IR 05000259/2015005: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(7 intermediate revisions by the same user not shown)
Line 3: Line 3:
| issue date = 09/01/2015
| issue date = 09/01/2015
| title = Mid-Cycle Assessment Letter for the Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Report 005000259/2015005, 005000260/2015005, and 005000296/2015005
| title = Mid-Cycle Assessment Letter for the Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Report 005000259/2015005, 005000260/2015005, and 005000296/2015005
| author name = Blamey A J
| author name = Blamey A
| author affiliation = NRC/RGN-II/DRP
| author affiliation = NRC/RGN-II/DRP
| addressee name = Shea J W
| addressee name = Shea J
| addressee affiliation = Tennessee Valley Authority
| addressee affiliation = Tennessee Valley Authority
| docket = 05000259, 05000260, 05000296
| docket = 05000259, 05000260, 05000296
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION ber 1, 2015
[[Issue date::September 1, 2015]]


Mr. Joseph Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37402-2801
==SUBJECT:==
MID-CYCLE ASSESSMENT LETTER FOR THE BROWNS FERRY NUCLEAR PLANT UNITS 1, 2 and 3, NRC INSPECTION REPORT 005000259/2015005, 005000260/2015005, and 005000296/2015005


SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR THE BROWNS FERRY NUCLEAR PLANT UNITS 1, 2 and 3, NRC INSPECTION REPORT 005000259/2015005, 005000260/2015005, and 005000296/2015005
==Dear Mr. Shea:==
On August 13, 2015, the NRC completed its mid-cycle performance review of Browns Ferry Nuclear Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015.
 
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
 
The NRC determined that overall, Browns Ferry Nuclear Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Browns Ferry Nuclear Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green).
 
Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
 
The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
 
In addition to the routine ROP baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include Inspection Procedure (IP) 43004, Inspection of Commercial-Grade Dedication Programs, and an initial operator license examination. In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. This Order requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. This Order requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The audit was completed for Browns Ferry in January of 2015, and the information gathered will aid staff in development of the Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above performing TI 191: Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.
 
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
Please contact me at 404-997-4415 with any questions you have regarding this letter.
 
Sincerely,
/RA/
Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-259, 50-260, 50-296 License Nos. DPR-33, DPR-52, DPR-68 Enclosure: Browns Ferry Inspection/Activity Plan (07/01/2015 - 06/30/2017)
cc distribution via ListServ
 
_________________________  XSUNSI REVIEW COMPLETE OFFICE  RII:DRP RII:DRP RII:DRP SIGNATURE BDB3 CRK1 AJB3 NAME  BBISHOP CKONTZ ABLAMEY DATE  8/25/2015 8/25/2015 8/31/2015 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO Letter to Joseph Shea from Alan Blamey dated September 1, 2015 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR THE BROWNS FERRY NUCLEAR PLANT UNITS 1, 2 and 3, NRC INSPECTION REPORT 005000259/2015005, 005000260/2015005, and 005000296/2015005 DISTRIBUTION:
D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR RidsNrrPMBrownsFerry Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)


