Letter Sequence Supplement |
|---|
EPID:L-2023-LLA-0005, License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation (Approved, Closed) EPID:L-2023-LLA-0025, (Open) |
|
MONTHYEARML22249A0972022-09-0808 September 2022 Constellations Open Presentation for September 8, 2022 Partially Closed Public Meeting Project stage: Request NL-23-0020, Emergency License Amendment Request: Technical Specification Limiting Conditions for Operation 3.4.11, 3.4.12, and 3.4.13 Operability Requirements for Automatic Depressurization System Stage 4 Flow Paths Prior to Initial Criticality2023-01-12012 January 2023 Emergency License Amendment Request: Technical Specification Limiting Conditions for Operation 3.4.11, 3.4.12, and 3.4.13 Operability Requirements for Automatic Depressurization System Stage 4 Flow Paths Prior to Initial Criticality Project stage: Request ML23013A2202023-01-13013 January 2023 Safety Evaluation for License Amendment No. 189 Tech Spec Limiting Conditions for Operability Reqs for Auto Depressurization System Stage 4 Flow Paths Prior to Initial Criticality Project stage: Approval ML23013A2182023-01-13013 January 2023 Amendment No. 189 to License NPF-91 - Tech Spec Limiting Conditions for Operability Req for Auto Depressurization System Stage 4 Flow Paths Prior to Initial Criticality Project stage: Other ML23013A2172023-01-13013 January 2023 Letter for License Amend No. 189 Tech Spec Limiting Conditions for Operability Req for Auto Depressurization System Stage 4 Flow Paths Prior to Initial Criticality Project stage: Other ML23013A2192023-01-13013 January 2023 Amendment No. 189 - Amendment Attachment Project stage: Other ML23052A0232023-02-17017 February 2023 License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation Project stage: Request ML23086B9282023-03-27027 March 2023 Acceptance of Requested Licensing Action for License Amendment Request to Support Digital Modernization Project Installation Project stage: Acceptance Review ML23086A0822023-03-27027 March 2023 – Acceptance of Requested Licensing Action for Exemption Request to Support Digital Modernization Project Installation Project stage: Acceptance Review ML23114A3472023-05-0202 May 2023 Request for Withholding Information from Public Disclosure for Limerick Generating Station, Units 1 and 2 (EPIDs L-2023-LLA-0025 and L-2023-LLE-0005) Project stage: Withholding Request Acceptance ML23173A0632023-06-20020 June 2023 RAIs for Limerick Generation Station, Units 1 and 2 - LAR and Exemption Request for Digital I&C Installation Support Project stage: RAI ML23201A1262023-07-18018 July 2023 Additional RAIs for Limerick Generation Station, Units 1 and 2 - LAR and Exemption Request for Digital I&C Installation Support Project stage: RAI ML23193B0122023-07-20020 July 2023 Audit Plan in Support of Review of License Amendment Request and Exemption Request for Digital Instrumentation and Controls Installation Support (Epids L-2023-LLA-0025 and L-2023-LLE-0005) Project stage: Other ML23202A2192023-07-21021 July 2023 Response to Request for Additional Information for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the . Project stage: Supplement ML23228A0942023-08-16016 August 2023 Response to Request for Additional Information for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the . Project stage: Supplement ML23292A0742023-10-19019 October 2023 Response to Request for Additional Information (RAI-14) for Supplemental License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Project stage: Supplement ML23271A0042023-10-24024 October 2023 Installation Support License Amendment Request Public Notice and Hearing Request Notice Project stage: Other ML23278A0542023-10-24024 October 2023 Regulatory Audit Report in Support of the Limerick Installation Support License Amendment Request Project stage: Other ML24109A0702024-04-18018 April 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFRC50.52 ATWS Rule to Support the Digital Modernization Project Installation . Project stage: Supplement LG-24-063, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-05-28028 May 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation Project stage: Other ML24149A2112024-05-28028 May 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation Project stage: Supplement ML24176A1292024-06-20020 June 2024 Estimated Completion Schedule Change Email Project stage: Other ML24278A3022024-10-0404 October 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10 CFR 50.62 ATWS Rule to Support the Digital Modernization Project Installation - Rev Unit 2 Technical Spec Project stage: Supplement ML24151A3842024-10-31031 October 2024 – Issuance of Amendment Nos. 264 and 226 Support to Digital Modernization Project Installation (EPID L-2023-LLA-0025) and Exemption from the Requirements of 10 CFR 50.62 Project stage: Approval ML24029A2492024-11-0505 November 2024 Exemption from the Requirements of 10 CFR 50.62 (EPID L-2023-LLE-0005) - FRN Project stage: Approval 2023-07-18
