{{#Wiki_filter:Trial Use RG 1.247 Acceptability of Probabilistic Risk Assessment Results for Advanced Non-Light Water Reactor Risk-informed Activities Briefing for the Advisory Committee on Reactors Safeguards Subcommittee on Future Plant Designs Michelle Gonzalez, RES Anders Gilbertson, RES Hanh Phan, NRR Martin Stutzke, NRR Karl Fleming, JCNRM Dennis Henneke, JCNRM Donna Williams, NRR September 20, 2021 1
 
Presentation Outline
: 1. Background (Michelle Gonzalez)
: 2. Approach to Developing RG 1.247 (Anders Gilbertson)
: 3. Scope of the Endorsement RG and Staff Position Issues Addressed in RG (Hanh Phan/Martin Stutzke)
: 4. Future Activities/Revision of Non-LWR PRA Standard (Karl Fleming/Dennis Henneke)
: 5. Next Steps and Stakeholder Engagement (Donna Williams) 2
 
===Background===
Michelle Gonzalez, RES 3
 
===Background===
* The advanced non-light water reactor (ANLWR) PRA standard (ASME/ANS RA-S-1.4-2013) was issued in 2013 by ASME/ANS for trial use.
* In February 2021, ASME and ANS jointly issued ASME/ANS RA-S-1.4-2021, Probabilistic Risk Assessment Standard for Advanced Non- Light Water Reactor Nuclear Power Plants
  - The scope of the standard includes all levels of analysis (i.e. from initiating event to radiological consequence), all hazards and all operating modes (except internal fire PRA for LPSD-types of POSs).
  - The requirements in this standard cover PRAs performed during design, pre-operational, and post-operational phases.
4
 
Background (contd)
* ACRS Subcommittee on Future Plant Designs-November 2, 2020
  - Staff discussed the updated endorsement plan and the ballot results
* Updates from last ACRS meeting
  - Draft white paper issued January 15, 2021 (ML21015A434)
  - Performance of PRA Peer Reviews Using the ASME/ANS Advanced Non-LWR PRA Standard issued May 5, 2021 (NEI 20-09)
  - Pre-decisional trial use RG made public September 7, 2021 (ML21246A216) 5
 
Draft White Paper: Demonstrating the Acceptability of PRA Results Used to Support Advanced Non-LWR Plant Licensing
 
==Purpose:==
to provide staff views and perspectives on demonstrating acceptability of PRA results
* Provided early communication to stakeholders on issues to be addressed in RG 1.247
  - Public meeting held on February 23, 2021
  - Issues not addressed in RG 1.247 will be included in later documents 6
 
Endorsement of the Non-LWR PRA Standard and NEI 20-09
* NLWR PRA Standard will be endorsed with a trial use RG
  - Trial use will allow for incorporation of lessons learned from early use and incorporation of ongoing regulatory efforts (10 CFR Part 53)
  - Comments accepted throughout the trial use period (Informal comment period)
  - Formal comment period to follow after the draft RG is issued
* Peer Review Guidance in NEI 20-09
  - Clean endorsement with no exceptions taken 7
 
Approach to Developing RG 1.247 Anders Gilbertson, RES 8
 
Topics
* RG 1.247 regulatory paradigm
* RG 1.247 development approach
* RG 1.247 v. RG 1.200 comparison
* Novel staff positions in RG 1.247 9
 
RG 1.247 Regulatory Paradigm (1 of 2)
* RG 1.247 may be used to meet regulatory requirements related to the use of PRA
* The use of RG 1.247 helps reduce the need for an in-depth review of the PRA (RG 1.200 relates to obviating the need)
* RG 1.247 defines an application more broadly to accommodate design, pre-, and post-operational regulatory activities 10
 
RG 1.247 Regulatory Paradigm (2 of 2)
* Guidance on NLWR PRA peer review considers that peer reviews are not required (consistent with DC/COL-ISG-028)
* However, RG 1.247 emphasizes the importance and utility of the peer review process and suggests that a pre-application peer review be performed
  - Promotes more efficient staff reviews of applications
* With the existing regulations, the staff have greater latitude to request information about an applicants PRA 11
 
RG 1.247 Development Approach (1 of 2)
* RG 1.200 is the starting point for RG 1.247
  - Organization and substance of content in RG 1.247 broadly mimics that of RG 1.200
* Staff positions in RG 1.247 consider the close relationships between the NLWR and LWR PRA standards
* Staff have considered the potential impact on future endorsements of LWR PRA standards 12
 
RG 1.247 Development Approach (2 of 2)
* An information database tool was developed to help identify relationships and analyze differences between related requirements in different PRA standards and staff endorsements
* Applicability of current staff endorsement in RG 1.200 for related LWR PRA standard requirements were cross-checked against the NLWR PRA standard requirements 13
 
RG 1.247 v. RG 1.200 Comparison (1 of 4)
Some differences:
* RG 1.247 directly relates to meeting regulations
* RG 1.247 provides staff positions on the acceptability of PRA technical aspects for NLWRs that have not previously been provided for LWRs in RG 1.200
* RG 1.247 provides specific guidance on determining risk significance and the use of relative and absolute importance measures 14
 
RG 1.247 v. RG 1.200 Comparison (2 of 4)
Some differences:
* Consistent with the approach in the NLWR PRA standard, RG 1.247 does not use terms such as:
  - Level 1, Level 2, or Level 3 PRA
* RG 1.247 accommodates determining the acceptability of an NLWR PRA for an LMP application
* Because the staff identified no exceptions for NEI 20-09, the endorsement is only contained in the body of the RG
* Scope of RG 1.247 PRA elements not addressed in RG 1.200:
  - Plant Operating State Analysis for all POSs
  - Internal fire PRA for LPSD-types of POSs
  - Radiological consequence
  - Risk Integration 15
 
RG 1.247 v. RG 1.200 Comparison (3 of 4)
Some similarities:
* Most PRA elements addressed in RG 1.247 have an analog in RG 1.200, such as:
  - Initiating Event Analysis    - Hazards Screening Analysis
  - Event Sequence Analysis      - High Wind PRA
  - Success Criteria Development - External Flood PRA
  - Systems Analysis            - Other Hazards PRA
  - Human Reliability Analysis  - Event Sequence Quantification
  - Data Analysis                - Mechanistic Source Term
  - Internal Flood PRA            Analysis
  - Internal Fire PRA
  - Seismic PRA 16
 
RG 1.247 v. RG 1.200 Comparison (4 of 4)
Some similarities:
* Both include a table of hazards to consider in the development of a PRA
* Both provide guidance to applicants and licensees on:
  - What is an acceptable PRA (Section C.1)
  - The use of voluntary consensus standards and an acceptable peer review process (Section C.2)
  - How to demonstrate acceptability of PRA for an application (Section C.3)
  - PRA documentation needed to support a regulatory decision (Section C.4) 17
 
Novel Staff Positions in RG 1.247 (1 of 5)
* Plant Operating State Analysis for all POSs
  - (Section C.1.3.1)
* Internal fire PRA for LPSD-types of POSs
  - (Section C.1.3.9)
* Radiological consequence
  - (Section C.1.3.17)
* Risk integration
  - (Section C.1.3.18) 18
 
Novel Staff Positions in RG 1.247 (2 of 5):
Plant Operating States Analysis, all POSs
* Staff position in RG 1.247 goes beyond the scope of RG 1.200 to address all POSs
* Considers that there may be more than one type of at-power POS (e.g., online refueling)
* Staff position accounts for the potential need for a similar staff position for LWRs 19
 
Novel Staff Positions in RG 1.247 (3 of 5):
Internal Fire PRA, LPSD-Types of POSs
* No analogous staff positions for LWRs
* The NLWR PRA standard does not provide related requirements; as such, acceptability is measured against the staff position in Section C.1.3.9 of RG 1.247
* Staff position accounts for the potential need for a similar staff position for LWRs
* NRC initiating a research project to develop guidance 20
 
Novel Staff Positions in RG 1.247 (4 of 5):
Radiological Consequence
* An LMP application evaluates frequency and radiological consequence risk
* Outside of LMP applications, there are no regulatory requirements to perform a PRA that assesses consequence risk
* However, it is still important to meet Commission expectations as expressed in various policy statements
* Risk surrogates used for NLWRs will need to be justified 21
 
Novel Staff Positions in RG 1.247 (5 of 5):
Risk Integration
* No staff position on risk integration has previously been promulgated
* Basis for staff position relates to meeting Commission expectations, as expressed in the Advanced Reactor Policy Statement, which in turn references the Safety Goal Policy Statement and the importance of meeting the QHOs
* Unless justified, relative risk significance criteria should be used to develop the PRA.
* Staff determination of PRA acceptability does not include consideration of risk reporting thresholds 22
 
Scope of RG 1.247 and Staff Positions on Non-LWR PRA Standard Hanh Phan, NRR 23
 
RG 1.247 Guidance RG 1.247 provides guidance, for trial use, in the following four areas:
: 1. Defining the acceptability of a PRA and its results used in support of an application - RG 1.247, Section C.1
: 2. Demonstrating the acceptability of the PRA and its results used in an application - RG 1.247, Section C.3
: 3. Documentation to support a regulatory decision - RG 1.247, Section C.4
: 4. Staffs positions on NLWR PRA standard and industry PRA peer review process - RG 1.247, Section C.2 and Appendix A 24
 
Technical Reviewers Technical Element                NRC Reviewer Plant Operating States Analysis  Marie Pohida Initiating Event Analysis        Keith Tetter Event Sequence Analysis          Keith Tetter Success Criteria Analysis        Keith Tetter Systems Analysis                  Hanh Phan Human Reliability Analysis        Jonathan DeJesus Data Analysis                    Hanh Phan Internal Flood PRA                Matt Humberstone Internal Fire PRA                JS Hyslop Internal Fire PRA LPSD            JS Hyslop Seismic PRA                      Shilp Vasavada Hazard Screening Analysis        Alissa Neuhausen High Winds PRA                    John Lane External Flooding PRA            Shilp Vasavada Other Hazards PRA                Alissa Neuhausen Event Sequence Quantification    Hanh Phan Mechanistic Source Term Analysis  Michelle Hart Radiological Consequence Analysis Keith Compton Risk Integration                  Susan Cooper Newly Developed Methods          Shilp Vasavada Peer Review                      Hanh Phan 25
 
NLWR PRA Scope
* Address all radiological sources at the plant
  - Reactor cores
  - Spent fuel
  - Fuel reprocessing facilities
  - Accident scenarios that lead to a radioactive release from multiple radiological sources
* Address all hazards
  - All internal hazards such as, but not limited, to internal initiating events, internal floods, and internal fires
  - All external hazards such as, but not limited to, seismic events, external floods, and high wind events
* Address all plant operating states (e.g., at-power, low-power, shutdown)
* NLWR PRA should be a Level 3 PRA
  - Develop the frequencies of accident scenarios from the occurrence of an initiating event until the release of radioactive materials to the environment
  - Estimate the consequences that result from the release                            26
 
