MONTHYEARML20160A0532020-06-0808 June 2020 Digital Modernization Project LAR - Presubmittal Meeting - NRC Presubmittal Meeting Telecon June 12, 2020 Project stage: Meeting ML20162A0192020-06-10010 June 2020 NRC Staff Presentation for June 12, 2020, Public Pre-Application Meeting: ISG-06 Alternate Review Process Lessons Learned from Pre-Application Meetings Project stage: Meeting ML20175A2402020-06-30030 June 2020 Summary of June 12, 2020, Public Telephone Conference with Exelon Generation Company, LLC Regarding Planned Digital Modernization License Amendment Request Project stage: Other ML21063A1192021-03-0404 March 2021 Digital Modernization Project LAR Pre-submittal Meeting - March 16, 2021 (EPID L-2020-LRM-0041) (Slides) Project stage: Meeting ML21133A1342021-04-29029 April 2021 0 to Updated Final Safety Analysis Report, Chapter 15, Sections 15.0 Through 15.5 Project stage: Request ML21123A1362021-05-13013 May 2021 Summary of March 16, 2021, Public Webinar with Exelon Generation Company, LLC Regarding Planned Digital Modernization License Amendment Request Project stage: Other ML21174A0852021-06-23023 June 2021 Digital Modernization Project LAR Pre-submittal Meeting Project stage: Meeting PMNS20210655, Pre-Submittal Meeting with Exelon Generation Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22021-06-25025 June 2021 Pre-Submittal Meeting with Exelon Generation Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML21175A1732021-06-29029 June 2021 Digital Modernization Project LAR Pre-submittal Meeting Project stage: Meeting ML21286A0302021-10-13013 October 2021 Staffs Questions Pertaining to Limerick Generating Station Digital Modernization Project LAR Pre-submittal Meeting Slides October 20, 2021 Project stage: Meeting PMNS20211169, Pre-Submittal Meeting with Exelon Generating Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22021-10-16016 October 2021 Pre-Submittal Meeting with Exelon Generating Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML21278A5452021-10-20020 October 2021 Digital Modernization Project LAR Pre-submittal Meeting Presentation Slides October 20, 2021 Project stage: Meeting ML21300A2772021-11-0909 November 2021 Summary of October 20, 2021, Pre-Submittal Public Teams Meeting with Exelon Generation Company, LLC Regarding Planned Digital Modernization License Amendment Request Project stage: Meeting ML21301A1612021-11-15015 November 2021 Summary of June 29, 2021, Public Meeting with Exelon Generation Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting PMNS20211501, Pre-Submittal Meeting with Exelon Generating Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22021-11-26026 November 2021 Pre-Submittal Meeting with Exelon Generating Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML21335A0772021-12-0707 December 2021 Dec 07 2021 LGS Digital Modernization Pre-submittal Meeting Slides Project stage: Request ML22005A1812022-01-0505 January 2022 NRR E-mail Capture - Staffs Questions Pertaining to Limerick Generating Station Digital Modernization Project LAR Pre-submittal Meeting Slides December 7, 2021 Project stage: Meeting PMNS20211500, Pre-Submittal Meeting with Exelon Generating Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22022-01-10010 January 2022 Pre-Submittal Meeting with Exelon Generating Company, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML22021B2942022-02-0202 February 2022 Summary of December 7, 2021, Public Meeting with Exelon Generation Company, LLC Regarding Planned Digital Modernization License Amendment Project stage: Meeting ML22038A0992022-02-23023 February 2022 Summary of January 11, 2022, Public Meeting with Exelon Generation Company, LLC Regarding Planned Digital Modernization License Amendment Request Project stage: Meeting ML22080A1992022-03-18018 March 2022 Affidavit for Proprietary Presentation for March 31, 2022 Pre-Submittal Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML22089A1162022-03-28028 March 2022 Comments and Questions on Constellations March 31st Presentation Project stage: Other ML22089A1172022-03-30030 March 2022 Additional Comments and Questions on Constellations March 31st Presentation Project stage: Other ML22124A2862022-05-0404 May 2022 Information Needed to Provide Substantive Feedback on Human Factors Engineering Supporting the Planned Limerick Digital I&C License Amendment