MONTHYEARML22011A1312022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML21012A4342021-01-13013 January 2021 Security Inspection Plan ML20015A5772020-01-15015 January 2020 Security and Emergency Preparedness Inspection Plan for Three Mile Island Generating Station, Unit 1 IR 05000289/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000289/2019005 IR 05000289/20180062019-03-0404 March 2019 Annual Assessment Letter for Three Mile Island Station, Unit 1 (Report 05000289/2018006) IR 05000289/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000289/2018005 IR 05000289/20170062018-02-28028 February 2018 Annual Assessment Letter for Three Mile Island Station-Unit 1 (Reports 05000289-2017006 and 05000289-2017402 and 05000289-2017501) IR 05000289/20170052017-08-28028 August 2017 Updated Inspection Plan for Three Mile Island Station, Unit 1, with Report 22 (Report 05000289/2017005) IR 05000289/20160062017-03-0101 March 2017 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2016006) IR 05000289/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2016005) IR 05000289/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2015006) IR 05000289/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2015005) IR 05000289/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289/2014001) IR 05000289/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000289-14-006 IR 05000289/20130012014-03-0404 March 2014 ROP-14 2013 Three Mile Island Nuclear Station Unit 1, Annual Assessment Letter, Report 05000289/2013001, and Inspection Plan IR 05000289/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000289-13-006 IR 05000289/20120012013-03-0404 March 2013 Annual Assessment Letter for Three Mile Island Nuclear Station, Unit 1 (Report 05000289-12-001) IR 05000289/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Three Mile Island Nuclear Station (Report 05000289/2012006) TMI-12-069, Submittal of Inspection Plan for Reactor Internals2012-04-16016 April 2012 Submittal of Inspection Plan for Reactor Internals IR 05000289/20110012012-03-0505 March 2012 Annual Assessment Letter for Three Mile Island Nuclear Generating Station Unit 1 (Report 05000289-11-001) ML1124206742011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Three Mile Island IR 05000289/20100012011-03-0404 March 2011 Annual Assessment Letter for Three Mile Island Nuclear Generating Station, Unit 1, EOC-11 (Report 05000289-10-001) ML1024407172010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Three Mile Island ML1006213042010-03-0303 March 2010 Annual Performance Review and Inspection Plan Three Mile Island 2009 EOC Letter and Report 22 (05000289-10-001) ML0924402202009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Three Mile Island (September 1, 2009) IR 05000289/20090012009-03-0404 March 2009 Annual Assessment Letter - Three Mile Island Unit 1 (05000289/2009001) IR 05000289/20080012008-03-0303 March 2008 2007 Annual Assessment Letter - Three Mile Island (Report 05000289/2008001) ML0734706292007-12-13013 December 2007 ROP 8 - Three Mile Island - Change to Inspection Plan, 12/13/07 ML0724309352007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan IR 05000289/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Three Mile Island (05000289/2007001) ML0706004472006-10-31031 October 2006 1R21 Outage - NRC Inspection Question Log Complied by Amergen (12 Pages) ML0606202072006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Three Mile Island Unit 1 (Report 05-289/2006001) ML0524207232005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Three Mile Island, Unit 1 ML0424401732004-08-30030 August 2004 TMI ROP5 Mid-Cycle Performance Review and Inspection Plan ML0323907022003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for TMI, Unit 1 IR 05000289/20030012003-03-0404 March 2003 2003-Annual Assessment Letter - Three Mile Island, Unit 1 (Report No. 50-289/2003-001) ML0223803152002-08-26026 August 2002 2002 Three Mile Island Unit 1 Mid-Cycle Performance Review & Inspection Plan IR 05000289/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Three Mile Island Station, Unit 1 (Report 50-289/02-01) 2022-01-31
[Table view] Category:Letter
