Category:Inspection Plan
MONTHYEARML22011A1312022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML21012A4342021-01-13013 January 2021 Security Inspection Plan ML20015A5772020-01-15015 January 2020 Security and Emergency Preparedness Inspection Plan for Three Mile Island Generating Station, Unit 1 IR 05000289/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000289/2019005 IR 05000289/20180062019-03-0404 March 2019 Annual Assessment Letter for Three Mile Island Station, Unit 1 (Report 05000289/2018006) IR 05000289/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000289/2018005 IR 05000289/20170062018-02-28028 February 2018 Annual Assessment Letter for Three Mile Island Station-Unit 1 (Reports 05000289-2017006 and 05000289-2017402 and 05000289-2017501) IR 05000289/20170052017-08-28028 August 2017 Updated Inspection Plan for Three Mile Island Station, Unit 1, with Report 22 (Report 05000289/2017005) IR 05000289/20160062017-03-0101 March 2017 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2016006) IR 05000289/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2016005) IR 05000289/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2015006) IR 05000289/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2015005) IR 05000289/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2014001) IR 05000289/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000289-14-006 IR 05000289/20130012014-03-0404 March 2014 ROP-14 2013 Three Mile Island Nuclear Station Unit 1, Annual Assessment Letter, Report 05000289/2013001, and Inspection Plan IR 05000289/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000289-13-006 IR 05000289/20120012013-03-0404 March 2013 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289-12-001) IR 05000289/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Three Mile Island Nuclear Station (Report 05000289/2012006) TMI-12-069, Submittal of Inspection Plan for Reactor Internals2012-04-16016 April 2012 Submittal of Inspection Plan for Reactor Internals IR 05000289/20110012012-03-0505 March 2012 Annual Assessment Letter for Three Mile Island Nuclear Generating Station Unit 1 (Report 05000289-11-001) ML1124206742011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Three Mile Island IR 05000289/20100012011-03-0404 March 2011 Annual Assessment Letter for Three Mile Island Nuclear Generating Station, Unit 1, EOC-11 (Report 05000289-10-001) ML1024407172010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Three Mile Island ML1006213042010-03-0303 March 2010 Annual Performance Review and Inspection Plan Three Mile Island 2009 EOC Letter and Report 22 (05000289-10-001) ML0924402202009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Three Mile Island (September 1, 2009) IR 05000289/20090012009-03-0404 March 2009 Annual Assessment Letter - Three Mile Island Unit 1 (05000289/2009001) IR 05000289/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Three Mile Island (Report 05000289/2008001) ML0734706292007-12-13013 December 2007 ROP 8 - Three Mile Island - Change to Inspection Plan, 12/13/07 ML0724309352007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan IR 05000289/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Three Mile Island (05000289/2007001) ML0706004472006-10-31031 October 2006 1R21 Outage - NRC Inspection Question Log Complied by Amergen (12 Pages) ML0606202072006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Three Mile Island Unit 1 (Report 05-289/2006001) ML0524207232005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Three Mile Island, Unit 1 ML0424401732004-08-30030 August 2004 TMI ROP5 Mid-Cycle Performance Review and Inspection Plan ML0323907022003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for TMI, Unit 1 IR 05000289/20030012003-03-0404 March 2003 2003-Annual Assessment Letter - Three Mile Island, Unit 1 (Report No. 50-289/2003-001) ML0223803152002-08-26026 August 2002 2002 Three Mile Island Unit 1 Mid-Cycle Performance Review & Inspection Plan IR 05000289/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Three Mile Island Station, Unit 1 (Report 50-289/02-01) 2022-01-31
[Table view] Category:Inspection Report