Applicable Regulations and Applications
* This RG applies to applications for NLWR licensing under 10 CFR Part 50
  - Current regulations do not require applicants for Part 50 construction permits or operating licenses to provide PRA-related information
  - Rulemaking Incorporation of Lessons Learned from New Reactor Licensing Process (Parts 50 and 52 Licensing Process Alignment), Docket NRC-2009-0196, RIN-3150-AI66
* This RG applies to applications for NLWR licensing under 10 CFR Part 52
  - Subpart B - Standard Design Certification (DC)
  - Subpart C - Combined License (COL)
  - Subpart E - Standard Design Approval (SDA)
  - Subpart F - Manufacturing License (ML)
* This RG is coordinated with 10 CFR Part 53 rulemaking effort
  - Rulemaking Risk Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors, Docket NRC-2019-0062, RIN 3150-AK31
  - Being developed as required by the Nuclear Energy Innovation and Modernization Act (NEIMA) 27
 
Applicability of RG 1.247 Applies to only stationary NLWRs:
* Reactors that are constructed at a site
* Reactors that are constructed at an offsite facility and subsequently transported and installed at a site
* Does not address PRAs used to assess the risk of transporting NLWRs from an offsite facility to the site
* Does not address mobile reactors, which may be relocated to different sites after initial criticality 28
 
Technical Elements RG 1.247 endorses the following PRA standard technical elements:
: 1. Plant Operating State Analysis        10. Seismic PRA
: 2. Initiating Event Analysis            11. Hazards Screening Analysis
: 3. Event Sequence Analysis              12. High Wind PRA
: 4. Success Criteria Development          13. External Flooding
: 5. Systems Analysis                      14. Other Hazards PRA
: 6. Human Reliability Analysis            15. Event Sequence Quantification
: 7. Data Analysis                        16. Mechanistic Source Term Analysis
: 8. Internal Flood PRA                    17. Radiological Consequence Analysis
: 9. Internal Fire PRA                    18. Risk Integration and ASME/ANS RA-S-1.4-2021:
* Definitions and Risk Assessment Application
* PRA configuration control
* Peer review
* Newly Developed Methods 29
 
Endorsement of Nonmandatory Appendices
* The nonmandatory appendices in ASME/ANS NLWR PRA standard may be binned into two groups:
a) Notes that support the understanding of various SRs, and b) Commentaries
* The NRC staff generally accepts the Notes
* The NRC staff provides no opinion about the Commentaries 30
 
Capability Categories In general, about 20% of the supporting requirements distinguish between CC-I and CC-II 31
 
Section C.1 - Acceptability of a PRA and Its Results Used in Support of an Application
* The staff assesses acceptability of the PRA and its results with respect to:
  - PRA scope
  - Level of detail
  - Conformance with consensus standard PRA elements
  - Plant representation of a PRA 32
 
PRA Acceptability PRA Scope                                      PRA Level of Detail
* Metrics used to characterize risk
* Defined in terms of the resolution of the
* Plant operating states (POSs) for which              modeling used to represent the the risk is to be evaluated                          behavior and operations of the plant
* Causes of initiating events (hazard
* A minimal level of detail is necessary to groups)                                              ensure that the impacts of designed-in dependencies are correctly captured PRA Acceptability PRA Technical Elements                                Plant Representation
* Defined in terms of the fundamental
* How closely the base PRA represents the technical analyses needed to develop and            plant as it is actually built and operated quantify the base PRA model for its
* The PRA should be maintained and intended purpose                                    upgraded, where necessary, to ensure it
* The characteristics and attributes of PRA            represents the as-built and as-operated technical elements define specific                  plant requirements that should be met 33
 
Section C.3 - Demonstrating Acceptability of PRA and Its Results Used in an Application For all applications, the PRA-related information provided in the submittal should:
* Describe the PRAs scope, level of detail, and degree of plant representation
* Demonstrate that the PRA has been developed and used in a technically acceptable manner, including the appropriateness of the assumptions and approximations
* Identify the application-specific acceptance criteria and demonstrate that they have been met 34
 
Section C.4 - Documentation to Support a Regulatory Decision
* Documentation of the PRA model and the analyses performed should comprise both:
  - Archival information (i.e., available for audit or inspection), and
  - submittal information (i.e., submitted as part of the risk-informed request)
* Archival PRA documentation may be required on an as-needed basis to facilitate the NRC staffs review of the application 35
 
Section C. 4 - Documentation (continued)
Archival PRA documentation should include:
* The process used to determine the acceptability of the PRA
* The methodology used to assess the risk of the application
* SSCs, operator actions, and plant operational characteristics affected by the application
* How the cause-effect relationships are mapped onto the PRA elements
* The PRA results that will be used to compare against the applicable acceptance criteria
* The scope of risk contributors (hazard groups and modes of operation) included in the PRA to support the application
* The results of the peer reviews of the PRA, PRA upgrades, and use of NDMs, and the results of F&O independent assessments, the resolution of all of the peer reviews
* The processes for maintaining & upgrading the PRA and the use of NDMs 36
 
Section C.4 - Documentation (continued)
Submittal PRA documentation should include:
* Demonstration that the PRA model represents the as-designed, as-to-be-built, and as-to-be-operated plant or the as-built and as-operated plant
* The appropriateness of key assumptions and approximations and sensitivity studies
* The appropriateness of a given portion of the PRA that meets a capability category lower than deemed required for the application under consideration
* The appropriateness of PRA model upgrades, including the use of NDMs, for the application under consideration 37
 
Section C.2 and Appendix A - Staff Positions on PRA Standard and PRA Peer Review Process
* About 80% of the requirements in the NLRW PRA standard were taken as-is from the set of LWR PRA standards
* First consideration ballot for the ANLWR PRA standard (3/24/20 -
5/26/20)
    - NRC staff submitted 489 comments, represented a broad set of staff views and perspectives
* Recirculation ballot for the ANLWR PRA standard (7/23/20 -
8/26/20)
    - NRC staff submitted 70 comments, included a mix of proposed technical changes and observations related to regulatory issues 38
 
Section C.2 and Appendix A - Staff Position on PRA Standard (continued)
The staff position on each requirement in ASME/ANS RA-S-1.4-2021 is categorized as:
* No objection - The staff has no objection to the requirement
* No objection with clarification - The staff has no objection to the requirement. However, certain requirements, as written, are either unclear or ambiguous, and therefore the staff has provided its understanding of these requirements
* No objection subject to the following qualification - The staff has a technical concern with the requirement and has provided a qualification to resolve the concern 39
 
Rationale for the Staff Positions
* JCNRM did not address during ballot process stating that comment needs to be addressed first in the LWR Level 1/LERF PRA standard
* Regulatory issue
* New issue
* Issue was not adequately addressed during balloting
* Not fully addressed by JCNRM
* Added for consistency with the staffs position in RG 1.200, Rev. 3 40
 
Clarification and Qualification Positions Table                Description        Clarification Qualification Total A-1  Front Matter                            3            2        5 A-2  Plant Operating States                  3            5          8 A-3  Initiating Events                        0            0        0 A-4  Event Sequences                          0            0          0 A-5  Success Criteria                        0            0        0 A-6  Systems Analysis                        5            0          5 A-7  Human Reliability Analysis              7            4        11 A-8  Data Analysis                            0            1        1 A-9  Internal Floods                          7            1        8 A-10  Internal Fires                          1            0          1 A-11  Seismic                                22            6        28 A-12  Hazard Screening                        8            1          9 A-13  High Winds                              4            2        6 A-14  External Floods                        14            1        15 A-15  Other Hazards                          10            1        11 A-16  Quantification                          0            0        0 A-17  Mechanistic Source Terms                0            0        0 A-18  Radiological Consequences              23            5        28 A-19  Risk Integration                        6            2        8 A-20  Configuration Control                    0            1        1 A-21  Peer Review                              0            0          0 A-22  Newly Developed Methods                  1            1          2 Totals    114            33        147 41
 
Substantive Clarifications and Qualifications Group                Clarifications Qualifications Total Group 1: Low Power and Shutdown Risk          2            2          4 Group 2: External Hazard Risk                4            2          6 Group 3: Errors of Commission                0            2          2 Group 4: Risk Significance                    1            0          1 Group 5: Reporting Requirements              2            2          4 Total        9            8        17 42
 
Group 1 - Low Power and Shutdown Risk
#  Index No.                    Issue                  Position                                  Resolution 1.1 POS-N-2  All stages of the licensing process    Clarification Early pre-operational stage PRAs are typically limited to at-power should address low power and                          PRAs only. All stages of the licensing process should address low shutdown-types of evolutions                          power and shutdown-types of evolutions 1.2 POS-N-4  All stages of the licensing process    Clarification Depending on the application, the evolution to be addressed may should address low power and                          range from at-power only to all plant operating states outage shutdown-types of evolutions                          types. All stages of the licensing process should address low power and shutdown-types of evolutions.
1.3 POS-A1    Limiting the CC-I requirement for POS- Qualification CC-I A1 only to at-power plant evolutions                  IDENTIFY a representative set of plant evolutions to be analyzed.
potentially excludes a significant risk              INCLUDE, at a minimum, plant evolutions from at-power contributor as low-power and                          operations.
shutdown-types of POSs have been                      See Note POS-N-1, POS-N-2, POS-N-3, POS-N-4 shown to have a comparable risk in                    CC-I and CC-II IDENTIFY a representative set of plant evolutions to be analyzed, some cases to at-power POSs. As such, including refueling outages, other controlled shutdowns, and the scope of the CC-I requirement forced outages.
should be the same as the scope of See Note POS-N-3 the CC-II requirement to avoid excluding potentially significant contributors to risk.
1.4 POS-B1    Omitting the condition to ensure that Qualification CC-I the POS grouping does not impact                      GROUP plant evolutions into a set of representative evolutions.
risk-significant event sequences could                ENSURE that significantly impact the results and                  (a) the evolutions within a group can be considered similar in insights from the PRA. As such, a new                terms of the set of plant operating states that they contain; requirement is needed for CCI to                      (b) the evolutions are bounded by the worst case impact within reflect as much.                                      the group; (c) the grouping does not impact risk-significant event sequences.
43
 
Group 2 - External Hazard Risk
#  Index No.                        Issue                        Position                          Resolution 2.1 SFR-C1    Justification of the selected basis needs to be  Clarification SPECIFY the basis for screening of inherently provided, especially for cases where the basis                  rugged components justifying the applicability to in an extension or expansion of available                      the plant and site or range of sites identified in information. Note S-N-27 also mentions                          SHA-A1.
plant-specific justification which is not reflected in the SR.
2.2 SFR-C2    Justification of the selected basis needs to be  Clarification SPECIFY the basis and methodologies established provided, especially for cases where the basis                  for achieving the fragility thresholds defined in in an extension or expansion of available                      Requirement SPR-B5 justifying the applicability to information. This comment is also supported                    the plant and site or range of sites identified in by the discussion in Note S-N-28.                              SHA-A1.
2.3 HS-A3    The requirement does not address plant-          Clarification IDENTIFY site-, plant-, or and design-specific unique specific hazards, which may not be identified                  hazards and hazard groups, as applicable to the as part of the identification of site-specific or              stage of the plant lifecycle, not already identified in design-specific hazards or hazard groups.                      Requirement HS-A2.
Additionally, note HS-N-5 appears to be                        See Notes HS-N3, HS-N-4, HS-N-5.
applicable to HS-A3 as it directly relates to plant-specific hazards and hazard groups.
2.4 WHA-A5    150 mile distance is arbitrary                    Clarification
: a. meet SCR-3 in Table 1.10-1 by showing that the site is more than 150 miles (approximately 250 km) is sufficiently far away from the nearest tropical cyclone-prone coast to screen out tropical cyclone (hurricane or typhoon) high wind hazards from the probabilistic wind hazard analysis; 44
 
