MONTHYEARML24032A4762024-02-0101 February 2024 Final Report of a Part 21 Evaluation Associated with Starter Contactors for the BFN Unit 1 High Pressure Coolant Injection Suppression Pool Inboard Suction Valve ML24023A2802024-01-23023 January 2024 Final Report of a Deviation or Failure to Comply Associated with a Relay in the Reactor Core Isolation Cooling Condensate Pump CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24016A3042024-01-16016 January 2024 Final Report of a Part 21 Evaluation Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 ML24022A1732024-01-0303 January 2024 Receipt and Availability of the Subsequent License Renewal Application ML23319A1992024-01-0303 January 2024 Issuance of Amendment Nos. 333, 356, and 316 Regarding the Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves ML23355A2062023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23348A3942023-12-14014 December 2023 Interim Part 21 Report of a Potential Deviation or Failure to Comply Associated with Starter Contactors for the High Pressure Coolant Injection Suppression Pool Inboard Suction Valve IR 05000259/20230102023-12-11011 December 2023 Commercial Grade Dedication Inspection Report 05000259/2023010 and 05000260/2023010 and 05000296/2023010 ML23335A0722023-12-0101 December 2023 Interim Report of a Deviation or Failure to Comply Associated with a Relay in the Unit 2 Reactor Core Isolation Cooling Condensate Pump ML23334A2492023-11-30030 November 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-070, Submittal of Fifth 10-Year Interval Inservice Testing Program Plan2023-11-29029 November 2023 Submittal of Fifth 10-Year Interval Inservice Testing Program Plan ML23331A2532023-11-27027 November 2023 Summary Report for 10 CFR 50.9 Evaluations, Technical Specifications Bases Changes, Technical Requirement Manual Changes, and NRC Commitment Revisions CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23325A1102023-11-21021 November 2023 Anchor Darling Double Disc Gate Valve Commitment Revision ML23320A2542023-11-16016 November 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump IR 05000259/20230032023-11-13013 November 2023 Integrated Inspection Report 05000259/2023003, 05000260/2023003 and 05000296/2023003 IR 05000259/20230402023-11-0202 November 2023 Supplemental Inspection Supplemental Report 05000259 2023040 and Follow-Up Assessment Letter ML23292A2532023-10-18018 October 2023 BFN 2024-301, Corporate Notification Letter (210-day Ltr) ML23282A0022023-10-0606 October 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump ML23278A0122023-10-0505 October 2023 Updated Final Safety Analysis Report, Amendment 30 ML23271A1702023-09-28028 September 2023 Site Emergency Plan Implementing Procedure Revision ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23257A1232023-09-22022 September 2023 Administrative Changes to Technical Specification Pages Issued for License Amendment Nos. 332, 355, and 315 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23263B1042023-09-20020 September 2023 Special Report 260/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML23205A2132023-09-0808 September 2023 Issuance of Amendment Nos. 332, 355, and 315 Regarding the Revision of Technical Specifications to Adopt TSTF-566-A and TSTF-580-A, Rev. 1 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 ML23233A0432023-08-18018 August 2023 Enforcement Action EA-22-122 Inspection Readiness Notification ML23219A1542023-08-17017 August 2023 Request to Use Later Edition of ASME Code for Operation and Maintenance and Alternative Requests BFN-IST-01 Through 05 for the Fifth 10-Year Interval Inservice Testing Program ML23228A1642023-08-16016 August 2023 Site Emergency Plan Implementing Procedure Revision ML23228A0202023-08-15015 August 2023 (BFN) Unit 1 - Special Report 259/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation IR 05000259/20230022023-08-10010 August 2023 Integrated Inspection Report 05000259/2023002, 