MONTHYEARIR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 IR 05000320/20230012023-04-12012 April 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report No. 05000320/2023001 IR 05000320/20220042023-02-16016 February 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report Nos. 05000320/2022004 and 05000320/2022401 IR 05000289/20220022023-02-13013 February 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 NRC Inspection Report Nos. 05000289/2022002 and 005000289/2022402 IR 05000289/20220012022-08-26026 August 2022 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report Nos. 05000289/2022001 and 07200077/2022001 ML22228A0142022-08-17017 August 2022 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report IR 05000289/20224012022-04-12012 April 2022 NRC Security Decommissioning Inspection Report No. 05000289/2022401 IR 05000289/20210022022-01-31031 January 2022 NRC Inspection Report 05000289/2021002 and 07200077/2021001 IR 05000320/20210042022-01-27027 January 2022 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2021004 IR 05000289/20210012021-06-28028 June 2021 NRC Inspection Report No. 05000289/2021001, Exelon Generation Co., LLC, Three Mile Island Nuclear Station, Unit 1 IR 05000289/20214012021-06-28028 June 2021 Security Decommissioning Inspection Report 05000289/2021401 IR 05000320/20210032021-06-22022 June 2021 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2021003 IR 05000289/20200052021-02-0101 February 2021 NRC Inspection Report No. 05000289/2020005, Exelon Generation Co., LLC, Three Mile Island Nuclear Station Unit 1 IR 05000320/20200022020-10-19019 October 2020 Gpu Nuclear, Inc., Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report 05000320/2020002 IR 05000289/20204012020-09-0101 September 2020 Unit 1 - Security Baseline Inspection Report 05000289/2020401 IR 05000289/20200032020-07-20020 July 2020 NRC Inspection Report No. 05000289/2020003, Exelon Generation Co., LLC, Three Mile Island Nuclear Station, Unit 1 IR 05000289/20200012020-04-30030 April 2020 NRC Inspection Report 05000289/2020001 IR 05000289/20190102020-02-0404 February 2020 NRC Inspection Report No. 05000289/2019010, Exelon Generation Co., LLC, Three Mile Island Unit 1, Middletown, PA IR 05000289/20190032019-11-0606 November 2019 Integrated Inspection Report 05000289/2019003 IR 05000289/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000289/2019005 IR 05000289/20193012019-08-15015 August 2019 Initial Operator Licensing Examination Report 05000289/2019301 IR 05000289/20190022019-08-0909 August 2019 Integrated Inspection Report 05000289/2019002 IR 05000320/20190012019-06-10010 June 2019 Gpu Nuclear, Inc., Three Mile Island Station, Unit 2 - NRC Inspection Report 05000320/2019001 IR 05000289/20195012019-06-0303 June 2019 Emergency Preparedness Biennial Exercise Inspection Report 05000289/2019501 IR 05000289/20194102019-03-18018 March 2019 Baseline Security Inspection Report 05000289/2019410 IR 05000289/20180062019-03-0404 March 2019 Annual Assessment Letter for Three Mile Island Station, Unit 1 (Report 05000289/2018006) IR 05000289/20180042019-01-31031 January 2019 Integrated Inspection Report 5000289/2018004 IR 05000289/20182012018-12-13013 December 2018 NRC Inspection Report 05000289/2018201 IR 05000289/20180032018-11-0808 November 2018 Integrated Inspection Report 5000289/2018003 IR 05000289/20184102018-09-18018 September 2018 Baseline Security Inspection Report 05000289/2018410 (Letter Only) IR 05000289/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000289/2018005 IR 05000289/20180022018-08-0202 August 2018 Integrated Inspection Report 5000289/2018002 IR 05000320/20180112018-05-23023 May 2018 NRC Inspection Report 05000320/2018011 IR 05000289/20180102018-05-0202 May 2018 Design Bases Assurance Inspection (Teams) Report 05000289/2018010 IR 05000289/20180012018-05-0202 May 2018 Integrated Inspection Report 5000289/2018001 and Exercise of Enforcement Discretion IR 05000289/20170062018-02-28028 February 2018 Annual Assessment Letter for Three Mile Island Station-Unit 1 (Reports 05000289-2017006 and 05000289-2017402 and 05000289-2017501) IR 05000289/20170042018-01-25025 January 2018 Integrated Inspection Report 05000289-2017004 IR 05000289/20174052017-11-29029 November 2017 Problem Identification and Resolution Cyber Security Inspection Report 05000289/2017405 (Cover Letter) IR 05000289/20170032017-10-25025 October 2017 Integrated Inspection Report 5000289/2017003 IR 05000289/20174032017-09-25025 September 2017 Baseline Security Inspection Report 05000289/2017403 (Cover Letter) IR 05000289/20170052017-08-28028 August 2017 Updated Inspection Plan for Three Mile Island Station, Unit 1, with Report 22 (Report 05000289/2017005) IR 05000289/20170102017-08-25025 August 2017 Susquehanna Steam Electric Station, Units 1 and 2 - Problem Identification and Resolution Cyber Security Inspection Report 05000387/2017405 and 05000388/2017405 (Cover Letter) IR 05000289/20173012017-08-23023 August 2017 Initial Operator Licensing Examination Report 05000289/2017301 IR 05000289/20170022017-08-0808 August 2017 Integrated Inspection Report 05000289/2017002 IR 05000320/20170092017-07-17017 July 2017 Gpu Nuclear, Inc., Three Mile Island Station, Unit 2 - NRC Inspection Report 05000320/2017009 IR 05000289/20170082017-07-11011 July 2017 NRC Investigation Report No. 1-2016-008 and Three Mile Island, Unit 1 - Inspection Report 05000289/2017008 IR 05000289/20174042017-06-20020 June 2017 Material Control and Accounting Program Inspection Report 05000289/2017404 (Letter Only) 2024-01-29
