| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406 | | {{#Wiki_filter:March 4, 2019 |
| -2713 March 4, 2019 Mr. Bryan Hanson Senior Vice President, Exelon Generation President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 SUBJECT: ANNUAL ASSESSMENT LETTER FOR THREE MILE ISLAND STATION, UNIT 1 (REPORT 05000 289/2018006)
| |
|
| |
|
| ==Dear Mr. Hanson ,== | | ==SUBJECT:== |
| The NRC has completed its end
| | ANNUAL ASSESSMENT LETTER FOR THREE MILE ISLAND STATION, UNIT 1 January 1, 2018 |
| -of-cycle performance assessment of Three Mile Island Station, Unit 1, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2018 , through December 31, 201 This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facilit The NRC concluded that overall performance at your facility preserved public health and safet The NRC determined the performance at Three Mile Island Station, Unit 1, during the most recent quarter was within the Licensee Response Column (Column 1) of the NRC's Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, "Operating Reactor Assessment Program,"
| | |
| because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at Three Mile Island Station, Unit The enclosed inspection plan lists the inspections scheduled through December 31, 202 This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondenc The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issue Routine inspections performed by resident inspectors are not included in the inspection pla You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY
| | ==subject== |
| -18-0113, "Recommendations for Modifying the Reactor Oversight Process Engineering Inspections").
| | to change in scope, as well as schedule, beginning in January 202 In a letter (ML17171A151) dated June 20, 201 7, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(1)(i), you notified the NRC of your intent to permanently cease power operations at Three Mile Island Station, Unit 1 no later than September 30, 201 Therefore, the inspection schedule is tentative and may be revise Once you formally notify the NRC in accordance with 10 CFR 50.82(a)(1)(ii) that Three Mile Island Station, Unit 1 is permanently shutdown and that all the nuclear fuel has been removed from the reactor vessel, then Three Mile Island Station, Unit 1 will transition from NRC IMC 0305, "Operating Reactor Assessment Program," and IMC 2515, "Light |
| Should these changes to the ROP be implemented, the engineering and other region
| |
| -based inspections are subject to change in scope, as well as schedule, beginning in January 202 In a letter (ML17171A151) dated June 20, 201 7, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(1)(i), you notified the NRC of your intent to permanently cease power operations at Three Mile Island Station, Unit 1 no later than September 30, 201 Therefore, the inspection schedule is tentative and may be revise Once you formally notify the NRC in accordance with 10 CFR 50.82(a)(1)(ii) that Three Mile Island Station, Unit 1 is permanently shutdown and that all the nuclear fuel has been removed from the reactor vessel, then Three Mile Island Station, Unit 1 will transition from NRC IMC 0305, "Operating Reactor Assessment Program," and IMC 2515, "Light
| |
| -Water Reactor Inspection Program - Operations Phase," to IMC 2561, "Decommissioning Power Reactor Inspection Program." The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any change B. Hanson 2 Finally, the Reactor Oversight Process and Inspection Program provides inherent flexibility to permit inspection sampling adjustments using IMC 2515, Appendix G, "Baseline Inspection Guidance for Power Reactors Preparing for Transition to Decommissioning Phase." | | -Water Reactor Inspection Program - Operations Phase," to IMC 2561, "Decommissioning Power Reactor Inspection Program." The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any change B. Hanson 2 Finally, the Reactor Oversight Process and Inspection Program provides inherent flexibility to permit inspection sampling adjustments using IMC 2515, Appendix G, "Baseline Inspection Guidance for Power Reactors Preparing for Transition to Decommissioning Phase." |
|
| |
|
|
---|
Category:Inspection Plan
