MONTHYEARML11179A0962011-06-22022 June 2011 Application for Renewed Operating Licenses Project stage: Request ML11209B7092011-07-22022 July 2011 Submittal of Summary Report for Inservice Inspections (2R11) Project stage: Request ML11255A0322011-09-15015 September 2011 Plan for the Scoping and Screening Regulatory Audit Regarding the Limerick Generating Station, Units 1 and 2 License Renewal Application Review Project stage: Other ML11258A1092011-09-20020 September 2011 Plan for the Aging Management Program Regulatory Audit Regarding the Limerick Generating Station, Units 1 and 2 License Renewal Application Review Project stage: Other ML1134101442011-12-0707 December 2011 Response to NRC Request for Additional Information, Dated November 18, 2011 Project stage: Response to RAI ML11342A2052011-12-0909 December 2011 Scoping and Screening Methodology Audit Report Regarding the Limerick Generating Station, Units 1 and 2 Project stage: Other ML1133402312011-12-12012 December 2011 Request for Additional Information for Limerick Generating Station, Units 1 and 2 License Renewal Application-Scoping and Screening Project stage: RAI ML11343A4382011-12-15015 December 2011 Requests for Additional Information for the Review of the Limerick Generating Station License Renewal Application Project stage: RAI ML11335A3172012-01-0505 January 2012 RAI for the Review of the Limerick Generating Station License Renewal Application Project stage: RAI ML11347A3602012-01-17017 January 2012 Requests for Additional Information for the Review of the Limerick Generating Station License Renewal Application Project stage: RAI ML11361A0832012-01-18018 January 2012 Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application Project stage: RAI ML11361A0792012-01-24024 January 2012 Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application Project stage: RAI ML12027A2282012-01-27027 January 2012 Response to NRC Request for Information, Dated January 5, 2012, Related to License Renewal Application Project stage: Response to RAI ML11364A0992012-01-30030 January 2012 Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application Project stage: RAI ML12163A7532012-01-31031 January 2012 Lr - FW: Request for Additional Information for the Review of the Limerick Generation Station, Units 1 and 2 License Renewal Application Project stage: Request ML12005A2512012-01-31031 January 2012 Request for Additional Information for the Review of the Limerick Generating Station Units 1 and 2 License Renewal Application (TAC Nos. ME6555, ME6556) TLAA 43 and 468 RAIs Project stage: RAI ML12018A0332012-02-14014 February 2012 Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555, ME6556) Rapb AMR2 RAIs Project stage: RAI ML1204700842012-02-15015 February 2012 Response to NRC RAI Dated Jan. 17, 2012 Re. Limerick Gen. Station LRA Project stage: Request ML12017A1592012-02-16016 February 2012 Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application Project stage: RAI ML12024A2312012-02-16016 February 2012 Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555 and ME6556) OE and Other RAIs Project stage: RAI ML1204703722012-02-16016 February 2012 Response to NRC Request for Additional Information, Dated January 17, 2012 Project stage: Response to RAI ML12019A1562012-02-17017 February 2012 Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application Project stage: RAI ML12018A0352012-02-23023 February 2012 Requests for Addtional Information for the Review of the Limerick Generating Station, Units 1 & 2, License Renewal Application Project stage: Approval ML12059A3452012-02-28028 February 2012 Response to NRC Request for Additional Information, Dated January 30, 2012, Related to License Renewal Application Project stage: Response to RAI ML12018A3322012-02-28028 February 2012 Letter Aging Management Programs Audit Report Regarding the Limerick Generating Station, Units 1 and 2 (TAC NO.ME6555 & ME6556) Project stage: Other ML12060A1542012-02-29029 February 2012 Response to NRC Request for Additional Information, Dated January 31, 2012 Related to License Renewal Application Project stage: Response to RAI ML12065A2062012-03-0505 March 2012 Response to NRC Requests for Additional Information, Dated February 16, 2012, and February 17, 2012, Related to Renewal Application Project stage: Response to RAI ML12009A1352012-03-0909 March 2012 Summary of the Telephone Conference Call Held on December 14, 2011, Between the U.S. Nuclear Regulatory Commission and Exelon on Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Limerick 12-14-11 Tel Project stage: RAI ML12046A8992012-03-0909 March 2012 Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555 and ME6556) Limerick App J RAIs Project stage: RAI ML1207303612012-03-13013 March 2012 Response to NRC Requests for Additional Information, Dated February 14 and February 16, 2012, Related to the Limerick Generating Station License Renewal Application Project stage: Response to RAI ML12080A1182012-03-20020 March 2012 Response to NRC Requests for Additional Information, Dated February 23 and March 9, 2012, Related to License Renewal Application Project stage: Response to RAI ML12074A0372012-03-22022 March 2012 Letter Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555, ME6556) Buried Piping and FP Follow Up Project stage: RAI ML12090A4892012-03-30030 March 2012 Response to NRC Request for Additional Information, Dated March 