MONTHYEARIR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 IR 05000259/20220062023-03-0101 March 2023 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022006, 05000260/2022006 and 05000296/2022006 ML23020A0602023-01-20020 January 2023 Long Term Steam Dryer Inspection Plan IR 05000259/20220052022-08-30030 August 2022 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022005, 05000260/2022005 and 05000296/2022005 ML22210A1342022-07-20020 July 2022 Requalification Inspection Notification Letter ML22174A2722022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20224012022-03-0808 March 2022 Information Request for the Cyber-Security Baseline Inspection Notification to Perform Inspection 05000259/2022401; 05000260/2022401; 05000296/2022401 ML22091A1942022-03-0808 March 2022 2022 BFN POV Inspection Information Request IR 05000259/20210062022-03-0202 March 2022 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 (Report No. 05000259/2021006, 05000260/2021006 and 05000296/2021006 ML22025A4132022-01-25025 January 2022 RP Inspection Doc Request ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21343A4232021-12-0909 December 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000259/2022010, 05000260/2022010, and 05000296/2022010) and Request for Information (RFI) IR 05000259/20210052021-08-23023 August 2021 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2, and 3- Report Nos. 05000259/2021005, 05000260/2021005 and 5000296/2021005 IR 05000259/20200062021-03-0303 March 2021 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020006, 05000260/2020006 and 05000296/2020006 ML21047A4732021-02-16016 February 2021 Notification of Browns Ferry Nuclear Power Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2021010, 05000260/2021010, and 05000296/2021010 ML20338A3682020-12-0303 December 2020 Notification of Inspection and Request for Information ML20266G4472020-09-22022 September 2020 Notification of Inspection and Request for Information IR 05000259/20200052020-08-18018 August 2020 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020005, 05000260/2020005, and 05000296/2020005 ML20191A2232020-07-0909 July 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20190062020-03-0303 March 2020 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1,2,and 3 - NRC Report 05000259/2019006, 05000260/2019006, and 05000296/2019006 ML19108A1682019-04-18018 April 2019 EP Exercise Inspection RFI IR 05000259/20180062019-03-0404 March 2019 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2018006, 05000260/2018006 and 05000328/2018006 ML19030A6712019-01-25025 January 2019 U2 ISI RFI ML19024A4112019-01-24024 January 2019 Transmittal of RP Baseline Inspection Document Request 2019 ML18264A2052018-09-21021 September 2018 U1 ISI Emailed RFI Notification ML18059A1052018-02-28028 February 2018 EOC Assessment Letter ML18029A4672018-01-29029 January 2018 Notification of Browns Ferry Nuclear Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2018010, 05000260/2018010, and 05000296/2018010 ML18029A2552018-01-29029 January 2018 U3 RFI Email Request ML17236A1972017-08-24024 August 2017 Updated Inspection Plan ML17156A1612017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000259/20160062017-03-0101 March 2017 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2, and 3 (Report 05000259/2016006, 05000260/2016006 and 05000296/2016006) IR 05000259/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Reports 05000259/2016005, 05000260/2016005 and 05000296/2016005 ML16243A2242016-08-30030 August 2016 Notification of Inspection and Request for Information ML16120A1182016-04-27027 April 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection - U.S. Nuclear Regulatory Commission Inspection Report Nos. 05000259/2016011, 05000260/2016011 and 05000296/2016011 IR 05000259/20150062016-03-0202 March 2016 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 NRC Inspection Reports 05000259/2015006, 05000260/2015006 and 05000296/2015006 ML16013A0812016-01-12012 January 2016 Browns Ferry Nuclear Plant, Unit 3 - Notification of Inspection and Request for Information ML15348A1802015-12-14014 December 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for the Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Report 005000259/2015005, 005000260/2015005, and 005000296/2015005 IR 05000259/20140012015-03-0404 March 2015 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 - NRC Inspection Reports 05000259/2014001, 05000260/2014001 and 05000296/2014001 IR 05000259/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 (NRC Inspection