05000260/2023002, 05000296/2023002 and 07200052/2023001 ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills ML23171A8862023-07-24024 July 2023 Issuance of Amend. Nos. 331, 354, and 314; 365 and 359 Regarding Adoption of TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML23201A2182023-07-20020 July 2023 Registration of Use of Cask to Store Spent Fuel (MPC-298 and -299) ML23159A2552023-07-20020 July 2023 Proposed Alternative to the Requirements of the ASME Code Regarding Volumetric Inspection of Standby Liquid Control Nozzles ML23199A3072023-07-18018 July 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions IR 05000259/20233012023-07-18018 July 2023 NRC Operator License Examination Report Nos. 05000259/2023301, 05000260/2023301, and 05000296/2023301 2024-02-01
[Table view] Category:Inspection Plan
MONTHYEARIR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 IR 05000259/20220062023-03-0101 March 2023 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022006, 05000260/2022006 and 05000296/2022006 ML23020A0602023-01-20020 January 2023 Long Term Steam Dryer Inspection Plan IR 05000259/20220052022-08-30030 August 2022 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Report 05000259/2022005, 05000260/2022005 and 05000296/2022005 ML22210A1342022-07-20020 July 2022 Requalification Inspection Notification Letter ML22174A2722022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20224012022-03-0808 March 2022 Information Request for the Cyber-Security Baseline Inspection Notification to Perform Inspection 05000259/2022401; 05000260/2022401; 05000296/2022401 ML22091A1942022-03-0808 March 2022 2022 BFN POV Inspection Information Request IR 05000259/20210062022-03-0202 March 2022 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 (Report No. 05000259/2021006, 05000260/2021006 and 05000296/2021006 ML22025A4132022-01-25025 January 2022 RP Inspection Doc Request ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21343A4232021-12-0909 December 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000259/2022010, 05000260/2022010, and 05000296/2022010) and Request for Information (RFI) IR 05000259/20210052021-08-23023 August 2021 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2, and 3- Report Nos. 05000259/2021005, 05000260/2021005 and 5000296/2021005 IR 05000259/20200062021-03-0303 March 2021 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020006, 05000260/2020006 and 05000296/2020006 ML21047A4732021-02-16016 February 2021 Notification of Browns Ferry Nuclear Power Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2021010, 05000260/2021010, and 05000296/2021010 ML20338A3682020-12-0303 December 2020 Notification of Inspection and Request for Information ML20266G4472020-09-22022 September 2020 Notification of Inspection and Request for Information IR 05000259/20200052020-08-18018 August 2020 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2020005, 05000260/2020005, and 05000296/2020005 ML20191A2232020-07-0909 July 2020 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20190062020-03-0303 March 2020 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1,2,and 3 - NRC Report 05000259/2019006, 05000260/2019006, and 05000296/2019006 ML19108A1682019-04-18018 April 2019 EP Exercise Inspection RFI IR 05000259/20180062019-03-0404 March 2019 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2018006, 05000260/2018006 and 05000328/2018006 ML19030A6712019-01-25025 January 2019 U2 ISI RFI ML19024A4112019-01-24024 January 2019 Transmittal of RP Baseline Inspection Document Request 2019 ML18264A2052018-09-21021 September 2018 U1 ISI Emailed RFI Notification ML18059A1052018-02-28028 February 2018 EOC Assessment Letter ML18029A4672018-01-29029 January 2018 Notification of Browns Ferry Nuclear Plant Design Bases Assurance Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000259/2018010, 05000260/2018010, and 05000296/2018010 ML18029A2552018-01-29029 January 2018 U3 RFI Email