ML081930252: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:July 11, 2008 | {{#Wiki_filter:UNITE D S TATES | ||
NUC LEAR RE GULATOR Y C OMMIS SI ON | |||
Rick A. Muench, President and | R EG I O N I V | ||
612 EAST LAMAR BLVD , SU ITE 400 | |||
AR L IN GTON , TEXAS 7 6 011 - 4125 | |||
July 11, 2008 | |||
Rick A. Muench, President and | |||
Chief Executive Officer | |||
Wolf Creek Nuclear Operating Corporation | |||
P.O. Box 411 | |||
Burlington, KS 66839 | |||
SUBJECT: WOLF CREEK GENERATING STATION - NOTIFICATION OF AN NRC | |||
TRIENNIAL FIRE PROTECTION BASELINE INSPECTION (NRC INSPECTION | |||
REPORT 05000482/2008010) AND REQUEST FOR INFORMATION | |||
Dear Mr. Muench: | |||
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC), | |||
Region IV staff will conduct a triennial fire protection baseline inspection at your Wolf Creek | |||
Generating Station in September and October of 2008. The inspection team will be comprised | |||
of reactor inspectors from the NRC Region IV office and a contractor. The team will conduct the | |||
inspection in accordance with the baseline Inspection Procedure 71111.05T, "Fire Protection | |||
(Triennial)." | |||
The schedule for the inspection is as follows: | |||
* Information gathering visit: September 10 - 11, 2008 | |||
* Onsite inspection: September 29 - October 3, 2008 | |||
October 20 - 24, 2008 | |||
The team will visit the Wolf Creek Generating Station on September 10-11, 2008, to gather | |||
information, select the fire areas for evaluation, identify documents needed to support the | |||
inspection, obtain unescorted access, and to become familiar with your fire protection program. | |||
The enclosure to this letter provides an initial list of the documents the team will want to review. | |||
You are requested to transmit copies of the documents listed in the enclosure to the NRC | |||
Region IV office for team use in preparation for the inspection. We would appreciate it if you | |||
could send this information so that it will arrive in our office in Arlington, Texas, by the dates | |||
listed in the enclosure. | |||
We request that during the onsite inspection weeks, you ensure that copies of analyses, | |||
evaluations, or documentation regarding the implementation and maintenance of the fire | |||
protection program, including post-fire safe shutdown capability, be readily accessible to the | |||
team for their review. Of specific interest are those documents that establish that your fire | |||
protection program satisfies the NRC regulatory requirements and conforms to applicable NRC | |||
Wolf Creek Nuclear Operating Corp. -2- | |||
and industry fire protection guidance. Also, appropriate personnel knowledgeable of: (1) plant | |||
systems required to achieve and maintain safe shutdown conditions from inside and outside the | |||
control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant | |||
fire protection systems, and (4) the fire protection program and its implementation should be | |||
available to support the team at the site during the inspection. | |||
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its | |||
enclosure will be available electronically for public inspection in the NRC Public Document | |||
Room or from the Publicly Available Records (PARS) component of NRCs document system | |||
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading- | |||
rm/adams.html (the Public Electronic Reading Room). | |||
Your cooperation and support during this inspection will be appreciated. If you have questions | |||
concerning this inspection or the inspection team's information or logistical needs, please | |||
contact the lead inspector, John Mateychick, at 817-276-6560. | |||
Sincerely, | |||
/RA/ | |||
Neil OKeefe, Chief | |||
Engineering Branch 2 | |||
Division of Reactor Safety | |||
Docket: 50-482 | |||
License: DPR-42 | |||
Enclosure: Triennial Fire Protection | |||
Inspection Supporting Documentation | |||
cc w/enclosure: | |||
Vice President Operations/Plant Manager | |||
Wolf Creek Nuclear Operating Corporation | |||
P.O. Box 411 | |||
Burlington, KS 66839 | |||
Jay Silberg, Esq. | |||
Pillsbury Winthrop Shaw Pittman LLP | |||
2300 N Street, NW | |||
