IR 05000352/2025010

From kanterella
Jump to navigation Jump to search
Comprehensive Engineering Team Inspection Report 05000352/2025010 and 05000353/2025010
ML25069A592
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 03/11/2025
From: Erin Carfang
Division of Operating Reactors
To: Rhoades D
Constellation Energy Generation
References
IR 2025010
Download: ML25069A592 (1)


Text

March 11, 2025

SUBJECT:

LIMERICK GENERATING STATION, UNITS 1 AND 2 - COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000352/2025010 AND 05000353/2025010

Dear David Rhoades:

On January 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Limerick Generating Station, Units 1 and 2, and discussed the results of this inspection with Michael Gillin, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at Limerick Generating Station, Units 1 and 2.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 205550001; with copies to the Regional Administrator, Region I; and the NRC Resident Inspector at Limerick Generating Station, Units 1 and 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Erin E. Carfang, Chief Engineering Branch 1 Division of Operating Reactor Safety

Docket Nos. 05000352 and 05000353 License Nos. NPF-39 and NPF-85

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000352 and 05000353

License Numbers:

NPF-39 and NPF-85

Report Numbers:

05000352/2025010 and 05000353/2025010

Enterprise Identifier: I-2025-010-0022

Licensee:

Constellation Energy Generation, LLC

Facility:

Limerick Generating Station, Units 1 and 2

Location:

Sanatoga, PA

Inspection Dates:

January 13, 2025 to January 31, 2025

Inspectors:

C. Bickett, Senior Reactor Analyst

P. Cataldo, Senior Reactor Inspector

J. Kulp, Senior Reactor Inspector

S. McClay, Reactor Inspector

D. McHugh, Reactor Inspector

A. Patel, Senior Reactor Inspector

B. Pinson, Senior Reactor Inspector

Approved By:

Erin E. Carfang, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at Limerick Generating Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Diesel Generator Load Reject Surveillance Test Procedure Acceptance Criteria Not In Accordance with Technical Specification Surveillance Requirements.

Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000352,05000353/2025010-01 Open/Closed

[H.3] - Change Management 71111.21M The inspectors identified a Green non-cited violation (NCV) of Technical Specification (TS)6.8.1.d, Procedures and Programs, when Constellation did not implement diesel generator load-reject surveillance requirements (SR) into their surveillance test acceptance criteria.

Specifically, they did not implement SR 4.8.1.1.2.e.2.c into surveillance test procedure ST-6-092-324-2, D24 Diesel Generator LOCA/Load Reject Testing and Fast Start Operability Test Run. SR 4.8.1.1.2.e.2.c verifies that emergency diesel generator (EDG) steady-state frequency is within the band of 59.8 to 60.8 Hz after rejection of a load greater than or equal to the single largest post-accident load.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Comprehensive Engineering Team Inspection

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Structures, Systems, and Components (SSCs) (IP section 03.01)===

(1) Residual Heat Removal (RHR) Heat Exchanger (1BE205)
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(2) D22 EDG and Associated Safety Bus
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(3) D Residual Heat Removal Service Water (RHRSW) Pump
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(4) RHRSW Bypass Valve (HV-51-048B), Valve and Risk Significant Operator Action to Recover Valve
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electrical Loads, Motor Control Centers, and As-Built System.

(5) Station Blackout Procedure E-1
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(6) Suppression Pool Vent Valve (HV-57-204) and Depressurize Containment Procedure
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.

The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electrical Loads, Motor Control Centers, and As-Built System.