Request ML17236A1972017-08-24024 August 2017 Updated Inspection Plan ML17156A1612017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000259/20160062017-03-0101 March 2017 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2, and 3 (Report 05000259/2016006, 05000260/2016006 and 05000296/2016006) IR 05000259/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Reports 05000259/2016005, 05000260/2016005 and 05000296/2016005 ML16243A2242016-08-30030 August 2016 Notification of Inspection and Request for Information ML16120A1182016-04-27027 April 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection - U.S. Nuclear Regulatory Commission Inspection Report Nos. 05000259/2016011, 05000260/2016011 and 05000296/2016011 IR 05000259/20150062016-03-0202 March 2016 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 NRC Inspection Reports 05000259/2015006, 05000260/2015006 and 05000296/2015006 ML16013A0812016-01-12012 January 2016 Browns Ferry Nuclear Plant, Unit 3 - Notification of Inspection and Request for Information ML15348A1802015-12-14014 December 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000259/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for the Browns Ferry Nuclear Plant Units 1, 2 and 3, NRC Inspection Report 005000259/2015005, 005000260/2015005, and 005000296/2015005 IR 05000259/20140012015-03-0404 March 2015 Annual Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 - NRC Inspection Reports 05000259/2014001, 05000260/2014001 and 05000296/2014001 IR 05000259/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Browns Ferry Nuclear Plant Units 1, 2 and 3 (NRC Inspection Reports 05000259/2014006, 05000260/2014006 and 05000296/2014006) ML14063A1092014-03-0404 March 2014 2013 Annual Assessment Letter for Browns Ferry ML14031A4122014-01-31031 January 2014 U3 2014002 ISI RFI Final - Copy ML13353A5852013-12-19019 December 2013 PIR Notification Letter 2014 ML13246A1842013-09-0303 September 2013 Mid Cycle Assessment Letter ML13084A0052013-03-25025 March 2013 Emergency Preparedness Inspection Notification and Request for Information IR 05000259/20120012013-03-0404 March 2013 Annual Assessment Letter for Browns Ferry Nuclear Plant, Units 1, 2 & 3 (IR 05000259-12-001, 05000260-12-001, and 05000296-12-001) ML13037A1662013-02-0101 February 2013 Notification of Inspection and Request for Information IR 05000259/20120062012-09-0404 September 2012 Browns Ferry 2012 Mid Cycle ML12248A2962012-09-0404 September 2012 Mid Cycle ML12066A0602012-03-0505 March 2012 Inspection/Activity Plan, 30/01/2012 - 06/01/2013, RPT 22 2023-08-29
[Table view] |
Text
September 4, 2012
Mr. Joseph Manager, Corp. Nuclear Licensing Programs Tennessee Valley Authority 1101 Market Street, LP 4B-C Chattanooga, TN 37402-2801
SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR BROWNS FERRY NUCLEAR PLANT UNITS 1, 2, and 3 (NRC INSPECTION REPORT 05000259, 260, 296/2012006)
Dear Mr. Shea:
On August 16, 2012, the NRC completed its mid-cycle performance review of Browns Ferry Nuclear Plant, Units 1, 2, and 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011, through June 30, 2012. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility. This assessment reflects the integration of the security cornerstone into the Reactor Oversight Process performance assessment program governed by IMC 0305, "Operating Reactor Assessment Program." The NRC determined the plant performance at Browns Ferry Unit 1 during the most recent quarter was within the Multiple/Repetitive Degraded Cornerstone column (Column 4) of the NRC's Reactor Oversight Process Action Matrix, beginning the fourth quarter 2010, based on the issuance of one finding classified as having a high safety significance (Red). This was detailed in Final Significance Determination of a Red Finding, Notice of Violation, and Assessment Follow-Up Letter (NRC Inspection Report No. 05000259/2011008, (ML111290482)) for Browns Ferry Nuclear Plant, dated May 9, 2011.