Washington, DC 20037 | |||
Wolf Creek Nuclear Operating Corp. -3- | |||
Supervisor Licensing | |||
Wolf Creek Nuclear Operating Corporation | |||
P.O. Box 411 | |||
Burlington, KS 66839 | |||
Chief Engineer | |||
Utilities Division | |||
Kansas Corporation Commission | |||
1500 SW Arrowhead Road | |||
Topeka, KS 66604-4027 | |||
Office of the Governor | |||
State of Kansas | |||
Topeka, KS 66612 | |||
Attorney General | |||
120 S.W. 10th Avenue, 2nd Floor | |||
Topeka, KS 66612-1597 | |||
County Clerk | |||
Coffey County Courthouse | |||
110 South 6th Street | |||
Burlington, KS 66839 | |||
Chief, Radiation and Asbestos | |||
Control Section | |||
Kansas Department of Health and | |||
Environment | |||
Bureau of Air and Radiation | |||
1000 SW Jackson, Suite 310 | |||
Topeka, KS 66612-1366 | |||
Wolf Creek Nuclear Operating Corp. -4- | |||
Electronic distribution by RIV: | |||
Wolf Creek Nuclear Operating Corp. - | Regional Administrator (Elmo.Collins@nrc.gov ) | ||
DRP Director (Dwight.Chamberlain@nrc.gov) | |||
DRP Deputy Director (Anton.Vegel@nrc.gov ) | |||
DRS Director (Roy.Caniano@nrc.gov ) | |||
DRS Deputy Director (Troy.Pruett@nrc.gov) | |||
Senior Resident Inspector (Chris.Long@nrc.gov ) | |||
Branch Chief, DRP/B (Vincent.Gaddy@nrc.gov) | |||
Senior Project Engineer, DRP/B (Rick Deese@nrc.gov) | |||
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov ) | |||
DRS STA (Dale.Powers@nrc.gov ) | |||
P. Lougheed, OEDO RIV Coordinator (Patricia.Lougheed@nrc.gov ) | |||
ROPreports | |||
WC Site Secretary (Shirley.Allen@nrc.gov ) | |||
SUNSI Review Completed: ______ADAMS: Yes G No Initials: ______ | |||
Publicly Available G Non-Publicly Available G Sensitive Non-Sensitive | |||
S :DRS\REPORTS\WC 2008010 tfp-JMM. | |||
SRI:DRS/EB2 C: EB2 | |||
JMM/tek NFOKeefe | |||
/RA/ /RA/ | |||
07/7/08 07/10/08 | |||
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax | |||
ENCLOSURE | |||
Triennial Fire Protection Inspection Documentation Requested | |||
Please provide the following documentation prior to the onsite information-gathering trip, | |||
preferably no later than August 29, 2008. Where practical, please provide copies electronically. | |||
1. The current version of your fire protection program and fire hazards analysis. | |||
2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate | |||
acceptable plant response. | |||
3. Copies of the licensing basis documents for fire protection (Safety Evaluation Reports, | |||
pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters | |||
to/from the NRC regarding fire protection/fire safe shutdown, etc.). | |||
4. The Fire Probabilistic Risk Assessment or portions of the plants Individual Plant | |||
Examination for External Events report addressing fire events. | |||
Please provide the following documentation during the information-gathering visit or by | |||
September 19, 2008, in order to support inspection preparation. Where practical, please | |||
provide copies electronically. However, drawings should be provided as paper copies of | |||
sufficient size that all details are legible. | |||
5. Fire protection program implementing procedures (e.g., administrative controls, operator | |||
response procedures for fires, fire fighting procedures, etc.). | |||
6. Operating procedures used for achieving and maintaining hot and cold shutdown | |||
conditions from the control room in the event of a fire outside the control room (III.G.2 | |||
areas). | |||
7. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas) | |||
capability with or without control room evacuation. | |||
8. Pre-fire plans for the selected fire areas (areas to be selected by the team during the | |||
information-gathering trip). | |||
9. A list of equipment used to achieve and maintain hot standby and cold shutdowns in the | |||
event of a fire (safe shutdown equipment lists). | |||
10. Piping and instrumentation (flow) diagrams showing the components used to achieve | |||
and maintain hot standby and cold shutdown for normal and alternate shutdown. Please | |||
provide two copies of the piping and instrumentation (flow) diagrams for these systems | |||
of a size sufficient to read all details. These should include the systems used for RCS | |||