Group 2 - External Hazard Risk (continued)
Index No.                  Issue                  Position                                  Resolution 2.5 SHA-B5    SHA-B5 does not include                Qualification Add the following to SHA-B5:
consideration of (1) the use of an                  If an existing probabilistic SHA is used, DEMONSTRATE that an existing probabilistic SHA for a site                updated catalog of earthquakes does not make the existing and, (2) the impact of an updated                    probabilistic SHA unviable.
catalog on the use of the existing probabilistic SHA. Given the likelihood of using an existing site as the bounding site (see SHA-A1),
the considerations identified above are warranted.
2.6 HS-B5    The values in RI-A5 referenced in      Qualification USE SCR-3 in Table 1.10-1 when qualitatively screening out a item (f) are presented as reporting                  hazard or hazard group by showing that either:
values, not screening values. Using                  (a) the hazard or hazard group cannot physically impact the the reporting values as screening                    plant or plant operations (e.g., it cannot occur close enough to values could be too permissive in                    the plant to affect it);
excluding contributors from the                      (b) the hazard or hazard group does not result in a plant trip (manual or automatic) or require a plant shutdown; PRA as screening using a (c) the hazard or hazard group is included in the definition of consequence criterion may not be another hazard; effectively equivalent to screening                  (d) the hazard or hazard group could not result in worse effects using a frequency criterion.                        to the plant as another hazard that has a significantly higher Additionally, this requirement is                    frequency; effectively for qualitative screening,              (e) the hazard or hazard group is slow in developing and there is as per SCR-3 in Table 1.10-1 and                    demonstrably sufficient time to eliminate the source of the because item (f) is a quantitative                  threat or to provide an adequate response; criterion, it should therefore not be                (f) the hazard or hazard group cannot produce a consequence included in the list.                                above the value set in RI-A5.
45
 
Group 3 - Errors of Commission
#  Index No.                                  Issue                                Position                Resolution 3.1 HLR-HR-E  The scope of high-level requirement (HLR) HR-E does not include      Qualification A systematic review of relevant errors of commission. See HR-E4 in this table for more details about              available procedures, any past the basis for this issue.                                                          operational events, procedural guidance, and training shall be used to identify the set of post-initiator operator responses required for each of the event sequences, as well as, the well-intended post-initiator operator responses that result in adverse safety impacts.
3.2 HR-E4    HR-E4 does not include errors of commission (EOC). EOCs should be Qualification Add the following to item to included in the advanced non-light water reactor (LWR) PRA                        HR-E4:
standard for the following reasons: (1) the significant amount of experience in operating LWRs facilitates a consensus between NRC                  (c) those well-intended and industry to exclude EOCs from the LWR Level 1/large, early                    actions performed by control release frequency (LERF) PRA standard; however, there is very little              room staff that disable a (if any) advanced non-LWR operating experience to allow the                        system, sub-system, or consensus to exclude EOCs from the advanced non-LWR PRA                            component needed in an event standard; (2) it is expected that advanced non-LWRs would rely less                scenario.
on human actions than LWRs, which implies that EOCs would play a more important role in advanced non-LWR PRAs than in LWR Level 1/LERF PRAs; and (3) given that (a) the scope of the advanced non-LWR PRA standard covers what in the LWR world is known as Level 2 PRA and (b) there is no consensus about EOCs in Level 2 PRA, the developers of PRAs for advanced non-LWRs should demonstrate that EOCs are not an issue before eliminating them from consideration.
46
 
Group 4 - Risk Significance
#  Index No.            Issue              Position                                    Resolution 4.1 RI-N-1    Proper use of relative and Clarification Add this text: The choice between using relative or absolute risk absolute risk significance              significance criteria to develop a PRA should consider issues such as, criteria.                                but not limited to the following:
* The use of absolute risk significance criteria may yield a limited set of risk-significant items that is insufficient for developing risk insights or verifying the PRA model.
* Importance measures traditionally used in LWR PRAs to identify relative risk significant items (e.g., FV and RAW) may be inaccurate or misleading when applied to noncoherent logic models (i.e., logic models that contain NOT logic).
* A PRA that is developed using absolute risk significance criteria should be revised if relative risk significance criteria are used to support a subsequent application, and vice versa.
The use of risk significance criteria (relative or absolute) should address the entire set of risk metrics computed by the PRA.
47
 
Group 5: Reporting Requirements
#  Index No.                              Issue                                  Position              Resolution 5.1 RI-N-3    The staff do not consider reporting requirements when              Clarification The reporting requirement in RI-determining the acceptability of a PRA for a given application,                  A4 does not need to be met to such reporting requirements should be provided by the                            demonstrate PRA acceptability.
appropriate regulatory authority on an application-specific basis.
5.2 RI-N-4    The staff do not consider reporting requirements when              Clarification The reporting requirement in RI-determining the acceptability of a PRA for a given application.                  A5 does not need to be met to Such reporting requirements should be provided by the                            demonstrate PRA acceptability.
appropriate regulatory authority on an application-specific basis.
5.3 RI-A4    The staff do not consider reporting requirements when              Qualification This requirement does not need determining the acceptability of a PRA for a given application.                  to be met to demonstrate PRA Such reporting requirements should be provided by the                            acceptability.
appropriate regulatory authority on an application-specific basis.
5.4 RI-A5    The staff do not consider reporting requirements when              Qualification This requirement does not need determining the acceptability of a PRA for a given application.                  to be met to demonstrate PRA Such reporting requirements should be provided by the                            acceptability.
appropriate regulatory authority on an application-specific basis.
48
 
NEI 20-09 PRA Peer Review Guidance
* NRC staff received NEI 20-09, Rev. 0 on June 1, 2020
* Staff reviewed and provided observations during a public meeting on July 22, 2020
* Staff received a revision to NEI 20-09 on August 24, 2020
* Staff provided additional comments during a public meeting on October 26, 2020
* NEI submitted Revision 1 of NEI 20-09 on May 5, 2021 49
 
NEI 20-09 PRA Peer Review Guidance
* NEI 20-09, Rev. 1, is based on a related industry PRA peer review guidance document, NEI 17-07, Rev. 2, Performance of PRA Peer Reviews Using the ASME/ANS PRA Standard, as endorsed by RG 1.200, Rev. 3
* NEI 20-09 addresses all radiological sources, all hazards, all POSs, and all levels of PRA analysis
* NEI 20-09 process is applicable for a peer review performed for a PRA representing any stage of plant lifecycle
* The staff finds that the guidance in NEI 20-09, Rev. 1, is acceptable and thus endorses NEI 20-09, Rev. 1, without exception, in RG 1.247, Section C.2.2
* The ASME/ANS NLWR PRA standard contains requirements for the performance of an acceptable peer review process. The staff reviewed the requirements and takes no exceptions to them 50
 
NEI 20-09 Pilots
* NEI plans to pilot the peer review process
* Staff to observe the pilots
* Observations will enhance the staffs positions in RG 1.247 51
 
NLWR PRA Acceptability Issues (1 of 3)
* Ten issues were identified as a result of stakeholder feedback on the draft staff white paper Demonstrating the Acceptability of Probabilistic Risk Assessment Results Used to Support Advanced Non-Light Water Reactor Plant Licensing:
    - Draft staff white paper: ML21015A434 dated 1/19/2021
    - Public meeting held 2/23/2021
* Staff presentation: ML21050A240
* Industry presentation: ML21055A732
* Meeting summary: ML21069A123 dated 3/17/2021
    - Public meeting held 3/30/2021
* Staff presentation: ML21085A594
* Meeting summary: ML21096A107 dated 4/15/2021
* Issue resolution status:
    - Addressed in RG 1.247, or
    - Being addressed in other staff guidance, or
    - Initiating research and developmental activities 52
 
NLWR PRA Acceptability Issues (2 of 3)
No.                  Issue                                    Resolution 1  Provide guidance on initial licensing    LMP-based applications:
that addresses all NLWRs (LMP or not
* NEI 21-07 (industry TICAP guidance)
LMP)
* Trial use RG to endorse NEI 21-07
* ARCAP roadmap ISG
* ARCAP-related ISGs on specific topics Non-LMP-based Applications: deferred 2  Provide guidance on graded PRA          Working group formed to explore alternatives to approaches                              PRA that achieve the same underlying purposes 3  Provide guidance on voluntary risk-      NRR/RES work request informed applications (in addition to LMP) that may be part of an initial license application or after the license has been issued 4  Address the use of risk surrogates      Addressed in RG 1.247 5  Address the use of seismic margins
* SMA excluded in NLWR PRA standard and, analysis (SMA)                              hence, not addressed in RG 1.247
* Applicants who seek to use SMA are encouraged to discuss during pre-application interactions 53
 
NLWR PRA Acceptability Issues (3 of 3)
No.                    Issue                                Resolution 6  Address completeness uncertainty
* LPSD fires: NRR/RES work request
* Uncertainty: NRR/RES work request 7  Define the bounding site for external Each applicant to propose and justify on a case-hazards and radiological consequence  by-case basis evaluation 8  Address the applicability of          Develop ISG supporting requirements (SRs) during various licensing stages 9  Address the use of absolute and      Addressed in RG 1.247 relative risk significance criteria 10  Use of peer reviews (full-scope and  Addressed in RG 1.247 focused-scope) to demonstrate PRA acceptability 54
 
Risk Significance (1 of 3)
* Goal: Identify what is important
* Uses:
  - Develop the PRA model
* Increase level of detail and plant representation for risk significant items
* Logic model debugging
* Iterative process
  - Report PRA results
* Two approaches:
  - Relative risk significance
* Normalized to total risk
* Traditional PRA approach
  - Absolute risk significance
* Normalized to a specified risk target (e.g., LMP frequency-consequence target curve, QHOs)
* Concept evolved as a result of various LMP pilot exercises 55
 
Risk Significance (2 of 3)
Risk Significant Basic Event Relative A basic event that contributes significantly to baseline risk. It is defined as any basic event that has an Fussell-Vesely (FV) importance greater than 0.005 or a risk achievement worth (RAW) importance greater than 2 where the importance is normalized against the baseline total integrated risk or risk of a specific combination of source of radioactive material, hazard, and plant operating state.
Absolute A basic event that contributes significantly to an absolute risk significance criterion selected for RIDM. It is defined as any basic event that contributes significantly to an absolute risk significance criterion selected for RIDM. It is defined as any basic event that a) contributes at least 1% to any identified absolute risk target; or b) would result in exceeding the criterion if the basic event is assumed to fail with probability of 1.0.
56
 