Since the last performance assessment, Browns Ferry Unit 1 received one additional action matrix input for Mitigating System Performance Index, High Pressure Injection Systems (HPCI) Performance Indicator, when it changed from Green to White. During this reporting period, 4 HPCI system failures were included. Unavailability also contributed to the performance indicator change due to HPCI steam admission valve leakage. The White performance indicator input does not change the current assessment of performance for Unit 1 because Unit 1 was already assessed to be in the Multiple/Repetitive Degraded Cornerstone column of the Reactor Oversight Process Action Matrix. Consistent with NRC Manual Chapter 0305, the NRC will conduct Part 3 of a supplemental inspection in accordance with Inspection Procedure (IP) 95003, "Supplemental Inspection for Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs, or One Red Input," following written notification from you on your readiness to support this inspection. The Red finding is being held open past 4 quarters pending completion of Part 3, IP 95003. Based on a review of the inspection results, the NRC will provide further clarification regarding any specific actions the Tennesse Valley Authority will need to take following completion of Part 3 of IP 95003. Additionally, the NRC will conduct a supplemental inspection (Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area) when you notify us of your readiness for the NRC to review the actions taken to address the White Mitigating System Performance Index, High Pressure Injection Systems, for Unit 1.
Plant performance for Browns Ferry Units 2 and 3 for the most recent quarter was in the Regulatory Response Column (Column 2) of the NRC's Reactor Oversight Process Action Matrix. As detailed in Final Significance Determination Of A White Finding, Notice Of Violation, And Assessment Follow-Up Letter (NRC Inspection Reports 05000259,260,296/2012013, (ML12226A647)) for Browns Ferry Nuclear Plant, dated Aug 13, 2012, Units 2 and 3 were determined to be in the Regulatory Response Column beginning in the second quarter 2012.
As stated in this assessment, additional regulatory oversight actions will be implemented at your facility. We will conduct a supplemental inspection (Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area) when you notify us of your readiness for the NRC to review the actions taken to address the White Finding. Since the last performance assessment, Browns Ferry Unit 3 received one additional action matrix input for the Unplanned Scrams Performance Indicator, which changed from Green to White in May of 2012. Reactor scrams on September 28, 2011, May 22, May 24, 2012, and May 29, 2012, caused the Performance Indicator to change from Green to White. The White performance indicator input does not change the current assessment of performance for Unit 3 because Unit 3 was already assessed to be in the Regulatory Response column of the NRC's Action Matrix based on an input from a different Reactor Oversight Process cornerstone. The NRC will conduct a supplemental inspection (Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area) when you notify us of your readiness for the NRC to review the actions taken to address the White Unplanned Scrams Performance Indicator for Unit 3.
In its Annual Assessment Letter, dated March 4, 2011, (ML11063042), the NRC opened a Substantive Cross-Cutting Issue (SCCI) in the Corrective Action Program component of the Problem Identification and Resolution cross-cutting area. Specifically, a cross-cutting theme was identified based on four Green inspection findings for the associated 12-month assessment period with documented cross-cutting aspects in the area of Problem Identification and Resolution, in the aspect of "appropriate and timely corrective actions" (P.1(d)). The NRC determined that an SCCI existed because the NRC had a concern with your staff's scope of effort and progress in addressing the cross-cutting theme (NRC Inspection Report No.