[Table view] Category:Letter
MONTHYEARML24038A0222024-02-0505 February 2024 Achp Letter on Section 106 Programmatic Agreement Participation IR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 ML23342A1242024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23325A1092024-01-0505 January 2024 Review of the Management Plan for Three Mile Island Station, Unit No. 2, Debris Material ML23354A2062023-12-20020 December 2023 (TMI-2), Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23354A2112023-12-20020 December 2023 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 ML23243A9082023-08-29029 August 2023 Shpo Letter to TMI-2 Regarding Section 106 Activities IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 ML23216A1742023-08-14014 August 2023 Consultation Letter to David Morrison for TMI-2 ML23216A1772023-08-14014 August 2023 Consultation Letter to Rebecca Countess for TMI-2 ML23216A1752023-08-14014 August 2023 Consultation Letter to Joanna Cain for TMI-2 ML23216A1732023-08-14014 August 2023 Consultation Letter to Christine Turner for TMI-2 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 ML23216A1782023-08-14014 August 2023 Consultation Letter to Steve Letavic for TMI-2 ML23221A1402023-08-0808 August 2023 (TMI-2), Response to Requests for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML23200A1882023-07-31031 July 2023 TMI-2 Correction Letter Amendment 67 ML23209A7632023-07-28028 July 2023 Letter from PA Shpo to TMI-2 Solutions on Cultural and Historic Impacts of Decommissioning ML23192A8272023-07-10010 July 2023 TMI-2 Solutions, LLC - Response to Shpo Request for Additional Information for Er Project 2021PR03278.006, TMI-2 Decommissioning Project ML23167A4642023-07-0505 July 2023 Letter - TMI-2- Exemption 10 CFR Part 20 Append G Issuance ML23167A0312023-06-28028 June 2023 Acceptance Review and Schedule for the Request for Exemption from a Requirement from 10 CFR 20, Appendix G, Section Iii.E, EPID L-2023-LLE-0016 ML23171B0222023-06-19019 June 2023 (TMI-2) - Notification Pursuant to 10 CFR 72.140(d) Regarding Application of Previously Approved TMI-2 Quality Assurance Program to Independent Spent Fuel Storage Installation Activities ML23137A2822023-05-17017 May 2023 (TMI-2), Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML23138A0662023-05-17017 May 2023 TMI-2 NHPA Section 106 Shpo Letter to NRC 5-17-23 ML23026A3132023-05-0202 May 2023 Issuance of Exemption from 10 CFR 70.24 (EPID-L-2023-LLE-0003) ML23122A1842023-05-0101 May 2023 Shpo_Er_Summary_Letter ML23121A2492023-05-0101 May 2023 License Amendment Request, Historic and Cultural Resources Review, Response to Request for Additional Information ML23117A0012023-04-26026 April 2023 Commitment Revision Summary Report ML23027A0832023-04-24024 April 2023 Environmental Assessment/Finding of No Significant Impact - Request for Exemption from 10 CFR 70.24 ML23108A0802023-04-18018 April 2023 Annual Radiological Effluent Release Report ML23108A0822023-04-18018 April 2023 Annual Radiological Environmental Operating Report IR 05000320/20230012023-04-12012 April 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report No. 05000320/2023001 ML23102A0382023-04-10010 April 2023 Occupational Radiation Exposure Annual Report ML23108A2002023-04-10010 April 2023 CFR 20.2206(b) Personnel Radiation Exposure Report for 2022 ML23094A2582023-04-0606 April 2023 Letter to Sidney Hill, Chief, Onondaga Nation, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23093A0572023-04-0606 April 2023 Letter to Joanna Cain, President, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2362023-04-0606 April 2023 Letter to Carissa Speck, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2542023-04-0606 April 2023 Ltr J Bendremer Thpo Stockbridge-Munsee Community Band of Mohican Indians Re Initiation of Consultation Under Section 106 of the NHPA for Proposed License Amendment Request for TMI 2 ML23086C0652023-04-0606 April 2023 Ltr Larry Heady, Thpo, De. Tribe of Indian; Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI Nuclear Station, Unit 2 ML23093A0562023-04-0606 April 2023 Letter to Steve Minnick, Site Decommissioning Director, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2602023-04-0606 April 2023 Letter to William Tarrant, Seneca-Cayuga Nation, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23094A2392023-04-0606 April 2023 Letter to Courtney Gerzetich, Thpo, Onedia Nation of Wisconsin, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23093A0592023-04-0606 April 2023 Letter to Rebecca Countess, Chair, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 2024-02-05
[Table view] |
Text
[Addressee, First UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION I
2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 September 2, 2014 Mr. Michael Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.