(7)1A2 Battery and Charger

  • Process medium (electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(8) D214 480V Switchgear
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

Modifications (IP section 03.02) (7 Samples)

(1)

===631464, Implementation EC for D24 Governor Replacement Reference EC 627703, Revision 0 (2)633190, RPS UPS Inverter - Class 1E DC Feeder Breaker Replacements, Revision 0 (3)620491, Change MOV HV-011-015A to Manual Valve 011-0124A and Convert Manual Valve 011-0124A to MOV HV-011-015A Configuration Change Package (4)625439, Replace 'A' ESW Return to 'B' RHRSW Return Piping - Online Work (Downstream of HV-011-015A)

(5)628755, ESW Pump Vent Modification (6)637740, Resolve DC Ground Associated with HPCI IR 04529359 (IR 04529355)

(7)631040 - Issue 125/250V DC System ETAP Calculations, Revision 1

10 CFR 50.59 Evaluations/Screening (IP section 03.03)===

(1) LG2022E001, EC 636016 Revision 0, TCCP to Bypass FT-087-220B Signal to Return Drywell Cooler Drain Flow Monitoring System to Service
(2) LG2024E001, EC 640509 Revision 0, TCCP to Bypass FT-087-220B Signal to Return Drywell Cooler Drain Flow Monitoring System to Service
(3) EC 634483 Revision 1, Unit 1 (1R19) Core Shroud Weld Flaw Evaluation
(4) EC 638196, TCCP - Lift Leads and Jumper to Defeat 2C Main Steam Line Rad Monitor Alarms
(5) EC 628238, 8A/8B Transformer Replacement
(6) GP-7 & GP-7.1, MSIV Group 1 Turbine Enclosure (TE) Steam Leak Detection (SLD)

High Temperature Isolation Thermocouple Groups 119/219 Warm Weather Periods Supplemental Cooling Procedurally Controlled Temporary Configuration Change (PCTCC)

(7) EC 631464 Revision 1, Implementation EC for D24 Governor Replacement
(8) UFSAR Change Package 2023-015, BWR CRD return line nozzles
(9) UFSAR Change Package 2023-016, BWR Stress Corrosion Cracking
(10) UFSAR Change Package 23-012, Frequency change of LR Commitment of Charcoal Filter Air Tests and Visual Inspections of FP Deluge Piping
(11) EC 640700, Safety Relief Valve (SRV) Pressure Switch
(12) EC 641478, Temporary Bypass of the Sensor Trip inputs to the Robertshaw Motor and Bearing Temperature Modules (0B CE Chiller)
(13) EC 625439, Replace A Emergency Service Water (ESW) Return to B Residual Heat Removal Service Water (RHRSW) Return Piping

Operating Experience Samples (IP section 03.04) (2 Samples)

(1) IN 20-02 Flex EDG Operational Challenges
(2) IN 17-06 Battery and Battery Charger Short-Circuit Current Contributions to a Fault on the Direct Current Distribution System

INSPECTION RESULTS

Diesel Generator Load Reject Surveillance Test Procedure Acceptance Criteria Not In Accordance with Technical Specification Surveillance Requirements.

Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000352,05000353/2025010-01 Open/Closed

[H.3] - Change Management 71111.21M The inspectors identified a Green non-cited violation (NCV) of Technical Specification (TS)6.8.1.d, Procedures and Programs, when Constellation did not implement diesel generator load-reject surveillance requirements (SR) into their surveillance test acceptance criteria.

Specifically, they did not implement SR 4.8.1.1.2.e.2.c into surveillance test procedure ST-6-092-324-2, D24 Diesel Generator LOCA/Load Reject Testing and Fast Start Operability Test Run. SR 4.8.1.1.2.e.2.c verifies that emergency diesel generator (EDG) steady-state frequency is within the band of 59.8 to 60.8 Hz after rejection of a load greater than or equal to the single largest post-accident load.

Description:

In January 2023, the NRC issued Licensee Amendments 258 and 220 (ML22272A037) for Limerick Generating Station (LGS), Units 1 and 2, which corrected a non-conservative TS identified during a 2015 Component Design Basis Inspection (Inspection Report 05000352/2015007 and 05000353/2015007, ML15251A438). SR 4.8.1.1.2.e.2.c requires that the licensee verify each diesel generator's capability to reject a load of greater than or equal to that of its single largest post-accident load on a periodic basis. The license amendments modified SR 4.8.1.1.2.e.2.c. to include a steady-state frequency operating band for the EDG following rejection of the single largest post-accident load. In April 2023, LGS had completed activities to implement the changes to TSs. As of January 2025, LGS completed surveillance testing for 7 out of the 8 station EDGs utilizing the revised surveillance test procedures for fast start and load rejection testing.