Risk Significance (3 of 3)
Risk Significant Event Sequence or Event Sequence Family Relative An event sequence or event sequence family that, when rank-ordered by decreasing frequency, contributes a specified percentage of the baseline risk, or that individually contributes more than a specified percentage of the risk. For this version of the Standard, the aggregate percentage for the set is 95%, and the individual event sequence or event sequence family percentage is 1% of the total integrated risk or risk of a specific combination of source of radioactive material, hazard, and plant operating state.
Absolute An event sequence or event sequence family included in a PRA model, defined at the functional or systematic level, that makes a significant contribution to an absolute risk target selected for RIDM. It is defined as any event sequence or event sequence family that contributes at least 1% to any identified absolute risk target.
57
 
PERSONAL COMMENTS ON RG 1.247 Karl N. Fleming Former Chair JCNRM WG on Advanced non-LWRs (Currently Vice Chair) karlfleming@comcast.net
 
59 MY PERSONAL COMMENTS The following comments are my personal opinions and do not reflect the official position of the JCNRM or supporting groups and subcommittees ACRS Meeting on RG 1.247
 
60 BACKGROUND
* Per NRC request JCNRM prioritized the schedule for this standard ahead of next edition LWR PRA standard
* JCNRM appreciates extensive involvement of NRC staff and NRC contractors in producing the standard and support of Ballot Reviews
* First consideration ballot in May 2020 yielded over 1300 comments including nearly 500 from NRC staff
* Second consideration ballot in July 2020 was unanimously approved by the JCNRM with 86 largely editorial comments mostly from the NRC
* Final editorial changes approved by JCNRM via two unanimous voice votes
* Standard approved by ASME and ANS boards, no comments in public review and final approval by ANSI
* Changes were made to the next edition of LWR standard recently balloted to minimize editorial inconsistencies.
* Given that background I was surprised that the approach taken to express clarifications in the RG was expressed in terms of so many further editorial changes rather than commentary regarding HOW the NRC staff expects the requirements to be addressed for regulatory applications.
ACRS Meeting on RG 1.247
 
61
 
==GENERAL COMMENT==
S
* There are several places that claim that risk characterization for NLWRs is typically expressed by cumulative risk metrics or risk surrogates.
* These statements should be modified to clarify the that fundamental metrics used to formulate the requirements characterize risk in terms of the frequencies and radiological consequences of event sequence families (not individual sequences).
* The NLWR standard does not use the LWR risk metrics CDF or LERF as explained in Section 1.9.1 so not clear why it is suggested as a possibility in the RG.
* The PRA standard does not support the use of surrogate risk metrics as a means of expressing the results of the PRA but only as intermediate states for developing the event sequence model. If such intermediate metrics are used, the standard still expects that risk integration and evaluation of risk significance will be based on quantification of frequencies and consequences.
* Sections C.1.3 and C.1.4 provide a long discussion of objectives and attributes for each of the technical elements in the standard. These discussions overlap extensively with material in the standard that cover the same ground but they are not one for one and it would take a long time to figure out if there is anything different here. Rather than paraphrasing material on objectives and attributes already covered in the standard, the RG should focus on the specific items that the staff wishes to clarify
* Many of the clarifications in Appendix A refer to language shared with LWR supporting standards
* In the clarifications provided in Appendix A, it would be helpful for the staff to point out which changes are for alignment with LWR standard vs. those unique to the NLWR standard ACRS Meeting on RG 1.247
 
62 SPECIFIC COMMENTS
* Suggestion that PRA technical adequacy are the same as PRA acceptability needs clarification; technical adequacy is based on meeting requirements in an international consensus PRA standard while acceptability expresses a U.S. regulatory position.
* The PRA technical elements presented in Table 1 are not consistent with the ones used in the standard (See Table 1.4-1). The elements listed for internal events are applicable to all internal and external hazard groups. This is one of a number of examples where the RG is paraphrasing material in the standard but in a manner that is not always accurate.
* Should be clarified that the technical requirements for peer review are actually part of the standard and not separate entities as suggested in Figure 1 (Triangle Figure).
* Discussion on POS, MST, and other elements seem to lack appreciation of the need to address the impact of multiple reactors and sources.
* The RG treats documentation in one section whereas standard has documentation requirements specialized for each technical element
* Regarding the staff position on reporting requirements RI-A4(low frequency item) and RI-A5(low consequence item), which defer to specific applications, the authors of the standard believe these are fundamental to recognizing limitations in PRA technology.
* My colleague Dennis Henneke has additional general and specific comments to offer ACRS Meeting on RG 1.247
 
63 PLANS FOR NEXT REVISION
* Per JCNRM guidance, need to wait until all the supporting LWR standards are revised for consistency with the recently balloted LWR Level 1/LERF Standard
* Low Power Shutdown Standard
* Level 2 Standard
* Level 3 Standard
* Advanced LWR Standard
* Advanced non-LWR community needs to gain sufficient experience using the 2021 edition of the NLWR standard to identify the issues unique to NLWRs and to justify application of standard writing resources.
* Schedule for next revision is undefined ACRS Meeting on RG 1.247
 
Review of Draft RG 1.247 Appendix A - NRC Position on ASME/ANA RA-S-1.4-2021 Dennis Henneke Consulting Engineer - GE Hitachi JCNRM ANS Chair*
* Not representing ANS or the JCNRM for this presentation.
64
 
Overview of ASME/ANS PRA Standard Requirements
* The Joint Committee on Nuclear Risk Management (JCNRM) develops and maintains PRA standards for LWRs and NLWRs using a consensus committee made up of all stakeholders including the NRC and its contractors.
* The NRC provided hundreds of comments on RA-S-1.4-2021, the vast majority were accepted.
* PRA Standards for existing LWRs (draft 2021) and NLWRs (RA-S-1.4-2021) define the following to determine a technically acceptable PRA:
* Scope: This includes the hazards (internal events, internal hazards and external hazards) and the plant operational states (full power, low power and shutdown) for each hazard.
* PRA Attributes: as defined by the High Level Requirements (HLRs) and Supporting Requirements (SRs). HLRs are in the form of Shall statements and SRs support the HLRs.
Content of HLRs and SRs are prescribed by the ASME and ANS guidance.
* The PRA standard SRs define what is required (performance-based) to meet the HLRs but should not describe how to meet the requirement or limit the approach to a single methodology by referencing a document in an SR.
* The NRC and JCNRM members have provided numerous comments on removing wording from the SRs that were too much how to perform the PRAs.
65
 
Feedback on NRC Clarifications
* The standard has undergone numerous rounds of review including in 2020, and the resulting standard is a consensus product. Many of the NRC clarifications have either gone through consensus review or should go through consensus review for determination of technical correctness:
* POS-A8: the addition of requiring review of POSs identification by operations personnel prior to plant operations (in design) - when we will not necessarily have operations personnel.
* POS-A10: The clarification requires POS definitions to include changes in barriers, propagation pathways and modification of fragilities in the POS definitions.
* This both disagrees with the definition of POS and is too much how to in the SR.
* Changes such as this are addressed in the PRA modeling, not POS definition.
* POS-A1 and Note POS-N-2: Clarification is requiring LPSD to be included at All stages of the Licensing Process.
* Disagrees with the discussion throughout the standard and the consensus wording of POS-A1.
* The standard is not a licensing document and should not discuss what is required at various stages of licensing.
66
 
Feedback on NRC Clarifications
* HLR-HR-E; Added words to the HLR: A systematic review shall be used to identify post-initiator operator responses as well as, the well-intended post-initiator operator responses that result in adverse safety impacts
* Too much how to in the HLR.
* When combined with changes to HR-E4 (actions that disable a system); the changes now require additional analysis of errors of commission, not currently required by any PRA standard.
* HR-D4: Adds reference to NUREG-0700 for adherence to human factors guidelines
* Again, too much how to.
* Additionally, reference to a specific document in the SR is not appropriate, since this indicates only one acceptable approach to meet the SR.
* HR-G1: Adds to the requirement wording to ASSESS the feasibility of the HFE.;
ASSIGN an HEP of 1.0 if not feasible.
* Again, too much how to.
* HRA techniques already include a feasibility step during the qualitative portion of the HRA.
* A similar change was rejected by the JCNRM previously for the above reasons.
* HR-G4: Adds the wording: in supporting the decision, diagnosis, decision-making and action execution given the plant-specific and event scenario-specific contextcommunication among personnel in the same team and in different teams.
* Again, too much how to 67
 
Feedback on NRC Clarifications
* JCNRM standard are not perfect, and we welcome feedback and improvements through the consensus process.
* Generally, we try to accommodate most comments through change in the standard wording.
* Some of the NRC exceptions were changes incorporated into the LWR draft in publication (no objection to these).
* RG 1.247 exceptions do not point to any significant gaps in the NLWR standard.
* The previous examples above are just a few examples where the draft RG should be improved (see backup slide for more examples):
* Overall, these types of changes should be submitted to the JCNRM NLWR working group for review and consideration to ensure the standard SRs are correctly worded and supported by consensus review.
* Any NRC recommended changes to the standard wording should be consistent with standard development guidance:
* Wording should focus on what is required versus how to perform the PRA.
* HLRs and SRs should not reference specific documents or limit the approach to one approach.
* The standard should not dictate what scope is required at different phases of licensing.
68
 
DWH Backup
* Other NRC clarifications which should be reviewed:
* HR-G14 (to much how to shown in blue), HR-H2, DA-C20, FLEV-C1 (1st mention of temp. alignments - under documentation), SHA-B5, SHA-D3, SFR-C1, C2, SFR-D5 (no other mention of pathways), SFR-E3, E4, E5, E7 (wording is too limiting), HLR-SPR-B, SPR-B6 (expands the relay chatter from Risk-Significant SSCs to all SSCs), SPR-D6 (see previous feasibility comment), SPR-E8 (and/or not appropriate), HS-A3 (hazards are not applicable to a design stage), HS-B5 (change should be reviewed by JCNRM in brown), WFR-I1 (fix the bullet numbers), WPR-D11 (see previous feasibility comment),
XFPR-E6, OPR-A4, OPR-C6 (feasibility), RCRE-A2, RCPA-A3, RCPA-A10, RCME-A2/4/7/8 (also refers to RG 1.23), RCME-A3, RCAD-A5, RCAD-B2, C1, RCDO-A and A1/6 (skin absorption not previously mentioned in the standard), RCDO-A8, RCQ-A3, RCQ-B3 (results of interest inaccurate).
* Notes not reviewed for this presentation.
69
 
Next Steps and Stakeholder Engagement Donna Williams, NRR 70
 
Next Steps
* Consider feedback from ACRS/other stakeholders (September
  - mid-October)
* Public meeting October 20, 2021
* NRC concurrence and trial use RG publication - October -
November
* Issue for trial use - December 2021
* Initial use by near-term applicants
* Trial use period is flexible, depending on timing of the next version of standard, rulemakings, and feedback from early use 57
 
Comments and Feedback
* Comments and improvements on all published RGs including this trial use RG are encouraged at any time and the NRC will ensure consideration of such comments and suggestions.
* Preliminary trial use RG made public - September 7, 2021
* October 20, 2021- public meeting
* Trial Use RG published in FRN. FRN includes information on submitting comments.
* Public meetings/workshops to discuss feedback from first uses 72
 