Warrenville, IL 60555 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR THREE MILE ISLAND NUCLEAR STATION, UNIT 1 (REPORT 05000289/2014006)
Dear Mr. Pacilio:
On August 13, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Three Mile Island Nuclear Station, Unit No. 1. The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from July 1, 2013 through June 30, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Three Mile Island Nuclear Station, Unit No. 1 was operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Three Mile Island Nuclear Station, Unit No. 1 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all performance indicators demonstrated that your performance was within the nominal, expected range (i.e, green). Therefore, the NRC plans to conduct Reactor Oversight Process baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff.
A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 will reflect this revision to Inspection Manual Chapter (IMC)
0310. During the 2014 mid-cycle assessment review, cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310, and were evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's Agencywide Document Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610)337-5046 with any questions you have regarding this letter.
Sincerely,
/RA/
Silas R. Kennedy, Chief Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-289 License Nos.: DPR-50 Enclosure: Inspection Plan cc w/encl: Distribution via ListServ
ML14239A219 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME DWerkheiser/ LC for LCline/ LC SKennedy/ SRK DATE 08/26/14 08/26/14 08/ 27/14 Distribution w/encl:
W. Dean, RA D. Lew, DRA H. Nieh, DRP M. Scott, DRP J. Trapp, DRS B. Welling, DRS S. Kennedy, DRP L. Cline, Acting, DRP C. Roettgen, DRP B. Bollinger, DRP D. Werkheiser, DRP, SRI J. Heinly, DRP, RI A. Diaz, DRP, AA A. Bowers, RI OEDO R. J. Powell, DRP DRS Branch Chiefs (6)
N. McNamara, RI, SLO D. Tifft, RI, SLO D. Screnci, RI, PAO N. Sheehan, RI, PAO RidsNrrDirslpab Resource ROPassessment Resource RidsNrrPMThreeMileIsland Resource RidsNrrDorlLpl1-2 Resource ROPReports Resource
Page 1 of 2 Three Mile Island 08/26/2014 09:35:14 Inspection / Activity Plan Report 22 07/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - RAD SAFETY INSPECTIONS 1 1 11/03/2014 11/07/2014 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 11/03/2014 11/07/2014 IP 71151 Performance Indicator Verification CDBI - COMPONENT DESIGN BASIS INSPECTION 7 1 01/26/2015 01/30/2015 IP 7111121 Component Design Bases Inspection 1 02/09/2015 02/13/2015 IP 7111121 Component Design Bases Inspection 1 02/23/2015 02/27/2015 IP 7111121 Component Design Bases Inspection 71124 - RAD SAFETY INSPECTION 1 1 03/09/2015 03/13/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 03/09/2015 03/13/2015 IP 71124.02 Occupational ALARA Planning and Controls 1 03/09/2015 03/13/2015 IP 71124.04 Occupational Dose Assessment 7111111B - REQUAL INSP W/ P/F RESULTS 2 1 03/16/2015 03/20/2015 IP 7111111B Licensed Operator Requalification Program EP - EP EXERCISE 8 1 04/13/2015 04/17/2015 IP 7111401 Exercise Evaluation 1 04/13/2015 04/17/2015 IP 7111408 Exercise Evaluation - Scenario Review 71124 - RAD SAFETY INSP 1 1 05/11/2015 05/15/2015 IP 71124.02 Occupational ALARA Planning and Controls 1 05/11/2015 05/15/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 05/11/2015 05/15/2015 IP 71124.04 Occupational Dose Assessment 10/12EXM - INITIAL OL EXAM 4 1 08/31/2015 09/04/2015 U01913 FY16-TMI INITIAL OPERATOR LICENSING EXAM 1 09/28/2015 10/07/2015 U01913 FY16-TMI INITIAL OPERATOR LICENSING EXAM 71124.07 - RAD SAFETY INSPECTION 1 1 06/08/2015 06/12/2015 IP 71124.07 Radiological Environmental Monitoring Program 1 06/08/2015 06/12/2015 IP 71151 Performance Indicator Verification 71124.08 - RADWASTE 1 1 09/14/2015 09/18/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 7111108P - INSERVICE INSPECTION 1 1 10/26/2015 11/06/2015 IP 7111108P Inservice Inspection Activities - PWR 71124 - RAD SAFETY INSPECTION 1 1 11/02/2015 11/06/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 11/02/2015 11/06/2015 IP 71124.02 Occupational ALARA Planning and Controls 1 11/02/2015 11/06/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Three Mile Island 08/26/2014 09:35:14 Inspection / Activity Plan Report 22 07/01/2014 - 12/31/2015 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - RAD SAFETY INSPECTION 1 1 11/02/2015 11/06/2015 IP 71124.04 Occupational Dose Assessment 1 11/02/2015 11/06/2015 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.