Reports 05000259/2014006, 05000260/2014006 and 05000296/2014006) ML14063A1092014-03-0404 March 2014 2013 Annual Assessment Letter for Browns Ferry ML14031A4122014-01-31031 January 2014 U3 2014002 ISI RFI Final - Copy ML13353A5852013-12-19019 December 2013 PIR Notification Letter 2014 ML13246A1842013-09-0303 September 2013 Mid Cycle Assessment Letter ML13084A0052013-03-25025 March 2013 Emergency Preparedness Inspection Notification and Request for Information IR 05000259/20120012013-03-0404 March 2013 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 & 3 (IR 05000259-12-001, 05000260-12-001, and 05000296-12-001) ML13037A1662013-02-0101 February 2013 Notification of Inspection and Request for Information IR 05000259/20120062012-09-0404 September 2012 Browns Ferry 2012 Mid Cycle ML12248A2962012-09-0404 September 2012 Mid Cycle ML12066A0602012-03-0505 March 2012 Inspection/Activity Plan, 30/01/2012 - 06/01/2013, RPT 22 2023-08-29
[Table view] Category:Letter
MONTHYEARML24032A4762024-02-0101 February 2024 Final Report of a Part 21 Evaluation Associated with Starter Contactors for the BFN Unit 1 High Pressure Coolant Injection Suppression Pool Inboard Suction Valve ML24023A2802024-01-23023 January 2024 Final Report of a Deviation or Failure to Comply Associated with a Relay in the Reactor Core Isolation Cooling Condensate Pump CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24016A3042024-01-16016 January 2024 Final Report of a Part 21 Evaluation Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 ML24022A1732024-01-0303 January 2024 Receipt and Availability of the Subsequent License Renewal Application ML23319A1992024-01-0303 January 2024 Issuance of Amendment Nos. 333, 356, and 316 Regarding the Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves ML23355A2062023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23348A3942023-12-14014 December 2023 Interim Part 21 Report of a Potential Deviation or Failure to Comply Associated with Starter Contactors for the High Pressure Coolant Injection Suppression Pool Inboard Suction Valve IR 05000259/20230102023-12-11011 December 2023 Commercial Grade Dedication Inspection Report 05000259/2023010 and 05000260/2023010 and 05000296/2023010 ML23335A0722023-12-0101 December 2023 Interim Report of a Deviation or Failure to Comply Associated with a Relay in the Unit 2 Reactor Core Isolation Cooling Condensate Pump ML23334A2492023-11-30030 November 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-070, Submittal of Fifth 10-Year Interval Inservice Testing Program Plan2023-11-29029 November 2023 Submittal of Fifth 10-Year Interval Inservice Testing Program Plan ML23331A2532023-11-27027 November 2023 Summary Report for 10 CFR 50.9 Evaluations, Technical Specifications Bases Changes, Technical Requirement Manual Changes, and NRC Commitment Revisions CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23325A1102023-11-21021 November 2023 Anchor Darling Double Disc Gate Valve Commitment Revision ML23320A2542023-11-16016 November 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump IR 05000259/20230032023-11-13013 November 2023 Integrated Inspection Report 05000259/2023003, 05000260/2023003 and 05000296/2023003 IR 05000259/20230402023-11-0202 November 2023 Supplemental Inspection Supplemental Report 05000259 2023040 and Follow-Up Assessment Letter ML23292A2532023-10-18018 October 2023 BFN 2024-301, Corporate Notification Letter (210-day Ltr) ML23282A0022023-10-0606 October 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump ML23278A0122023-10-0505 October 2023 Updated Final Safety Analysis Report, Amendment 30 ML23271A1702023-09-28028 September 2023 Site Emergency Plan Implementing Procedure Revision ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23257A1232023-09-22022 September 2023 Administrative Changes to Technical Specification Pages Issued for License Amendment Nos. 332, 355, and 315 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23263B1042023-09-20020 September 2023 Special Report 260/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML23205A2132023-09-0808 September 2023 Issuance of Amendment Nos. 332, 355, and 315 Regarding the Revision of Technical Specifications to Adopt TSTF-566-A and TSTF-580-A, Rev. 1 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 ML23233A0432023-08-18018 August 2023 Enforcement Action EA-22-122 Inspection Readiness Notification ML23219A1542023-08-17017 August 2023 Request to Use Later Edition of ASME Code for Operation and Maintenance and Alternative Requests BFN-IST-01 Through 05 for the Fifth 