Acronyms
* ANLWR - advanced non-light water reactor
* RG - regulatory guide
* ANS - American Nuclear Society
* SC - subcommittee
* ASME - American Society of Mechanical Engineers
* SSC - structures, systems and components
* CFR - Code of Federal Regulations
* SP - staff position
* COL - combined license
* SR - supporting requirement
* CP - construction permit
* SSC - structure, system, and component
* DC - design certification
* ISG - interim staff guidance
* JCNRM - Joint Committee on Nuclear Risk Management
* LMP - licensing modernization project
* LPSD - low-power and shutdown
* LWR - light-water reactor
* NEI - Nuclear Energy Institute
* NRC - Nuclear Regulatory Commission
* NRR - Office of Nuclear Reactor Regulation
* OGC - Office of the General Counsel
* OL - operating license
* QHO - quantitative health objective
* POS - plant operating state
* PRA - probabilistic risk assessment
* RES - Office of Nuclear Regulatory Research 73
 
General Framework for PRA Acceptability 74}}

Latest revision as of 16:16, 18 January 2022

ACRS Sc Meeting Slides 9-20-21 NRC and Jcnrm
ML21262A000
Person / Time
Issue date: 09/20/2021
From:
Office of Nuclear Reactor Regulation
To:
Williams D
References
Download: ML21262A000 (74)


Text

Trial Use RG 1.247 Acceptability of Probabilistic Risk Assessment Results for Advanced Non-Light Water Reactor Risk-informed Activities Briefing for the Advisory Committee on Reactors Safeguards Subcommittee on Future Plant Designs Michelle Gonzalez, RES Anders Gilbertson, RES Hanh Phan, NRR Martin Stutzke, NRR Karl Fleming, JCNRM Dennis Henneke, JCNRM Donna Williams, NRR September 20, 2021 1

Presentation Outline

1. Background (Michelle Gonzalez)
2. Approach to Developing RG 1.247 (Anders Gilbertson)
3. Scope of the Endorsement RG and Staff Position Issues Addressed in RG (Hanh Phan/Martin Stutzke)
4. Future Activities/Revision of Non-LWR PRA Standard (Karl Fleming/Dennis Henneke)
5. Next Steps and Stakeholder Engagement (Donna Williams) 2

Background

Michelle Gonzalez, RES 3

Background

  • The advanced non-light water reactor (ANLWR) PRA standard (ASME/ANS RA-S-1.4-2013) was issued in 2013 by ASME/ANS for trial use.

- The scope of the standard includes all levels of analysis (i.e. from initiating event to radiological consequence), all hazards and all operating modes (except internal fire PRA for LPSD-types of POSs).

- The requirements in this standard cover PRAs performed during design, pre-operational, and post-operational phases.

4

Background (contd)

  • ACRS Subcommittee on Future Plant Designs-November 2, 2020

- Staff discussed the updated endorsement plan and the ballot results

  • Updates from last ACRS meeting

- Draft white paper issued January 15, 2021 (ML21015A434)

- Performance of PRA Peer Reviews Using the ASME/ANS Advanced Non-LWR PRA Standard issued May 5, 2021 (NEI 20-09)

- Pre-decisional trial use RG made public September 7, 2021 (ML21246A216) 5

Draft White Paper: Demonstrating the Acceptability of PRA Results Used to Support Advanced Non-LWR Plant Licensing

Purpose:

to provide staff views and perspectives on demonstrating acceptability of PRA results

  • Provided early communication to stakeholders on issues to be addressed in RG 1.247

- Public meeting held on February 23, 2021

- Issues not addressed in RG 1.247 will be included in later documents 6

Endorsement of the Non-LWR PRA Standard and NEI 20-09

  • NLWR PRA Standard will be endorsed with a trial use RG

- Trial use will allow for incorporation of lessons learned from early use and incorporation of ongoing regulatory efforts (10 CFR Part 53)

- Comments accepted throughout the trial use period (Informal comment period)

- Formal comment period to follow after the draft RG is issued

- Clean endorsement with no exceptions taken 7

Approach to Developing RG 1.247 Anders Gilbertson, RES 8

Topics

RG 1.247 Regulatory Paradigm (1 of 2)

  • RG 1.247 may be used to meet regulatory requirements related to the use of PRA
  • The use of RG 1.247 helps reduce the need for an in-depth review of the PRA (RG 1.200 relates to obviating the need)
  • RG 1.247 defines an application more broadly to accommodate design, pre-, and post-operational regulatory activities 10

RG 1.247 Regulatory Paradigm (2 of 2)

  • Guidance on NLWR PRA peer review considers that peer reviews are not required (consistent with DC/COL-ISG-028)
  • However, RG 1.247 emphasizes the importance and utility of the peer review process and suggests that a pre-application peer review be performed

- Promotes more efficient staff reviews of applications

  • With the existing regulations, the staff have greater latitude to request information about an applicants PRA 11

RG 1.247 Development Approach (1 of 2)

- Organization and substance of content in RG 1.247 broadly mimics that of RG 1.200

  • Staff positions in RG 1.247 consider the close relationships between the NLWR and LWR PRA standards
  • Staff have considered the potential impact on future endorsements of LWR PRA standards 12

RG 1.247 Development Approach (2 of 2)

  • An information database tool was developed to help identify relationships and analyze differences between related requirements in different PRA standards and staff endorsements
  • Applicability of current staff endorsement in RG 1.200 for related LWR PRA standard requirements were cross-checked against the NLWR PRA standard requirements 13

RG 1.247 v. RG 1.200 Comparison (1 of 4)

Some differences:

  • RG 1.247 directly relates to meeting regulations
  • RG 1.247 provides staff positions on the acceptability of PRA technical aspects for NLWRs that have not previously been provided for LWRs in RG 1.200
  • RG 1.247 provides specific guidance on determining risk significance and the use of relative and absolute importance measures 14

RG 1.247 v. RG 1.200 Comparison (2 of 4)

Some differences:

  • Consistent with the approach in the NLWR PRA standard, RG 1.247 does not use terms such as:

- Level 1, Level 2, or Level 3 PRA

  • RG 1.247 accommodates determining the acceptability of an NLWR PRA for an LMP application
  • Because the staff identified no exceptions for NEI 20-09, the endorsement is only contained in the body of the RG

- Plant Operating State Analysis for all POSs

- Internal fire PRA for LPSD-types of POSs

- Radiological consequence

- Risk Integration 15

RG 1.247 v. RG 1.200 Comparison (3 of 4)

Some similarities:

- Initiating Event Analysis - Hazards Screening Analysis

- Event Sequence Analysis - High Wind PRA

- Success Criteria Development - External Flood PRA

- Systems Analysis - Other Hazards PRA

- Human Reliability Analysis - Event Sequence Quantification

- Data Analysis - Mechanistic Source Term

- Internal Flood PRA Analysis

- Internal Fire PRA

- Seismic PRA 16

RG 1.247 v. RG 1.200 Comparison (4 of 4)

Some similarities:

  • Both include a table of hazards to consider in the development of a PRA
  • Both provide guidance to applicants and licensees on:

- What is an acceptable PRA (Section C.1)

- The use of voluntary consensus standards and an acceptable peer review process (Section C.2)

- How to demonstrate acceptability of PRA for an application (Section C.3)

- PRA documentation needed to support a regulatory decision (Section C.4) 17

Novel Staff Positions in RG 1.247 (1 of 5)

  • Plant Operating State Analysis for all POSs

- (Section C.1.3.1)

  • Internal fire PRA for LPSD-types of POSs

- (Section C.1.3.9)

  • Radiological consequence

- (Section C.1.3.17)

  • Risk integration

- (Section C.1.3.18) 18

Novel Staff Positions in RG 1.247 (2 of 5):

Plant Operating States Analysis, all POSs

  • Staff position in RG 1.247 goes beyond the scope of RG 1.200 to address all POSs
  • Considers that there may be more than one type of at-power POS (e.g., online refueling)
  • Staff position accounts for the potential need for a similar staff position for LWRs 19

Novel Staff Positions in RG 1.247 (3 of 5):

Internal Fire PRA, LPSD-Types of POSs

  • No analogous staff positions for LWRs
  • The NLWR PRA standard does not provide related requirements; as such, acceptability is measured against the staff position in Section C.1.3.9 of RG 1.247
  • Staff position accounts for the potential need for a similar staff position for LWRs
  • NRC initiating a research project to develop guidance 20

Novel Staff Positions in RG 1.247 (4 of 5):

Radiological Consequence

  • An LMP application evaluates frequency and radiological consequence risk
  • Outside of LMP applications, there are no regulatory requirements to perform a PRA that assesses consequence risk
  • However, it is still important to meet Commission expectations as expressed in various policy statements
  • Risk surrogates used for NLWRs will need to be justified 21

Novel Staff Positions in RG 1.247 (5 of 5):

Risk Integration

  • No staff position on risk integration has previously been promulgated
  • Basis for staff position relates to meeting Commission expectations, as expressed in the Advanced Reactor Policy Statement, which in turn references the Safety Goal Policy Statement and the importance of meeting the QHOs
  • Unless justified, relative risk significance criteria should be used to develop the PRA.
  • Staff determination of PRA acceptability does not include consideration of risk reporting thresholds 22

Scope of RG 1.247 and Staff Positions on Non-LWR PRA Standard Hanh Phan, NRR 23

RG 1.247 Guidance RG 1.247 provides guidance, for trial use, in the following four areas:

1. Defining the acceptability of a PRA and its results used in support of an application - RG 1.247, Section C.1
2. Demonstrating the acceptability of the PRA and its results used in an application - RG 1.247, Section C.3
3. Documentation to support a regulatory decision - RG 1.247, Section C.4
4. Staffs positions on NLWR PRA standard and industry PRA peer review process - RG 1.247, Section C.2 and Appendix A 24

Technical Reviewers Technical Element NRC Reviewer Plant Operating States Analysis Marie Pohida Initiating Event Analysis Keith Tetter Event Sequence Analysis Keith Tetter Success Criteria Analysis Keith Tetter Systems Analysis Hanh Phan Human Reliability Analysis Jonathan DeJesus Data Analysis Hanh Phan Internal Flood PRA Matt Humberstone Internal Fire PRA JS Hyslop Internal Fire PRA LPSD JS Hyslop Seismic PRA Shilp Vasavada Hazard Screening Analysis Alissa Neuhausen High Winds PRA John Lane External Flooding PRA Shilp Vasavada Other Hazards PRA Alissa Neuhausen Event Sequence Quantification Hanh Phan Mechanistic Source Term Analysis Michelle Hart Radiological Consequence Analysis Keith Compton Risk Integration Susan Cooper Newly Developed Methods Shilp Vasavada Peer Review Hanh Phan 25

NLWR PRA Scope

  • Address all radiological sources at the plant

- Reactor cores

- Spent fuel

- Fuel reprocessing facilities

- Accident scenarios that lead to a radioactive release from multiple radiological sources

  • Address all hazards

- All internal hazards such as, but not limited, to internal initiating events, internal floods, and internal fires

- All external hazards such as, but not limited to, seismic events, external floods, and high wind events

  • Address all plant operating states (e.g., at-power, low-power, shutdown)
  • NLWR PRA should be a Level 3 PRA

- Develop the frequencies of accident scenarios from the occurrence of an initiating event until the release of radioactive materials to the environment