On January 14, 2025, while evaluating the modification package associated with the D24 EDG governor replacement, the inspectors determined that the steady-state frequency band specified in SR 4.8.1.1.2.e.2.c was omitted from the acceptance criteria for the D24 post-modification testing. The inspectors then reviewed ST-6-092-324-2, D24 Diesel Generator LOCA/Load Reject Testing and Fast Start Operability Test Run, to determine if the steady state frequency was verified as part of the periodic (48 month) surveillance test. The inspectors found that the frequency band verification had been omitted from the procedure when it had been updated for the implementation of the license amendments in 2023.

LGS performed an extent of condition review for the remaining 7 EDGs and determined that the surveillance procedures for all the EDGs were missing the acceptance criteria for the steady-state frequency and that one EDG had not yet been tested. LGS was able to retrieve testing data from on the data logger for the last testing activities and verified that all 7 tested EDGs met the frequency band requirements of SR 4.8.1.1.2.e.2.c.

Corrective Actions: Verification of surveillance testing data for all EDGs, revised applicable test procedures to include the test acceptance criteria resulting from implementation of the License Amendments 258 and 220, and updated maintenance procedures to ensure that data and traces from data recorders are attached to completed surveillance test procedures.

Corrective Action References: LGS entered the issue into the corrective action program as IR 4830283.

Performance Assessment:

Performance Deficiency: LGS did not maintain procedures governing the surveillance testing of safety-related equipment as required by TSs and was a performance deficiency.

Specifically, surveillance test procedure ST-6-092-321(2,3,4)-1(2), Diesel Generator LOCA/Load Reject Testing and Fast Start Operability Test Run, did not verify that the EDG met steady-state frequency criteria required by TS SR 4.8.1.1.2.e.2.c.

Screening: This performance deficiency was determined to be more than minor because if left uncorrected, the performance deficiency would have the potential to lead to a more significant safety concern. The performance deficiency would lead to a reasonable doubt of operability and could have adversely affected the ability to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent adverse consequences.

Specifically, if the diesel generator load-reject surveillance test procedure was left uncorrected without SR 4.8.1.1.2.e.2.c, the capability of the diesel to operate appropriately at steady-state would not be ensured.

Significance: The inspectors assessed the significance of the finding using IMC 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined this finding to be of very low safety significance (Green) because when screened utilizing Exhibit 2, Mitigating Systems Screening Questions, Question 1, it was determined that the diesel generators maintained their operability and probabilistic risk analysis functionality.

Cross-Cutting Aspect: H.3 - Change Management: Leaders use a systematic process for evaluating and implementing change so that nuclear safety remains the overriding priority.

Specifically, the licensee did not effectively implement a process to ensure a changed SR was added to their surveillance procedures.

Enforcement:

Violation: TS 6.8.1.d, Programs and Procedures, requires that written procedures shall be established, implemented, and maintained covering the surveillance and testing activities of safety-related equipment.

Contrary to the above, from April 2023 to January 2025, LGS did not adequately maintain surveillance procedure ST-6-092-321(2,3,4)-1(2), D24 Diesel Generator LOCA/Load Reject Testing and Fast Start Operability Test Run. Specifically, ST-6-092-321(2,3,4)-1(2) did not incorporate changes to SR 4.8.1.1.2.e.2.c resulting in steady-state diesel generator frequency not being verified to be within the specified band after rejection of the largest post-accident load, calling into question the operability of the diesel generators.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 31, 2025, the inspectors presented the 2025 Limerick Comprehensive Engineering Team Inspection Exit Meeting inspection results to Michael Gillin, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

6300E.20

Voltage Regulation Study

Revision 17

6380E.07

Diesel Generator Loading (Steady State)