==Dear Mr. Shea:==
Page 1 of 2      Browns Ferry 09/01/2015 10:14:23    Inspection / Activity Plan Report 22 09/01/2015 - 06/30/2017 Unit Planned Dates        No. of Staff Number Start End Inspection Activity    Title  on Site OL EXAM - INITIAL LICENSE EXAM PREP      3 1 10/19/2015 10/23/2015 V23463 BROWNS FERRY NOVEMBER 2015 INITIAL EXAM AT POWER FACILITIES CDBI - COMPONENT DESIGN BASES INSPECTION      8 1, 2, 3 10/19/2015 10/23/2015 IP 7111121 Component Design Bases Inspection 1, 2, 3 11/30/2015 12/04/2015 IP 7111121 Component Design Bases Inspection 1, 2, 3 12/14/2015 12/18/2015 IP 7111121 Component Design Bases Inspection EP - EP EXERCISE      6 1, 2, 3 11/02/2015 11/06/2015 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2, 3 11/02/2015 11/06/2015 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event 1, 2, 3 11/02/2015 11/06/2015 IP 71151  Performance Indicator Verification OL EXAM - INITIAL LICENSE EXAM      3 1 11/16/2015 12/04/2015 V23463 BROWNS FERRY NOVEMBER 2015 INITIAL EXAM AT POWER FACILITIES PI&R - PROBLEM IDENTIFICATION AND RESOLUTION      4 1, 2, 3 02/08/2016 02/12/2016 IP 71152B Problem Identification and Resolution 1, 2, 3 02/22/2016 02/26/2016 IP 71152B Problem Identification and Resolution RP - RAD HAZARDS ANALYSIS AND TRANSPORTATION      2 1, 2, 3 02/29/2016 03/04/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 02/29/2016 03/04/2016 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation ISI - UNIT 3 IN-SERVICE INSPECTION      1 3 03/07/2016 03/11/2016 IP 7111108G Inservice Inspection Activities - BWR LR - UNIT 3 POST APPROVAL LR PHASE 1      2 3 03/07/2016 03/11/2016 IP 71003  Post-Approval Site Inspection for License Renewal EQ - ENVIRONMENTAL QUALIFICATION INSPECTION      3 1, 2, 3 03/21/2016 03/25/2016 IP 7111121 Component Design Bases Inspection 1, 2, 3 04/11/2016 04/15/2016 IP 7111121 Component Design Bases Inspection EP - EP PROGRAM INSPECTION      2 1, 2, 3 06/06/2016 06/10/2016 IP 7111401 Exercise Evaluation 1, 2, 3 06/06/2016 06/10/2016 IP 7111402 Alert and Notification System Testing 1, 2, 3 06/06/2016 06/10/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2, 3 06/06/2016 06/10/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2, 3 06/06/2016 06/10/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2, 3 06/06/2016 06/10/2016 IP 71151  Performance Indicator Verification This report does not include INPO and OUTAGE activities.
On August 13, 2015, the NRC completed its mid-cycle performance review of Browns Ferry Nuclear Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. The NRC determined that overall, Browns Ferry Nuclear Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Browns Ferry Nuclear Plant during the most recent quarter was within the Licensee Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
 
This report shows only on-site and announced inspection procedures.


In addition to the routine ROP baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include Inspection Procedure (IP) 43004, "Inspection of Commercial-Grade Dedication Programs," and an initial operator license examination. In response to the accident at Fukushima, the Commission issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events." This Order requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation." This Order requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The audit was completed for Browns Ferry in January of 2015, and the information gathered will aid staff in development of the Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above performing TI 191: "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans." In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 404-997-4415 with any questions you have regarding this letter.
Enclosure


Sincerely,/RA/
Page 2 of 2      Browns Ferry 09/01/2015 10:14:23    Inspection / Activity Plan Report 22 09/01/2015 - 06/30/2017 Unit Planned Dates      No. of Staff Number Start End Inspection Activity    Title on Site RP - RP PUBLIC RAD SAFETY BASELINE    2 1, 2, 3 06/13/2016 06/17/2016 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2, 3 06/13/2016 06/17/2016 IP 71124.07 Radiological Environmental Monitoring Program 1, 2, 3 06/13/2016 06/17/2016 IP 71151  Performance Indicator Verification TFPI - TRIENNIEL FIRE PROTECTION INSPECTION  4 1, 2, 3 07/25/2016 07/29/2016 IP 7111105T Fire Protection [Triennial]
Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-259, 50-260, 50-296 License Nos. DPR-33, DPR-52, DPR-68
1, 2, 3 08/08/2016 08/12/2016 IP 7111105T Fire Protection [Triennial]
OL RQ - REQUAL INSP    2 1, 2, 3 09/12/2016 09/16/2016 IP 7111111B Licensed Operator Requalification Program ISI - UNIT 1 IN-SERVICE INSPECTION    1 1 10/10/2016 10/14/2016 IP 7111108G Inservice Inspection Activities - BWR ISI - UNIT 2 IN-SERVICE INSPECTION    1 2 03/13/2017 03/17/2017 IP 7111108G Inservice Inspection Activities - BWR RP - RP OCCUPATIONAL INSPECTION WEEK 1    3 1, 2, 3 03/13/2017 03/17/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 03/13/2017 03/17/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2, 3 03/13/2017 03/17/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 03/13/2017 03/17/2017 IP 71124.04 Occupational Dose Assessment 1, 2, 3 03/13/2017 03/17/2017 IP 71124.05 Radiation Monitoring Instrumentation 1, 2, 3 03/13/2017 03/17/2017 IP 71151  Performance Indicator Verification RP - RP OCCUPATIONAL INSPECTION WEEK 2    2 1, 2, 3 03/27/2017 03/31/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 03/27/2017 03/31/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2, 3 03/27/2017 03/31/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 03/27/2017 03/31/2017 IP 71124.04 Occupational Dose Assessment 1, 2, 3 03/27/2017 03/31/2017 IP 71124.05 Radiation Monitoring Instrumentation 1, 2, 3 03/27/2017 03/31/2017 IP 71151  Performance Indicator Verification EP - EP EXERCISE    6 1, 2, 3 06/26/2017 06/30/2017 IP 7111401 Exercise Evaluation 1, 2, 3 06/26/2017 06/30/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2, 3 06/26/2017 06/30/2017 IP 7111408 Exercise Evaluation - Scenario Review 1, 2, 3 06/26/2017 06/30/2017 IP 71151  Performance Indicator Verification This report does not include INPO and OUTAGE activities.