- Estimate the consequences that result from the release 26

Applicable Regulations and Applications

- Current regulations do not require applicants for Part 50 construction permits or operating licenses to provide PRA-related information

- Rulemaking Incorporation of Lessons Learned from New Reactor Licensing Process (Parts 50 and 52 Licensing Process Alignment), Docket NRC-2009-0196, RIN-3150-AI66

- Subpart B - Standard Design Certification (DC)

- Subpart C - Combined License (COL)

- Subpart E - Standard Design Approval (SDA)

- Subpart F - Manufacturing License (ML)

- Rulemaking Risk Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors, Docket NRC-2019-0062, RIN 3150-AK31

- Being developed as required by the Nuclear Energy Innovation and Modernization Act (NEIMA) 27

Applicability of RG 1.247 Applies to only stationary NLWRs:

  • Reactors that are constructed at a site
  • Reactors that are constructed at an offsite facility and subsequently transported and installed at a site
  • Does not address PRAs used to assess the risk of transporting NLWRs from an offsite facility to the site
  • Does not address mobile reactors, which may be relocated to different sites after initial criticality 28

Technical Elements RG 1.247 endorses the following PRA standard technical elements:

1. Plant Operating State Analysis 10. Seismic PRA
2. Initiating Event Analysis 11. Hazards Screening Analysis
3. Event Sequence Analysis 12. High Wind PRA
4. Success Criteria Development 13. External Flooding
5. Systems Analysis 14. Other Hazards PRA
6. Human Reliability Analysis 15. Event Sequence Quantification
7. Data Analysis 16. Mechanistic Source Term Analysis
8. Internal Flood PRA 17. Radiological Consequence Analysis
9. Internal Fire PRA 18. Risk Integration and ASME/ANS RA-S-1.4-2021:
  • Definitions and Risk Assessment Application
  • PRA configuration control
  • Peer review
  • Newly Developed Methods 29

Endorsement of Nonmandatory Appendices

  • The nonmandatory appendices in ASME/ANS NLWR PRA standard may be binned into two groups:

a) Notes that support the understanding of various SRs, and b) Commentaries

  • The NRC staff generally accepts the Notes
  • The NRC staff provides no opinion about the Commentaries 30

Capability Categories In general, about 20% of the supporting requirements distinguish between CC-I and CC-II 31

Section C.1 - Acceptability of a PRA and Its Results Used in Support of an Application

  • The staff assesses acceptability of the PRA and its results with respect to:

- PRA scope

- Level of detail

- Conformance with consensus standard PRA elements

- Plant representation of a PRA 32

PRA Acceptability PRA Scope PRA Level of Detail

  • Metrics used to characterize risk
  • Defined in terms of the resolution of the
  • Plant operating states (POSs) for which modeling used to represent the the risk is to be evaluated behavior and operations of the plant
  • A minimal level of detail is necessary to groups) ensure that the impacts of designed-in dependencies are correctly captured PRA Acceptability PRA Technical Elements Plant Representation
  • Defined in terms of the fundamental
  • How closely the base PRA represents the technical analyses needed to develop and plant as it is actually built and operated quantify the base PRA model for its
  • The PRA should be maintained and intended purpose upgraded, where necessary, to ensure it
  • The characteristics and attributes of PRA represents the as-built and as-operated technical elements define specific plant requirements that should be met 33

Section C.3 - Demonstrating Acceptability of PRA and Its Results Used in an Application For all applications, the PRA-related information provided in the submittal should:

  • Describe the PRAs scope, level of detail, and degree of plant representation
  • Demonstrate that the PRA has been developed and used in a technically acceptable manner, including the appropriateness of the assumptions and approximations
  • Identify the application-specific acceptance criteria and demonstrate that they have been met 34

Section C.4 - Documentation to Support a Regulatory Decision

  • Documentation of the PRA model and the analyses performed should comprise both:

- Archival information (i.e., available for audit or inspection), and

- submittal information (i.e., submitted as part of the risk-informed request)

  • Archival PRA documentation may be required on an as-needed basis to facilitate the NRC staffs review of the application 35

Section C. 4 - Documentation (continued)

Archival PRA documentation should include:

  • The process used to determine the acceptability of the PRA
  • The methodology used to assess the risk of the application
  • SSCs, operator actions, and plant operational characteristics affected by the application
  • How the cause-effect relationships are mapped onto the PRA elements
  • The PRA results that will be used to compare against the applicable acceptance criteria
  • The scope of risk contributors (hazard groups and modes of operation) included in the PRA to support the application
  • The results of the peer reviews of the PRA, PRA upgrades, and use of NDMs, and the results of F&O independent assessments, the resolution of all of the peer reviews
  • The processes for maintaining & upgrading the PRA and the use of NDMs 36

Section C.4 - Documentation (continued)

Submittal PRA documentation should include:

  • Demonstration that the PRA model represents the as-designed, as-to-be-built, and as-to-be-operated plant or the as-built and as-operated plant
  • The appropriateness of key assumptions and approximations and sensitivity studies
  • The appropriateness of a given portion of the PRA that meets a capability category lower than deemed required for the application under consideration
  • The appropriateness of PRA model upgrades, including the use of NDMs, for the application under consideration 37

Section C.2 and Appendix A - Staff Positions on PRA Standard and PRA Peer Review Process

  • About 80% of the requirements in the NLRW PRA standard were taken as-is from the set of LWR PRA standards
  • First consideration ballot for the ANLWR PRA standard (3/24/20 -

5/26/20)

- NRC staff submitted 489 comments, represented a broad set of staff views and perspectives

  • Recirculation ballot for the ANLWR PRA standard (7/23/20 -

8/26/20)

- NRC staff submitted 70 comments, included a mix of proposed technical changes and observations related to regulatory issues 38

Section C.2 and Appendix A - Staff Position on PRA Standard (continued)

The staff position on each requirement in ASME/ANS RA-S-1.4-2021 is categorized as:

  • No objection - The staff has no objection to the requirement
  • No objection with clarification - The staff has no objection to the requirement. However, certain requirements, as written, are either unclear or ambiguous, and therefore the staff has provided its understanding of these requirements
  • No objection subject to the following qualification - The staff has a technical concern with the requirement and has provided a qualification to resolve the concern 39

Rationale for the Staff Positions

  • JCNRM did not address during ballot process stating that comment needs to be addressed first in the LWR Level 1/LERF PRA standard
  • Regulatory issue
  • New issue
  • Issue was not adequately addressed during balloting
  • Not fully addressed by JCNRM
  • Added for consistency with the staffs position in RG 1.200, Rev. 3 40

Clarification and Qualification Positions Table Description Clarification Qualification Total A-1 Front Matter 3 2 5 A-2 Plant Operating States 3 5 8 A-3 Initiating Events 0 0 0 A-4 Event Sequences 0 0 0 A-5 Success Criteria 0 0 0 A-6 Systems Analysis 5 0 5 A-7 Human Reliability Analysis 7 4 11 A-8 Data Analysis 0 1 1 A-9 Internal Floods 7 1 8 A-10 Internal Fires 1 0 1 A-11 Seismic 22 6 28 A-12 Hazard Screening 8 1 9 A-13 High Winds 4 2 6 A-14 External Floods 14 1 15 A-15 Other Hazards 10 1 11 A-16 Quantification 0 0 0 A-17 Mechanistic Source Terms 0 0 0 A-18 Radiological Consequences 23 5 28 A-19 Risk Integration 6 2 8 A-20 Configuration Control 0 1 1 A-21 Peer Review 0 0 0 A-22 Newly Developed Methods 1 1 2 Totals 114 33 147 41

Substantive Clarifications and Qualifications Group Clarifications Qualifications Total Group 1: Low Power and Shutdown Risk 2 2 4 Group 2: External Hazard Risk 4 2 6 Group 3: Errors of Commission 0 2 2 Group 4: Risk Significance 1 0 1 Group 5: Reporting Requirements 2 2 4 Total 9 8 17 42

Group 1 - Low Power and Shutdown Risk

  1. Index No. Issue Position Resolution 1.1 POS-N-2 All stages of the licensing process Clarification Early pre-operational stage PRAs are typically limited to at-power should address low power and PRAs only. All stages of the licensing process should address low shutdown-types of evolutions power and shutdown-types of evolutions 1.2 POS-N-4 All stages of the licensing process Clarification Depending on the application, the evolution to be addressed may should address low power and range from at-power only to all plant operating states outage shutdown-types of evolutions types. All stages of the licensing process should address low power and shutdown-types of evolutions.

1.3 POS-A1 Limiting the CC-I requirement for POS- Qualification CC-I A1 only to at-power plant evolutions IDENTIFY a representative set of plant evolutions to be analyzed.

potentially excludes a significant risk INCLUDE, at a minimum, plant evolutions from at-power contributor as low-power and operations.

shutdown-types of POSs have been See Note POS-N-1, POS-N-2, POS-N-3, POS-N-4 shown to have a comparable risk in CC-I and CC-II IDENTIFY a representative set of plant evolutions to be analyzed, some cases to at-power POSs. As such, including refueling outages, other controlled shutdowns, and the scope of the CC-I requirement forced outages.

should be the same as the scope of See Note POS-N-3 the CC-II requirement to avoid excluding potentially significant contributors to risk.

1.4 POS-B1 Omitting the condition to ensure that Qualification CC-I the POS grouping does not impact GROUP plant evolutions into a set of representative evolutions.

risk-significant event sequences could ENSURE that significantly impact the results and (a) the evolutions within a group can be considered similar in insights from the PRA. As such, a new terms of the set of plant operating states that they contain; requirement is needed for CCI to (b) the evolutions are bounded by the worst case impact within reflect as much. the group; (c) the grouping does not impact risk-significant event sequences.

43

Group 2 - External Hazard Risk

  1. Index No. Issue Position Resolution 2.1 SFR-C1 Justification of the selected basis needs to be Clarification SPECIFY the basis for screening of inherently provided, especially for cases where the basis rugged components justifying the applicability to in an extension or expansion of available the plant and site or range of sites identified in information. Note S-N-27 also mentions SHA-A1.

plant-specific justification which is not reflected in the SR.

2.2 SFR-C2 Justification of the selected basis needs to be Clarification SPECIFY the basis and methodologies established provided, especially for cases where the basis for achieving the fragility thresholds defined in in an extension or expansion of available Requirement SPR-B5 justifying the applicability to information. This comment is also supported the plant and site or range of sites identified in by the discussion in Note S-N-28. SHA-A1.

2.3 HS-A3 The requirement does not address plant- Clarification IDENTIFY site-, plant-, or and design-specific unique specific hazards, which may not be identified hazards and hazard groups, as applicable to the as part of the identification of site-specific or stage of the plant lifecycle, not already identified in design-specific hazards or hazard groups. Requirement HS-A2.

Additionally, note HS-N-5 appears to be See Notes HS-N3, HS-N-4, HS-N-5.

applicable to HS-A3 as it directly relates to plant-specific hazards and hazard groups.

