Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 ML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 2024-09-17
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML24057A0772024-03-0101 March 2024 Conforming License Amendments - Enclosure 1 ML24057A0782024-03-0101 March 2024 Amendments to Indemnity Agreements - Enclosure 2 ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary ML23237B4412023-09-29029 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Federal Register Notice, Direct and Indirect License Transfer Issuance Order ML23237B4282023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 2, Draft Conforming License Amendments ML23237B4302023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Enclosure 4, Safety Evaluation for Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0000) (Public) ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23019A0032023-03-16016 March 2023 Issuance of Amendment Nos. 320 and 210 Adoption of Technical Specifications Task Force (Tstf) Traveler Tstf-501, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23062A5212023-03-0606 March 2023 Issuance of Amendment No. 319 Revise Technical Specification (TS) 3.5.2, ECCS Operating, Limiting Condition for Operation (LCO) 3.5.2, ML22277A8142022-10-0707 October 2022 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 315 and 205 Regarding Changes to the Emergency Preparedness Plan ML22210A0102022-09-16016 September 2022 Energy Harbor Fleet- Issuance of Amendments Regarding Adoption of TSTF 554, Revise Reactor Coolant Leakage Requirements ML22222A0862022-09-0101 September 2022 Issuance of Amendment Nos. 317 and 208 Revise Technical Specification 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Bus Separation Instrumentation ML22140A2092022-06-28028 June 2022 Issuance of Amendment No. 207 Correct TS 3.1.7 Change Made by TSTF-547 ML22095A2352022-05-10010 May 2022 Issuance of Amendment Nos. 316 and 206 Revise Technical Specification 5.6.3, Core Operating Limits Report (COLR) ML21286A7822022-05-0606 May 2022 Issuance of Amendment Nos. 315 and 205 Regarding Changes to the Emergency Plan ML22077A1342022-05-0202 May 2022 Issuance of Amendment Nos. 314 and 204 Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML21320A3592021-11-23023 November 2021 Correction to License Page 4 ML21197A0092021-11-0101 November 2021 Issuance of Amendment Nos. 313 and 203 Reactor Coolant System, Pressure and Temperature Limits Report ML21214A2752021-10-15015 October 2021 Issuance of Amendment Nos. 312 and 202 Atmospheric Dump Valves ML21153A1762021-06-30030 June 2021 Issuance of Amendment No. 201 Revision of Technical Specifications Related to Steam Generator Tube Inspection, and Repair Methods ML21075A1132021-04-16016 April 2021 Issuance of Amendment Nos. 311, 200, and 302 to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, Into the Technical Specifications ML21070A0002021-03-22022 March 2021 Issuance of Amendment 310, Revise Technical Specification 5.5.5.1, Unit 1 SG Program, to Defer Spring 2021 Refueling Outage Steam Generator Inspections to Fall 2022 Refueling Outage ML20346A0222021-03-10010 March 2021 Issuance of Amendment Nos. 309 and 199 to Change Technical Specifications to Implement New Surveillance Methods for the Heat Flux Hot Channel Factor ML20335A0522021-02-18018 February 2021 Issuance of Amendment Nos. 308 and 198 to Modify Certified Fuel Handler Related Technical Specifications for Permanently Defueled Condition ML21034A3892021-02-18018 February 2021 Correction to Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address Generic Safety Issue 191 Issues ML21014A3042021-02-0505 February 2021 Correction to Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20345A2362021-01-28028 January 2021 Issuance of Amendment Nos. 307 and 197 to Add Containment Sump Technical Specifications to Address GSI-191 Issues ML21014A1142021-01-12012 January 2021 Correction Letter Notification from Licensee ML20335A0232020-12-28028 December 2020 Issuance of Amendment Nos. 306 and 196 to Remove License Conditions B and C Related to the Irradiated Fuel Management Plans ML20285A2662020-10-21021 October 2020 Correction to Safety Evaluation for Amendment Nos. 305 and 195 Issued September 23, 2020, Modify Primary and Secondary Coolant Activity Technical Specifications ML20213A7312020-09-23023 September 2020 Issuance of Amendment Nos. 305 and 195 to Modify Primary and Secondary Coolant Activity Technical Specifications ML20080H7112020-03-23023 March 2020 Correction Letter for Conforming License Amendments Nos. 304 and 194, Order Approving Transfer of Licenses and Conforming License Amendments ML20030A4402020-02-27027 February 2020 Issuance of Amendment Nos. 304, 194, 299, and 187; Order Approving Transfers of Facility Operating Licenses and Independent Spent Fuel Storage Installation General Licenses and Conforming Amendments ML19326A7592019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Non-Proprietary, Letter & Encl 2-5, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML18348B2062019-02-25025 February 2019 Issuance of Amendment No. 193 Revise Steam Generator Technical Specifications ML18179A4672018-07-30030 July 2018 FENOC-Beaver Valley Power Station, Unit No. 1 and 2; Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit 1 - Issuance of Amendments Request to Adopt TSTF-529, Clarify Use and Application Rules ML18099A2322018-04-18018 April 2018 Correction of an Error in the Renewed Facility Operating License No. DPR-66 Associated with License Amendment No. 301 CAC No. MF3301; EPID L-2013-LLF-0001) ML18022B1162018-03-0101 March 2018 Issuance of Amendment Nos. 302 and 191 Regarding the Use of Optimized Zirlo Fuel Rod Cladding (CAC Nos. MF9580 and MF9581; EPID L-2017-LLA-0201) ML17291A0812018-01-22022 January 2018 Issuance of Amendments Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants (CAC Nos. MF3301 and MF3302; EPID L-2013-LLF-0001) ML18016A1032018-01-19019 January 2018 Correction of Errors in Safety Evaluation Associated with License Amendment Nos. 300 and 189 (CAC Nos. MF8448 and MF8449; EPID L-2016-LLA-0011 and EPID L-2017-LRO-0069) ML17216A5702017-10-12012 October 2017 Issuance of Amendments Emergency Action Level Scheme Changed Based on NEI 99-01, Revision 6 (CAC Nos. MF8448 and MF8449; EPID L-2016-LLA-0011) ML17221A2802017-08-16016 August 2017 Issuance of Amendments to Adopt Technical Specifications Task Force (TSTF) Traveler 547, Revision 1 ML17157B2842017-06-0707 June 2017 Correction to Conforming Amendment No. 187 Order to Transfer License ML17115A1232017-05-30030 May 2017 Issuance of Amendment Application for Order to Transfer License and Conforming Amendment ML17081A5092017-05-11011 May 2017 ISFSI, Davis-Besse ISFSI, Perry Nuclear Power Plant, Perry Nuclear Power Plant ISFSI - Issuance of Amendments Re. Application to Revise Technical Specifications to Adopt TSTF-545 Revision 3 ML17081A4332017-04-14014 April 2017 Nonproprietary, Order Approving Transfer of License and Conforming Amendment ML16040A0842016-06-0707 June 2016 FENOC, Beaver Valley Power Station, Unit Nos. 1 and 2; and Davis-Besse Nuclear Power Station, Unit No. 1 - Issuance of Amendments Revision to Technical Specification 5.3.1, Unit Staff Qualifications ML15294A4392015-12-16016 December 2015 Issuance of Amendments License Amendment Request to Revise Steam Generator Technical Specifications (CAC Nos. MF6054 and 6055) ML15302A4332015-12-0101 December 2015 Issuance of Amendments Request to Change Cyber Security Implementation Plan Milestone 8 Completion Date ML15208A2852015-07-28028 July 2015 Correction to Amendment Nos. 294 and 182 Regarding Modification of Emergency Preparedness Plan Regarding the Emergency Planning Zone Boundary 2024-03-01
[Table view] |
Text
March 23, 2020 Mr. David B. Hamilton Senior Vice President and Chief Nuclear Officer Energy Harbor Nuclear Corp.