makeup, RCS pressure control, decay heat removal, and reactivity control, including the | |||
essential support systems. | |||
-1- Enclosure | |||
11. Plant layout and equipment drawings for the selected fire areas (these areas will be | |||
selected during the information gathering trip) that identify: (a) the physical plant | |||
locations of major hot standby and cold shutdown equipment; (b) plant fire area and/or | |||
fire zone delineation; and (c) the locations of fire protection equipment, such as | |||
detection, suppression, and post-fire emergency lighting units; and (d) fire area | |||
boundaries. | |||
12. A listing of design change packages which were determined to impact fire protection and | |||
post-fire safe shutdowns, performed in the last 3 years. | |||
13. Copies of Generic Letter 86-10 evaluations performed in the last 3 years. | |||
14. A listing of open and closed corrective action documents initiated in the last 3 years, | |||
which relate to the fire protection program or equipment. Include corrective action | |||
document number, date, and subject. | |||
15. A listing of the applicable codes and standards (with the versions) related to the design | |||
of plant fire protection features and evaluations of any code deviations. | |||
16. Drawings of the portions of the emergency lighting system which support fire response. | |||
17. Procedures used to remove smoke from safety-related areas and the engineering | |||
studies or calculations which support the design basis. | |||
18. Drawings of communication systems credited in the license basis for firefighting and | |||
plant operations during fires where control room is occupied and/or evacuated. | |||
19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems. | |||
20. A listing of maintenance and surveillance testing procedures for alternative shutdown | |||
capability and fire barriers, detectors, pumps and suppression systems. | |||
21. Maintenance Rule performance criteria and a summary of the last 3 years performance | |||
history for fire protection program systems or functions monitored within the | |||
Maintenance Rule program. | |||
22. A copy of fire protection program requirements (e.g. limiting conditions for operation, | |||
surveillance test requirements) covered by Technical Specifications, Technical | |||
Requirements Manual, Updated Final Safety Analysis Report, or similar documents. | |||
23. Copies of internal and external self-assessments, audits, peer-assessments or similar | |||
reviews related to post-fire safe shutdown capability or the fire protection program | |||
completed since November 1, 2005. | |||
24. A list of manual actions taken outside the control room which are credited to mitigate the | |||
consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should | |||
group actions by the initiating fire area or zone and indicate where the action must take | |||
place. | |||
-2- Enclosure | |||
25. Electronic copies of operator study guides (i.e. lesson plan text and graphics) or design | |||
basis documents that describe the purpose/function/operating characteristics of the safe | |||
shutdown systems (reactor coolant system (RCS) makeup, RCS pressure control, decay | |||
heat removal, and reactivity control, including the essential support systems). | |||
26. Two copies of one-line diagrams of the electrical distribution system. These should | |||
depict how power gets from the switchyard to the engineered safety feature loads (480V | |||
and 4160V). Also, include the vital DC distribution system one-line diagrams. | |||
27. A list of automatic and manually initiated gaseous fire suppression systems in the plant, | |||
giving location and the key equipment being protected. | |||
28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or | |||
maintain hot shutdown and b) reach and/or maintain cold shutdown. | |||
29. A list of high to low pressure interface valves. | |||
30. A copy of procedures governing the training and operation of the fire brigade. | |||
31. Organization charts of site personnel down to the level of fire protection staff personnel. | |||
32. A contact list of key site personnel who will be supporting this inspection, giving location | |||
of their office and phone number onsite. | |||
33. The team would like to observe a fire brigade drill in the plant, if possible, during the | |||
week of October 20, 2008. Please put us in contact with the appropriate personnel for | |||
planning drills during the onsite information gathering trip. | |||
34. The team would like to perform a walkthrough of the procedure for control room | |||
evacuation due to fire with qualified operators in the plant during the week of September | |||
29, 2008. Please put us in contact with the appropriate personnel for planning the | |||
walkthrough during the onsite information gathering trip. | |||
-3- Enclosure | |||
26. Two copies of one-line diagrams of the electrical distribution system. | |||
30. A copy of procedures governing the training and operation of the fire brigade. | |||
}} | }} |
Latest revision as of 16:01, 14 November 2019
ML081930252 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 07/11/2008 |
From: | O'Keefe N NRC/RGN-IV/DRS/EB2 |
To: | Muench R Wolf Creek |
References | |
IR-08-010 | |
Download: ML081930252 (7) | |
See also: IR 05000482/2008010
Text
UNITE D S TATES
NUC LEAR RE GULATOR Y C OMMIS SI ON
R EG I O N I V
612 EAST LAMAR BLVD , SU ITE 400
AR L IN GTON , TEXAS 7 6 011 - 4125
July 11, 2008
Rick A. Muench, President and
Chief Executive Officer
Wolf Creek Nuclear Operating Corporation
P.O. Box 411
Burlington, KS 66839
SUBJECT: WOLF CREEK GENERATING STATION - NOTIFICATION OF AN NRC
TRIENNIAL FIRE PROTECTION BASELINE INSPECTION (NRC INSPECTION
REPORT 05000482/2008010) AND REQUEST FOR INFORMATION
Dear Mr. Muench:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC),
Region IV staff will conduct a triennial fire protection baseline inspection at your Wolf Creek
Generating Station in September and October of 2008. The inspection team will be comprised
of reactor inspectors from the NRC Region IV office and a contractor. The team will conduct the
inspection in accordance with the baseline Inspection Procedure 71111.05T, "Fire Protection
(Triennial)."
The schedule for the inspection is as follows:
- Information gathering visit: September 10 - 11, 2008
- Onsite inspection: September 29 - October 3, 2008
October 20 - 24, 2008
The team will visit the Wolf Creek Generating Station on September 10-11, 2008, to gather
information, select the fire areas for evaluation, identify documents needed to support the
inspection, obtain unescorted access, and to become familiar with your fire protection program.
The enclosure to this letter provides an initial list of the documents the team will want to review.
You are requested to transmit copies of the documents listed in the enclosure to the NRC
Region IV office for team use in preparation for the inspection. We would appreciate it if you
could send this information so that it will arrive in our office in Arlington, Texas, by the dates
listed in the enclosure.
We request that during the onsite inspection weeks, you ensure that copies of analyses,
evaluations, or documentation regarding the implementation and maintenance of the fire
protection program, including post-fire safe shutdown capability, be readily accessible to the
team for their review. Of specific interest are those documents that establish that your fire
protection program satisfies the NRC regulatory requirements and conforms to applicable NRC
Wolf Creek Nuclear Operating Corp. -2-
and industry fire protection guidance. Also, appropriate personnel knowledgeable of: (1) plant
systems required to achieve and maintain safe shutdown conditions from inside and outside the
control room, (2) the electrical aspects of the post-fire safe shutdown analyses, (3) reactor plant
fire protection systems, and (4) the fire protection program and its implementation should be
available to support the team at the site during the inspection.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Your cooperation and support during this inspection will be appreciated. If you have questions
concerning this inspection or the inspection team's information or logistical needs, please
contact the lead inspector, John Mateychick, at 817-276-6560.