2.4 WHA-A5 150 mile distance is arbitrary Clarification

a. meet SCR-3 in Table 1.10-1 by showing that the site is more than 150 miles (approximately 250 km) is sufficiently far away from the nearest tropical cyclone-prone coast to screen out tropical cyclone (hurricane or typhoon) high wind hazards from the probabilistic wind hazard analysis; 44

Group 2 - External Hazard Risk (continued)

Index No. Issue Position Resolution 2.5 SHA-B5 SHA-B5 does not include Qualification Add the following to SHA-B5:

consideration of (1) the use of an If an existing probabilistic SHA is used, DEMONSTRATE that an existing probabilistic SHA for a site updated catalog of earthquakes does not make the existing and, (2) the impact of an updated probabilistic SHA unviable.

catalog on the use of the existing probabilistic SHA. Given the likelihood of using an existing site as the bounding site (see SHA-A1),

the considerations identified above are warranted.

2.6 HS-B5 The values in RI-A5 referenced in Qualification USE SCR-3 in Table 1.10-1 when qualitatively screening out a item (f) are presented as reporting hazard or hazard group by showing that either:

values, not screening values. Using (a) the hazard or hazard group cannot physically impact the the reporting values as screening plant or plant operations (e.g., it cannot occur close enough to values could be too permissive in the plant to affect it);

excluding contributors from the (b) the hazard or hazard group does not result in a plant trip (manual or automatic) or require a plant shutdown; PRA as screening using a (c) the hazard or hazard group is included in the definition of consequence criterion may not be another hazard; effectively equivalent to screening (d) the hazard or hazard group could not result in worse effects using a frequency criterion. to the plant as another hazard that has a significantly higher Additionally, this requirement is frequency; effectively for qualitative screening, (e) the hazard or hazard group is slow in developing and there is as per SCR-3 in Table 1.10-1 and demonstrably sufficient time to eliminate the source of the because item (f) is a quantitative threat or to provide an adequate response; criterion, it should therefore not be (f) the hazard or hazard group cannot produce a consequence included in the list. above the value set in RI-A5.

45

Group 3 - Errors of Commission

  1. Index No. Issue Position Resolution 3.1 HLR-HR-E The scope of high-level requirement (HLR) HR-E does not include Qualification A systematic review of relevant errors of commission. See HR-E4 in this table for more details about available procedures, any past the basis for this issue. operational events, procedural guidance, and training shall be used to identify the set of post-initiator operator responses required for each of the event sequences, as well as, the well-intended post-initiator operator responses that result in adverse safety impacts.

3.2 HR-E4 HR-E4 does not include errors of commission (EOC). EOCs should be Qualification Add the following to item to included in the advanced non-light water reactor (LWR) PRA HR-E4:

standard for the following reasons: (1) the significant amount of experience in operating LWRs facilitates a consensus between NRC (c) those well-intended and industry to exclude EOCs from the LWR Level 1/large, early actions performed by control release frequency (LERF) PRA standard; however, there is very little room staff that disable a (if any) advanced non-LWR operating experience to allow the system, sub-system, or consensus to exclude EOCs from the advanced non-LWR PRA component needed in an event standard; (2) it is expected that advanced non-LWRs would rely less scenario.

on human actions than LWRs, which implies that EOCs would play a more important role in advanced non-LWR PRAs than in LWR Level 1/LERF PRAs; and (3) given that (a) the scope of the advanced non-LWR PRA standard covers what in the LWR world is known as Level 2 PRA and (b) there is no consensus about EOCs in Level 2 PRA, the developers of PRAs for advanced non-LWRs should demonstrate that EOCs are not an issue before eliminating them from consideration.

46

Group 4 - Risk Significance

  1. Index No. Issue Position Resolution 4.1 RI-N-1 Proper use of relative and Clarification Add this text: The choice between using relative or absolute risk absolute risk significance significance criteria to develop a PRA should consider issues such as, criteria. but not limited to the following:
  • The use of absolute risk significance criteria may yield a limited set of risk-significant items that is insufficient for developing risk insights or verifying the PRA model.
  • Importance measures traditionally used in LWR PRAs to identify relative risk significant items (e.g., FV and RAW) may be inaccurate or misleading when applied to noncoherent logic models (i.e., logic models that contain NOT logic).
  • A PRA that is developed using absolute risk significance criteria should be revised if relative risk significance criteria are used to support a subsequent application, and vice versa.

The use of risk significance criteria (relative or absolute) should address the entire set of risk metrics computed by the PRA.

47

Group 5: Reporting Requirements

  1. Index No. Issue Position Resolution 5.1 RI-N-3 The staff do not consider reporting requirements when Clarification The reporting requirement in RI-determining the acceptability of a PRA for a given application, A4 does not need to be met to such reporting requirements should be provided by the demonstrate PRA acceptability.

appropriate regulatory authority on an application-specific basis.

5.2 RI-N-4 The staff do not consider reporting requirements when Clarification The reporting requirement in RI-determining the acceptability of a PRA for a given application. A5 does not need to be met to Such reporting requirements should be provided by the demonstrate PRA acceptability.

appropriate regulatory authority on an application-specific basis.

5.3 RI-A4 The staff do not consider reporting requirements when Qualification This requirement does not need determining the acceptability of a PRA for a given application. to be met to demonstrate PRA Such reporting requirements should be provided by the acceptability.

appropriate regulatory authority on an application-specific basis.

5.4 RI-A5 The staff do not consider reporting requirements when Qualification This requirement does not need determining the acceptability of a PRA for a given application. to be met to demonstrate PRA Such reporting requirements should be provided by the acceptability.

appropriate regulatory authority on an application-specific basis.

48

NEI 20-09 PRA Peer Review Guidance

  • NRC staff received NEI 20-09, Rev. 0 on June 1, 2020
  • Staff reviewed and provided observations during a public meeting on July 22, 2020
  • Staff received a revision to NEI 20-09 on August 24, 2020
  • Staff provided additional comments during a public meeting on October 26, 2020
  • NEI submitted Revision 1 of NEI 20-09 on May 5, 2021 49

NEI 20-09 PRA Peer Review Guidance

  • NEI 20-09, Rev. 1, is based on a related industry PRA peer review guidance document, NEI 17-07, Rev. 2, Performance of PRA Peer Reviews Using the ASME/ANS PRA Standard, as endorsed by RG 1.200, Rev. 3
  • NEI 20-09 addresses all radiological sources, all hazards, all POSs, and all levels of PRA analysis
  • NEI 20-09 process is applicable for a peer review performed for a PRA representing any stage of plant lifecycle
  • The staff finds that the guidance in NEI 20-09, Rev. 1, is acceptable and thus endorses NEI 20-09, Rev. 1, without exception, in RG 1.247, Section C.2.2
  • The ASME/ANS NLWR PRA standard contains requirements for the performance of an acceptable peer review process. The staff reviewed the requirements and takes no exceptions to them 50

NEI 20-09 Pilots

  • NEI plans to pilot the peer review process
  • Staff to observe the pilots
  • Observations will enhance the staffs positions in RG 1.247 51

NLWR PRA Acceptability Issues (1 of 3)

  • Ten issues were identified as a result of stakeholder feedback on the draft staff white paper Demonstrating the Acceptability of Probabilistic Risk Assessment Results Used to Support Advanced Non-Light Water Reactor Plant Licensing:

- Draft staff white paper: ML21015A434 dated 1/19/2021

- Public meeting held 2/23/2021

- Public meeting held 3/30/2021

  • Issue resolution status:

- Addressed in RG 1.247, or

- Being addressed in other staff guidance, or

- Initiating research and developmental activities 52

NLWR PRA Acceptability Issues (2 of 3)

No. Issue Resolution 1 Provide guidance on initial licensing LMP-based applications:

that addresses all NLWRs (LMP or not

LMP)

  • ARCAP roadmap ISG
  • ARCAP-related ISGs on specific topics Non-LMP-based Applications: deferred 2 Provide guidance on graded PRA Working group formed to explore alternatives to approaches PRA that achieve the same underlying purposes 3 Provide guidance on voluntary risk- NRR/RES work request informed applications (in addition to LMP) that may be part of an initial license application or after the license has been issued 4 Address the use of risk surrogates Addressed in RG 1.247 5 Address the use of seismic margins
  • SMA excluded in NLWR PRA standard and, analysis (SMA) hence, not addressed in RG 1.247
  • Applicants who seek to use SMA are encouraged to discuss during pre-application interactions 53

NLWR PRA Acceptability Issues (3 of 3)

No. Issue Resolution 6 Address completeness uncertainty

  • LPSD fires: NRR/RES work request
  • Uncertainty: NRR/RES work request 7 Define the bounding site for external Each applicant to propose and justify on a case-hazards and radiological consequence by-case basis evaluation 8 Address the applicability of Develop ISG supporting requirements (SRs) during various licensing stages 9 Address the use of absolute and Addressed in RG 1.247 relative risk significance criteria 10 Use of peer reviews (full-scope and Addressed in RG 1.247 focused-scope) to demonstrate PRA acceptability 54

Risk Significance (1 of 3)

  • Goal: Identify what is important
  • Uses:

- Develop the PRA model

  • Increase level of detail and plant representation for risk significant items
  • Logic model debugging
  • Iterative process

- Report PRA results

  • Two approaches:

- Relative risk significance

  • Normalized to total risk
  • Traditional PRA approach

- Absolute risk significance

  • Normalized to a specified risk target (e.g., LMP frequency-consequence target curve, QHOs)
  • Concept evolved as a result of various LMP pilot exercises 55

Risk Significance (2 of 3)

Risk Significant Basic Event Relative A basic event that contributes significantly to baseline risk. It is defined as any basic event that has an Fussell-Vesely (FV) importance greater than 0.005 or a risk achievement worth (RAW) importance greater than 2 where the importance is normalized against the baseline total integrated risk or risk of a specific combination of source of radioactive material, hazard, and plant operating state.

Absolute A basic event that contributes significantly to an absolute risk significance criterion selected for RIDM. It is defined as any basic event that contributes significantly to an absolute risk significance criterion selected for RIDM. It is defined as any basic event that a) contributes at least 1% to any identified absolute risk target; or b) would result in exceeding the criterion if the basic event is assumed to fail with probability of 1.0.

56

Risk Significance (3 of 3)

Risk Significant Event Sequence or Event Sequence Family Relative An event sequence or event sequence family that, when rank-ordered by decreasing frequency, contributes a specified percentage of the baseline risk, or that individually contributes more than a specified percentage of the risk. For this version of the Standard, the aggregate percentage for the set is 95%, and the individual event sequence or event sequence family percentage is 1% of the total integrated risk or risk of a specific combination of source of radioactive material, hazard, and plant operating state.

Absolute An event sequence or event sequence family included in a PRA model, defined at the functional or systematic level, that makes a significant contribution to an absolute risk target selected for RIDM. It is defined as any event sequence or event sequence family that contributes at least 1% to any identified absolute risk target.