341 White Pine Drive Akron, OH 44320
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 - CORRECTION LETTER FOR CONFORMING LICENSE AMENDMENTS NOS. 304 AND 194, RE: ORDER APPROVING TRANSFER OF LICENSES AND CONFORMING LICENSE AMENDMENTS (EPID L-2020-LLM-0000)
Dear Mr. Hamilton:
By letter dated February 27, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20030A440), the U.S. Nuclear Regulatory Commission (NRC) staff issued the following conforming amendments:
- 1. Amendment No. 304 to Renewed Facility Operating License (FOL) No. DPR-66 for Beaver Valley Power Station (BVPS) Unit 1;
- 2. Amendment No. 194 to Renewed FOL No. NPF-73 for BVPS Unit 2;
- 3. Amendment No. 299 to Renewed FOL No. NPF-3 for Davis-Besse Nuclear Power Station, Unit No. 1 (DBNPS); and
- 4. Amendment No. 187 to FOL No. NPF-58 for Perry Nuclear Power PIant, Unit No. 1 (PNPP).
The conforming amendments were to incorporate the transfer of Renewed FOL Nos. DPR-66 and NPF-73 for BVPS, Unit Nos. 1 and 2, and its generally licensed independent spent fuel storage installation (ISFSI); Renewed FOL No. NPF-3 for DBNPS, and its generally licensed ISFSI; and FOL No. NPF-58 for PNPP, and its generally licensed ISFSI. Specifically, the conforming amendments reflected the direct transfer of operating authority for the facilities from FirstEnergy Nuclear Operating Company (FENOC) to Energy Harbor Nuclear Corp.; a direct transfer of ownership of the facilities from FirstEnergy Nuclear Generation, LLC (FENGen) to Energy Harbor Nuclear Generation LLC; and an indirect transfer of ownership of the facilities from FirstEnergy Corp. to Energy Harbor Corp.
The NRC staff identified the following editorial errors:
- On page 1 of the Renewed FOL Nos. DPR-66 and NPF-73 for BVPS Units 1 and 2, in footnote ***, there should not be a -.
D. Hamilton The footnote on page 1 of each Renewed FOL currently reads:
- FirstEnergy -Nuclear Generation, LLC has been renamed Energy Harbor Nuclear Generation LLC.
The footnote on page 1 of each Renewed FOL has been corrected to read:
- FirstEnergy Nuclear Generation, LLC has been renamed Energy Harbor Nuclear Generation LLC.
These errors were inadvertently introduced during the administrative processing of the conforming license amendment. The corrections do not change any of the conclusions associated with the issuance of conforming amendment and do not affect the associated notice to the public. Please replace the Renewed FOL pages with the enclosed corrected pages. We regret any inconvenience caused by these errors.
If you have any questions concerning this action, please contact me at (301) 415-3308 or by e-mail to Bhalchandra.Vaidya@nrc.gov.
Sincerely,
/RA Scott P. Wall for/
Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334, 50-412, 72-1043
Enclosures:
- 1. Revised License Page 1 to Renewed FOL DPR-66
- 2. Revised License Page 1 to Renewed FOL NPF-73 cc:
Mr. Rod L. Penfield Mr. Mark Bezilla Mr. Frank R. Payne Site Vice President Site Vice President Site Vice President Energy Harbor Nuclear Corp. Energy Harbor Nuclear Corp. Energy Harbor Nuclear Corp.
Beaver Valley Power Station Davis-Besse Nuclear Power Perry Nuclear Power Plant Mail Stop A-BV-SSB Station P.O. Box 97, Mail Stop A-PY-A290 P.O. Box 4, Route 168 5501 N. State Route 2 Perry, OH 44081-0097 Shippingport, PA 15077 Mail Stop A-DB-3080 Oak Harbor, OH 43449-9760 Listserv
ENCLOSURE 1 REVISED LICENSE PAGE 1 BEAVER VALLEY POWER STATION, UNIT NO. 1 RENEWED FACILITY OPERATING LICENSE NO. DPR-66 DOCKET NO. 50-334
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 ENERGY HARBOR NUCLEAR CORP.