10-Year Interval Inservice Testing Program ML23228A1642023-08-16016 August 2023 Site Emergency Plan Implementing Procedure Revision ML23228A0202023-08-15015 August 2023 (BFN) Unit 1 - Special Report 259/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation IR 05000259/20230022023-08-10010 August 2023 Integrated Inspection Report 05000259/2023002, 05000260/2023002, 05000296/2023002 and 07200052/2023001 ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills ML23171A8862023-07-24024 July 2023 Issuance of Amend. Nos. 331, 354, and 314; 365 and 359 Regarding Adoption of TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML23201A2182023-07-20020 July 2023 Registration of Use of Cask to Store Spent Fuel (MPC-298 and -299) ML23159A2552023-07-20020 July 2023 Proposed Alternative to the Requirements of the ASME Code Regarding Volumetric Inspection of Standby Liquid Control Nozzles ML23199A3072023-07-18018 July 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions IR 05000259/20233012023-07-18018 July 2023 NRC Operator License Examination Report Nos. 05000259/2023301, 05000260/2023301, and 05000296/2023301 2024-02-01
[Table view] |
See also: IR 05000259/2018010
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
January 29, 2018
Mr. J. W. Shea
Vice President, Nuclear Licensing
Tennessee Valley Authority
1101 Market Street, LP 3D-C
Chattanooga, TN 37402-2801
SUBJECT: NOTIFICATION OF BROWNS FERRY NUCLEAR PLANT DESIGN BASES
ASSURANCE INSPECTION - U.S. NUCLEAR REGULATORY COMMISSION
INSPECTION REPORT 05000259/2018010, 05000260/2018010, AND
05000296/2018010
Dear Mr. Shea,
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a Design Bases Assurance Inspection (DBAI) at your Browns Ferry
Nuclear Plant during the weeks of April 30 and May 14, 2018. Mr. Geoffrey Ottenberg, a Senior
Reactor Inspector from the NRCs Region II office, will lead the inspection team. The inspection
will be conducted in accordance with Inspection Procedure 71111.21M, Design Bases
Assurance Inspection (Teams), dated December 8, 2016 (ADAMS ML16238A320).
The inspection will evaluate the capability of components that have been modified and risk-
significant/low-margin components to function as designed and to support proper system
operation. The inspection will also include a review of selected operator actions, operating
experience, and modifications.
During a telephone conversation on January 23, 2018, with Mr. Justin Garner, we confirmed
arrangements for an information-gathering site visit and the two-week onsite inspection. The
schedule is as follows:
- Information-gathering visit: Week of April 9, 2018
- Onsite weeks: Weeks of April 30 and May 14, 2018
The purpose of the information-gathering visit is to meet with members of your staff to identify
components that have been modified, risk-significant components and operator actions.
Information and documentation needed to support the inspection will also be identified. Mr.
Scott Freeman, a Region II Senior Risk Analyst, will support Mr. Ottenberg during the
information-gathering visit to review probabilistic risk assessment data and identify components
to be examined during the inspection. Additionally, during the onsite weeks, time will be needed
on the plant-referenced simulator in order to facilitate the development of operator action-based
scenarios.
J. Shea 2
The enclosure lists documents that will be needed prior to the information-gathering visit.
Please provide the referenced information to the Region II Office by April 2, 2018. Additional
documents will be requested following the information-gathering visit. The inspectors will try to
minimize your administrative burden by specifically identifying only those documents required
for inspection preparation. The additional information will be needed in the Region II office by
April 20, 2018, to support the inspection teams preparation week. During the information-
gathering trip, Mr. Ottenberg will also discuss the following inspection support administrative
details: (1) availability of knowledgeable plant engineering and licensing personnel to serve as
points of contact during the inspection; (2) method of tracking inspector requests during the
inspection; (3) licensee computer access; (4) working space; (5) arrangements for site access;
and (6) other applicable information.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
Thank you for your cooperation in this matter. If you have any questions, regarding the
information requested or the inspection, please contact Mr. Ottenberg at 404-997-4658 or
contact me at 404-997-4629.