Revision 15F

6900E.02

Safeguard Auxiliary System - Phase Overcurrent Relays

Selection and Coordination

Revision 11

6900E.02

Safeguard Aux Sys-Phase Overcurrent Relays Selection

and Coordination

Revision 11

6900E.11

Load Center Circuit Breakers - Overcurrent Trip Devices

Revision 14

ECR 07-00392

RCIC Blackout Rule Calculations and Documentation

Revision 0

LE-0130

Class 1E 125/250V DC System Analysis

Revision 1

LM-0060

Blackout Analysis RCIC Room

Revision 2

LM-0638

RHR Heat Exchanger Min. RHRSW Flow/Structural

Evaluation for Tube Plugging-Suppression Pool Cooling

Service

Revision 4

LM-0640

RHR Heat Exchanger Min. RHRSW Flow/Fouling

Factor/Tube Plugging Limits for Shutdown Cooling

Revision 3

LM-0689

RCIC Pump Room Temperatures for Extended Loss of AC

Power Post-Fukushima Scenario

Revision 0

TODI-14-00019-

04-DC

DC Battery Load Shedding Input for Fukushima FLEX ECR

Development at LGS

Revision 0

Corrective Action

Documents

4352540

4389680

4389684

4475750

4491715

4494135

29355

29359

4541869

4555478

20918

47993551

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4804978

4813711

4815024

Corrective Action

Documents

Resulting from

Inspection

28704

29315

29322

29324

29614

29904

29913

29913

29918

29918

29920

29920

4830283

4830369

4832043

4832817

4833261

4833261

4833632

Drawings

8031-M-87

P&ID Drywell Chilled Water (Unit 1) Sh 4 & 5

Revision 42

E-0027

MCC Load Tabulation D214-R-G1

Revision 33

Engineering

Changes

631464

Implementation EC for D24 Governor Replacement

Revision 1

643468

Post RHR Reject Data Documentation

Revision 0

Engineering

Evaluations

633213

Technical Evaluation of Potential Reportability Related to

Breakers 72-20307 and 72-20308

Revision 0

LIM-0-2024-0124

Simple Issue Risk Assessment - B CECW Chiller Trip

Bypass

Revision 0

Miscellaneous

NRC Letter LIMERICK GENERATING STATION, UNITS 1

AND 2 - ISSUANCE OF AMENDMENTS NOS. 258 AND

20 REGARDING TECHNICAL SPECIFICATIONS 3/4.8.1,

dated

01/03/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AC SOURCES-OPERATING AND 3/4.5.1, ECCS-

OPERATING (EPID L-2020-LLA-0233) (ML22272A037)

294652

MOV Post-Test Data Review Worksheet

Dated

5/27/2023

L-S-02

Emergency Service Water System Design Baseline

Document

Revision 15

RT-2-011-251-0

ESW Loop A Flow Balance

Performed

8/29/2023

RT-2-011-252-0

ESW Loop B Flow Balance

Performed

9/24/2024

ST-4-095-952-1

Division I 1A2D101 Safeguard Battery Modified Performance

Test

Performed

4/5/2020

ST-4-LLR-582-2

Suppression Pool Purge Exhaust

Performed

5/8/2023

ST-6-051-232-1

B RHR Pump, Valve and Flow Test

Performed

9/6/2024

Procedures

1FSSG-3044W

Fire Area 044W Fire Guide

Revision 12

E-D214

Loss of D214 Safeguard Load Center

Revision 14

ER-LG-330-1002

LGS ISI Augmented Inspection Program

Revision 10

S.12.1.A

RHR Service Water System Startup

Revision 59

ST-6-092-324-2

D24 Diesel Generator LOCA/Load Reject Testing and Fast

Start Operability Test Run

Revision 32

ST-6-092-324-2

D24 Diesel Generator LOCA/LOAD Reject Testing and Fast

Start Operability Test Run

Revision 32

Work Orders

247310

05177184

05548912

274413

R09352424