Line 3: Line 3:
| issue date = 01/24/2012
| issue date = 01/24/2012
| title = Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555, ME6556)
| title = Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555, ME6556)
| author name = Kuntz R F
| author name = Kuntz R
| author affiliation = NRC/NRR/DLR/RPB1
| author affiliation = NRC/NRR/DLR/RPB1
| addressee name = Gallagher M P
| addressee name = Gallagher M
| addressee affiliation = Exelon Generation Co, LLC
| addressee affiliation = Exelon Generation Co, LLC
| docket = 05000352, 05000353
| docket = 05000352, 05000353
| license number = NPF-039, NPF-085
| license number = NPF-039, NPF-085
| contact person = Kuntz R F
| contact person = Kuntz R
| case reference number = TAC ME6555, TAC ME6556
| case reference number = TAC ME6555, TAC ME6556
| document type = Letter, Request for Additional Information (RAI)
| document type = Letter, Request for Additional Information (RAI)
| page count = 5
| page count = 5
| project = TAC:ME6555, TAC:ME6556
| project = TAC:ME6555, TAC:ME6556
| stage = Other
| stage = RAI
}}
}}


=Text=
=Text=
{{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 January 24, 2012 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348 REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556) Dear Mr. Gallagher: By letter dated June 22, 2011. Exelon Generation Company, LLC submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Limerick Generating Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. These requests for additional information (RAls) were discussed with Christopher Wilson, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at (301) 415-3733 or bye-mail at Robert. Kuntz@nrc.gov. Sincerely, ) Rob¢rt F. Project Manager Projects Branch (1 J Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352, Requests for Additional cc w/encl:
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 24, 2012 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
LIMERICK GENERATING LICENSE RENEWAL REQUESTS FOR ADDITIONAL RAI The staff notes that license renewal boundary drawing LR-M-22, Sheet 5, at location F3, shows the cable spreading room's fire walls and associated components including fire doors, fire dampers, and penetration seals as out of scope (Le., not colored in green). The staff requests that the applicant verify whether the cable spreading rooms fire walls and associated components are in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an aging management review (AMR) in accordance with 10 CFR 54.21 (a)(1). The staff requested that, if these fire walls and associated components are excluded from the scope of license renewal and are not subject to an AMR, the applicant provide justification for the exclusion. RAJ 2.3.3.9-2 LRA Tables 2.3.3-9 and 3.3.2-9 of the LRA do not include the following fire protection components: fire hose stations, fire hose connections, and hose racks fire protection water curtain systems in the reactor enclosures and hatchways floor drains for fire water passive components in fire protection water and foam solution tanks heat exchanger fire dampers fire retardant coating (fireproofing material) for structural steel members passive components in diesel driven fire pump engine passive components in lightning plant protection system (NFPA 78, Lightning Protection Code) The staff requests that the applicant verify whether the fire protection components listed above are in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an AMR in accordance with 10 CFR 54.21(a)(1). If they are excluded from the scope of license renewal and are not subject to an AMR, the staff requests that the applicant provide justification for the exclusion. RAJ 2.3.3.9-3 Section 2.4, "Scoping and Screening Results: Structures," of the LRA provides the scoping and screening results of various structures within the scope of license renewal and subject to an AMR. Further, Section 2.4 states that the fire barriers are evaluated separately with the Fire Protection System, LRA Section 2.3.3.9. LRA Table 2.3.3.9, includes fire barriers (doors), fire barriers (fire rated enclosures), fire barriers (for steel components), fire barriers (penetration seals), fire barriers (walls and slabs), that are subject to an AMR. The staff requests that the ENCLOSURE
 
-applicant provide a summary of the list of buildings or structures where fire barriers are credited, and the specific types of barriers at these locations in the plant's fire protection program.
==SUBJECT:==
January 24, 2012 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348 REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556) Dear Mr. Gallagher: By letter dated June 22, 2011, Exelon Generation Company, LLC submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Limerick Generating Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review. These requests for additional information (RAls) were discussed with Christopher Wilson, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at (301) 415-3733 or bye-mail at Robert.Kuntz@nrc.gov. Sincerely, IRA! Robert F. Kuntz, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352, Requests for Additional cc w/encl: Listserv DISTRIBUTION: See next page ADAMS Accession No'.. ML *concurrence via e-mail
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556)
* OFFICE LA:DLR PM:RPB1 :DLR BC:RPB1:DLR PM: RPB1:DLR
 