[Table View] |
Text
200 Exelon Way Kennett Square, PA 19348 www.ConstellationEnergy.com 10 CFR 50.90 April 23, 2024 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTN: Document Control Desk Limerick Generating Station, Units 1 and 2 Renewed Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353
Subject:
Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) -
Pivot to Unit 1 PPS First Installation in 2026
References:
- 1. Constellation Energy Generation, LLC (CEG) letter to the U.S. Nuclear Regulatory Commission (NRC), "License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS)," dated September 26, 2022 (NRC Agencywide Documents Access and Management System (ADAMS) Accession No. ML22269A569).
- 2. Constellation Energy Generation, LLC (CEG) letter to the NRC, Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) - Pivot to Unit 2 First Installation, dated May 23, 2023 (ML23143A342).
Per Reference 1 and in accordance with 10 CFR 50.90, Constellation Energy Generation, LLC (CEG) requested amendments to Renewed Facility Operating License Nos. NPF-39 and NPF-85 for Limerick Generating Station (LGS), Units 1 and 2, respectively. The proposed changes would revise the LGS licensing and design basis to incorporate a planned digital modification at LGS (i.e., the LGS Digital Modernization Project DMP)). In Reference 1, CEG communicated plans to implement the LGS DMP during the LGS Unit 1 20th refueling outage (Li1R20) and LGS Unit 2 18th refueling outage (Li2R18), scheduled in April 2024 and April 2025, respectively.
Constellation
Supplement to DMP License Amendment Request-PPS First Installation in 2026 Limerick Digital Modernization Project Docket Nos. 50-352 and 50-353 April 23, 2024 Page 2 Per Reference 2, CEG notified NRC that the final design activities for the Plant Protection System (PPS) had been delayed due to additional design refinement iterations with the system Original Equipment Manufacturer. CEG had concluded that it was no longer possible to have the design completed and equipment ready in time to support the Unit 1 installation during the April 2024 Refueling Outage. Therefore, CEG pivoted the final design and project activities to support the first installation of the PPS on Unit 2 during its planned April 2025 Refueling Outage.
After a careful review of the current final design and PPS equipment fabrication schedules, CEG has concluded that the current effort will not support a PPS installation during the Unit 2 Refueling Outage in April 2025. The reason for the delay is due to identification of additional new design considerations/issues that had to be addressed/resolved, and current final design and manufacturing schedules that do not meet the CEG internal 2025 Refueling Outage readiness requirements for installation. Accordingly, the Unit 1 first PPS installation is now planned for the LGS Unit 1 21st Refueling Outage (Li1R21) in April 2026, and second installation PPS is planned for the LGS Unit 2 19th Refueling Outage (Li2R19) in April 2027.
This supplemental letter contains no regulatory commitments.
In accordance with 10 CFR 50.91, "Notice for public comment; State consultation," paragraph (b), CEG is notifying the Commonwealth of Pennsylvania of this LAR supplemental letter by transmitting a copy of this letter to the designated State Official.
If you have any questions regarding this submittal, please contact Frank Mascitelli at Frank.Mascitelli@constellation.com.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 23nd day of April 2024.
Respectfully, David P. Helker Sr. Manager - Licensing Constellation Energy Generation, LLC cc:
USNRC Region I, Regional Administrator USNRC Project Manager, LGS USNRC Senior Resident Inspector, LGS Director, Bureau of Radiation Protection - Pennsylvania Department of Environmental Protection