05000259,260,296/2010005 ML110400431). Although you identified and implemented a range of actions to address the cross-cutting theme; these actions had not yet proven effective in substantially mitigating the cross-cutting theme, even though a reasonable duration of time has passed. In its Mid-Cycle Assessment Letter, dated August 29, 2011, (ML112411450), the NRC requested that this SCCI be addressed during your third party safety culture assessment which will be reviewed as part of the Independent NRC Safety Culture Assessment per IP 95003,
"Supplemental Inspection for Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs, or One Red Input." This SCCI will continue to remain open pending completion of these assessments and until the NRC has reviewed your other actions to address this SCCI, based on the following: 1) A comprehensive range of actions are identified in your Corrective Action Program that effectively demonstrate you will address the cross-cutting theme; 2) No significant increase in the number of findings with the cross-cutting aspect of "appropriate and timely corrective actions" (P.1(d)) during the previous twelve month assessment period; and 3) The NRC has an increased level of confidence in your ability to deal effectively with operational/equipment issues as related to the cross-cutting theme of
"appropriate and timely corrective actions" (P.1(d)) during the previous six months assessment period. This letter is the fourth consecutive assessment letter documenting an SCCI with the same cross-cutting aspect. In its Annual Assessment Letter, dated March 3, 2010, (ML100620960), the NRC opened a SCCI in the Corrective Action Program component of the Problem Identification and Resolution cross-cutting area. Specifically, a cross-cutting theme was identified based on four Green inspection findings for the associated 12-month assessment period with documented cross-cutting aspects in the area of Problem Identification and Resolution, in the aspect of "thorough evaluation of identified problems" (P.1(c)). The NRC determined that an SCCI existed because the NRC had a concern with your staff's scope of effort and progress in addressing the cross-
cutting theme (NRC Inspection Report No. 05000259,260,296/2010005). Although you identified and implemented a range of actions to address the cross-cutting theme; these actions had not yet proven effective in substantially mitigating the cross-cutting theme, even though a reasonable duration of time has passed. In its Mid-Cycle Assessment Letter, dated August 29, 2011, (ML112411450), the NRC requested that this SCCI be addressed during your third party safety culture assessment which will be reviewed as part of the Independent NRC Safety Culture Assessment per IP 95003, "Supplemental Inspection for Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs, or One Red Input." This SCCI will continue to remain open pending completion of these assessments and until the NRC has reviewed your other actions to address this SCCI, based on the following: 1) An appropriate and comprehensive range of actions identified by the Corrective Action Program, which will effectively address the cross-cutting theme; 2) No significant increase in the number of findings with the cross-cutting aspect of "thorough evaluation of identified problems" (P.1(c)) during the previous twelve month assessment period; and 3) An increased level of confidence in your ability to deal effectively with operational and equipment issues as related to the cross-cutting theme of "thorough evaluation of identified problems" (P.1(c)) during the previous six month assessment period. This letter is the sixth consecutive assessment letter documenting an SCCI with the same cross-cutting aspect.
During this assessment, the NRC identified a cross-cutting theme in the Resources component of the Human Performance & Error Prevention cross-cutting area. Specifically, five Green inspection findings for the current 12-month assessment period, each with a documented cross-
cutting aspect of "Complete Documentation and Component Labeling" (H.2.(c)) were identified.
The NRC determined that a SCCI did not exist because the NRC does not have a concern with your staff's scope of effort and progress in addressing the cross-cutting theme. This is based on TVA's proactive actions, which began in 2010, in addressing concerns associated with this Cross Cutting Aspect (CCA). Three of the five CCA's were assigned in the second quarter of 2012, which were the result of issues with the licensee's procurement and operations procedure processes that would not have been reasonably identified by the previous efforts to address this CCA. Each of the CCAs involved separate Reactor Oversight Process cornerstones. The NRC has concluded that it is reasonable to allow some amount of time for you to incorporate the new issues into your corrective action program. The NRC will evaluate the effectiveness of your corrective actions during the next assessment cycle and will continue to monitor your staff's effort and progress in addressing this theme. The enclosed inspection plan lists the inspections scheduled through December 30, 2013. Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, consistent with the Agency's actions related to Fukushima, the NRC will perform TI-187, "Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns" and TI-188 Inspection of Near-Term Task Force Recommmendation 2.3 Seismic Walkdowns." The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In addition to the baseline inspections at your facility, we also plan on conducting infrequently performed inspections which include: IP 92702, Follow up On Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, And Alternative Dispute Resolution Confirmatory Orders; initial reactor operator licensing examinations; and TI 2515/182, "Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks."
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Eugene Guthrie at 404-997-4662 with any questions you may have regarding this letter or the inspection plan.
Sincerely,/RA/ Victor M. McCree Regional Administrator Docket No.: 50-259, 50-260, 50-296 License No.: DPR-33, DPR-52, DPR-68
Enclosure:
Browns Ferry Inspection/Activity Plan (09/01/2012 - 12/31/2013)
cc w/encl: (See page 5)