22, 2012 and Information Addressing Minor Errors or Omissions Related to License Renewal Application Project stage: Response to RAI ML12080A1902012-04-0505 April 2012 Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555 and ME6556) BWR SCC SMP and Ctws Follow Up Project stage: RAI ML12066A0262012-04-0909 April 2012 February 9, 2012, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, Llc. Concerning Request for Additional Information Pertaining to the Limerick Project stage: RAI ML12104A1182012-04-13013 April 2012 Response to NRC Requests for Additional Information, Dated April 5, 2012, Related to License Renewal Application Project stage: Response to RAI ML12089A3772012-04-13013 April 2012 Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6556 and ME6555) Fluence and FP Followup RAIs Project stage: RAI ML12082A1552012-04-16016 April 2012 Requests for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application Project stage: RAI ML12095A3982012-04-17017 April 2012 Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos ME6555 and ME6556)TLAA Follow-up RAIs Project stage: RAI ML12025A0512012-04-20020 April 2012 Summary of Telephone Conference Call Held on January 18, 2012, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Request for Additional Information Pertaining to the Limerick Generation 1-18-12 Te Project stage: RAI ML12059A0802012-04-20020 April 2012 February 17, 2012, Summary of Telephone Conference Call Held Between U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Request for Additional Information Pertaining to the Limerick 2-17-12 Telecon Summary Project stage: RAI ML12018A0232012-04-26026 April 2012 1/12/2012 Telecon Summary Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Limerick Generating Station, License Renewal Application Project stage: RAI ML12118A5402012-04-27027 April 2012 Notices of Appearance of Paul M. Bessette and Stephen J. Burdick Project stage: Other ML12111A0342012-04-30030 April 2012 Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME6555 and ME6556)SCC RAIs Project stage: RAI ML12047A1242012-05-0101 May 2012 Summary of Telephone Conference Call Held Between NRC and Exelon Generation Co., LLC, Concerning Requests for Additional Information Pertaining to the Limerick, License Renewal Application Project stage: RAI ML12125A3342012-05-0404 May 2012 Responses to NRC Requests for Additional Information, Dated April 17, 2012, Related to the License Renewal Application Project stage: Response to RAI ML12128A4382012-05-0707 May 2012 Responses to NRC Requests for Additional Information, Dated April 30, 2012, Related to the License Renewal Application Project stage: Response to RAI ML12123A0922012-05-18018 May 2012 RAI for Review of the Limerick Generation Station, Units 1 & 2 & License Renewal Application Project stage: RAI ML12136A0362012-05-18018 May 2012 Request for Additional Information for the Review of the Limerick Generating Station, Units 1 and 2, (TAC Nos. ME6555 and ME6556)Scoping Drawings Followup RAI Project stage: RAI ML12115A2812012-05-24024 May 2012 4-17-12 Telecon Summary Project stage: Other 2012-02-28
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 19, 2012 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555 AND ME6556)
Dear Mr. Gallagher:
By letter dated June 22, 2011, Exelon Generation Company, LLC (applicant) submitted an application, pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Limerick Generating Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC). On July 31,2012, the staff issued the Safety Evaluation Report with Open Items related to this application, which includes Open Item 3.0.3.2.13-1 regarding the applicant's proposed aging management of the suppression pool liner and downcomers under the scope of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, Subsection IWE. In a letter dated September 12,2012, the applicant responded to the open item.
The staff is reviewing the information contained in the letter of September 12, 2012, and has identified that further information is needed to complete its review. The specific questions are in the enclosed request for additional information (RAI).
The RAI was discussed with Christopher Wilson, and a mutually agreeable date for the response is within 15 days from the date of this letter. If you have any questions, please contact me by telephone at (301) 415-1457 or bye-mail at Patrick.Milano@nrc.gov.
Sincerely,
~~Q).~
Patrick D. Milano, Sr. Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosure:
Request for Additional Information cc w/encl: Listserv
LIMERICK GENERATING STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REQUEST FOR ADDITIONAL INFORMATION License Renewal Application (LRA), Section B.2.1.30, "ASME Section XI, Subsection IWE" Request for Additional Information (RAI) 8.2.1.30-2.2
Background
In its response to RAI B.2.1.30-2.1, dated April 27, 2012, Exelon Generation Company, LLC (the applicant) stated that:
"[T]he acceptance criterion for the downcomers of 0.0625 inches for surface defects is applied to local degradation of less than or equal to 5.5 inches in any direction. An area of localized corrosion of 0.040 inches (or more) metal loss will be recoated. The criterion for acceptable general corrosion is less than or equal to 0.044 inches metal loss. An area greater than 5.5 inches in any direction with a depth of 0.030 inches (or more) metal loss will be recoated.