* NAME SFigueroa RKuntz DMorey RKuntz IDATE 12/27/11 12/30/11 12/31/11 1124112 OFFICIAL RECORD COpy Letter to M. Gallagher from R. Kuntz dated January 24, 2012 REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556) DISTRIBUTION: E-MAIL: PUBLIC RidsNrrDlr Resource RKuntz DMorey LPerkins MSmith,OGC
==Dear Mr. Gallagher:==
}}
 
By letter dated June 22, 2011. Exelon Generation Company, LLC submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Limerick Generating Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information (RAls) were discussed with Christopher Wilson, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at (301) 415-3733 or bye-mail at Robert. Kuntz@nrc.gov.
Sincerely,
                                    ~~~--C-~~~"'.              )
                                    '~/
Rob¢rt F. ~ior            Project Manager Projects Branch (1 J Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352, 50-353
 
==Enclosure:==
 
Requests for Additional Information cc w/encl: Listserv
 
LIMERICK GENERATING STATION LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION RAI 2.3.3.9-1 The staff notes that license renewal boundary drawing LR-M-22, Sheet 5, at location F3, shows the cable spreading room's fire walls and associated components including fire doors, fire dampers, and penetration seals as out of scope (Le., not colored in green). The staff requests that the applicant verify whether the cable spreading rooms fire walls and associated components are in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an aging management review (AMR) in accordance with 10 CFR 54.21 (a)(1). The staff requested that, if these fire walls and associated components are excluded from the scope of license renewal and are not subject to an AMR, the applicant provide justification for the exclusion.
RAJ 2.3.3.9-2 LRA Tables 2.3.3-9 and 3.3.2-9 of the LRA do not include the following fire protection components:
* fire hose stations, fire hose connections, and hose racks
* fire protection water curtain systems in the reactor enclosures and hatchways
* floor drains for fire water
* passive components in fire protection water and foam solution storc~ge tanks heat exchanger
* fire dampers
* fire retardant coating (fireproofing material) for structural steel members
* passive components in diesel driven fire pump engine
* passive components in lightning plant protection system (NFPA 78, Lightning Protection Code)
The staff requests that the applicant verify whether the fire protection components listed above are in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an AMR in accordance with 10 CFR 54.21(a)(1). If they are excluded from the scope of license renewal and are not subject to an AMR, the staff requests that the applicant provide justification for the exclusion.
RAJ 2.3.3.9-3 Section 2.4, "Scoping and Screening Results: Structures," of the LRA provides the scoping and screening results of various structures within the scope of license renewal and subject to an AMR. Further, Section 2.4 states that the fire barriers are evaluated separately with the Fire Protection System, LRA Section 2.3.3.9. LRA Table 2.3.3.9, includes fire barriers (doors), fire barriers (fire rated enclosures), fire barriers (for steel components), fire barriers (penetration seals), fire barriers (walls and slabs), that are subject to an AMR. The staff requests that the ENCLOSURE
 
                                                - 2 applicant provide a summary of the list of buildings or structures where fire barriers are credited, and the specific types of barriers at these locations in the plant's fire protection program.
 
January 24, 2012 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
 
==SUBJECT:==
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556)
 
==Dear Mr. Gallagher:==
 
By letter dated June 22, 2011, Exelon Generation Company, LLC submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Limerick Generating Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information (RAls) were discussed with Christopher Wilson, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at (301) 415-3733 or bye-mail at Robert.Kuntz@nrc.gov.
Sincerely, IRA!
Robert F. Kuntz, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352, 50-353
 
==Enclosure:==
 
Requests for Additional Information cc w/encl: Listserv DISTRIBUTION:
See next page ADAMS Accession No'.. ML11361A079                          *concurrence via e-mail
*OFFICE LA:DLR                   PM:RPB1 :DLR         BC:RPB1:DLR         PM: RPB1:DLR
*NAME       SFigueroa           RKuntz               DMorey             RKuntz IDATE       12/27/11             12/30/11             12/31/11             1124112 OFFICIAL RECORD COpy
 
Letter to M. Gallagher from R. Kuntz dated January 24, 2012
 
==SUBJECT:==
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RKuntz DMorey LPerkins MSmith,OGC}}

Latest revision as of 10:15, 12 November 2019

Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555, ME6556)
ML11361A079
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 01/24/2012
From: Robert Kuntz
License Renewal Projects Branch 1
To: Gallagher M
Exelon Generation Co
Kuntz R
References
TAC ME6555, TAC ME6556
Download: ML11361A079 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 24, 2012 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348

SUBJECT:

REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556)

Dear Mr. Gallagher:

By letter dated June 22, 2011. Exelon Generation Company, LLC submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Limerick Generating Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.