===Enclosure:===
This report shows only on-site and announced inspection procedures. Enclosure
Browns Ferry Inspection/Activity Plan  (07/01/2015 - 06/30/2017) cc distribution via ListServ
}}
}}

Latest revision as of 08:07, 31 October 2019

Mid-Cycle Assessment Letter for the Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Report 005000259/2015005, 005000260/2015005, and 005000296/2015005
ML15244B010
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 09/01/2015
From: Alan Blamey
Division Reactor Projects II
To: James Shea
Tennessee Valley Authority
References
IR 2015005
Download: ML15244B010 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION ber 1, 2015

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR THE BROWNS FERRY NUCLEAR PLANT UNITS 1, 2 and 3, NRC INSPECTION REPORT 005000259/2015005, 005000260/2015005, and 005000296/2015005

Dear Mr. Shea:

On August 13, 2015, the NRC completed its mid-cycle performance review of Browns Ferry Nuclear Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015.

This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Browns Ferry Nuclear Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Browns Ferry Nuclear Plant during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In addition to the routine ROP baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include Inspection Procedure (IP) 43004, Inspection of Commercial-Grade Dedication Programs, and an initial operator license examination. In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. This Order requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. This Order requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The audit was completed for Browns Ferry in January of 2015, and the information gathered will aid staff in development of the Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above performing TI 191: Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 404-997-4415 with any questions you have regarding this letter.

Sincerely,

/RA/

Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket Nos.: 50-259, 50-260, 50-296 License Nos. DPR-33, DPR-52, DPR-68 Enclosure: Browns Ferry Inspection/Activity Plan (07/01/2015 - 06/30/2017)

cc distribution via ListServ

_________________________ XSUNSI REVIEW COMPLETE OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE BDB3 CRK1 AJB3 NAME BBISHOP CKONTZ ABLAMEY DATE 8/25/2015 8/25/2015 8/31/2015 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO Letter to Joseph Shea from Alan Blamey dated September 1, 2015 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR THE BROWNS FERRY NUCLEAR PLANT UNITS 1, 2 and 3, NRC INSPECTION REPORT 005000259/2015005, 005000260/2015005, and 005000296/2015005 DISTRIBUTION:

D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR RidsNrrPMBrownsFerry Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)