MONTHYEARML22011A1312022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML21012A4342021-01-13013 January 2021 Security Inspection Plan ML20015A5772020-01-15015 January 2020 Security and Emergency Preparedness Inspection Plan for Three Mile Island Generating Station, Unit 1 IR 05000289/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000289/2019005 IR 05000289/20180062019-03-0404 March 2019 Annual Assessment Letter for Three Mile Island Station, Unit 1 (Report 05000289/2018006) IR 05000289/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000289/2018005 IR 05000289/20170062018-02-28028 February 2018 Annual Assessment Letter for Three Mile Island Station-Unit 1 (Reports 05000289-2017006 and 05000289-2017402 and 05000289-2017501) IR 05000289/20170052017-08-28028 August 2017 Updated Inspection Plan for Three Mile Island Station, Unit 1, with Report 22 (Report 05000289/2017005) IR 05000289/20160062017-03-0101 March 2017 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2016006) IR 05000289/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2016005) IR 05000289/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2015006) IR 05000289/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2015005) IR 05000289/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2014001) IR 05000289/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000289-14-006 IR 05000289/20130012014-03-0404 March 2014 ROP-14 2013 Three Mile Island Nuclear Station Unit 1, Annual Assessment Letter, Report 05000289/2013001, and Inspection Plan IR 05000289/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000289-13-006 IR 05000289/20120012013-03-0404 March 2013 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289-12-001) IR 05000289/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Three Mile Island Nuclear Station (Report 05000289/2012006) TMI-12-069, Submittal of Inspection Plan for Reactor Internals2012-04-16016 April 2012 Submittal of Inspection Plan for Reactor Internals IR 05000289/20110012012-03-0505 March 2012 Annual Assessment Letter for Three Mile Island Nuclear Generating Station Unit 1 (Report 05000289-11-001) ML1124206742011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Three Mile Island IR 05000289/20100012011-03-0404 March 2011 Annual Assessment Letter for Three Mile Island Nuclear Generating Station, Unit 1, EOC-11 (Report 05000289-10-001) ML1024407172010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Three Mile Island ML1006213042010-03-0303 March 2010 Annual Performance Review and Inspection Plan Three Mile Island 2009 EOC Letter and Report 22 (05000289-10-001) ML0924402202009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Three Mile Island (September 1, 2009) IR 05000289/20090012009-03-0404 March 2009 Annual Assessment Letter - Three Mile Island Unit 1 (05000289/2009001) IR 05000289/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Three Mile Island (Report 05000289/2008001) ML0734706292007-12-13013 December 2007 ROP 8 - Three Mile Island - Change to Inspection Plan, 12/13/07 ML0724309352007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan IR 05000289/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Three Mile Island (05000289/2007001) ML0706004472006-10-31031 October 2006 1R21 Outage - NRC Inspection Question Log Complied by Amergen (12 Pages) ML0606202072006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Three Mile Island Unit 1 (Report 05-289/2006001) ML0524207232005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Three Mile Island, Unit 1 ML0424401732004-08-30030 August 2004 TMI ROP5 Mid-Cycle Performance Review and Inspection Plan ML0323907022003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for TMI, Unit 1 IR 05000289/20030012003-03-0404 March 2003 2003-Annual Assessment Letter - Three Mile Island, Unit 1 (Report No. 50-289/2003-001) ML0223803152002-08-26026 August 2002 2002 Three Mile Island Unit 1 Mid-Cycle Performance Review & Inspection Plan IR 05000289/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Three Mile Island Station, Unit 1 (Report 50-289/02-01) 2022-01-31
[Table view] Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24242A3032024-09-0909 September 2024 Letter - Three Mile Island Station, Unit 2, Issuance of Amendment No. 68, Historic and Cultural Resources IR 05000320/20240012024-08-28028 August 2024 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report Nos. 05000320/2024001 and 05000320/2024002 ML24240A2222024-08-27027 August 2024 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 6 ML24220A2742024-08-15015 August 2024 Request for Additional Information Clarification Call Regarding Three Mile Island Station, Unit 2, Amended Post-Shutdown Decommissioning Activities Report, Rev. 6 ML24135A3292024-08-0909 August 2024 Amendment No 68, Historic and Cultural Resources Cover Letter IR 07200077/20240012024-06-18018 June 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 07200077/2024001 ML24135A1972024-06-13013 June 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0091 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24157A3672024-06-13013 June 2024 Updated Post-Shutdown Decommissioning Activities Report Request for Additional Information Transmittal Letter ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24120A3242024-05-24024 May 2024 TMI-2 Email to Fws RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24121A2472024-04-29029 April 2024 and Three Mile Island, Unit 2 - 2023 Occupational Radiation Exposure Annual Report ML24120A2552024-04-29029 April 