These requests for additional information (RAls) were discussed with Christopher Wilson, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at (301) 415-3733 or bye-mail at Robert. Kuntz@nrc.gov.

Sincerely,

~~~--C-~~~"'. )

'~/

Rob¢rt F. ~ior Project Manager Projects Branch (1 J Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352, 50-353

Enclosure:

Requests for Additional Information cc w/encl: Listserv

LIMERICK GENERATING STATION LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION RAI 2.3.3.9-1 The staff notes that license renewal boundary drawing LR-M-22, Sheet 5, at location F3, shows the cable spreading room's fire walls and associated components including fire doors, fire dampers, and penetration seals as out of scope (Le., not colored in green). The staff requests that the applicant verify whether the cable spreading rooms fire walls and associated components are in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an aging management review (AMR) in accordance with 10 CFR 54.21 (a)(1). The staff requested that, if these fire walls and associated components are excluded from the scope of license renewal and are not subject to an AMR, the applicant provide justification for the exclusion.

RAJ 2.3.3.9-2 LRA Tables 2.3.3-9 and 3.3.2-9 of the LRA do not include the following fire protection components:

  • fire hose stations, fire hose connections, and hose racks
  • fire protection water curtain systems in the reactor enclosures and hatchways
  • floor drains for fire water
  • passive components in fire protection water and foam solution storc~ge tanks heat exchanger
  • fire retardant coating (fireproofing material) for structural steel members
  • passive components in diesel driven fire pump engine
  • passive components in lightning plant protection system (NFPA 78, Lightning Protection Code)

The staff requests that the applicant verify whether the fire protection components listed above are in the scope of license renewal in accordance with 10 CFR 54.4(a) and whether they are subject to an AMR in accordance with 10 CFR 54.21(a)(1). If they are excluded from the scope of license renewal and are not subject to an AMR, the staff requests that the applicant provide justification for the exclusion.

RAJ 2.3.3.9-3 Section 2.4, "Scoping and Screening Results: Structures," of the LRA provides the scoping and screening results of various structures within the scope of license renewal and subject to an AMR. Further, Section 2.4 states that the fire barriers are evaluated separately with the Fire Protection System, LRA Section 2.3.3.9. LRA Table 2.3.3.9, includes fire barriers (doors), fire barriers (fire rated enclosures), fire barriers (for steel components), fire barriers (penetration seals), fire barriers (walls and slabs), that are subject to an AMR. The staff requests that the ENCLOSURE

- 2 applicant provide a summary of the list of buildings or structures where fire barriers are credited, and the specific types of barriers at these locations in the plant's fire protection program.

January 24, 2012 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348

SUBJECT:

REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556)

Dear Mr. Gallagher:

By letter dated June 22, 2011, Exelon Generation Company, LLC submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Limerick Generating Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.

These requests for additional information (RAls) were discussed with Christopher Wilson, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at (301) 415-3733 or bye-mail at Robert.Kuntz@nrc.gov.

Sincerely, IRA!

Robert F. Kuntz, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352, 50-353

Enclosure:

Requests for Additional Information cc w/encl: Listserv DISTRIBUTION:

See next page ADAMS Accession No'.. ML11361A079 *concurrence via e-mail

  • OFFICE LA:DLR PM:RPB1 :DLR BC:RPB1:DLR PM: RPB1:DLR
  • NAME SFigueroa RKuntz DMorey RKuntz IDATE 12/27/11 12/30/11 12/31/11 1124112 OFFICIAL RECORD COpy

Letter to M. Gallagher from R. Kuntz dated January 24, 2012

SUBJECT:

REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555, ME6556)

DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RKuntz DMorey LPerkins MSmith,OGC