MONTHYEARML24038A0222024-02-0505 February 2024 Achp Letter on Section 106 Programmatic Agreement Participation IR 05000289/20230062024-01-29029 January 2024 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report No. 05000289/2023006 ML23342A1242024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23325A1092024-01-0505 January 2024 Review of the Management Plan for Three Mile Island Station, Unit No. 2, Debris Material ML23354A2062023-12-20020 December 2023 (TMI-2), Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23354A2112023-12-20020 December 2023 Response to Request for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 IR 05000320/20230032023-11-28028 November 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2, NRC Inspection Report No. 05000320/2023003 ML23243A9082023-08-29029 August 2023 Shpo Letter to TMI-2 Regarding Section 106 Activities IR 05000320/20230022023-08-17017 August 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report 05000320/2023002 ML23216A1742023-08-14014 August 2023 Consultation Letter to David Morrison for TMI-2 ML23216A1772023-08-14014 August 2023 Consultation Letter to Rebecca Countess for TMI-2 ML23216A1752023-08-14014 August 2023 Consultation Letter to Joanna Cain for TMI-2 ML23216A1732023-08-14014 August 2023 Consultation Letter to Christine Turner for TMI-2 IR 05000289/20230052023-08-14014 August 2023 Constellation Energy Generation, LLC, Three Mile Island Nuclear Station, Unit 1 - NRC Inspection Report 05000289/2023005 ML23216A1782023-08-14014 August 2023 Consultation Letter to Steve Letavic for TMI-2 ML23221A1402023-08-0808 August 2023 (TMI-2), Response to Requests for Additional Information for the TMI-2 Post-Shutdown Decommissioning Activities Report, Rev. 5 ML23200A1882023-07-31031 July 2023 TMI-2 Correction Letter Amendment 67 ML23209A7632023-07-28028 July 2023 Letter from PA Shpo to TMI-2 Solutions on Cultural and Historic Impacts of Decommissioning ML23192A8272023-07-10010 July 2023 TMI-2 Solutions, LLC - Response to Shpo Request for Additional Information for Er Project 2021PR03278.006, TMI-2 Decommissioning Project ML23167A4642023-07-0505 July 2023 Letter - TMI-2- Exemption 10 CFR Part 20 Append G Issuance ML23167A0312023-06-28028 June 2023 Acceptance Review and Schedule for the Request for Exemption from a Requirement from 10 CFR 20, Appendix G, Section Iii.E, EPID L-2023-LLE-0016 ML23171B0222023-06-19019 June 2023 (TMI-2) - Notification Pursuant to 10 CFR 72.140(d) Regarding Application of Previously Approved TMI-2 Quality Assurance Program to Independent Spent Fuel Storage Installation Activities ML23137A2822023-05-17017 May 2023 (TMI-2), Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E ML23138A0662023-05-17017 May 2023 TMI-2 NHPA Section 106 Shpo Letter to NRC 5-17-23 ML23026A3132023-05-0202 May 2023 Issuance of Exemption from 10 CFR 70.24 (EPID-L-2023-LLE-0003) ML23122A1842023-05-0101 May 2023 Shpo_Er_Summary_Letter ML23121A2492023-05-0101 May 2023 License Amendment Request, Historic and Cultural Resources Review, Response to Request for Additional Information ML23117A0012023-04-26026 April 2023 Commitment Revision Summary Report ML23027A0832023-04-24024 April 2023 Environmental Assessment/Finding of No Significant Impact - Request for Exemption from 10 CFR 70.24 ML23108A0802023-04-18018 April 2023 Annual Radiological Effluent Release Report ML23108A0822023-04-18018 April 2023 Annual Radiological Environmental Operating Report IR 05000320/20230012023-04-12012 April 2023 TMI-2 Solutions, LLC, Three Mile Island Nuclear Station, Unit 2 - NRC Inspection Report No. 05000320/2023001 ML23102A0382023-04-10010 April 2023 Occupational Radiation Exposure Annual Report ML23108A2002023-04-10010 April 2023 CFR 20.2206(b) Personnel Radiation Exposure Report for 2022 ML23094A2582023-04-0606 April 2023 Letter to Sidney Hill, Chief, Onondaga Nation, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23093A0572023-04-0606 April 2023 Letter to Joanna Cain, President, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2362023-04-0606 April 2023 Letter to Carissa Speck, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2542023-04-0606 April 2023 Ltr J Bendremer Thpo Stockbridge-Munsee Community Band of Mohican Indians Re Initiation of Consultation Under Section 106 of the NHPA for Proposed License Amendment Request for TMI 2 ML23086C0652023-04-0606 April 2023 Ltr Larry Heady, Thpo, De. Tribe of Indian; Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI Nuclear Station, Unit 2 ML23093A0562023-04-0606 April 2023 Letter to Steve Minnick, Site Decommissioning Director, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 ML23094A2602023-04-0606 April 2023 Letter to William Tarrant, Seneca-Cayuga Nation, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23094A2392023-04-0606 April 2023 Letter to Courtney Gerzetich, Thpo, Onedia Nation of Wisconsin, Re., Initiation of Consultation Under Section 106 of the NHPA for the Proposed License Amendment Request for TMI 2 ML23093A0592023-04-0606 April 2023 Letter to Rebecca Countess, Chair, Re., Ongoing Activities Related to the Proposed License Amendment Request for Three Mile Island Nuclear Station, Unit 2 2024-02-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406-1415 September 1, 2009 Mr. Charles G. Pardee Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Rd.