2024 Annual Radiological Environmental Operating Report ML24113A0212024-04-18018 April 2024 (TMI-2), Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24065A0042024-03-28028 March 2024 Submittal of 2023 Aircraft Movement Data Annual Report ML24088A0122024-03-28028 March 2024 Notification of Amended Post-Shutdown Decommissioning Activities Report (PSDAR) in Accordance with 10 CFR 50.82(a)(7), Revision 6 ML24092A0012024-03-28028 March 2024 (TMI-2), Decommissioning Trust Fund Annual Report ML24085A2152024-03-25025 March 2024 (TMI-2) - Annual Notification of Property Insurance Coverage RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. ML24052A0602024-03-20020 March 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0061 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24074A3922024-03-14014 March 2024 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML24075A0062024-03-14014 March 2024 List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24073A2312024-03-13013 March 2024 and Three Mile Island Nuclear Station, Unit 2 - Management Change ML24044A0092024-02-12012 February 2024 License Amendment Request – Three Mile Island, Unit 2, Historic and Cultural Resources Review, Response to Request for Additional Information IR 05000320/20230042024-02-0707 February 2024 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023004 ML24038A0222024-02-0505 February 2024 Achp Letter on Section 106 Programmatic Agreement Participation IR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 ML23342A1242024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23325A1092024-01-0505 January 2024 Review of the Management Plan for Three Mile Island Station, Unit No. 2, Debris Material ML23354A2112023-12-20020 December 2023 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML23354A2062023-12-20020 December 2023 (TMI-2), Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 ML23243A9082023-08-29029 August 2023 Shpo Letter to TMI-2 Regarding Section 106 Activities IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 ML23216A1772023-08-14014 August 2023 Consultation Letter to Rebecca Countess for TMI-2 ML23216A1782023-08-14014 August 2023 Consultation Letter to Steve Letavic for TMI-2 ML23216A1732023-08-14014 August 2023 Consultation Letter to Christine Turner for TMI-2 ML23216A1752023-08-14014 August 2023 Consultation Letter to Joanna Cain for TMI-2 ML23216A1742023-08-14014 August 2023 Consultation Letter to David Morrison for TMI-2 ML23221A1402023-08-0808 August 2023 (TMI-2), Response to Requests for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML23200A1882023-07-31031 July 2023 TMI-2 Correction Letter Amendment 67 ML23209A7632023-07-28028 July 2023 Letter from PA Shpo to TMI-2 Solutions on Cultural and Historic Impacts of Decommissioning ML23192A8272023-07-10010 July 2023 TMI-2 Solutions, LLC - Response to Shpo Request for Additional Information for Er Project 2021PR03278.006, TMI-2 Decommissioning Project ML23167A4642023-07-0505 July 2023 Letter - TMI-2- Exemption 10 CFR Part 20 Append G Issuance ML23167A0312023-06-28028 June 2023 Acceptance Review and Schedule for the Request for Exemption from a Requirement from 10 CFR 20, Appendix G, Section Iii.E, EPID L-2023-LLE-0016 ML23171B0222023-06-19019 June 2023 (TMI-2) - Notification Pursuant to 10 CFR 72.140(d) Regarding Application of Previously Approved TMI-2 Quality Assurance Program to Independent Spent Fuel Storage Installation Activities ML23138A0662023-05-17017 May 2023 TMI-2 NHPA Section 106 Shpo Letter to NRC 5-17-23 2024-09-09
[Table view] |
Text
March 4, 2019
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR THREE MILE ISLAND STATION, UNIT 1 January 1, 2018
subject
to change in scope, as well as schedule, beginning in January 202 In a letter (ML17171A151) dated June 20, 201 7, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(1)(i), you notified the NRC of your intent to permanently cease power operations at Three Mile Island Station, Unit 1 no later than September 30, 201 Therefore, the inspection schedule is tentative and may be revise Once you formally notify the NRC in accordance with 10 CFR 50.82(a)(1)(ii) that Three Mile Island Station, Unit 1 is permanently shutdown and that all the nuclear fuel has been removed from the reactor vessel, then Three Mile Island Station, Unit 1 will transition from NRC IMC 0305, "Operating Reactor Assessment Program," and IMC 2515, "Light
-Water Reactor Inspection Program - Operations Phase," to IMC 2561, "Decommissioning Power Reactor Inspection Program." The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any change B. Hanson 2 Finally, the Reactor Oversight Process and Inspection Program provides inherent flexibility to permit inspection sampling adjustments using IMC 2515, Appendix G, "Baseline Inspection Guidance for Power Reactors Preparing for Transition to Decommissioning Phase."