Sincerely,
/RA/
Marvin D. Sykes, Chief
Engineering Branch 1
Division of Reactor Safety
Docket Nos.: 50-259, 50-260, 50-296
License Nos.: DPR-33, DPR-52, DPR-68
Enclosure:
Notification of Browns Ferry Nuclear Plant
Design Bases Assurance Inspection (Teams)
cc: Distribution via Listserv
____MLXXXXXXXXX__________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED
OFFICE RII:DRS RII:DRS
SIGNATURE GKO MDS1
NAME G. Ottenberg M. Sykes
DATE 1/29/18 1/29/2018
E-MAIL COPY? YES NO YES NO
INFORMATION REQUEST FOR BROWNS FERRY NUCLEAR PLANT
DESIGN BASES ASSURANCE INSPECTION (TEAMS)
Please provide the information electronically in .pdf files, Excel, or other searchable format on
CDROM (or FTP site, SharePoint, etc.). The CDROM (or website) should be indexed and
hyperlinked to facilitate ease of use. The requested items below, identified with an asterisk (*),
should have a date range from November 1, 2016, until present.
1. *List and brief description of permanent and field work completed plant modifications
including permanent plant changes, design changes, set point changes, procedure
changes, equivalency evaluations, suitability analyses, calculations, and commercial grade
dedications. Include an index of systems (system numbers/designators and corresponding
names), the safety classification for each modification, and type of modification.
2. From your most recent probabilistic safety analysis (PSA) excluding external events and
fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by Risk
Achievement Worth (RAW), and the other sorted by Birnbaum Importance
b. A list of the top 500 cut-sets
c. A list of the top 500 LERF contributors
3. From your most recent PSA including external events and fires:
a. Two risk rankings of components from your site-specific PSA: one sorted by RAW,
and the other sorted by Birnbaum Importance
b. A list of the top 500 cut-sets
4. Risk ranking of operator actions from your site-specific PSA sorted by RAW and human
reliability worksheets for these items
5. List of time-critical operator actions with a brief description of each action
6. *List of components with low-design margins (i.e., pumps closest to the design limit for flow
or pressure, diesel generator close to design-required output, heat exchangers close to
rated design heat removal, and motor-operated valve risk-margin rankings, etc.) and
associated evaluations or calculations
7. *List and brief description of Root Cause Evaluations performed
8. *List and brief description of common-cause component failures that have occurred
9. List and brief description of equipment currently in degraded or nonconforming status as
described in NRC Inspection Manual Chapter 0326, issued December 3, 2015
10. *List and brief description of Operability Determinations and Functionality Assessments
Enclosure
2
11. *List and reason for equipment that has been classified in maintenance rule (a)(1) status
12. *List of equipment on the sites Station Equipment Reliability Issues List, including a
description of the reason(s) why each component is on that list, and summaries (if
available) of your plans to address the issue(s) along with dates added or removed from
the issues list
13. List of current operator work arounds/burdens
14. Copy of Updated Final Safety Analysis Report
15. Copy of Technical Specification(s)
16. Copy of Technical Specifications Bases
17. Copy of Technical Requirements Manual(s)
18. Copy of the Quality Assurance Program Manual
19. Copy of Corrective Action Program Procedure(s)
20. Copy of Operability Determination Procedure(s)
21. Copy of procedures addressing the following: Modifications, design changes, set point
changes, equivalency evaluations or suitability analyses, commercial grade dedications,
post-modifications testing, 10 CFR 50.59 screenings and evaluations, and UFSAR updates.
22. List of motor operated valves and air operated valves in the valve program, and their
associated design margin and risk ranking
23. Primary AC and DC calculations for safety-related buses
24. One-line diagram of electrical plant (Electronic only)
25. Index and legend for electrical plant one-line diagrams
26. Piping and instrumentation diagrams (P&IDs) for safety-related systems (Electronic)
27. Index and legend for P&IDs
28. Index (procedure number, title, and current revision) of station Emergency Operating
Procedures, Abnormal Operating Procedures, and Annunciator Response Procedures
29. Copies of corrective action documents generated from previous CDBI
30. Copy of any self-assessments performed, and corrective action documents generated, in
preparation for current DBAI
31. Contact information for a person to discuss PSA information prior to and during the
information-gathering trip (Name, title, phone number, and e-mail address)