Warrenville, IL 60555
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
THREE MILE ISLAND
Dear Mr. Pardee:
On August 11, 2009, the NRC staff completed its performance review of the Three Mile Island Nuclear Generating Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2008 through June 30, 2009. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as Official Use Only - Security Information will include the security cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter of 2009 at Three Mile Island was within the Licensee Response column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2010. In addition to the baseline inspections, a steam generator replacement inspection will be performed. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
C. Pardee 2 As you may know, the NRC is currently evaluating the scope and frequency of all the baseline inspection procedures as part of our biennial review of the ROP. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5200 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Ronald R. Bellamy, Ph.D., Chief Division of Reactor Projects Projects Branch 6 Docket Nos.: 50-289 License Nos: DPR-50
Enclosure:
Three Mile Island Inspection/ Activity Plan cc w/encl:
C. Crane, President and Chief Operating Officer, Exelon Corporation M. Pacilio, Chief Operating Officer, Exelon Nuclear W. Noll, Site Vice President, TMI Unit 1, Exelon Nuclear T. Dougherty, Plant Manager, TMI, Unit 1, Exelon Nuclear D. Atherholdt, Regulatory Assurance, TMI, Unit 1, Exelon Nuclear Senior Vice President, Nuclear Services, Exelon Nuclear Senior Vice President, Mid-Atlantic Operations, Exelon Nuclear Senior Vice President, Operations Support, Exelon Nuclear Vice President, Licensing and Regulatory Affairs, Exelon Nuclear P. Cowan, Director, Licensing, Exelon Nuclear D. Helker, Licensing, Exelon Generation J. Fewell, Esq., Associate General Counsel, Exelon Correspondence Control Desk, Exelon Nuclear Chairman, Board of County Commissioners of Dauphin County Chairman, Board of Supervisors of Londonderry Township R. Janati, Director, Bureau of Radiation Protection, State of PA D. Allard, Director, PA DEP J. Johnsrud, National Energy Committee E. Epstein, TMI-Alert (TMIA)
Page 1 of 2 Three Mile Island 08/31/2009 16:34:50 Inspection / Activity Plan Report 22 07/01/2009 - 12/31/2010 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7/6EXAM - OPERATOR LICENSING INITIAL EXAMS 5 1 07/06/2009 07/17/2009 U01760 FY-09 THREE MILE ISLAND INITIAL OPERATOR LICENSINT EXAM 50001 - S/G REPLACEMENT 2 1 08/17/2009 12/18/2009 IP 50001 Steam Generator Replacement Inspection 71121 - OCC RAD SAFETY 1 1 09/14/2009 09/18/2009 IP 50001 Steam Generator Replacement Inspection 1 09/14/2009 09/18/2009 IP 7112101 Access Control to Radiologically Significant Areas 1 09/14/2009 09/18/2009 IP 7112102 ALARA Planning and Controls 71121 - OCC RAD SAFETY 1 1 10/19/2009 10/23/2009 IP 50001 Steam Generator Replacement Inspection 1 10/19/2009 10/23/2009 IP 7112101 Access Control to Radiologically Significant Areas 1 10/19/2009 10/23/2009 IP 7112102 ALARA Planning and Controls 1 10/19/2009 10/23/2009 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 7111108P - INSERVICE INSPECTION 1 1 11/02/2009 11/06/2009 IP 7111108P Inservice Inspection Activities - PWR TI-172 - TI-172 RCS DISSIMILAR METAL WELDS 1 1 11/02/2009 11/06/2009 IP 2515/172 Reactor Coolant System Dissimiliar Metal Butt Welds 71121 - OCC RAD SAFETY 1 1 12/07/2009 12/11/2009 IP 50001 Steam Generator Replacement Inspection 1 12/07/2009 12/11/2009 IP 7112101 Access Control to Radiologically Significant Areas 1 12/07/2009 12/11/2009 IP 7112102 ALARA Planning and Controls 1 12/07/2009 12/11/2009 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 1 12/07/2009 12/11/2009 IP 71151 Performance Indicator Verification 71121 - OCC EXPOSURE 1 1 03/15/2010 03/19/2010 IP 7112101 Access Control to Radiologically Significant Areas 1 03/15/2010 03/19/2010 IP 7112102-7112102R ALARA - Required 1 03/15/2010 03/19/2010 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 1 03/15/2010 03/19/2010 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program TI-177 - MANAGING GAS ACCUMULATION IN ECCS 3 1 03/22/2010 03/26/2010 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System EP PROGR - EP PROGRAM INSPECTION 1 1 03/29/2010 04/02/2010 IP 7111402 Alert and Notification System Testing 1 03/29/2010 04/02/2010 IP 7111403 Emergency Response Organization Augmentation Testing 1 03/29/2010 04/02/2010 IP 7111404 Emergency Action Level and Emergency Plan Changes 1 03/29/2010 04/02/2010 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Three Mile Island 08/31/2009 16:34:50 Inspection / Activity Plan Report 22 07/01/2009 - 12/31/2010 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP PROGR - EP PROGRAM INSPECTION 1 1 03/29/2010 04/02/2010 IP 71151-EP01 Drill/Exercise Performance 1 03/29/2010 04/02/2010 IP 71151-EP02 ERO Drill Participation 1 03/29/2010 04/02/2010 IP 71151-EP03 Alert & Notification System MODS - PERMANENT PLANT MODIFICATIONS 5 1 04/12/2010 04/16/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 1 04/26/2010 04/30/2010 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 71122 - RETS 1 1 05/10/2010 05/14/2010 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems TI-173 - GROUND WATER TI 1 1 05/10/2010 05/14/2010 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 71152B - PI&R 4 1 07/12/2010 07/16/2010 IP 71152B Identification and Resolution of Problems 1 07/26/2010 07/30/2010 IP 71152B Identification and Resolution of Problems 7111107T - TRIENNIAL HEAT SINK 1 1 08/16/2010 08/20/2010 IP 7111107T Heat Sink Performance This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.