These adjustments are be made in order to better inform our assessment of performance during this unique period of operations prior to permanent plant shutdown
. In addition, the NRC will be implementing quarterly assessment reviews, consistent with the guidance contained in IMC 0305, "Operating Reactor Assessment Program," in order to more closely monitor and review overall plant activities to assure that there are no issues emerging that might indicate a decline in focus on the safe operation of the facilit In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC
's Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC's Website at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 610-337-5205 with any questions you have regarding this lette
Sincerely,
/RA/ Matt hew Young, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No. 50-289 License No
. DPR-50 Enclosure:
Three Mile Island Inspection Plan
ML19064B356 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME SShaffer MYoung DATE 2/26/19 2/27/19 Three Mile Island
01/01/2019 - 12/31/2020
Unit Start End Activity CAC Title Staff Count
RAD SAFETY 01,02,03,04
1 02/11/2019
02/15/2019
IP 71124.01
000725 Radiological Hazard Assessment and Exposure Controls
02/11/2019
02/15/2019
IP 71124.02
000726 Occupational ALARA Planning and Controls
ACCESS AUTH & CONTROL, FITNESS FOR DUTY
1 02/25/2019
03/01/2019
IP 71130.01
000733 Access Authorization
02/25/2019
03/01/2019
IP 71130.02
000734 Access Control
02/25/2019
03/01/2019
IP 71130.06
000738 Protection of Safeguards Information
02/25/2019
03/01/2019
IP 71130.08
000740 Fitness For Duty Program
02/25/2019
03/01/2019
IP 71151 001338 Performance Indicator Verification
TMI REQUAL INSP WITH P/F RESULTS
1 03/17/2019
03/22/2019
IP 71111.11A
000703 Licensed Operator Requalification Program and Licensed Operator Performance (Annual)
03/17/2019
03/22/2019
IP 71111.11B
000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)
Radwaste
1 03/18/2019
03/22/2019
IP 71124.08
000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and
Transportation
EP EXERCISE INSPECTION
1 05/06/2019
05/10/2019
IP 71114.01
000716 Exercise Evaluation
05/06/2019
05/10/2019
IP 71151 001397 Performance Indicator Verification
TMI INITIAL OL EXAM
1 05/12/2019
05/17/2019
OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
06/09/2019
06/14/2019
EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
RAD SAFETY REMP
1 06/10/2019
06/14/2019
IP 71124.07
000731 Radiological Environmental Monitoring Program
06/10/2019
06/14/2019
IP 71151 000746 Performance Indicator Verification
Triennial Heat Sink
1 06/16/2019
06/22/2019
IP 71111.07T
000700 Heat Sink Performance -Triennial
2/22/2019 9:42:30 AM
Page
of
This report does not include INPO and OUTAGE activitie This report shows only on-site and announced inspection procedure IP 22 Inspection Activity Plan Report
Three Mile Island
01/01/2019 - 12/31/2020
Unit Start End Activity CAC Title Staff Count
50.59 PROCESS
1 07/14/2019
07/20/2019
IP 71111.17T
000709 Evaluations of Changes, Tests, and Experiments
RAD SAFETY OUT 01,02,03,04
1 09/30/2019
10/04/2019
IP 71124.01
000725 Radiological Hazard Assessment and Exposure Controls
09/30/2019
10/04/2019
IP 71124.02
000726 Occupational ALARA Planning and Controls
09/30/2019
10/04/2019
IP 71124.03
000727 In-Plant Airborne Radioactivity Control and Mitigation