Sincerely,
/RA/
Neil OKeefe, Chief
Engineering Branch 2
Division of Reactor Safety
Docket: 50-482
License: DPR-42
Enclosure: Triennial Fire Protection
Inspection Supporting Documentation
cc w/enclosure:
Vice President Operations/Plant Manager
Wolf Creek Nuclear Operating Corporation
P.O. Box 411
Burlington, KS 66839
Jay Silberg, Esq.
Pillsbury Winthrop Shaw Pittman LLP
2300 N Street, NW
Washington, DC 20037
Wolf Creek Nuclear Operating Corp. -3-
Supervisor Licensing
Wolf Creek Nuclear Operating Corporation
P.O. Box 411
Burlington, KS 66839
Chief Engineer
Utilities Division
Kansas Corporation Commission
1500 SW Arrowhead Road
Topeka, KS 66604-4027
Office of the Governor
State of Kansas
Topeka, KS 66612
Attorney General
120 S.W. 10th Avenue, 2nd Floor
Topeka, KS 66612-1597
County Clerk
Coffey County Courthouse
110 South 6th Street
Burlington, KS 66839
Chief, Radiation and Asbestos
Control Section
Kansas Department of Health and
Environment
Bureau of Air and Radiation
1000 SW Jackson, Suite 310
Topeka, KS 66612-1366
Wolf Creek Nuclear Operating Corp. -4-
Electronic distribution by RIV:
Regional Administrator (Elmo.Collins@nrc.gov )
DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov )
DRS Director (Roy.Caniano@nrc.gov )
DRS Deputy Director (Troy.Pruett@nrc.gov)
Senior Resident Inspector (Chris.Long@nrc.gov )
Branch Chief, DRP/B (Vincent.Gaddy@nrc.gov)
Senior Project Engineer, DRP/B (Rick Deese@nrc.gov)
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov )
DRS STA (Dale.Powers@nrc.gov )
P. Lougheed, OEDO RIV Coordinator (Patricia.Lougheed@nrc.gov )
ROPreports
WC Site Secretary (Shirley.Allen@nrc.gov )
SUNSI Review Completed: ______ADAMS: Yes G No Initials: ______
Publicly Available G Non-Publicly Available G Sensitive Non-Sensitive
S :DRS\REPORTS\WC 2008010 tfp-JMM.
SRI:DRS/EB2 C: EB2
JMM/tek NFOKeefe
/RA/ /RA/
07/7/08 07/10/08
OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
ENCLOSURE
Triennial Fire Protection Inspection Documentation Requested
Please provide the following documentation prior to the onsite information-gathering trip,
preferably no later than August 29, 2008. Where practical, please provide copies electronically.
1. The current version of your fire protection program and fire hazards analysis.
2. Post-fire safe shutdown analysis and the supporting calculations that demonstrate
acceptable plant response.
3. Copies of the licensing basis documents for fire protection (Safety Evaluation Reports,
pertinent sections of the Final Safety Analysis Report, exemptions, deviations, letters
to/from the NRC regarding fire protection/fire safe shutdown, etc.).
4. The Fire Probabilistic Risk Assessment or portions of the plants Individual Plant
Examination for External Events report addressing fire events.
Please provide the following documentation during the information-gathering visit or by
September 19, 2008, in order to support inspection preparation. Where practical, please
provide copies electronically. However, drawings should be provided as paper copies of
sufficient size that all details are legible.
5. Fire protection program implementing procedures (e.g., administrative controls, operator
response procedures for fires, fire fighting procedures, etc.).
6. Operating procedures used for achieving and maintaining hot and cold shutdown
conditions from the control room in the event of a fire outside the control room (III.G.2
areas).
7. Operating procedure(s) used to implement an alternative shutdown (III.G.3 areas)
capability with or without control room evacuation.
8. Pre-fire plans for the selected fire areas (areas to be selected by the team during the
information-gathering trip).
9. A list of equipment used to achieve and maintain hot standby and cold shutdowns in the
event of a fire (safe shutdown equipment lists).