ENERGY HARBOR NUCLEAR GENERATION LLC DOCKET NO. 50-334 BEAVER VALLEY POWER STATION, UNIT NO. 1 RENEWED FACILITY OPERATING LICENSE License No. DPR-66
- 1. The Nuclear Regulatory Commission (the Commission) having found that:
A. The application to renew Facility Operating License No. DPR-66, filed by FirstEnergy Nuclear Operating Company (FENOC),*, ** acting on its own behalf and as agent for FirstEnergy Nuclear Generation, LLC*** (the licensees), complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I, and all required notifications to other agencies or bodies have been duly made; B. Construction of the Beaver Valley Power Station, Unit No. 1 (facility), has been substantially completed in conformity with Construction Permit No. CPPR-75 and the application, as amended, the provisions of the Act and the rules and regulations of the Commission; C. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; D. There is reasonable assurance: (i) that the activities authorized by this renewed operating license can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the rules and regulations of the Commission; E. Energy Harbor Nuclear Corp. is technically qualified and the licensees are financially qualified to engage in the activities authorized by this renewed operating license in accordance with the rules and regulations of the Commission; F. The licensees have satisfied the applicable provisions of 10 CFR Part 140, "Financial Protection Requirements and Indemnity Agreements," of the Commission's regulations;
- FirstEnergy Nuclear Operating Company has been renamed Energy Harbor Nuclear Corp.
- Energy Harbor Nuclear Corp. is authorized to act as agent for Energy Harbor Nuclear Generation LLC and has exclusive responsibility and control over the physical construction, operation, and maintenance of the facility.
- FirstEnergy Nuclear Generation, LLC has been renamed Energy Harbor Nuclear Generation LLC.
Amendment No. 304 Renewed Operating License DPR-66
ENCLOSURE 2 REVISED LICENSE PAGE 1 BEAVER VALLEY POWER STATION, UNIT NO. 2 RENEWED FACILITY OPERATING LICENSE NO. NPF-73 DOCKET NO. 50-412
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 ENERGY HARBOR NUCLEAR CORP.
ENERGY HARBOR NUCLEAR GENERATION LLC DOCKET NO. 50-412 BEAVER VALLEY POWER STATION, UNIT 2 RENEWED FACILITY OPERATING LICENSE License No. NPF-73
- 1. The Nuclear Regulatory Commission (the Commission or the NRC) has found that:
A. The application to renew Facility Operating License No. NPF-73 filed by FirstEnergy Nuclear Operating Company (FENOC),*, ** acting on its own behalf and as agent for FirstEnergy Nuclear Generation, LLC*** (the licensees), complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's regulations set forth in 10 CFR Chapter I, and all required notifications to other agencies or bodies have been duly made; B. Construction of the Beaver Valley Power Station, Unit 2 (the facility), has been substantially completed in conformity with Construction Permit No. CPPR-105 and the application, as amended, the provisions of the Act, and the regulations of the Commission; C. The facility will operate in conformity with the application, the provisions of the Act, and the regulations of the Commission (except as exempted from compliance in Section 2.D. below);
D. There is reasonable assurance: (i) that the activities authorized by this renewed operating license can be conducted without endangering the health and safety of the public and (ii) that such activities will be conducted in compliance with the Commission's regulations set forth in 10 CFR Chapter I (except as exempted from compliance in Section 2.D. below);
- FirstEnergy Nuclear Operating Company has been renamed Energy Harbor Nuclear Corp.
- Energy Harbor Nuclear Corp. is authorized to act as agent for Energy Harbor Nuclear Generation LLC and has exclusive responsibility and control over the physical construction, operation, and maintenance of the facility.
- FirstEnergy Nuclear Generation, LLC has been renamed Energy Harbor Nuclear Generation LLC.
Amendment No. 194 Renewed Operating License NPF-73
ML20080H711 *via e-mail OFFICE NRR/DORL/LPL3/PM* NRR/DORL/LPL3/LA* NRR/DORL/LPL3/BC* NRR/DORL/LPL3/PM*
NAME BVaidya (SWall for) JBurkhardt NSalgado BVaidya (SWall for)
DATE 03/20/2020 03/20/2020 03/23/2020 03/23/2020