09/30/2019
10/04/2019
IP 71124.04
000728 Occupational Dose Assessment
Inservice Inspection
1 10/06/2019
10/19/2019
IP 71111.08P
000702 Inservice Inspection Activities (PWR)
EQ PROGRAM
1 11/04/2019
11/08/2019
IP 71111.21N
000714 Design Bases Assurance Inspection (Programs)
11/18/2019
11/22/2019
IP 71111.21N
000714 Design Bases Assurance Inspection (Programs)
RAD SAFETY 01,02,03,04
1 11/18/2019
11/22/2019
IP 71124.01
000725 Radiological Hazard Assessment and Exposure Controls
11/18/2019
11/22/2019
IP 71124.02
000726 Occupational ALARA Planning and Controls
11/18/2019
11/22/2019
IP 71124.03
000727 In-Plant Airborne Radioactivity Control and Mitigation
11/18/2019
11/22/2019
IP 71124.04
000728 Occupational Dose Assessment
11/18/2019
11/22/2019
IP 71151 000746 Performance Indicator Verification
Rad Safety Insp
1 01/06/2020
01/10/2020
IP 71124.01
000725 Radiological Hazard Assessment and Exposure Controls
01/06/2020
01/10/2020
IP 71124.02
000726 Occupational ALARA Planning and Controls
01/06/2020
01/10/2020
IP 71124.03
000727 In-Plant Airborne Radioactivity Control and Mitigation
01/06/2020
01/10/2020
IP 71124.04
000728 Occupational Dose Assessment
PI&R Biennial Team Inspection
1 01/20/2020
01/24/2020
IP 71152B 000747 Problem Identification and Resolution
02/10/2020
02/14/2020
IP 71152B 000747 Problem Identification and Resolution
THREE MILE ISLAND EP PROGRAM INSPECTION
1 03/09/2020
03/13/2020
IP 71114.02
000717 Alert and Notification System Testing
03/09/2020
03/13/2020
IP 71114.03
000718 Emergency Response Organization Staffing and Augmentation System
2/22/2019 9:42:30 AM
Page
of
This report does not include INPO and OUTAGE activitie This report shows only on-site and announced inspection procedure IP 22 Inspection Activity Plan Report
Three Mile Island
01/01/2019 - 12/31/2020
Unit Start End Activity CAC Title Staff Count
THREE MILE ISLAND EP PROGRAM INSPECTION
1 03/09/2020
03/13/2020
IP 71114.05
000720 Maintenance of Emergency Preparedness
03/09/2020
03/13/2020
IP 71151 001397 Performance Indicator Verification
Rad Safety RETS
1 03/23/2020
03/27/2020
IP 71124.06
000730 Radioactive Gaseous and Liquid Effluent Treatment
03/23/2020
03/27/2020
IP 71151 000746 Performance Indicator Verification
TRIENNIAL FIRE PROTECTION
1 05/04/2020
05/08/2020
IP 71111.05T
000696 Fire Protection (Triennial)
05/18/2020
05/22/2020
IP 71111.05T
000696 Fire Protection (Triennial)
Material Control and Accountability
1 06/01/2020
06/05/2020
IP 71130.11
000742 Material Control and Accounting (MC&A)
Rad Safety Rad Insts
1 07/06/2020
07/10/2020
IP 71124.05
000729 Radiation Monitoring Instrumentation
CYBER FULL IMP
1 07/20/2020
07/24/2020
IP 71130.10P
000741 Cyber Security
08/03/2020
08/07/2020
IP 71130.10P
000741 Cyber Security
Rad Safety Insp
1 12/14/2020
12/18/2020
IP 71124.01
000725 Radiological Hazard Assessment and Exposure Controls
12/14/2020
12/18/2020
IP 71124.02
000726 Occupational ALARA Planning and Controls
12/14/2020
12/18/2020
IP 71124.03
000727 In-Plant Airborne Radioactivity Control and Mitigation
12/14/2020
12/18/2020
IP 71124.04
000728 Occupational Dose Assessment
12/14/2020
12/18/2020
IP 71151 000746 Performance Indicator Verification
2/22/2019 9:42:30 AM
Page
of
This report does not include INPO and OUTAGE activitie This report shows only on-site and announced inspection procedure IP 22 Inspection Activity Plan Report