| number = ML103480750 | | number = ML103480750 | ||
| issue date = 12/14/2010 | | issue date = 12/14/2010 | ||
| title = | | title = Request for Additional Information Email Sent 10-13-2010, Request for Alternative ANO1-R&R-013, Fourth 10-Year Inservice Inspection Interval, Repairs to the Pressurizer Instrumentation Penetrations | ||
| author name = Kalyanam K | | author name = Kalyanam K | ||
| author affiliation = NRC/NRR/DORL/LPLIV | | author affiliation = NRC/NRR/DORL/LPLIV | ||
| addressee name = Clark R | | addressee name = Clark R | ||
| addressee affiliation = Entergy Operations, Inc | | addressee affiliation = Entergy Operations, Inc | ||
| docket = 05000313 | | docket = 05000313 | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:From: Kalyanam, Kaly Sent: Tuesday, December 14, 2010 11:12 AM To: CLARK, ROBERT W Cc: Lent, Susan; Burkhardt, Janet | {{#Wiki_filter:From: Kalyanam, Kaly Sent: Tuesday, December 14, 2010 11:12 AM To: CLARK, ROBERT W Cc: Lent, Susan; Burkhardt, Janet | ||
==Subject:== | ==Subject:== | ||
RAI - Questions from the CPNB Branch CHief | RAI - Questions from the CPNB Branch CHief | ||
: Bob, I am formalizing the Request for Additional Information sent on October 13, 2010, to Entergys Request for Alternative ANO1-R&R-013, Fourth 10-Year Inservice Inspection Interval, Repairs to the Pressurizer Instrumentation Penetrations. | |||
Bob, | Thanks. | ||
N. Kalyanam PM, Arkansas Nuclear One, Unit 1 and 2 and Waterford 3. | |||
Thanks. N. Kalyanam PM, Arkansas Nuclear One, Unit 1 and 2 and Waterford 3. | |||
The SUNSI information as follows: | The SUNSI information as follows: | ||
Plant: | Plant: Arkansas Nuclear One, Unit 1 Docket No.: 50-313 | ||
==Subject:== | ==Subject:== | ||
RAI on Requests for Alternative ANO1-R&R-013 TAC Nos.: | RAI on Requests for Alternative ANO1-R&R-013 TAC Nos.: ME3701, SUNSI Review Done: Yes. Publicly Available, Normal Release, Non-sensitive, From: N. Kalyanam To: Robert Clark | ||
: 1. On page 8, question no. 10, of the | : 1. On page 8, question no. 10, of the licensees letter of response to the staff RAI dated April 12, 2010, the licensee stated in part, These nine penetrations consist of seven penetrations that are one-inch (nominal pipe size) nozzles that are attached to the pressurizer with a partial penetration weld located at the inside surface of the pressurizer. The other two penetrations consist of a 1.5-inch diameter thermowell that is attached to the pressurizer with a partial penetration weld located at the inside surface of the pressurizer, and a smaller thermowell that was installed through a spare penetration that was originally a one-inch nozzle similar to the other seven discussed above. Please clarify the sentence underlined/bold. Is this the 10th nozzle? | ||
: 2. Flaw evaluation document ANO-34Q-326, pages 4, 5, and .. talk about | Please explain. | ||
: 2. Flaw evaluation document ANO-34Q-326, pages 4, 5, and .. talk about Self Similar Crack Growth assumption and indicates that this assumption is a conservative approach. Please describe underlying nature of Self Similar Growth and state why this assumption is considered conservative approach. | |||
: 3. Was buttering applied/used between the J-groove attachment weld and the pressurizer carbon steel shell at the nozzle location?}} | : 3. Was buttering applied/used between the J-groove attachment weld and the pressurizer carbon steel shell at the nozzle location?}} |
Latest revision as of 05:28, 13 November 2019
ML103480750 | |
Person / Time | |
---|---|
Site: | Arkansas Nuclear |
Issue date: | 12/14/2010 |
From: | Kalyanam K Plant Licensing Branch IV |
To: | Clark R Entergy Operations |
Kalyanam N, NRR/DORL/LPL4, 415-1480 | |
References | |
TAC ME3701 | |
Download: ML103480750 (1) | |
Text
From: Kalyanam, Kaly Sent: Tuesday, December 14, 2010 11:12 AM To: CLARK, ROBERT W Cc: Lent, Susan; Burkhardt, Janet
Subject:
RAI - Questions from the CPNB Branch CHief
- Bob, I am formalizing the Request for Additional Information sent on October 13, 2010, to Entergys Request for Alternative ANO1-R&R-013, Fourth 10-Year Inservice Inspection Interval, Repairs to the Pressurizer Instrumentation Penetrations.
Thanks.
N. Kalyanam PM, Arkansas Nuclear One, Unit 1 and 2 and Waterford 3.
The SUNSI information as follows:
Plant: Arkansas Nuclear One, Unit 1 Docket No.: 50-313
Subject:
RAI on Requests for Alternative ANO1-R&R-013 TAC Nos.: ME3701, SUNSI Review Done: Yes. Publicly Available, Normal Release, Non-sensitive, From: N. Kalyanam To: Robert Clark
- 1. On page 8, question no. 10, of the licensees letter of response to the staff RAI dated April 12, 2010, the licensee stated in part, These nine penetrations consist of seven penetrations that are one-inch (nominal pipe size) nozzles that are attached to the pressurizer with a partial penetration weld located at the inside surface of the pressurizer. The other two penetrations consist of a 1.5-inch diameter thermowell that is attached to the pressurizer with a partial penetration weld located at the inside surface of the pressurizer, and a smaller thermowell that was installed through a spare penetration that was originally a one-inch nozzle similar to the other seven discussed above. Please clarify the sentence underlined/bold. Is this the 10th nozzle?
Please explain.
- 2. Flaw evaluation document ANO-34Q-326, pages 4, 5, and .. talk about Self Similar Crack Growth assumption and indicates that this assumption is a conservative approach. Please describe underlying nature of Self Similar Growth and state why this assumption is considered conservative approach.