57

PERSONAL COMMENTS ON RG 1.247 Karl N. Fleming Former Chair JCNRM WG on Advanced non-LWRs (Currently Vice Chair) karlfleming@comcast.net

59 MY PERSONAL COMMENTS The following comments are my personal opinions and do not reflect the official position of the JCNRM or supporting groups and subcommittees ACRS Meeting on RG 1.247

60 BACKGROUND

  • Per NRC request JCNRM prioritized the schedule for this standard ahead of next edition LWR PRA standard
  • JCNRM appreciates extensive involvement of NRC staff and NRC contractors in producing the standard and support of Ballot Reviews
  • First consideration ballot in May 2020 yielded over 1300 comments including nearly 500 from NRC staff
  • Second consideration ballot in July 2020 was unanimously approved by the JCNRM with 86 largely editorial comments mostly from the NRC
  • Final editorial changes approved by JCNRM via two unanimous voice votes
  • Standard approved by ASME and ANS boards, no comments in public review and final approval by ANSI
  • Changes were made to the next edition of LWR standard recently balloted to minimize editorial inconsistencies.
  • Given that background I was surprised that the approach taken to express clarifications in the RG was expressed in terms of so many further editorial changes rather than commentary regarding HOW the NRC staff expects the requirements to be addressed for regulatory applications.

ACRS Meeting on RG 1.247

61

GENERAL COMMENT

S

  • There are several places that claim that risk characterization for NLWRs is typically expressed by cumulative risk metrics or risk surrogates.
  • These statements should be modified to clarify the that fundamental metrics used to formulate the requirements characterize risk in terms of the frequencies and radiological consequences of event sequence families (not individual sequences).
  • The NLWR standard does not use the LWR risk metrics CDF or LERF as explained in Section 1.9.1 so not clear why it is suggested as a possibility in the RG.
  • The PRA standard does not support the use of surrogate risk metrics as a means of expressing the results of the PRA but only as intermediate states for developing the event sequence model. If such intermediate metrics are used, the standard still expects that risk integration and evaluation of risk significance will be based on quantification of frequencies and consequences.
  • Sections C.1.3 and C.1.4 provide a long discussion of objectives and attributes for each of the technical elements in the standard. These discussions overlap extensively with material in the standard that cover the same ground but they are not one for one and it would take a long time to figure out if there is anything different here. Rather than paraphrasing material on objectives and attributes already covered in the standard, the RG should focus on the specific items that the staff wishes to clarify
  • Many of the clarifications in Appendix A refer to language shared with LWR supporting standards
  • In the clarifications provided in Appendix A, it would be helpful for the staff to point out which changes are for alignment with LWR standard vs. those unique to the NLWR standard ACRS Meeting on RG 1.247

62 SPECIFIC COMMENTS

  • Suggestion that PRA technical adequacy are the same as PRA acceptability needs clarification; technical adequacy is based on meeting requirements in an international consensus PRA standard while acceptability expresses a U.S. regulatory position.
  • The PRA technical elements presented in Table 1 are not consistent with the ones used in the standard (See Table 1.4-1). The elements listed for internal events are applicable to all internal and external hazard groups. This is one of a number of examples where the RG is paraphrasing material in the standard but in a manner that is not always accurate.
  • Should be clarified that the technical requirements for peer review are actually part of the standard and not separate entities as suggested in Figure 1 (Triangle Figure).
  • Discussion on POS, MST, and other elements seem to lack appreciation of the need to address the impact of multiple reactors and sources.
  • The RG treats documentation in one section whereas standard has documentation requirements specialized for each technical element
  • Regarding the staff position on reporting requirements RI-A4(low frequency item) and RI-A5(low consequence item), which defer to specific applications, the authors of the standard believe these are fundamental to recognizing limitations in PRA technology.
  • My colleague Dennis Henneke has additional general and specific comments to offer ACRS Meeting on RG 1.247

63 PLANS FOR NEXT REVISION

  • Per JCNRM guidance, need to wait until all the supporting LWR standards are revised for consistency with the recently balloted LWR Level 1/LERF Standard
  • Low Power Shutdown Standard
  • Level 2 Standard
  • Level 3 Standard
  • Advanced LWR Standard
  • Advanced non-LWR community needs to gain sufficient experience using the 2021 edition of the NLWR standard to identify the issues unique to NLWRs and to justify application of standard writing resources.
  • Schedule for next revision is undefined ACRS Meeting on RG 1.247

Review of Draft RG 1.247 Appendix A - NRC Position on ASME/ANA RA-S-1.4-2021 Dennis Henneke Consulting Engineer - GE Hitachi JCNRM ANS Chair*

  • Not representing ANS or the JCNRM for this presentation.

64

Overview of ASME/ANS PRA Standard Requirements

  • The Joint Committee on Nuclear Risk Management (JCNRM) develops and maintains PRA standards for LWRs and NLWRs using a consensus committee made up of all stakeholders including the NRC and its contractors.
  • The NRC provided hundreds of comments on RA-S-1.4-2021, the vast majority were accepted.
  • PRA Standards for existing LWRs (draft 2021) and NLWRs (RA-S-1.4-2021) define the following to determine a technically acceptable PRA:
  • Scope: This includes the hazards (internal events, internal hazards and external hazards) and the plant operational states (full power, low power and shutdown) for each hazard.
  • PRA Attributes: as defined by the High Level Requirements (HLRs) and Supporting Requirements (SRs). HLRs are in the form of Shall statements and SRs support the HLRs.

Content of HLRs and SRs are prescribed by the ASME and ANS guidance.

  • The PRA standard SRs define what is required (performance-based) to meet the HLRs but should not describe how to meet the requirement or limit the approach to a single methodology by referencing a document in an SR.
  • The NRC and JCNRM members have provided numerous comments on removing wording from the SRs that were too much how to perform the PRAs.

65

Feedback on NRC Clarifications

  • The standard has undergone numerous rounds of review including in 2020, and the resulting standard is a consensus product. Many of the NRC clarifications have either gone through consensus review or should go through consensus review for determination of technical correctness:
  • POS-A8: the addition of requiring review of POSs identification by operations personnel prior to plant operations (in design) - when we will not necessarily have operations personnel.
  • POS-A10: The clarification requires POS definitions to include changes in barriers, propagation pathways and modification of fragilities in the POS definitions.
  • This both disagrees with the definition of POS and is too much how to in the SR.
  • Changes such as this are addressed in the PRA modeling, not POS definition.
  • POS-A1 and Note POS-N-2: Clarification is requiring LPSD to be included at All stages of the Licensing Process.
  • Disagrees with the discussion throughout the standard and the consensus wording of POS-A1.
  • The standard is not a licensing document and should not discuss what is required at various stages of licensing.

66

Feedback on NRC Clarifications

  • HLR-HR-E; Added words to the HLR: A systematic review shall be used to identify post-initiator operator responses as well as, the well-intended post-initiator operator responses that result in adverse safety impacts
  • Too much how to in the HLR.
  • When combined with changes to HR-E4 (actions that disable a system); the changes now require additional analysis of errors of commission, not currently required by any PRA standard.
  • HR-D4: Adds reference to NUREG-0700 for adherence to human factors guidelines
  • Again, too much how to.
  • Additionally, reference to a specific document in the SR is not appropriate, since this indicates only one acceptable approach to meet the SR.
  • HR-G1: Adds to the requirement wording to ASSESS the feasibility of the HFE.;

ASSIGN an HEP of 1.0 if not feasible.

  • Again, too much how to.
  • HRA techniques already include a feasibility step during the qualitative portion of the HRA.
  • A similar change was rejected by the JCNRM previously for the above reasons.
  • HR-G4: Adds the wording: in supporting the decision, diagnosis, decision-making and action execution given the plant-specific and event scenario-specific contextcommunication among personnel in the same team and in different teams.
  • Again, too much how to 67

Feedback on NRC Clarifications

  • JCNRM standard are not perfect, and we welcome feedback and improvements through the consensus process.
  • Generally, we try to accommodate most comments through change in the standard wording.
  • Some of the NRC exceptions were changes incorporated into the LWR draft in publication (no objection to these).
  • RG 1.247 exceptions do not point to any significant gaps in the NLWR standard.
  • The previous examples above are just a few examples where the draft RG should be improved (see backup slide for more examples):
  • Overall, these types of changes should be submitted to the JCNRM NLWR working group for review and consideration to ensure the standard SRs are correctly worded and supported by consensus review.
  • Any NRC recommended changes to the standard wording should be consistent with standard development guidance:
  • Wording should focus on what is required versus how to perform the PRA.
  • HLRs and SRs should not reference specific documents or limit the approach to one approach.
  • The standard should not dictate what scope is required at different phases of licensing.

68

DWH Backup

  • Other NRC clarifications which should be reviewed:
  • HR-G14 (to much how to shown in blue), HR-H2, DA-C20, FLEV-C1 (1st mention of temp. alignments - under documentation), SHA-B5, SHA-D3, SFR-C1, C2, SFR-D5 (no other mention of pathways), SFR-E3, E4, E5, E7 (wording is too limiting), HLR-SPR-B, SPR-B6 (expands the relay chatter from Risk-Significant SSCs to all SSCs), SPR-D6 (see previous feasibility comment), SPR-E8 (and/or not appropriate), HS-A3 (hazards are not applicable to a design stage), HS-B5 (change should be reviewed by JCNRM in brown), WFR-I1 (fix the bullet numbers), WPR-D11 (see previous feasibility comment),

XFPR-E6, OPR-A4, OPR-C6 (feasibility), RCRE-A2, RCPA-A3, RCPA-A10, RCME-A2/4/7/8 (also refers to RG 1.23), RCME-A3, RCAD-A5, RCAD-B2, C1, RCDO-A and A1/6 (skin absorption not previously mentioned in the standard), RCDO-A8, RCQ-A3, RCQ-B3 (results of interest inaccurate).

  • Notes not reviewed for this presentation.

69

Next Steps and Stakeholder Engagement Donna Williams, NRR 70

Next Steps

  • Consider feedback from ACRS/other stakeholders (September

- mid-October)

  • Public meeting October 20, 2021
  • NRC concurrence and trial use RG publication - October -

November

  • Issue for trial use - December 2021
  • Initial use by near-term applicants
  • Trial use period is flexible, depending on timing of the next version of standard, rulemakings, and feedback from early use 57

Comments and Feedback

  • Comments and improvements on all published RGs including this trial use RG are encouraged at any time and the NRC will ensure consideration of such comments and suggestions.
  • Preliminary trial use RG made public - September 7, 2021
  • October 20, 2021- public meeting
  • Trial Use RG published in FRN. FRN includes information on submitting comments.
  • Public meetings/workshops to discuss feedback from first uses 72

Acronyms

  • ANLWR - advanced non-light water reactor
  • RG - regulatory guide
  • ANS - American Nuclear Society
  • SC - subcommittee
  • ASME - American Society of Mechanical Engineers
  • SSC - structures, systems and components
  • CFR - Code of Federal Regulations
  • SP - staff position
  • COL - combined license
  • SR - supporting requirement
  • CP - construction permit
  • SSC - structure, system, and component
  • DC - design certification
  • ISG - interim staff guidance
  • JCNRM - Joint Committee on Nuclear Risk Management
  • LMP - licensing modernization project
  • LPSD - low-power and shutdown
  • LWR - light-water reactor
  • NEI - Nuclear Energy Institute
  • NRC - Nuclear Regulatory Commission
  • NRR - Office of Nuclear Reactor Regulation
  • OGC - Office of the General Counsel
  • OL - operating license
  • QHO - quantitative health objective
  • POS - plant operating state
  • RES - Office of Nuclear Regulatory Research 73

General Framework for PRA Acceptability 74