The applicant, in a letter dated September 12, 2012, stated that downcomer recoating acceptance criteria, as described in its letter dated April 27, 2012, will be incorporated into the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code)
Section XI, Subsection IWE aging management program (AMP). However, the applicant revised ASME Section XI, Subsection IWE AMP B.2.1.30, LRA Appendix A, Updated Final Safety Analysis Report (UFSAR) Supplement (Section A.2.1.30 and Commitment 30) to state that ASME Section XI, Subsection IWE AMP will be enhanced prior to period of extended operation (PEO) "to include the criteria used to determine when the downcomer areas affected by corrosion will be recoated."
The applicant has not incorporated the downcomer recoating criteria, which was described in its letter dated April 27,2012, into ASME Section XI, Subsection IWE AMP submitted to the NRC on September 12, 2012. In addition, LRA Appendix A, UFSAR Supplement (Section A.2.1.30 and Commitment 30) does not describe the downcomer recoating criteria. This is not consistent with Title 10 of the Code of Federal Regulations (10 CFR) 54.21 (d), which requires that the FSAR supplement for the facility must contain a summary description of the programs and activities for managing the effects of aging for the PEO.
In its letter dated September 12, 2012, the applicant stated that the Coating Maintenance Plan, which addresses recoating the areas of general and local corrosion of the liner plate, began in 2012 to allow the prioritized actions to be implemented prior to reaching PEO. However, it is not clear to the staff why the enhancement for the downcomer inspection and recoating criteria will not be implemented (as a part of the Coating Maintenance Plan) until the PEO starts for Unit 1 in 2024 and for Unit 2 in 2029.
ENCLOSURE
- 2 Request Revise ASME Section XI, Subsection IWE AMP B.2.1.30, LRA Appendix A, UFSAR Supplement (Section A.2.1.30 and Commitment 30) to incorporate the downcomer recoating criteria. In addition, explain why prioritized actions to implement the downcomer recoating criteria are not planned prior to the PEO.
RAI 8.2.1.30-6
Background
In its letter dated September 12, 2012, the applicant stated that ultrasonic (UT) thickness measurements were performed on four liner plates in areas affected by general corrosion to determine the remaining wall thickness (two readings per plate). The thickness of these four plates was also visually assessed and compared to the UT measurements. It was determined from this comparison that the visual assessment of general corrosion metal loss for these four plates was conservative and correlated well with the UT measurements. The applicant further stated that to confirm visual assessments of general corrosion, a UT measurement will be performed, when IWE examinations are conducted, on any area of the submerged suppression pool liner affected by corrosion and significant metal loss.
The staff is concerned that a UT examination only on an area of suppression pool liner affected by general corrosion during each IWE inspection period (four years) may not be sufficient to conclude that visual assessment of general corrosion metal loss correlates well with the UT measurement.
Request Provide the justification for not performing UT examinations on a number of plates at more than one location to determine the correlation between visual assessments of general corrosion metal loss and the UT measurements.
RAI 8.2.1.30-7
Background
In its letter dated September 12, 2012, the applicant stated that the Limerick Generating Station acceptance criteria and examination methodology are consistent with ASME Section XI, Subsection IWE (specifically with the Subsections IWE -1241 and IWE-1242) and Table IWE 2500-1 requirement that 100 percent of areas having substantial corrosion require augmented inspection. Substantial liner corrosion is defined by the applicant as general corrosion that exhibits greater than 25 mils of average metal loss, or local areas of general corrosion with greater than 50 mils of metal loss. The applicant further stated that VT-1 detailed visual examinations are performed as required by ASME Section XI, Subsection IWE, Table IWE-2500-1 and 10 CFR 50.55a requirements.
-3 The staff reviewed the applicant's revised ASME Section XI, Subsection IWE AMP and UFSAR Supplement (Section A.2.1.30 and Commitment 30) provided in the letter dated September 12, 2012. The staff did not find any reference to the applicant's (owner's) defined criteria for augmented inspection as general corrosion greater than 25 mils average metal loss or local areas of general corrosion greater than 50 mil loss in the LRA AMP 8.2.1.30 and the UFSAR Supplement (Section A.2.1.30 and Commitment 30). Section CFR 54.21 (d) of 10 CFR requires that the FSAR Supplement for a facility must contain a summary description of the programs and activities for managing the effects of aging for the PEG.
Request Revise LRA AMP 8.2.1.30 and the UFSAR Supplement (Section A.2.1.30 and Commitment 30) to include owner's defined criteria for augmented inspection.
ML12290A853
- via email OFFICE PM:RPB1:DLR NAME PMilano IKing SB:DLR BC:RPB1 :DLR PM: RPB1 :DLR MMarshali DMorey PMilano DATE 10/19/2012 10/19/2012 10/19/2012 10/19/2012 10/19/2012
Letter to M. Gallagher from P Milano dated October 19, 2012
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE LIMERICK GENERATING STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME6555 AND ME6556)
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRsrg Resource RidsNrrPN I Limerick Resource RidsOgcMailCenter Resource DMorey PMilano LPerkins ASheik MSmith,OGC ABurritt, RI MModes, RI GDiPaolo, RI NSielier, RI