10. Piping and instrumentation (flow) diagrams showing the components used to achieve
and maintain hot standby and cold shutdown for normal and alternate shutdown. Please
provide two copies of the piping and instrumentation (flow) diagrams for these systems
of a size sufficient to read all details. These should include the systems used for RCS
makeup, RCS pressure control, decay heat removal, and reactivity control, including the
essential support systems.
-1- Enclosure
11. Plant layout and equipment drawings for the selected fire areas (these areas will be
selected during the information gathering trip) that identify: (a) the physical plant
locations of major hot standby and cold shutdown equipment; (b) plant fire area and/or
fire zone delineation; and (c) the locations of fire protection equipment, such as
detection, suppression, and post-fire emergency lighting units; and (d) fire area
boundaries.
12. A listing of design change packages which were determined to impact fire protection and
post-fire safe shutdowns, performed in the last 3 years.
13. Copies of Generic Letter 86-10 evaluations performed in the last 3 years.
14. A listing of open and closed corrective action documents initiated in the last 3 years,
which relate to the fire protection program or equipment. Include corrective action
document number, date, and subject.
15. A listing of the applicable codes and standards (with the versions) related to the design
of plant fire protection features and evaluations of any code deviations.
16. Drawings of the portions of the emergency lighting system which support fire response.
17. Procedures used to remove smoke from safety-related areas and the engineering
studies or calculations which support the design basis.
18. Drawings of communication systems credited in the license basis for firefighting and
plant operations during fires where control room is occupied and/or evacuated.
19. Piping and instrumentation (flow) diagrams for the fire water and sprinkler systems.
20. A listing of maintenance and surveillance testing procedures for alternative shutdown
capability and fire barriers, detectors, pumps and suppression systems.
21. Maintenance Rule performance criteria and a summary of the last 3 years performance
history for fire protection program systems or functions monitored within the
22. A copy of fire protection program requirements (e.g. limiting conditions for operation,
surveillance test requirements) covered by Technical Specifications, Technical
Requirements Manual, Updated Final Safety Analysis Report, or similar documents.
23. Copies of internal and external self-assessments, audits, peer-assessments or similar
reviews related to post-fire safe shutdown capability or the fire protection program
completed since November 1, 2005.
24. A list of manual actions taken outside the control room which are credited to mitigate the
consequences of fires in III.G.2 areas (non-alternative shutdown areas). The list should
group actions by the initiating fire area or zone and indicate where the action must take
place.
-2- Enclosure
25. Electronic copies of operator study guides (i.e. lesson plan text and graphics) or design
basis documents that describe the purpose/function/operating characteristics of the safe
shutdown systems (reactor coolant system (RCS) makeup, RCS pressure control, decay
heat removal, and reactivity control, including the essential support systems).
26. Two copies of one-line diagrams of the electrical distribution system. These should
depict how power gets from the switchyard to the engineered safety feature loads (480V
and 4160V). Also, include the vital DC distribution system one-line diagrams.
27. A list of automatic and manually initiated gaseous fire suppression systems in the plant,
giving location and the key equipment being protected.
28. A list of repairs (and the procedure that controls the actions) needed to: a) reach and/or
maintain hot shutdown and b) reach and/or maintain cold shutdown.
29. A list of high to low pressure interface valves.
30. A copy of procedures governing the training and operation of the fire brigade.
31. Organization charts of site personnel down to the level of fire protection staff personnel.
32. A contact list of key site personnel who will be supporting this inspection, giving location
of their office and phone number onsite.
33. The team would like to observe a fire brigade drill in the plant, if possible, during the
week of October 20, 2008. Please put us in contact with the appropriate personnel for
planning drills during the onsite information gathering trip.
34. The team would like to perform a walkthrough of the procedure for control room
evacuation due to fire with qualified operators in the plant during the week of September
29, 2008. Please put us in contact with the appropriate personnel for planning the
walkthrough during the onsite information gathering trip.
-3- Enclosure