Request Project stage: Other ML22153A3602022-06-0909 June 2022 Constellations Presentation for June 9, 2022 Public Meeting About Limerick Generating Station Digital Modernization Project Project stage: Meeting ML22172A0752022-06-17017 June 2022 Response: Review and Feedback on Draft Limerick Digital License Amendment Request (L-2020-LRM-0041) Project stage: Draft Other ML22249A2202022-09-0606 September 2022 Constellations Non-Proprietary Presentation for Limerick Generating Station Digital Modernization Project LAR Pre-submittal Meeting September 8, 2022 Project stage: Meeting ML22250A4372022-09-0808 September 2022 NRC Staffs Presentation for September 8, 2022 Partially Closed Public Meeting with Constellation - Review Planning and Tentative Review Timeline Project stage: Meeting 2021-06-23
[Table View] |
Text
From:
Marshall, Michael To:
Mascitelli, Francis J:(Constellation Nuclear)
Cc:
Jain, Bhagwat; Pareez Golub; Helker, David P:(Constellation Nuclear)
Subject:
RESPONSE: Review and Feedback on Draft Limerick Digital License Amendment Request (L-2020-LRM-0041)
Date:
Friday, June 17, 2022 11:20:00 AM Hello Frank,
During a public meeting between the NRC and Constellation on June 9, 2022, Constellation asked the NRC staff whether the NRC staff would review and provide feedback within 30 days on a draft of the planned Limerick digital instrumentation and controls license amendment request that Constellation plans to submit to the NRC by the end of August 2022. Earlier this week you asked whether the draft needed to be formally submitted to the NRC via the docket. The NRC staff did not ask Constellation for a draft copy of the planned Limerick digital instrumentation and controls license amendment request. Yes, the NRC staff will provide feedback (i.e., observations and comments) on the draft of the Limerick digital instrumentation and controls license amendment request 30 days after receipt of the draft. Yes, Constellations request for feedback on the draft and the draft should be submitted to the docket by the normal means of providing correspondence to the NRC. The draft Waterford license amendment request mentioned by Constellation during the June 9th meeting was provided on the docket and a copy is available in the NRCs document management system under ADAMS Accession No. ML20168A904.
Please note the following:
The NRC does not have an established process for providing feedback to licensees on draft operating reactor license amendment requests.
The NRC staff is advised to discourage licensees and applicants from submitting drafts of routine licensing correspondence for review. In cases the NRC staff does review draft information,
NRC staff will refrain from assuming role of advisor or consultant.
NRC staffs comments will be limited to addressing issues concerning regulatory decision making, regulatory or industry guidance, or editorial and formatting suggestions that would facilitate staff review.
NRC staff comments on detailed technical content may not be appropriate.
NRC staff will refrain from providing comments that would give more of an advantage to one licensee or applicant than to any other.
The NRC staffs review and feedback on the draft license amendment request is not direction from the NRC staff to Constellation to update the draft license amendment request before it is submitted to the NRC.
The NRC staffs review of the draft license amendment request is not a substitute for either an acceptance review or detailed technical review normally performed by the NRC staff.
The lack of NRC staffs comments on a particular aspect of the draft license amendment request does not mean that the NRC staff will not identify issues during either the acceptance review or the detailed technical review by the NRC staff.
The NRC staff may not review the draft license amendment request in its entirety.
The request from Constellation to review the draft, the draft, and NRC staffs feedback on the draft will be handled as official agency records. Therefore, they will be placed in the NRCs document management system, ADAMS. The NRC does not rely on draft material when making regulatory decisions. If you have any additional questions, please feel free to contact me.
Best Regards, Michael L. Marshall, Jr.
Senior Project Manager
Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
301-415-2871