Page 1 of 2 Browns Ferry 09/01/2015 10:14:23 Inspection / Activity Plan Report 22 09/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site OL EXAM - INITIAL LICENSE EXAM PREP 3 1 10/19/2015 10/23/2015 V23463 BROWNS FERRY NOVEMBER 2015 INITIAL EXAM AT POWER FACILITIES CDBI - COMPONENT DESIGN BASES INSPECTION 8 1, 2, 3 10/19/2015 10/23/2015 IP 7111121 Component Design Bases Inspection 1, 2, 3 11/30/2015 12/04/2015 IP 7111121 Component Design Bases Inspection 1, 2, 3 12/14/2015 12/18/2015 IP 7111121 Component Design Bases Inspection EP - EP EXERCISE 6 1, 2, 3 11/02/2015 11/06/2015 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2, 3 11/02/2015 11/06/2015 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event 1, 2, 3 11/02/2015 11/06/2015 IP 71151 Performance Indicator Verification OL EXAM - INITIAL LICENSE EXAM 3 1 11/16/2015 12/04/2015 V23463 BROWNS FERRY NOVEMBER 2015 INITIAL EXAM AT POWER FACILITIES PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 4 1, 2, 3 02/08/2016 02/12/2016 IP 71152B Problem Identification and Resolution 1, 2, 3 02/22/2016 02/26/2016 IP 71152B Problem Identification and Resolution RP - RAD HAZARDS ANALYSIS AND TRANSPORTATION 2 1, 2, 3 02/29/2016 03/04/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 02/29/2016 03/04/2016 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation ISI - UNIT 3 IN-SERVICE INSPECTION 1 3 03/07/2016 03/11/2016 IP 7111108G Inservice Inspection Activities - BWR LR - UNIT 3 POST APPROVAL LR PHASE 1 2 3 03/07/2016 03/11/2016 IP 71003 Post-Approval Site Inspection for License Renewal EQ - ENVIRONMENTAL QUALIFICATION INSPECTION 3 1, 2, 3 03/21/2016 03/25/2016 IP 7111121 Component Design Bases Inspection 1, 2, 3 04/11/2016 04/15/2016 IP 7111121 Component Design Bases Inspection EP - EP PROGRAM INSPECTION 2 1, 2, 3 06/06/2016 06/10/2016 IP 7111401 Exercise Evaluation 1, 2, 3 06/06/2016 06/10/2016 IP 7111402 Alert and Notification System Testing 1, 2, 3 06/06/2016 06/10/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2, 3 06/06/2016 06/10/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2, 3 06/06/2016 06/10/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2, 3 06/06/2016 06/10/2016 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 2 Browns Ferry 09/01/2015 10:14:23 Inspection / Activity Plan Report 22 09/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RP - RP PUBLIC RAD SAFETY BASELINE 2 1, 2, 3 06/13/2016 06/17/2016 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2, 3 06/13/2016 06/17/2016 IP 71124.07 Radiological Environmental Monitoring Program 1, 2, 3 06/13/2016 06/17/2016 IP 71151 Performance Indicator Verification TFPI - TRIENNIEL FIRE PROTECTION INSPECTION 4 1, 2, 3 07/25/2016 07/29/2016 IP 7111105T Fire Protection [Triennial]

1, 2, 3 08/08/2016 08/12/2016 IP 7111105T Fire Protection [Triennial]

OL RQ - REQUAL INSP 2 1, 2, 3 09/12/2016 09/16/2016 IP 7111111B Licensed Operator Requalification Program ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 10/10/2016 10/14/2016 IP 7111108G Inservice Inspection Activities - BWR ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 03/13/2017 03/17/2017 IP 7111108G Inservice Inspection Activities - BWR RP - RP OCCUPATIONAL INSPECTION WEEK 1 3 1, 2, 3 03/13/2017 03/17/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 03/13/2017 03/17/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2, 3 03/13/2017 03/17/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 03/13/2017 03/17/2017 IP 71124.04 Occupational Dose Assessment 1, 2, 3 03/13/2017 03/17/2017 IP 71124.05 Radiation Monitoring Instrumentation 1, 2, 3 03/13/2017 03/17/2017 IP 71151 Performance Indicator Verification RP - RP OCCUPATIONAL INSPECTION WEEK 2 2 1, 2, 3 03/27/2017 03/31/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2, 3 03/27/2017 03/31/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2, 3 03/27/2017 03/31/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2, 3 03/27/2017 03/31/2017 IP 71124.04 Occupational Dose Assessment 1, 2, 3 03/27/2017 03/31/2017 IP 71124.05 Radiation Monitoring Instrumentation 1, 2, 3 03/27/2017 03/31/2017 IP 71151 Performance Indicator Verification EP - EP EXERCISE 6 1, 2, 3 06/26/2017 06/30/2017 IP 7111401 Exercise Evaluation 1, 2, 3 06/26/2017 06/30/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2, 3 06/26/2017 06/30/2017 IP 7111408 Exercise Evaluation - Scenario Review 1, 2, 3 06/26/2017 06/30/2017 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure