ML17271A431: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX 76011-4511 September 27, 2017 EA-16-168 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 56, Mail Code 104/6 Avila Beach, CA  93424 SUBJECT: DIABLO CANYON POWER PLANT - NRC SUPPLEMENTAL INSPECTION REPORT AND ASSESSMENT FOLLOW-UP LETTER; 05000275/2017008 AND 05000323/2017008  Dear Mr. Halpin: On June 15, 2017, the NRC completed the on-site portion of a supplemental inspection using Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs."  On September 21, 2017, the NRC inspection team discussed the results of this inspection with Mr. J. Welsch and other members of your staff. The results of this inspection are documented in the enclosed report. The NRC performed this inspection to review your station's actions in response to a White finding in the Mitigating Systems cornerstone which was documented in NRC Inspection Reports 05000275/2016010 and 05000323/2016010, dated October 3, 2016, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16277A340), and finalized in a letter to you from Kriss Kennedy, Regional Administrator, dated December 28, 2016 (ADAMS Accession No. ML16363A429).  On May 3, 2017, you informed the NRC that your station was ready for the supplemental inspection. The NRC inspectors did not identify any finding or violation of more than minor significance. The NRC determined that your staff's cause evaluations were not performed to the depth and breadth described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs." Your staff did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding).  In particular, the questioning process concluded prior to the causes identified being beyond your control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs."  Had continued questioning occurred, additional organizational and programmatic causes associated with the failure to provide supervisory oversight and the failure to provide adequate guidance for developing work instructions would   
{{#Wiki_filter:UNITED STATES
E. Halpin 2 likely have been identified.  The additional organizational and programmatic causes would also require the development of corrective actions and effectiveness measures.  Therefore, the adequacy of the extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed. After reviewing your performance in addressing the White finding, the NRC concluded your actions did not meet the objectives of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs."  As a result, in accordance with the guidance in Inspection Manual Chapter (IMC) 0305, "Operating Reactor Assessment Program," the White finding will be held open and will continue to be considered in assessing plant performance until you notify the NRC of your readiness for additional inspection on this issue and the NRC concludes, by inspection, that the objectives of the inspection procedure have been met.  This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding." Sincerely, /RA/ Troy W. Pruett, Director Division of Reactor Projects Docket Nos. 50-275 and 50-323 License Nos. DPR-80 and DPR-82 Enclosure:   Inspection Report 05000275/2017008 and 05000323/2017008 w/ Attachment:  Supplemental Information
NUCLEAR REGULATORY COMMISSION
REGION IV 1600 E. LAMAR BLVD.
ARLINGTON, TX
  76011-4511 September 27, 2017
EA-16-168 Mr. Edward D. Halpin
Senior Vice President
  and Chief Nuclear Officer
Pacific Gas and Electric Company
Diablo Canyon Power Plant
P.O. Box 56, Mail Code 104/6
Avila Beach, CA  93424
SUBJECT: DIABLO CANYON POWER PLANT
- NRC SUPPLEMENTAL
INSPECTION REPORT AND ASSESSMENT FOLLOW
-UP LETTER; 05000275/2017008 AND 05000323/2017008  Dear Mr. Halpin:
On June 15, 2017, the NRC completed the on
-site portion of a supplemental inspection using Inspection Procedure 9500
1, "Supplemental Inspection Response to Action Matrix Column 2 Inputs."  On September 21, 2017, the NRC inspection team discussed the results of this inspection with Mr. J. Welsch
and other members of your staff.
  The results of this inspection are documented in the enclosed report. The NRC performed this inspection to review your station's actions in response to a White finding in the Mitigating Systems
cornerstone which was documented in NRC Inspection Reports 05000275/2016010 and 05000323/2016010, dated October
3, 2016, (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML16277A340), and finalized in a letter to you from Kriss Kennedy, Regional Administrator, dated December
28, 2016 (ADAMS Accession No. ML16363A429)
.  On May 3, 2017, you informed the NR
C that your station was ready for the supplemental inspection.
The NRC inspectors did not identify any finding or violation of more than minor significance.
  The NRC determined that your staff's cause evaluations were not performed to the depth and breadth described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column
2 Inputs."
  Your staff did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding).  In
particular, the questioning process concluded prior to the causes identified being beyond your control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column
2 Inputs."  Had continued questioning occurred, additional organizational and programmatic causes associated with the
failure to provide supervisory oversight and the failure to provide adequate guidance for developing work instructions would   
E. Halpin
2 likely have been identified.  The additional
organizational and programmatic causes would also require the development of corrective actions and effectiveness measures.  Therefore, the adequacy of the extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed.
After reviewing your performance in addressing the White finding, the NRC concluded your actions did not meet the objectives of Inspection Procedure 9500
1, "Supplemental Inspection Response to Action Matrix Column 2 Inputs.
"  As a result, in accordance with the guidance in Inspection Manual Chapter (IMC)
0305, "Operating Reactor Assessment Program," the White finding will be held open and will continue to be considered in assessing plant performance until you notify the NRC of your readiness for additional inspection on this issue and the NRC concludes, by inspection, that the objectives of the inspection procedure have been met
.  This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading
-rm/adams.html
and at the NRC Public Document Room in accordance with 10
CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding.
" Sincerely,
/RA/ Troy W. Pruett, Director
Division of Reactor Projects
Docket Nos. 50
-275 and 50
-323 License Nos. DPR
-80 and DPR
-82 Enclosure:
Inspection Report 05000275/2017008 and  
05000323/2017008 w/ Attachment:  Supplemental Information
 


   SUNSI Review:  ADAMS:  Non-Publicly Available Non-Sensitive By: MSH2/dll  Yes    No  Publicly Available Sensitive OFFICE RIV/PBD RIV/PE BC:DRP/A RIV/DRP NAME CPeabody CJewett MHaire TPruett SIGNATURE NON-CONCUR /RA/ /RA/ /RA/ DATE 08/15/17 08/24/17 08/23/17 9/26/17   
   SUNSI Review:  ADAMS:  Non-Publicly Available
  Non-Sensitive
By: MSH2/dll  Yes    No  Publicly Available
  Sensitive OFFICE RIV/PBD RIV/PE BC:DRP/A RIV/DRP NAME CPeabody CJewett MHaire TPruett SIGNATURE
NON-CONCUR /RA/ /RA/ /RA/ DATE 08/15/17 08/24/17 08/23/17 9/26/17   


    SUNSI Review:   ADAMS:    Non-Publicly Available  Non-Sensitive   By: MSH2/dll  Yes    No  Publicly Available Sensitive  OFFICE RIV/PBD RIV/PE BC:DRP/A RIV/DRP  NAME CPeabody CJewett MHaire TPruett  SIGNATURE NON-CONCUR /RA/ /RA/ /RA/  DATE 09/26/17 09/25/17 09/22/17 09/26/17     
 
   Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION IV Docket: 05000275; 05000323 License: DPR-80; DPR-82 Report: 05000275/2017008; 05000323/2017008 Licensee: Pacific Gas and Electric Company Facility: Diablo Canyon Power Plant, Units 1 and 2 Location: 7 1/2 miles NW of Avila Beach Avila Beach, CA Dates: June 12 through September 21, 2017 Inspectors: C. Peabody, Senior Resident Inspector C. Jewett, Project Engineer Approved By: Troy W. Pruett Director, Division of Reactor Projects  
  SUNSI Review:
   2  SUMMARY IR 05000275/2017008, 05000323/2017008; 06/07/2017 - 09/21/2017; Diablo Canyon Power Plant; Supplemental Inspection - Inspection Procedure 95001 This supplemental inspection was conducted by a senior resident inspector from the Palo Verde Generating Station and a project engineer from NRC's Region IV office.  The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process." No findings were identified. Cornerstone:  Mitigating Systems  The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs." The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding).  In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs."  Had continued questioning occurred, additional organizational and programmatic causes associated with the failure to provide supervisory oversight and the failure to provide adequate guidance for developing work instructions would likely have been identified.  The additional organizational and programmatic causes would also require the development of corrective actions and effectiveness measures.  Therefore, the adequacy of the extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed. After reviewing the licensee's performance in addressing the White finding, the NRC concluded the licensee's actions did not meet the objectives of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs."  As a result, in accordance with the guidance in Inspection Manual Chapter (IMC) 0305, "Operating Reactor Assessment Program," the White finding will be held open and will continue to be considered in assessing plant performance until the licensee notifies the NRC of its readiness for additional inspection on this issue and the NRC concludes, by inspection, that the objectives of the inspection procedure have been met.      
ADAMS:    Non-Publicly Available  Non-Sensitive
   3  REPORT DETAILS 4. OTHER ACTIVITIES Cornerstones:  Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Security 4OA4 Supplemental Inspection (95001) .01 Inspection Scope This inspection was conducted in accordance with Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs," to assess the licensee's evaluation of a White finding, which affected the Mitigating Systems Cornerstone in the Reactor Safety Strategic Performance Area.  The inspection objectives included the following:  Assure that the root causes and contributing causes of the significant performance issues are understood. Independently assess and assure that the extent of condition and extent of cause of significant performance issues are identified. Assure that corrective actions taken to address and preclude repetition of significant performance issues are prompt and effective. Assure that corrective plans direct prompt actions to effectively address and preclude  
  By: MSH2/dll  Yes    No  Publicly Available
repetition of significant performance issues. The licensee remained in the Regulatory Response Column (Column 2) of the NRC's Action Matrix in the second quarter of 2017 as a result of one inspection finding of low to moderate safety significance (White).  The finding was associated with the failure to establish adequate work instructions for installation of NamcoŽ Snap Lock limit switches.  Specifically, the licensee failed to provide site-specific instructions for limiting the travel of these external limit switches when installed on safety-related motor operated valves (MOVs).  Consequently, the lever switch actuator for valve RHR-2-8700B, residual heat removal pump 2-2 suction from the refueling water storage tank, was operated repeatedly in an over-travel condition resulting in a sheared internal roll pin that ultimately caused the limit switch to fail.  The NRC staff characterized this issue as having low to moderate safety significance (White), as documented in NRC  
  Sensitive  
Inspection Report 05000275; 05000323/2016010, dated October 3, 2016, (ADAMS Accession No. ML16277A340), and updated in a letter to E. Halpin from K. Kennedy, dated December 28, 2016, (ADAMS Accession No. ML16363A429). On May 3, 2017, the licensee informed the NRC that they were ready for the supplemental inspection.   In preparation for the inspection, the licensee performed root cause evaluation (RCE) 50886801 to address the performance deficiency associated with the White finding.  The licensee provided revision 1A of the report, completed in April 2017, to the inspectors for review.  This evaluation determined two root causes for the White finding.  The first root cause identified that Electrical Maintenance leadership was not ensuring that workers perform procedures as written.  The second root cause identified that guidance for   
   OFFICE RIV/PBD RIV/PE BC:DRP/A RIV/DRP  NAME CPeabody CJewett MHaire TPruett  SIGNATURE
   4  determining Maintenance Verification Testing work instructions in the electrical maintenance procedures writing process was not sufficient. In addition, the licensee performed RCE 50870357 to address why a probabilistic risk assessment (PRA)-significant component failure was not recognized in a timely manner.  The licensee provided revision 2 of RCE 50870357, completed in October 2016, to the inspectors for review.  There were two root causes and one contributing cause identified  
NON-CONCUR /RA/ /RA/ /RA/  DATE 09/26/17 09/25/17 09/22/17 09/26/17     
for RCE 50870357.  The first root cause involved a non-industry standard design feature of the emergency core cooling system (ECCS) interlocks which resulted in a failure mechanism that was not immediately recognizable.  Specifically, Diablo Canyon utilizes external limit switches to provide feedback to the ECCS pump suction interlocks, whereas it is more common for nuclear power plants to use the limit switches internal to the valve's motor operator.  Having a separate external limit switch provides additional  
   Enclosure
separation and redundancy in the design, but warrants additional testing and verification beyond the normal MOV testing to ensure that the external limit switch is functioning properly.  The second root cause identifieded that the external limit switch was not identified as requiring additional post-maintenance testing to verify proper operation.  A similar contributing cause identified that the external limit switches were not identified as requiring additional monitoring which could eliminate missed opportunities to identify degraded conditions. The inspectors reviewed the licensee's two RCE reports and supporting evaluations.  The inspectors reviewed corrective actions that were taken or planned to address the identified causes.  The inspectors also interviewed licensee personnel to determine whether the root and contributing causes were understood, and whether corrective actions taken or planned were appropriate to address the causes and preclude repetition. .02 Evaluation of the Inspection Requirements 02.01 Problem Identification a. Determine that the evaluation documented who identified the issue and under what conditions the issue was identified. The RHR-2-8700B valve failure event of May 16, 2016, was self-revealing.  The initial licensee corrective actions in response to the event failed to identify the performance deficiencies associated with the inadequate level of guidance provided by the maintenance work instructions that constituted the White finding.  The NRC inspection effort identified the performance deficiency independently of the efforts of the licensee's corrective action program. This 95001 inspection requirement is closed. b. Determine the evaluation documented how long the issue existed and prior opportunities for identification. The limit switch failed sometime after the last successful stroke test of interlocked valves 2-RHR-8982A and 2-RHR-8982B during the Unit 2, fall 2014 refueling outage.  The condition can be reasonably determined to have been introduced at the last maintenance interval during the Unit 2, spring refueling outage of 2013.  The misalignment which caused the limit switch to over-travel was not detected during the   
U.S. NUCLEAR REGULATORY COMMISSION
   5  post-maintenance testing of 2-RHR-8700B.  The misaligned switch repeatedly over-traveled during quarterly stroke testing.  RCE 50886801 determined that the quarterly stroke testing and other maintenance activities performed on 2-RHR-8700B were missed opportunities to visually identify the misaligned external limit switch.  In recognition of the safety significance of the interlocks associated with the external limit switch, involved personnel missed the opportunity to visually inspect the valve and limit switch travel during quarterly stroke testing as a means of validating proper switch alignment.  The inspectors noted the licensee also missed opportunities to confirm interlock circuit continuity during valve testing.  However, since there was not adequate guidance to include additional procedural direction to check this separate external limit switch or the ECCS interlock circuitry, the deficiency was not identified.  The licensee's corrective actions included direction to visually inspect the valve and limit switch travel and circuit continuity during quarterly stroke testing as a means of validating proper switch alignment.  Both RCE 50886801 and RCE 50870357 concluded that the physical positioning of the switch adjacent to the building wall, combined with the lack of indication of switch position for the external limit switch and ECCS interlock, made the degradation and failure of the switch unlikely to be identified during quarterly testing of 2-RHR-8700B without the additional guidance to specifically observe operation.
REGION IV
This 95001 inspection requirement is closed. c. Determine that the evaluation documented significant plant-specific consequence, as applicable, and compliance concerns associated with the issue. The licensee conducted RCE 50886801 to address the White finding and RCE 50870357 to address their failure to timely recognize a PRA-signficant component failure.  RCE 50870357 addressed plant specific consequences by using PRA information to compile a list of components with elevated failure consequences.  These components were flagged in the corrective action program system so that future conditions adverse to quality identified on these components will prompt automated notifications, instructing the initiators to take corrective action in the timeliest manner possible. RCE 50886801 addressed the White finding and restoration of compliance.  RCE 50886801 corrective actions (as outlined in Section 02.03.a below) added procedural guidance to ensure the external limit switches are operating correctly and surveillance monitoring of the ECCS interlock circuitry. This 95001 inspection requirement is closed. 02.02 Root Cause, Extent of Condition, and Extent of Cause Evaluation a. Determine that the problem was evaluated using a systematic methodology to identify the root and contributing causes. The White finding RCE 50886801 used Comparative Timeline©, Event and Causal Factors Analysis, and a Barrier Analysis.  The undetected failure RCE 50870357 used Factor Tree Analysis and ABS Consulting Root Cause MapTM.  These cause evaluation tools provided a systematic methodology that can be used to identify the root and contributing causes of the event.
Docket: 05000275;  
   6  No deficiencies were noted with the licensee's selection of root cause methods.  This 95001 inspection requirement is closed. b. Determine that the root cause evaluation was conducted to a level of detail commensurate with the significance of the problem. The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs." The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding).  In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs."  This 95001 inspection requirement will remain open. c. Determine that the root cause evaluation included a consideration of prior occurrences of the problem and knowledge of prior operating experience. Both RCEs included a thorough review of internal and external operating experience to search for previous occurrences.  No identical failures of ECCS interlocks resulting from external limit switches were identified.  There were two instances from early refueling outages in the fall of 1988 and fall of 1989 that identified maintenance difficulties in setting the external limit switches, but no identical service failures were identified.  There were six industry operating experience events for over-travel failure of NamcoŽ external limit switches in low safety applications such as plant process systems or alarm and indication functions, but none in applications related to safety system interlocks.  As a result of the low safety significance of these operating experience items, the six industry events were characterized as broke/fix conditions rather than formally evaluated under the respective licensees' corrective action program.
05000323 License: DPR-80; DPR-82 Report: 05000275/2017008; 05000323/201700
This 95001 inspection requirement will remain remain open pending completion of a re-assessment of the licensee's root cause to satisfy Section 02.02.b, above.  In particular, the licensee should consider whether there are organizational and programmatic concerns associated with how the licensee dispositions low risk operating experience from other sites that may have risk significance at Diablo Canyon. d. Determine that the root cause evaluation addressed the extent of condition and the extent of cause of the problem. Both RCEs identified the extent of condition as the population of risk significant valves containing NamcoŽ external limit switches which provided input into ECCS or other engineered safety features actuation system (ESFAS) interlocks.  The extent of condition identified 8 ECCS valves on each unit, 16 in total, that met this criteria. Extent of condition and extent of cause cannot be fully evaluated at this time because of the determination that the root cause evaluations were not conducted to sufficient depth and breadth.  Of particular concern is whether or not organizational and programmatic deficiencies involving management oversight of work activities, operating experience, and guidance documents existed and corrective actions that may be warranted.  This 95001 inspection requirement will remain open.
8 Licensee:
   7  e. Determine that the root cause, extent of condition, and extent of cause evaluation appropriately considered the safety culture traits in NUREG-2165, "Safety Culture Common Language," referenced in IMC 0310, "Aspects within Cross-Cutting Areas." Both RCEs contained a safety culture analysis.  The White finding RCE 50886801 identified seven safety culture attributes associated with the White Finding.  The RCE identified H.2 Field Presence and H.8 Procedure Adherences as safety culture attributes associated with the leadership oversight root cause.  RCE 50886801 also identified X.5 Leader Behaviors, X.6 Standards, and X.10 Expectations as supplemental cross cutting aspects associated with the leadership oversight root cause.  In addition, RCE 50886801identified H.1 Resources and H.7 Documentation as safety culture attributes associated with the inadequate work instructions root cause.  The undetected failure RCE 50870357 identified the H.1 and H.7 as safety culture attributes associated with the inadequate test requirements root cause and the inadequate monitoring contributing cause.   No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional safety culture attributes that would require NRC review.  This 95001 inspection requirement will remain remain open. f. Examine the common cause analyses for potential programmatic weaknesses in performance when a licensee has a second white input in the same cornerstone. Not applicable; there was not a second White input in the affected cornerstone. 02.03 Corrective Actions Taken a. Determine that appropriate corrective actions are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary. Immediate corrective actions were taken under Notification 50852345 to walk down and visually inspect all of the accessible affected MOVs in the extent of condition population for physical signs of damage to the external limit switch assemblies. Corrective actions taken in response to the White finding RCE 50886801 included the following actions: (1) Establishment of supervisory observation signoffs for maintenance verification testing on NamcoŽ external limit switches. (2) Revision of the Nuclear Procedure Writer's Manual to include specific guidance for  
Pacific Gas and Electric Company
establishing maintenance verification testing in electrical procedures. (3) Revision of MOV maintenance procedures that set and test external limit switches to provide explicit instructions for switch configuration control, as well as switch travel setting and testing. (4) Development and implementation of a dynamic learning activity for Electrical Maintenance MOV crews.  Revision of the Pre-outage Just in Time Training module offered to MOV technicians to include operating experience on this event.
Facility:
   8  (5) Revision of the MOV Sizing, Switch Setpoint Determination and Test Evaluation procedure to include the NamcoŽ vendor total travel limits and parameters, as well as associated testing criteria. (6) Education of the Diablo Canyon Power Plant's extended leadership team on this event and recent related human performance events in accordance with the Diablo Canyon Power Plant's Human Performance Reinforcement policy. Corrective actions taken in response to the undetected failure RCE 50870357 included the following actions: (1) Development of a routine check to verify interlock circuit continuity for the RHR 8700A/B valves and their associated external limit switches on a quarterly basis in conjunction with the quarterly valve stroke surveillance. (2) Revision of applicable maintenance procedures to specify direction as appropriate: (a) Inclusion of external limit switch operation data. (b) Specific evaluation of external limit switch and geared limit switch settings. (c) Provide instructions for standardized assembly, configuration, and adjustment of external limit switches. (d) Provide inspection of external limit switch configuration against a set of standardized criteria. (e) Perform visual inspections of the external limit switch with each quarterly valve stroke surveillance test. (f) Apply position indication lamacoids on the 16 extent of condition valves.  The actions taken have restored compliance.  The revised maintenance procedure work instructions contain adequate and specific guidance to ensure confidence of operability to the affected extent of condition valve population.  Subsequent visual inspections and electrical testing of the affected ECCS interlocks has confirmed operability. No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional corrective action items that would require NRC review.  This 95001 inspection requirement will remain open. b. Determine that the corrective actions have been prioritized with consideration of significance and regulatory compliance. The licensee's corrective actions have been prioritized with consideration of significance and regulatory compliance.  All corrective actions for the White finding RCE 50886801 are completed. There is one remaining corrective action planned for the undetected failure RCE 50870357.  This action is to implement a design change to remove the external limit switches associated with the ECCS MOV interlocks. Plans to modify the system to remove the external limit switches will take until Spring 2019 to analyze and implement in order to ensure the modification is conducted in accordance with 10 CFR 50.59 and   
Diablo Canyon Power Plant, Units 1 and 2 Location:
   9  50.90.  In the interim, the licensee added test requirements to electrically verify the condition of the ECCS interlock when valves are stroked quarterly for surveillance testing.  During the quarterly stroke tests, the licensee also added visual field inspections of the valve stroke by qualified MOV engineers.  As the actions were implemented at the first reasonable opportunity following the White finding, the inspector concluded that the actions were prioritized. No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional corrective action items that would require NRC review to assess  
7 1/2 miles NW of Avila Beach
prioritization.  This 95001 inspection requirement will remain remain open. c. Determine that corrective actions taken to address and preclude repetition of significant performance issues are prompt and effective. Corrective actions to prevent recurrence (CAPR) of the White finding RCE 50886801 included the following: (1) Establishment of supervisory observation signoffs for maintenance verification testing on NamcoŽ external limit switches. (2) Revision of the Nuclear Procedure Writer's Manual to include specific guidance for establishing maintenance verification testing in electrical procedures. (3) Revision of MOV maintenance procedures that set and test external limit switches to provide explicit instructions for switch figure configuration control and switch travel setting and testing. Corrective actions to prevent recurrence of the undetected failure RCE 50870357 included the following actions: (1) Development of a routine check to verify interlock circuit continuity for the RHR 8700A/B valves and their associated external limit switches on a quarterly basis; which was performed concurrent with the quarterly valve stroke surveillance. (2) Revision of applicable maintenance procedures to specify direction as appropriate: (a) Inclusion of external limit switch operation data. (b) Specific evaluation of external limit switch and geared limit switch settings. (c) Provide instructions for standardized assembly, configuration, and adjustment of external limit switches. The corrective actions taken to address and preclude repetition of significant performance issues were prompt and effective.  All but one CAPR is completed, and that action has a corresponiding interim CAPR to monitor the interlock directly.  The CAPRs implemented have restored regulatory compliance and demonstrated operability for the affected ECCS interlocks. No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional CAPR items that would require NRC review to assess effectiveness.  This 95001 inspection requirement will remain remain open.
Avila Beach, CA
   10  d. Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed, either in corrective actions taken or planned. Corrective actions taken thus far have restored compliance with Technical Specification 5.4.1.a., "Procedures."  The licensee has made applicable and appropriate revisions to the maintenance procedures pertaining to VIO 05000323/2016010-01.  The licensee has taken steps to ensure that there are no additional failures in the extent of condition valve population.  As outlined above, surveillance testing of the affected valves has been enhanced to provide additional means of verification, including visual testing of proper external limit switch operation and electrical circuit verification of the associated ECCS interlock function.
Dates: June 12 through September 21, 2017 Inspectors:
This 95001 inspection requirement is closed. 02.04 Corrective Action Plans a. Determine that appropriate corrective action plans are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary.  Determine that the corrective action plans have been prioritized with consideration of significance and regulatory compliance. All corrective actions for the White finding RCE 50886801 are completed. There is one remaining corrective action planned for the undetected failure RCE 50870357.  This action is to implement a design change to remove the external limit switches associated with the ECCS MOV interlocks.  This design change is expected to be implemented during the respective unit refueling outages in the spring 2018 and the spring 2019. Corrective actions taken thus far have been appropriate.  Corrective actions taken and planned have been prioritized with consideration of safety significance and regulatory compliance.  The interim actions to verify the design basis of the ECCS interlocks and NamcoŽ external limit switches provide a reliable means of maintaining safety and regulatory compliance. This 95001 inspection requirement will remain remain open pending completion of a re-assessment of the licensee's root cause to satisfy Section 02.02.b, above. b. Determine that corrective plans direct prompt actions to effectively address and preclude repetition of significant performance issue. All corrective actions to prevent recurrence under White finding RCE 50886801 are completed. The remaining actions planned for the undetected failure RCE 50870357 to modify the system by removing the external limit switches have corresponding interim actions in place to verify the ECCS interlocks associated with the NamcoŽ external limit switches are functioning properly. This 95001 inspection requirement will remain remain open pending completion of a re-assessment of the licensee's root cause to satisfy Section 02.02.b, above.   
C. Peabody, Senior Resident Inspector
   11  c. Determine that appropriate quantitative or qualitative measures of success have been developed for determining the effectiveness of planned and completed corrective actions. The White finding RCE 50886801 specified the following effectiveness evaluations: (1) Procedure use and adherence - Targeted supervisory observations during outages and online; review of station and department level events for procedure use and adherence as a causal factor; and quick hit self-assessments. (2) Procedure writers guide changes - 100 percent review of maintenance procedure revisions, as well as interviews with maintenance procedure writers to confirm understanding of the writers guide changes. The undetected failure RCE 50870357 specified the following effectiveness evaluations: (1) Design verification testing and return to service following the design change modification to remove the external limit switches from the ECCS interlocks. (2) During outages 1R20 and 2R20, satisfactory verifications of the setting, testing, and adjustment of affected NamcoŽ external limit switches. (3) Satisfactory testing of the interlock circuit continuity testing during the quarterly surveillance testing. The success measures for RCE 50886801 were appropriate and provide qualitative measures of success of the corrective actions taken.  RCE 50870357 effectiveness measures are satisfactory; the second and third criteria provide appropriate effectiveness measures until the modifications associated with the first criteria are implemented. This 95001 inspection requirement will remain remain open pending completion of a re-assessment of the licensee's root cause to satisfy Section 02.02.b, above. d. Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed in corrective actions taken or planned. As discussed in Section 02.03.d (above), the corrective actions have restored compliance with Technical Specification 5.4.1.a., "Procedures." for which the NOV was issued associated with the White finding.  This 95001 inspection requirement is closed. 02.05 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues. Not applicable; the performance deficiency associated with the White finding does not warrant treatment as an old design issue. This 95001 inspection requirement is closed.     
C. Jewett
   12  03.00 Inspection Results Summary  The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs." The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding).  In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs."  Had continued questioning occurred, additional organizational and  
, Project Engineer
  Approved By: Troy W. Pruett
Director, Division of Reactor Projects
   
   2  SUMMARY IR 05000275/2017008, 05000323/201700
8; 06/07/2017 - 09/21/2017; Diablo Canyon Power Plant; Supplemental Inspection  
- Inspection Procedure 95001
This supplemental inspection was conducted by a senior
resident inspector from the Palo Verde Generating Station and a project engineer from NRC's Region IV office.  The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG
-1649, "Reactor Oversight Process."
No findings were identified.
  Cornerstone:  Mitigating
Systems  The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column
2 Inputs."
  The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding).  In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column
2 Inputs."  Had continued questioning occurred, additional organizational and programmatic causes associated with the failure to provide supervisory oversight and the failure to provide adequate guidance for developing work instructions would likely have been identified.  The additional organizational and programmatic causes would also require the development of corrective actions and effectiveness measures.  Therefore, the adequacy of the extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed.
After reviewing the licensee's performance in addressing the White finding, the NRC concluded the licensee's actions did not meet the objectives of Inspection Procedure 9500
1, "Supplemental Inspection Response to Action Matrix Column 2 Inputs.
"  As a result, i
n accordance with the guidance in Inspection
Manual Chapter (IMC)
0305, "Operating Reactor Assessment Program," the White finding will be held open and will continue to be considered in assessing plant performance until the licensee notifies the NRC of its readiness for additional inspection on this
issue and the NRC concludes, by inspection, that the objectives of the inspection procedure have been met.
       
   3  REPORT DETAILS
4. OTHER ACTIVITIES
Cornerstones:  Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Security 4OA4 Supplemental Inspection (95001)
.01 Inspection Scope
  This inspection was conducted in accordance with Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs," to assess the licensee's evaluation of a White finding, which affected the Mitigating Systems Cornerstone in the Reactor Safety Strategic Performance Area.  The inspection objectives included the following
:  Assure that the root causes and contributing causes of the significant performance issues are understood.
  Independently assess and assure that the extent of condition and extent of cause of significant performance issues are identified.
  Assure that corrective actions taken to address and preclude
repetition of significant performance issues are prompt and effective.
  Assure that corrective plans direct prompt actions to effectively address and preclude  
repetition of significant performance issues.
The licensee remained in the Regulatory Response Column (Column
2) of the NRC
's Action Matrix in the second quarter of 2017 as a result of one inspection finding of low to moderate safety significance (White).  The finding was associated with
the failure to establish adequate work instructions for installation of Namco
Ž Snap Lock limit switches.  Specifically, the licensee failed to provide site
-specific instructions for limiting the travel of these external limit switches when installed on safety-related motor operated valves (MOVs).  Consequently, the lev
er switch actuator for valve  
RHR-2-8700B, residual heat removal pump 2
-2 suction from the refueling water storage tank, was operated repeatedly in an over
-travel condition resulting in a sheared internal roll pin that ultimately caused the limit switch to fail.  The NRC staff characterized this issue as having low to moderate safety significance (White), as documented in NRC  
Inspection Report 05000275; 05000323/2016010, dated October
3, 2016, (ADAMS Accession No. ML16277A340), and updated in a letter to E.
Halpin from K.
Kennedy, dated December
28, 2016, (ADAMS Accession No. ML16363A429).
  On May 3, 2017, the licensee informed the NRC that they were ready for the supplemental inspection.
In preparation for the inspection, the licensee performed root cause evaluation (
RCE) 50886801 to address the performance deficiency associated with the White finding
.  The licensee provided revision 1A of the report
, completed in April 2017
, to the inspectors for review.  This evaluation determined two root causes
for the White finding.  The first root cause identified that Electrical Maintenance
leadership was not ensuring that workers perform procedures as written.  The second root cause identified that guidance for   
   4  determining Maintenance Verification Testing work instructions in the electrical maintenance procedures writing process  
was not sufficient.
In addition, the licensee performed RCE 50870357
to address why a probabilistic risk assessment (PRA)
-significant component failure was not recognized in a timely manner
.  The licensee provided revision 2 of RCE 50870357
, completed in October
2016, to the inspectors for review.  There were two root causes and one contributing cause identified
for RCE 50870357.  The first root cause involved a non
-industry standard design feature of the emergency core cooling system (ECCS)
interlocks which resulted in a failure mechanism that  
was not immediately recognizable.  Specifically, Diablo Canyon utilizes external limit switches to provide feedback to the ECCS pump suction interlocks, whereas it is more common for nuclear power plants to use the limit switches internal to the valve's motor operator.  Having a separate external limit switch provides additional  
separation and redundancy in the design, but warrants additional testing and verification
beyond the normal MOV testing to ensure that the external limit switch is functioning properly.  The second root cause identifieded
that the external limit switch was not identified as requiring additional post
-maintenance testing to verify proper operation.  A similar contributing cause identified
that the external limit switches were not identified as requiring additional monitoring which could eliminate missed opportunities to identify degraded conditions.
The inspectors reviewed the licensee's two RCE reports and supporting
evaluations.  The inspectors reviewed corrective actions that were taken or planned to address the identified causes.  The inspectors also interviewed licensee personnel to determine whether the root and contributing causes were understood, and whether corrective actions taken or planned were appropriate to address the causes and preclude repetition.
.02 Evaluation of the Inspection Requirements
02.01 Problem Identification
a. Determine that the evaluation documented who identified the issue and under what conditions the issue was identified
. The RHR-2-8700B valve failure event of May
16, 2016, was self-revealing.  The initial licensee corrective actions in response to the event failed to identify the performance deficiencies associated with the inadequate
level of guidance provided by the maintenance work instructions that constituted the White  
finding.  The NRC inspection effort identified the performance deficiency independent
ly of the efforts of the licensee's corrective action program.
This 95001 inspection requirement  
is closed. b. Determine the evaluation documented how long the issue existed and prior opportunities for identification
. The limit switch failed sometime after the last successful stroke test of interlocked valve
s 2-RHR-8982A and 2
-RHR-8982B during the Unit
2, fall 2014 refueling outage
.  The condition can be reasonably
determined to have been introduced at the last maintenance interval during
the Unit 2, spring refueling outage of 2013.   
The misalignment which caused the limit switch to over
-travel was not detected during the   
   5  post-maintenance testing
of 2-RHR-8700B.  The misaligned switch
repeatedly over-traveled during quarterly stroke testing.  
  RCE 50886801
determined that the quarterly stroke testing and other maintenance activities performed on  
2-RHR-8700B were missed opportunities
to visually identify the misaligned external limit switch
.  In recognition of the safety significance of the interlocks associated with the external limit switch, involved personnel missed the opportunity to visually inspect the valve and limit switch travel during quarterly stroke testing as a means of validating proper switch alignment
.  The inspectors noted the licensee also missed opportunities to confirm interlock circuit continuity during valve testing.  However, since there was not adequate guidance to include additional procedural direction to check this separate external limit switch or the ECCS interlock circuitry, the deficiency was not identified
.  The licensee's corrective
actions included direction to visually inspect the valve and limit switch travel and circuit continuity during quarterly stroke testing  
as a means of validating proper switch alignment
.  Both RCE 50886801 and RCE 50870357 concluded that the physical positioning of the switch
adjacent to the building wall
, combined with the lack of indication
of switch position for the external limit switch and ECCS interlock
, made the degradation and failure of the switch unlikely to be identified
during quarterly testing of 2-RHR-8700B without the additional guidance to specifically observe operation.
 
This 95001 inspection requirement  
is closed. c. Determine that the evaluation documented significant plant
-specific consequence, as applicable, and compliance concerns associated with the issue
. The licensee conducted RCE 50886801 to address
the White finding
and RCE 50870357 to address their failure to timely recognize a PRA
-signficant component failure.  RCE 50870357 addressed plant specific consequences
by using PRA information to compile a list of components with elevated failure consequences.  These components were
flagged in the corrective action program system
so that future conditions adverse to quality identified on these components
will prompt automated notification
s, instructing the initiators
to take corrective action in the timeliest manner possible.
RCE 50886801 addressed the White finding and  
restoration of compliance.  RCE 50886801 corrective
actions (as outlined in Section 02.03.a below)  
added procedural guidance to ensure the external limit switches are operating correctly
and surveillance monitoring of the ECCS interlock circuitry.
This 95001 inspection requirement  
is closed. 02.02 Root Cause, Extent of Condition, and Extent of Cause Evaluation
a. Determine that the
problem was evaluated using a systematic methodology to identify the root and contributing causes
. The White finding  
RCE 50886801 used Comparative Timeline
©, Event and Causal Factors Analysis, and a Barrier Analysis.  The undetected failure  
RCE 50870357  
used Factor Tree Analysis and ABS Consulting Root Cause Map
TM.  These cause evaluation tools provided a systematic methodology that can be used to identify the root and contributing causes of the event.
 
   6  No deficiencies were noted
with the licensee's selection of root cause methods
.  This 95001 inspection requirement is closed
. b. Determine that the root cause evaluation was conducted to a level of detail commensurate with the significance of the problem
. The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth
described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column
2 Inputs."
  The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding).  In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column
2 Inputs."  This 95001 inspection requirement will remain open.
c. Determine that the root cause evaluation included a consideration of prior occurrences of the problem and knowledge of prior operating experience
. Both RCEs included a thorough review of internal and external operating experience to search for previous occurrences.  No identical failures
of ECCS interlocks
resulting from external limit switches were identified
.  There were two instances from early refueling outages in the fall of 1988 and  
fall of 1989 that identified maintenance difficulties in setting the external limit switches, but no identical service failures were identified
.  There were six industry operating experience events for over-travel failure of
NamcoŽ external limit switches
in low safety applications such as plant process systems or alarm and indication functions, but none in applications related to safety system interlocks.  As a result of the low safety significance
of these operating experience items, the six industry events were characterized as broke/fix conditions
rather than formally evaluated under the respective licensees' corrective action program.
 
This 95001 inspection requirement will remain remain open
pending completion of a re
-assessment of the
licensee's root cause to satisfy Section 02.02.b, above.  In particular, the licensee should consider whether there are organizational and programmatic concerns associated with how the licensee dispositions low risk operating experience from other sites that may have risk significance at Diablo Canyon
. d. Determine that the root cause evaluation addressed the extent of condition and the extent of cause of the problem
. Both RCEs identified the extent of condition
as the population of risk significant valves  
containing Namco
Ž external limit switches which provided input into ECCS or other engineered safety features actuation system
(ESFAS) interlocks.  The extent of condition identified 8 ECCS valves on each unit, 16 in total, that met this criteria.
Extent of condition and extent of cause cannot be fully evaluated at this time because of the determination that the root cause evaluations were not conducted to sufficient depth and breadth
.  Of particular concern is whether or not organizational and programmatic  
deficiencies involving management oversight of work activities, operating experience, and guidance documents existed and corrective actions that may be warranted.  This 95001 inspection requirement will remain open.
 
   7  e. Determine that the root cause, extent of condition, and extent of cause evaluation appropriately considered the safety culture traits in NUREG
-2165, "Safety Culture Common Language,
" referenced in IMC 0310, "Aspects within Cross
-Cutting Areas."
Both RCEs contained a  
safety culture analysis.  The White finding RCE
50886801 identified seven safety culture attributes associated with the White Finding.  The RCE identified H.2 Field Presence and H.8 Procedure Adherences
as safety culture attributes associated with the leadership oversight
root cause
.  RCE 50886801 also identified X.5 Leader Behaviors, X.6 Standards, and X.10 Expectations
as supplemental cross cutting aspects associated with the leadership oversight root cause
.  In addition,  
RCE 50886801identified H.1 Resources and H.7 Documentation
as safety culture attributes associated with the inadequate work instructions root cause.  The undetected  
failure RCE
50870357 identified
the H.1 and H.7 as safety culture attributes associated with the inadequate  
test requirements root cause and the inadequat
e monitoring contributing cause.
No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional safety culture attributes that would require NRC review.  This 95001 inspection requirement will remain remain open
. f. Examine the common cause analyses for potential programmatic weaknesses in performance when a licensee has a second  
white input in the same cornerstone
. Not applicable
; there was not a second White input in
the affected cornerstone.
02.03 Corrective Actions Taken
a. Determine that appropriate corrective actions are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary
. Immediate corrective actions were taken under Notification 50852345 to walk down and visually inspect all
of the accessible affected MOVs in the extent of condition population for physical signs of damage to the external limit switch assemblies.
Corrective actions taken in response to the White finding RCE 50886801 included
the following
actions: (1) Establishment
of supervisory observation signoffs for maintenance verification testing on NamcoŽ external limit switches.
(2) Revision of the Nuclear Procedure Writer's Manual to include specific guidance for  
establishing maintenance verification testing in electrical procedures.
(3) Revision of MOV maintenance procedures that set and test external limit switches to provide explicit instructions for switch configuration control, as well as
switch travel setting and testing.
(4) Development and implementation of a dynamic learning activity for Electrical Maintenance MOV crews.  Revision of the Pre
-outage Just in Time Training module offered to MOV technicians to include operating experience on this event.
 
   8  (5) Revision of the MOV Sizing, Switch Setpoint Determination and Test Evaluation procedure to include the NamcoŽ vendor total travel limits and parameters
, as well as associated testing criteria.
(6) Education of the Diablo Canyon Power Plant's extended leadership team on this event and recent related human performance events in accordance with the Diablo Canyon Power Plant's Human Performance Reinforcement policy.
Corrective actions taken in response to the undetected failure RCE 50870357 included
the following
actions: (1) Development of a routine check to verify interlock circuit continuity for the  
RHR 8700A/B valves and their associated external limit switches on a quarterly basis
in conjunction with
the quarterly valve stroke surveillance.
(2) Revision of applicable maintenance procedures to specify direction as appropriate:
(a) Inclusion of external limit switch operation data
. (b) Specific evaluation of external limit switch and geared limit switch settings
. (c) Provide instructions for standardized assembly, configuration, and adjustment of external limit switches.
(d) Provide inspection of external limit switch configuration against a set of standardized criteria.
(e) Perform visual inspections of the external limit switch with each quarterly valve stroke surveillance test.
(f) Apply position indication lamacoids on the 16 extent of condition valves.  
  The actions taken have restored compliance.   
The revised maintenance procedure work instructions contain adequate
and specific guidance to ensure confidence of
operability to the affected extent of condition valve population.  Subsequent visual inspections
and electrical testing of the affected ECCS interlocks has confirmed operability
. No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional corrective action items that would require NRC review.  This 95001 inspection
requirement will remain  
open. b. Determine that the corrective actions have been prioritized with consideration of significance and regulatory compliance
. The licensee
's corrective actions have been prioritized with consideration of significance and regulatory compliance.  All corrective actions for the White finding RCE 50886801 are completed.
There is one remaining corrective action planned for the undetected failure  
RCE 50870357.  This action is to implement a design change to remove the external limit switches associated with the ECCS MOV interlocks.
  Plans to modify the system to remove the external limit switches will take until Spring 2019
to analyze and implement
in order to ensure the modification is conducted in accordance with 10 CFR 50.59 and   
   9  50.90.  In the interim, the licensee added test requirements to electrically verify the condition of the
ECCS interlock when valves are stroked quarterly for surveillance testing.  During the
quarterly stroke tests, the licensee also added visual field inspections of the valve stroke by qualified
MOV engineers.  As the actions were implemented at the first reasonable opportunity following
the White  
finding, the inspector concluded that the actions were
prioritized.
No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional corrective action items that would require NRC review to assess  
prioritization.  This 95001 inspection requirement will remain remain open.
c. Determine that corrective actions taken to address and preclude repetition of significant performance issues are prompt and effective
. Corrective actions to prevent recurrence (CAPR) of the White finding RCE 50886801 included the following
: (1) Establishment
of supervisory observation signoffs for maintenance verification testing on NamcoŽ external limit switches.
(2) Revision of the Nuclear Procedure Writer's Manual to include specific guidance for establishing maintenance verification testing in electrical procedures.
(3) Revision of MOV maintenance procedures that set and test external limit switches to provide explicit instructions for switch figure configuratio
n control and switch travel setting and testing.
Corrective actions to prevent recurrence of
the undetected failure RCE 50870357 included the following
actions: (1) Development of a routine check to verify interlock circuit continuity for the  
RHR 8700A/B valves and their associated external limit switches on a quarterly basis; which was performed concurrent with the quarterly
valve stroke surveillance.
(2) Revision of applicable maintenance procedures t
o specify direction as appropriate:
(a) Inclusion of external limit switch operation data
. (b) Specific evaluation of external limit switch and geared limit switch settings
. (c) Provide instructions for standardized assembly, configuration, and adjustment of external limit switches.
The corrective actions taken to address and preclude repetition of significant performance issues were prompt and effective.  All but one CAPR is completed, and that
action has a corresponiding
interim CAPR to monitor the interlock directly.  The CAPRs implemented  
have restored regulatory compliance and demonstrated
operability for the affected ECCS interlocks.
  No deficiencies were noted in this area, however further
revisions of the RCEs could introduce additional CAPR items that would require NRC review to assess effectiveness.  This 95001 inspection requirement will remain remain open.
 
   10  d. Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed, either in corrective actions taken or planned
. Corrective actions taken thus far have restored compliance with Technical Specification
5.4.1.a., "Procedures
."  The licensee has made applicable and appropriate revisions to the maintenance procedures pertaining to VIO 05000323/2016010
-01.  The licensee has taken steps to ensure that there are no additional failures in the extent of condition valve population
.  As outlined above, surveillance testing of the affected valves has been enhanced to provide additional means of verification
, including
visual testing of proper external limit switch operation and electrical circuit verification  
of the associated ECCS interlock function.
 
This 95001 inspection requirement  
is closed. 02.04 Corrective Action Plans
a. Determine that appropriate corrective action plans are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary.  Determine that the corrective action plans have been prioritized with consideration of significance and regulatory compliance
. All corrective actions for the White finding RCE 50886801
are completed.
There is one remaining
corrective action planned for the undetected failure  
RCE 50870357.  This action is to implement a design change to remove the external limit switches associated with the ECCS MOV interlocks.  This design change is expected to be implemented during the respective
unit refueling outages in the spring 2018 and the spring
2019. Corrective actions taken thus far have been
appropriate.  Corrective
actions taken and planned have been prioritized with consideration of safety significance and regulatory compliance.   
The interim actions to verify the design basis of the ECCS interlocks and NamcoŽ external limit switches provide a reliable means of maintaining safety and regulatory compliance.
This 95001 inspection requirement will remain remain open
pending completion of a re
-assessment of the licensee's root cause to satisfy Section 02.02.b, above
. b. Determine that corrective plans direct prompt actions to effectively address and preclude repetition of significant performance issue
. All corrective actions to prevent recurrence under White finding RCE 50886801 are completed.
  The remaining
actions planned for the undetected failure RCE 50870357 to modify the system by removing the external limit switches have corresponding
interim actions in place to verify the ECCS interlocks associated with the
NamcoŽ external limit switches are functioning properly
. This 95001 inspection requirement will remain remain open
pending completion of a re
-assessment of the licensee's root cause to satisfy Section 02.02.b, above
.   
   11  c. Determine that appropriate quantitative or qualitative measures of success have been
developed for determining the effectiveness of planned and completed corrective actions. The White finding RCE 50886801 specified the following effectiveness evaluations:
(1) Procedure use and adherence  
- Targeted supervisory observations during outages  
and online; review of station and department level events for procedure use and adherence as a causal factor; and quick hit self-assessments
. (2) Procedure writers guide changes  
- 100 percent review of maintenance procedure revisions
, as well as interviews with
maintenance procedure writers to confirm understanding of the writers guide changes. The undetected failure RCE 50870357 specified the following effectiveness evaluations:
(1) Design verification testing and return to service following the design change modification to remove the external limit switches from the ECCS interlocks.
(2) During outages 1R20 and 2R20
, satisfactory
verifications of the setting, testing, and adjustment
of affected Namco
Ž external limit switches
. (3) Satisfactory testing of the interlock circuit continuity testing during the quarterly surveillance testing.
The success measures for RCE 50886801
were appropriate and provide
qualitative measures of success
of the corrective actions taken.  RCE 50870357
effectiveness measures are satisfactory; the second and third criteria provide appropriate effectiveness measures until the modifications associated with the first criteria are implemented
. This 95001 inspection requirement will remain remain open
pending completion of a re
-assessment of the licensee's root cause to satisfy Section 02.02.b, above
. d. Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed in corrective actions taken or planned
. As discussed in Section 02.03.d (above), the corrective actions have restored compliance with Technical Specification
5.4.1.a., "Procedures
." for which the NOV was issued associated with the White finding.  
  This 95001 inspection requirement  
is closed. 02.05 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues. Not applicable
; the performance deficiency associated with the White finding does not warrant treatment as an old design issue
. This 95001 inspection requirement  
is closed.     
   12  03.00 Inspection Results
Summary  The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth
described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column
2 Inputs."
  The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding).  In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column
2 Inputs."  Had continued questioning occurred, additional organizational and  
programmatic causes associated with the failure to provide supervisory oversight and  
programmatic causes associated with the failure to provide supervisory oversight and  
the failure to provide adequate guidance for developing work instructions would likely have been identified.  The additional organizational and programmatic causes would also require the development of corrective actions and effectiveness measures.  Therefore, the adequacy of the  extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed. The status of the inspection requirements of Inspection Procedure 95001 have been categorized below.  Requirements held open in entirety by this inspection will require a full re-evaluation by NRC inspectors at a later date.  Requirements held open for changes only are those for which no deficiencies were noted during this inspection but may be impacted, and therefore require additional review, as a result of revisions to the licensee's RCEs.  In this instance, only the changes added by future revisions of the RCEs will have to be evaluated by NRC inspectors at a later date.  Requirements closed by this inspection effort will require no additional inspection effort. 03.01 Inspection Requirements Held Open in Entirety 02.02b Determine that the root cause evaluation was conducted to a level of detail commensurate with the significance of the problem 02.02d Determine that the root cause evaluation addressed the extent of condition and the extent of cause of the problem 03.02 Inspection Requirements Held Open for Changes Only 02.02c Determine that the root cause evaluation included a consideration of prior occurrences of the problem and knowledge of prior operating experience 02.02e Determine that the root cause, extent of condition, and extent of cause evaluation appropriately considered the safety culture traits in NUREG-2165, "Safety Culture Common Language," referenced in IMC 0310, "Aspects within Cross-Cutting Areas" 02.03a Determine that appropriate corrective actions are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary 02.03b Determine that the corrective actions have been prioritized with consideration of significance and regulatory compliance
the failure to provide adequate guidance for developing work instructions would likely have been identified.  The additional organizational and programmatic causes would also require the development of corrective actions and effectiveness measures.  Therefore, the adequacy of the  extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed.
   13  02.03c Determine that corrective actions taken to address and preclude repetition of significant performance issues are prompt and effective 02.04a Determine that appropriate corrective action plans are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary.  Determine that the corrective action plans have been prioritized with consideration of significance and  
The status of the
regulatory compliance 02.04b Determine that corrective plans direct prompt actions to effectively address and preclude repetition of significant performance issue 02.04c Determine that appropriate quantitative or qualitative measures of success have been developed for determining the effectiveness of planned and completed corrective actions 03.03 Inspection Requirements Closed 02.01a Determine that the evaluation documented who identified the issue and under what conditions the issue was identified 02.01b Determine the evaluation documented how long the issue existed and prior opportunities for identification 02.01c Determine that the evaluation documented significant plant-specific consequence, as applicable, and compliance concerns associated with the  
inspection requirements of  
issue 02.02a Determine that the problem was evaluated using a systematic methodology to identify the root and contributing causes 02.02f Examine the common cause analyses for potential programmatic weaknesses in performance when a licensee has a second white input in the same cornerstone 02.03d Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed, either in corrective actions taken or planned 02.04d Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed in corrective actions taken or planned 02.05 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues    
Inspection  
   14  4OA6 Meetings, Including Exit Exit Meeting Summary On September 21, 2017, the inspectors presented the inspection results to Mr. J. Welsch, Site Vice President, and other members of the licensee staff.  The licensee acknowledged the issues presented.  The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.  
Procedure 95001 have been categorized below.  Requirement
   Attachment SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT  Licensee Personnel    T. Baldwin, Director, Nuclear Site Services J. Cheek, MOV Program Engineer D. Evans, Director, Security & Emergency Services M. Fraunheim, Manager Nuclear Performance Improvement P. Gerfen, Senior Director Plant Manager M. Ginn, Manager, Emergency Planning E. Halpin, Sr. Vice President, Chief Nuclear Officer Generation H. Hamzehee, Manager, Regulatory Services A. Heffner, NRC Interface, Regulatory Services J. Hinds, Director, Quality Verification L. Hopson, Director Maintenance Services T. Irving, Manager, Radiation Protection K. Johnston, Director of Operations M. McCoy, NRC Interface, Regulatory Services J. Morris, Senior Advising Engineer C. Murry, Director Nuclear Work Management J. Nimick, Senior Director Nuclear Services A. Peck, Director, Nuclear Engineering R. Walthos, Nuclear Engineering Specialist, Principal J. Welsch, Site Vice President NRC Personnel C. Newport, Senior Resident Inspector J. Reynoso, Resident Inspector   LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED  Discussed 05000323/2016010-01 VIO Failure to Establish Adequate Work Instructions for Installation of NamcoŽ Snap Lock Limit Switches (Section 4OA4)   LIST OF DOCUMENTS REVIEWED Section 4OA4:  Supplemental Inspection (95001) Procedures Number Title Revision AD1 Administrative Controls Program 17 AD1.ID1 Nuclear Generation Procedure Writer's Manual 30   
s held open in entirety by this inspection will require a full re-evaluation by NRC inspectors at a later date.   
   A-2 Procedures Number Title Revision AD7.ID12 Work Management Process 6 AD7.ID15 On-Line Maintenance Outrage Window Execution 3 AD7.ID16 Tool Pouch and Minor Maintenance 4 AD7.ID2 Daily Notification Review Team (DRT) & Standard Plant Priority Assignment Scheme 27 AD7.ID4 On-line Maintenance Scheduling 25 AWP E-027 Motor Operated Valve Sizing, Switch Setpoint Determination and Test evaluation 4 MA1.DC58 Troubleshooting Evidence Preservation and Forensic Analysis 1 MP E-53.10A Preventive Maintenance of Limitorque Motor Operators 41 MP E-53.10A1 Low Impact External Inspections of Limitorque Motor Operators 2 MP E-53.10R Augmented Stem Lubrication for Limitorque Operated Valves 9 MP E-53.10S Limitorque Swap-Out and Switch Settings 14 MP-E-53.10V1 MOV Diagnostic Testing 18 OM15.ID8 Human Performance Error Prevention Tools 7 OM7.ID1 Problem Identification and Resolution 49A OM7.ID3 Root Cause Evaluation 45 OM7.ID4 Cause Determinations 36 OM7.ID7 Emerging Issue and Event Investigations 18A OP1.DC18 Authorization of Test Equipment Operation, Maintenance, and Testing 11 OP2.ID1 Clearances 39 PEP V-7B Test of ECCS Valve Interlocks 10 PRA 17-02 Probabilistic Risk Assessment 1 STP V-2B2 Exercising and Position Verification of Valves 9003A and 9003B Unit 2 0 STP V-2B2 Exercising and Position Verification of Valves 9003A and 9003B Unit 1 16 STP V-2D2A Exercising and Position Verification of Valve 8700A Unit 2 0 STP V-2D2A Exercising and Position Verification of Valve 8700A Unit 1 3   
Requirement
   A-3 Procedures Number Title Revision STP V-2D2B Exercising and Position Verification of Valve 8700B Unit 2 0 STP V-2D2B Exercising and Position Verification of Valve 8700B Unit 1 3 STP V-2O6 Exercising and Position Verification of Valves 8982A and 8982B Unit 2 1 STP V-2O6 Exercising and Position Verification of Valves 8982A and 8982B Unit 1 10 STP V-2V1 Exercising and Position Verification of Valves 8804A and 8804B Unit 2 0 STP V-2V1 Exercising and Position Verification of Valves 8804A and 8804B Unit 1 11 TP V-3M5 Exercising Valves RHR-8701 and RHR-8702, Reactor Coolant Loop 4 to RHR Pump Suction 16  Notifications 50852345 50870357 50923338 50923339 50857553 50874911 50886801 50871499 50910294 50908100 50915340 50891772 50906150 50906119 50915775 50893249 50874463 50875300 50866497 50872919 50913951 50891005 50910293 50891005  Miscellaneous Documents Number Title Revision / Date  Cause Determination Manual May 18, 2017 2016 Maintenance Audit November 7, 2016 HUJITDC055 JITT Validating Assumptions April 20, 2017 HUJITDC050 Confined Space DLA February 16, 2017 HUJITIS041 Human Performance Training March 29, 2016 JITTEM1604 JITT Pre-Outage MOV Training April 19, 2017  1R20 Supervisor Stand Down May 1, 2017 R165C11 Task Training: Nuclear Operators 0  Program and Process Codes May 2, 2013  Cause Codes  
s held open for changes only
   A-4 Miscellaneous Documents Number Title Revision / Date  Site Standards Handbook WG-24 NRC Administrative Support 7 WG-7 Reportability Reviews 8 2017-S009-001 Undetected ECCS Interlock Failure April 18, 2017 50870357 Root Cause Evaluation Report Undetected ECCS Interlock Failure 2 50886801 Root Cause Evaluation Report DCPP Inadequate NAMCO Procedure 1A 50913375 95-001 Pre-Inspection Assessment May 3, 2017 130100011 Work Order Preparation January 28, 2013 150360043 Assessment of 1Y19 February 5, 2015 163620001 2017 Fire Protection Audit 1 9000035423 Motor Operated Valve Sizing and Switch Setting Calculations September 30, 2013  Work Orders 60098575 60098576 60098577 60098578 60094730 60094731 60090383 64090172 60100131 64065079  LIST OF ACRONYMS ADAMS Agencywide Document Access and Management System CAPR corrective action to prevent recurrence CFR Code of Federal Regulations ECCS emergency core cooling system ESFAS engineered safety features actuation system MOV motor-operated valve PRA probabilistic risk assessment RCE Root Cause Evaluation RCS reactor coolant system RHR residual heat removal
are those for which
no deficiencies were noted
during this inspection but may be impacted, and therefore require additional review, as a result of revisions to the
licensee's RCEs.  In this instance, only the changes added by future revisions of the RCEs will have to be evaluated by NRC inspectors at a later date.  Requirements
closed by this inspection effort will require no
additional
inspection effort.
03.01 Inspection Requirements Held Open in Entirety
02.02b Determine that the root cause evaluation was conducted to a level of detail commensurate with the significance of the problem
02.02d Determine that the root cause evaluation addressed the extent of condition and the extent of cause of the problem
03.02 Inspection Requirements Held Open for Changes Only
02.02c Determine that the root cause evaluation included a consideration of prio
r occurrences of the problem and knowledge of prior operating experience
02.02e Determine that the root cause, extent of condition, and extent of cause evaluation appropriately considered the safety culture traits in NUREG
-2165, "Safety Culture Common Language," referenced in IMC 0310, "Aspects within Cross
-Cutting Areas
" 02.03a Determine that appropriate corrective actions are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary
02.03b Determine that the corrective actions have been prioritized with consideration of significance and regulatory compliance
 
   13  02.03c Determine that corrective actions taken to address and preclude repetition of significant performance issues are prompt and effective
02.04a Determine that appropriate corrective action plans are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary.  Determine that the corrective action plans have been prioritized with consideration of significance and  
regulatory compliance
02.04b Determine that corrective plans direct prompt actions to effectively address and preclude repetition of significant performance issue
02.04c Determine that appropriate quantitative or qualitative measures of success have been developed for determining the effectiveness of planned and completed corrective actions
03.03 Inspection Requirements Closed
02.01a Determine that the evaluation documented who identified the issue and under what conditions the issue was identified
02.01b Determine the evaluation documented how long the issue existed and prior opportunities for identification
02.01c Determine that the evaluation documented significant plant
-specific consequence, as applicable, and compliance concerns associated with the  
issue 02.02a Determine that the problem was evaluated using a systematic methodology to identify the root and contributing causes
02.02f Examine the common cause analyses for potential programmatic weaknesses in performance when a licensee has a second white input in the same cornerstone
02.03d Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed, either in corrective actions taken or planned 02.04d Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed in corrective actions taken or planned
02.05 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues
   
   14  4OA6 Meetings, Including Exit
Exit Meeting Summary
On September 21, 2017, the inspectors presented the inspection results to Mr. J. Welsch
, Site Vice President,
and other members of the licensee staff.  The licensee acknowledged the issues presented.  The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.
 
   Attachment SUPPLEMENTAL INFORMATION
  KEY POINTS OF CONTACT  
   Licensee Personnel    T. Baldwin, Director, Nuclear Site Services
J. Cheek, MOV Program Engineer D. Evans, Director, Security & Emergency Services
M. Fraunheim, Manager Nuclear Performance Improvement
P. Gerfen, Senior Director Plant Manager
M. Ginn, Manager, Emergency Planning
E. Halpin, Sr. Vice President, Chief Nuclear Officer Generation
H. Hamzehee, Manager, Regulatory Services
A. Heffner, NRC Interface, Regulatory Services
J. Hinds, Director, Quality Verification
L. Hopson, Director Maintenance Services
T. Irving, Manager, Radiation Protection
K. Johnston, Director of Operations
M. McCoy, NRC Interface, Regulatory Services
J. Morris, Senior Advising Engineer
C. Murry, Director Nuclear Work Management
J. Nimick, Senior Director Nuclear Services
A. Peck, Director, Nuclear Engineering
R. Walthos, Nuclear Engineering Specialist, Principal
J. Welsch, Site Vice President
  NRC Personnel
  C. Newport, Senior Resident Inspector
J. Reynoso, R
esident Inspector
    LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED  
  Discussed
05000323/2016010
-01 VIO Failure to Establish Adequate Work Instructions for Installation  
of NamcoŽ Snap Lock Limit Switches (Section 4OA4)
  LIST OF DOCUMENTS REVIEWED
Section 4OA
4:  Supplemental Inspection (95001)
Procedures
Number Title Revision AD1 Administrative Controls Program
17 AD1.ID1 Nuclear Generation Procedure Writer's Manual
30   
   A-2 Procedures
Number Title Revision AD7.ID12 Work Management Process
6 AD7.ID15 On-Line Maintenance Outrage Window Execution
3 AD7.ID16 Tool Pouch and Minor Maintenance
4 AD7.ID2 Daily Notification Review Team (DRT) & Standard Plant Priority Assignment Scheme
27 AD7.ID4 On-line Maintenance Scheduling
25 AWP E-027 Motor Operated Valve Sizing, Switch Setpoint Determination and Test evaluation
4 MA1.DC58 Troubleshooting Evidence Preservation and Forensic Analysis 1 MP E-53.10A Preventive Maintenance of Limitorque Motor Operators
41 MP E-53.10A1 Low Impact External Inspections of Limitorque Motor Operators
2 MP E-53.10R Augmented Stem Lubrication for Limitorque Operated Valves 9 MP E-53.10S Limitorque Swap
-Out and Switch Settings
14 MP-E-53.10V1 MOV Diagnostic Testing
18 OM15.ID8 Human Performance Error Prevention Tools
7 OM7.ID1 Problem Identification and Resolution
49A OM7.ID3 Root Cause Evaluation
45 OM7.ID4 Cause Determinations
36 OM7.ID7 Emerging Issue and Event Investigations
18A OP1.DC18 Authorization of Test Equipment Operation, Maintenance, and Testing
11 OP2.ID1 Clearances
39 PEP V-7B Test of ECCS Valve Interlocks
10 PRA 17-02 Probabilistic
Risk Assessment
1 STP V-2B2 Exercising and Position Verification of Valves  
9003A and 9003B Unit 2 0 STP V-2B2 Exercising and Position Verification of Valves  
9003A and 9003B Unit 1 16 STP V-2D2A Exercising and Position Verification of Valve  
8700A Unit 2 0 STP V-2D2A Exercising and Position Verification of Valve  
8700A Unit 1 3   
   A-3 Procedures
Number Title Revision STP V-2D2B Exercising and Position Verification of Valve 8700B Unit 2 0 STP V-2D2B Exercising and Position Verification of Valve  
8700B Unit 1 3 STP V-2O6 Exercising and Position Verification of Valves  
8982A and 8982B Unit 2 1 STP V-2O6 Exercising and Position Verification of Valves  
8982A and 8982B Unit 1 10 STP V-2V1 Exercising and Position Verification of Valves  
8804A and 8804B Unit 2 0 STP V-2V1 Exercising and Position Verification of Valves  
8804A and 8804B Unit 1 11 TP V-3M5 Exercising Valves RHR
-8701 and RHR
-8702, Reactor Coolant Loop 4 to RHR Pump Suction 16  Notifications
50852345 50870357 50923338 50923339 50857553 50874911 50886801 50871499 50910294 50908100 50915340 50891772 50906150 50906119 50915775 50893249 50874463 50875300 50866497 50872919 50913951 50891005 50910293 50891005  Miscellaneous Documents
Number Title Revision / Date  Cause Determination Manual
May 18, 2017
  2016 Maintenance Audit
November 7, 2016
HUJITDC055
JITT Validating Assumptions
April 20, 2017 HUJITDC050 Confined Space DLA
February  
16, 2017 HUJITIS041 Human Performance Training
March 29, 2016 JITTEM1604 JITT Pre-Outage MOV Training
April 19, 2017  1R20 Supervisor Stand Down
May 1, 2017 R165C11 Task Training: Nuclear Operators
0  Program and Process Codes
May 2, 2013  Cause Codes
 
   A-4 Miscellaneous Documents
Number Title Revision / Date  Site Standards Handbook
  WG-24 NRC Administrative Support
7 WG-7 Reportability Reviews
8 2017-S009-001 Undetected ECCS Interlock Failure
April 18, 2017 50870357 Root Cause Evaluation Report Undetected ECCS Interlock Failure
2 50886801 Root Cause Evaluation Report DCPP Inadequate NAMCO Procedure
1A 50913375 95-001 Pre-Inspection Assessment
May 3, 2017 130100011
Work Order Preparation
January 28, 2013 150360043
Assessment of  
1Y19 February  
5, 2015 163620001
2017 Fire Protection Audit
1 9000035423
Motor Operated Valve Sizing
and Switch Setting Calculations
September  
30, 2013  Work Order
s 60098575 60098576 60098577 60098578 60094730 60094731 60090383 64090172 60100131 64065079  LIST OF ACRONYMS
  ADAMS Agencywide
Document Access and Management System
CAPR corrective action to prevent recurrence
CFR Code of Federal Regulations
ECCS emergency core cooling system
ESFAS engineered safety features actuation system
MOV motor-operated valve
PRA probabilistic risk assessment
RCE Root Cause Evaluation
RCS reactor coolant syste
m RHR residual heat removal
}}
}}

Revision as of 12:10, 29 June 2018

Diablo Canyon Power Plant - NRC Supplemental Inspection Report and Assessment Follow-Up Letter; 05000275/2017008 and 05000323/2017008
ML17271A431
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 09/27/2017
From: Pruett T W
NRC/RGN-IV/DRP
To: Halpin E D
Pacific Gas & Electric Co
T. PRUETT
References
EA-16-168 IR 2017008
Download: ML17271A431 (22)


See also: IR 05000275/2017008

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV 1600 E. LAMAR BLVD.

ARLINGTON, TX

76011-4511 September 27, 2017

EA-16-168 Mr. Edward D. Halpin

Senior Vice President

and Chief Nuclear Officer

Pacific Gas and Electric Company

Diablo Canyon Power Plant

P.O. Box 56, Mail Code 104/6

Avila Beach, CA 93424

SUBJECT: DIABLO CANYON POWER PLANT

- NRC SUPPLEMENTAL

INSPECTION REPORT AND ASSESSMENT FOLLOW

-UP LETTER; 05000275/2017008 AND 05000323/2017008 Dear Mr. Halpin:

On June 15, 2017, the NRC completed the on

-site portion of a supplemental inspection using Inspection Procedure 9500

1, "Supplemental Inspection Response to Action Matrix Column 2 Inputs." On September 21, 2017, the NRC inspection team discussed the results of this inspection with Mr. J. Welsch

and other members of your staff.

The results of this inspection are documented in the enclosed report. The NRC performed this inspection to review your station's actions in response to a White finding in the Mitigating Systems

cornerstone which was documented in NRC Inspection Reports 05000275/2016010 and 05000323/2016010, dated October

3, 2016, (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML16277A340), and finalized in a letter to you from Kriss Kennedy, Regional Administrator, dated December

28, 2016 (ADAMS Accession No. ML16363A429)

. On May 3, 2017, you informed the NR

C that your station was ready for the supplemental inspection.

The NRC inspectors did not identify any finding or violation of more than minor significance.

The NRC determined that your staff's cause evaluations were not performed to the depth and breadth described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column

2 Inputs."

Your staff did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding). In

particular, the questioning process concluded prior to the causes identified being beyond your control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column

2 Inputs." Had continued questioning occurred, additional organizational and programmatic causes associated with the

failure to provide supervisory oversight and the failure to provide adequate guidance for developing work instructions would

E. Halpin

2 likely have been identified. The additional

organizational and programmatic causes would also require the development of corrective actions and effectiveness measures. Therefore, the adequacy of the extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed.

After reviewing your performance in addressing the White finding, the NRC concluded your actions did not meet the objectives of Inspection Procedure 9500

1, "Supplemental Inspection Response to Action Matrix Column 2 Inputs.

" As a result, in accordance with the guidance in Inspection Manual Chapter (IMC) 0305, "Operating Reactor Assessment Program," the White finding will be held open and will continue to be considered in assessing plant performance until you notify the NRC of your readiness for additional inspection on this issue and the NRC concludes, by inspection, that the objectives of the inspection procedure have been met

. This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading

-rm/adams.html

and at the NRC Public Document Room in accordance with 10

CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding.

" Sincerely,

/RA/ Troy W. Pruett, Director

Division of Reactor Projects

Docket Nos. 50

-275 and 50

-323 License Nos. DPR

-80 and DPR

-82 Enclosure:

Inspection Report 05000275/2017008 and

05000323/2017008 w/ Attachment: Supplemental Information

SUNSI Review: ADAMS: Non-Publicly Available

Non-Sensitive

By: MSH2/dll Yes No Publicly Available

Sensitive OFFICE RIV/PBD RIV/PE BC:DRP/A RIV/DRP NAME CPeabody CJewett MHaire TPruett SIGNATURE

NON-CONCUR /RA/ /RA/ /RA/ DATE 08/15/17 08/24/17 08/23/17 9/26/17

SUNSI Review:

ADAMS: Non-Publicly Available Non-Sensitive

By: MSH2/dll Yes No Publicly Available

Sensitive

OFFICE RIV/PBD RIV/PE BC:DRP/A RIV/DRP NAME CPeabody CJewett MHaire TPruett SIGNATURE

NON-CONCUR /RA/ /RA/ /RA/ DATE 09/26/17 09/25/17 09/22/17 09/26/17

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 05000275;

05000323 License: DPR-80; DPR-82 Report: 05000275/2017008; 05000323/201700

8 Licensee:

Pacific Gas and Electric Company

Facility:

Diablo Canyon Power Plant, Units 1 and 2 Location:

7 1/2 miles NW of Avila Beach

Avila Beach, CA

Dates: June 12 through September 21, 2017 Inspectors:

C. Peabody, Senior Resident Inspector

C. Jewett

, Project Engineer

Approved By: Troy W. Pruett

Director, Division of Reactor Projects

2 SUMMARY IR 05000275/2017008, 05000323/201700

8; 06/07/2017 - 09/21/2017; Diablo Canyon Power Plant; Supplemental Inspection

- Inspection Procedure 95001

This supplemental inspection was conducted by a senior

resident inspector from the Palo Verde Generating Station and a project engineer from NRC's Region IV office. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG

-1649, "Reactor Oversight Process."

No findings were identified.

Cornerstone: Mitigating

Systems The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column

2 Inputs."

The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding). In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column

2 Inputs." Had continued questioning occurred, additional organizational and programmatic causes associated with the failure to provide supervisory oversight and the failure to provide adequate guidance for developing work instructions would likely have been identified. The additional organizational and programmatic causes would also require the development of corrective actions and effectiveness measures. Therefore, the adequacy of the extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed.

After reviewing the licensee's performance in addressing the White finding, the NRC concluded the licensee's actions did not meet the objectives of Inspection Procedure 9500

1, "Supplemental Inspection Response to Action Matrix Column 2 Inputs.

" As a result, i

n accordance with the guidance in Inspection

Manual Chapter (IMC)

0305, "Operating Reactor Assessment Program," the White finding will be held open and will continue to be considered in assessing plant performance until the licensee notifies the NRC of its readiness for additional inspection on this

issue and the NRC concludes, by inspection, that the objectives of the inspection procedure have been met.

3 REPORT DETAILS

4. OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Security 4OA4 Supplemental Inspection (95001)

.01 Inspection Scope

This inspection was conducted in accordance with Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 Inputs," to assess the licensee's evaluation of a White finding, which affected the Mitigating Systems Cornerstone in the Reactor Safety Strategic Performance Area. The inspection objectives included the following

Assure that the root causes and contributing causes of the significant performance issues are understood.

Independently assess and assure that the extent of condition and extent of cause of significant performance issues are identified.

Assure that corrective actions taken to address and preclude

repetition of significant performance issues are prompt and effective.

Assure that corrective plans direct prompt actions to effectively address and preclude

repetition of significant performance issues.

The licensee remained in the Regulatory Response Column (Column

2) of the NRC

's Action Matrix in the second quarter of 2017 as a result of one inspection finding of low to moderate safety significance (White). The finding was associated with

the failure to establish adequate work instructions for installation of Namco

Ž Snap Lock limit switches. Specifically, the licensee failed to provide site

-specific instructions for limiting the travel of these external limit switches when installed on safety-related motor operated valves (MOVs). Consequently, the lev

er switch actuator for valve

RHR-2-8700B, residual heat removal pump 2

-2 suction from the refueling water storage tank, was operated repeatedly in an over

-travel condition resulting in a sheared internal roll pin that ultimately caused the limit switch to fail. The NRC staff characterized this issue as having low to moderate safety significance (White), as documented in NRC

Inspection Report 05000275; 05000323/2016010, dated October

3, 2016, (ADAMS Accession No. ML16277A340), and updated in a letter to E.

Halpin from K.

Kennedy, dated December

28, 2016, (ADAMS Accession No. ML16363A429).

On May 3, 2017, the licensee informed the NRC that they were ready for the supplemental inspection.

In preparation for the inspection, the licensee performed root cause evaluation (

RCE) 50886801 to address the performance deficiency associated with the White finding

. The licensee provided revision 1A of the report

, completed in April 2017

, to the inspectors for review. This evaluation determined two root causes

for the White finding. The first root cause identified that Electrical Maintenance

leadership was not ensuring that workers perform procedures as written. The second root cause identified that guidance for

4 determining Maintenance Verification Testing work instructions in the electrical maintenance procedures writing process

was not sufficient.

In addition, the licensee performed RCE 50870357

to address why a probabilistic risk assessment (PRA)

-significant component failure was not recognized in a timely manner

. The licensee provided revision 2 of RCE 50870357

, completed in October

2016, to the inspectors for review. There were two root causes and one contributing cause identified

for RCE 50870357. The first root cause involved a non

-industry standard design feature of the emergency core cooling system (ECCS)

interlocks which resulted in a failure mechanism that

was not immediately recognizable. Specifically, Diablo Canyon utilizes external limit switches to provide feedback to the ECCS pump suction interlocks, whereas it is more common for nuclear power plants to use the limit switches internal to the valve's motor operator. Having a separate external limit switch provides additional

separation and redundancy in the design, but warrants additional testing and verification

beyond the normal MOV testing to ensure that the external limit switch is functioning properly. The second root cause identifieded

that the external limit switch was not identified as requiring additional post

-maintenance testing to verify proper operation. A similar contributing cause identified

that the external limit switches were not identified as requiring additional monitoring which could eliminate missed opportunities to identify degraded conditions.

The inspectors reviewed the licensee's two RCE reports and supporting

evaluations. The inspectors reviewed corrective actions that were taken or planned to address the identified causes. The inspectors also interviewed licensee personnel to determine whether the root and contributing causes were understood, and whether corrective actions taken or planned were appropriate to address the causes and preclude repetition.

.02 Evaluation of the Inspection Requirements

02.01 Problem Identification

a. Determine that the evaluation documented who identified the issue and under what conditions the issue was identified

. The RHR-2-8700B valve failure event of May

16, 2016, was self-revealing. The initial licensee corrective actions in response to the event failed to identify the performance deficiencies associated with the inadequate

level of guidance provided by the maintenance work instructions that constituted the White

finding. The NRC inspection effort identified the performance deficiency independent

ly of the efforts of the licensee's corrective action program.

This 95001 inspection requirement

is closed. b. Determine the evaluation documented how long the issue existed and prior opportunities for identification

. The limit switch failed sometime after the last successful stroke test of interlocked valve

s 2-RHR-8982A and 2

-RHR-8982B during the Unit

2, fall 2014 refueling outage

. The condition can be reasonably

determined to have been introduced at the last maintenance interval during

the Unit 2, spring refueling outage of 2013.

The misalignment which caused the limit switch to over

-travel was not detected during the

5 post-maintenance testing

of 2-RHR-8700B. The misaligned switch

repeatedly over-traveled during quarterly stroke testing.

RCE 50886801

determined that the quarterly stroke testing and other maintenance activities performed on

2-RHR-8700B were missed opportunities

to visually identify the misaligned external limit switch

. In recognition of the safety significance of the interlocks associated with the external limit switch, involved personnel missed the opportunity to visually inspect the valve and limit switch travel during quarterly stroke testing as a means of validating proper switch alignment

. The inspectors noted the licensee also missed opportunities to confirm interlock circuit continuity during valve testing. However, since there was not adequate guidance to include additional procedural direction to check this separate external limit switch or the ECCS interlock circuitry, the deficiency was not identified

. The licensee's corrective

actions included direction to visually inspect the valve and limit switch travel and circuit continuity during quarterly stroke testing

as a means of validating proper switch alignment

. Both RCE 50886801 and RCE 50870357 concluded that the physical positioning of the switch

adjacent to the building wall

, combined with the lack of indication

of switch position for the external limit switch and ECCS interlock

, made the degradation and failure of the switch unlikely to be identified

during quarterly testing of 2-RHR-8700B without the additional guidance to specifically observe operation.

This 95001 inspection requirement

is closed. c. Determine that the evaluation documented significant plant

-specific consequence, as applicable, and compliance concerns associated with the issue

. The licensee conducted RCE 50886801 to address

the White finding

and RCE 50870357 to address their failure to timely recognize a PRA

-signficant component failure. RCE 50870357 addressed plant specific consequences

by using PRA information to compile a list of components with elevated failure consequences. These components were

flagged in the corrective action program system

so that future conditions adverse to quality identified on these components

will prompt automated notification

s, instructing the initiators

to take corrective action in the timeliest manner possible.

RCE 50886801 addressed the White finding and

restoration of compliance. RCE 50886801 corrective

actions (as outlined in Section 02.03.a below)

added procedural guidance to ensure the external limit switches are operating correctly

and surveillance monitoring of the ECCS interlock circuitry.

This 95001 inspection requirement

is closed. 02.02 Root Cause, Extent of Condition, and Extent of Cause Evaluation

a. Determine that the

problem was evaluated using a systematic methodology to identify the root and contributing causes

. The White finding

RCE 50886801 used Comparative Timeline

©, Event and Causal Factors Analysis, and a Barrier Analysis. The undetected failure

RCE 50870357

used Factor Tree Analysis and ABS Consulting Root Cause Map

TM. These cause evaluation tools provided a systematic methodology that can be used to identify the root and contributing causes of the event.

6 No deficiencies were noted

with the licensee's selection of root cause methods

. This 95001 inspection requirement is closed

. b. Determine that the root cause evaluation was conducted to a level of detail commensurate with the significance of the problem

. The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth

described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column

2 Inputs."

The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding). In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column

2 Inputs." This 95001 inspection requirement will remain open.

c. Determine that the root cause evaluation included a consideration of prior occurrences of the problem and knowledge of prior operating experience

. Both RCEs included a thorough review of internal and external operating experience to search for previous occurrences. No identical failures

of ECCS interlocks

resulting from external limit switches were identified

. There were two instances from early refueling outages in the fall of 1988 and

fall of 1989 that identified maintenance difficulties in setting the external limit switches, but no identical service failures were identified

. There were six industry operating experience events for over-travel failure of

NamcoŽ external limit switches

in low safety applications such as plant process systems or alarm and indication functions, but none in applications related to safety system interlocks. As a result of the low safety significance

of these operating experience items, the six industry events were characterized as broke/fix conditions

rather than formally evaluated under the respective licensees' corrective action program.

This 95001 inspection requirement will remain remain open

pending completion of a re

-assessment of the

licensee's root cause to satisfy Section 02.02.b, above. In particular, the licensee should consider whether there are organizational and programmatic concerns associated with how the licensee dispositions low risk operating experience from other sites that may have risk significance at Diablo Canyon

. d. Determine that the root cause evaluation addressed the extent of condition and the extent of cause of the problem

. Both RCEs identified the extent of condition

as the population of risk significant valves

containing Namco

Ž external limit switches which provided input into ECCS or other engineered safety features actuation system

(ESFAS) interlocks. The extent of condition identified 8 ECCS valves on each unit, 16 in total, that met this criteria.

Extent of condition and extent of cause cannot be fully evaluated at this time because of the determination that the root cause evaluations were not conducted to sufficient depth and breadth

. Of particular concern is whether or not organizational and programmatic

deficiencies involving management oversight of work activities, operating experience, and guidance documents existed and corrective actions that may be warranted. This 95001 inspection requirement will remain open.

7 e. Determine that the root cause, extent of condition, and extent of cause evaluation appropriately considered the safety culture traits in NUREG

-2165, "Safety Culture Common Language,

" referenced in IMC 0310, "Aspects within Cross

-Cutting Areas."

Both RCEs contained a

safety culture analysis. The White finding RCE

50886801 identified seven safety culture attributes associated with the White Finding. The RCE identified H.2 Field Presence and H.8 Procedure Adherences

as safety culture attributes associated with the leadership oversight

root cause

. RCE 50886801 also identified X.5 Leader Behaviors, X.6 Standards, and X.10 Expectations

as supplemental cross cutting aspects associated with the leadership oversight root cause

. In addition,

RCE 50886801identified H.1 Resources and H.7 Documentation

as safety culture attributes associated with the inadequate work instructions root cause. The undetected

failure RCE

50870357 identified

the H.1 and H.7 assafety culture attributes associated with the inadequate

test requirements root cause and the inadequat

e monitoring contributing cause.

No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional safety culture attributes that would require NRC review. This 95001 inspection requirement will remain remain open

. f. Examine the common cause analyses for potential programmatic weaknesses in performance when a licensee has a second

white input in the same cornerstone

. Not applicable

there was not a second White input in

the affected cornerstone.

02.03 Corrective Actions Taken

a. Determine that appropriate corrective actions are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary

. Immediate corrective actions were taken under Notification 50852345 to walk down and visually inspect all

of the accessible affected MOVs in the extent of condition population for physical signs of damage to the external limit switch assemblies.

Corrective actions taken in response to the White finding RCE 50886801 included

the following

actions: (1) Establishment

of supervisory observation signoffs for maintenance verification testing on NamcoŽ external limit switches.

(2) Revision of the Nuclear Procedure Writer's Manual to include specific guidance for

establishing maintenance verification testing in electrical procedures.

(3) Revision of MOV maintenance procedures that set and test external limit switches to provide explicit instructions for switch configuration control, as well as

switch travel setting and testing.

(4) Development and implementation of a dynamic learning activity for Electrical Maintenance MOV crews. Revision of the Pre

-outage Just in Time Training module offered to MOV technicians to include operating experience on this event.

8 (5) Revision of the MOV Sizing, Switch Setpoint Determination and Test Evaluation procedure to include the NamcoŽ vendor total travel limits and parameters

, as well as associated testing criteria.

(6) Education of the Diablo Canyon Power Plant's extended leadership team on this event and recent related human performance events in accordance with the Diablo Canyon Power Plant's Human Performance Reinforcement policy.

Corrective actions taken in response to the undetected failure RCE 50870357 included

the following

actions: (1) Development of a routine check to verify interlock circuit continuity for the

RHR 8700A/B valves and their associated external limit switches on a quarterly basis

in conjunction with

the quarterly valve stroke surveillance.

(2) Revision of applicable maintenance procedures to specify direction as appropriate:

(a) Inclusion of external limit switch operation data

. (b) Specific evaluation of external limit switch and geared limit switch settings

. (c) Provide instructions for standardized assembly, configuration, and adjustment of external limit switches.

(d) Provide inspection of external limit switch configuration against a set of standardized criteria.

(e) Perform visual inspections of the external limit switch with each quarterly valve stroke surveillance test.

(f) Apply position indication lamacoids on the 16 extent of condition valves.

The actions taken have restored compliance.

The revised maintenance procedure work instructions contain adequate

and specific guidance to ensure confidence of

operability to the affected extent of condition valve population. Subsequent visual inspections

and electrical testing of the affected ECCS interlocks has confirmed operability

. No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional corrective action items that would require NRC review. This 95001 inspection

requirement will remain

open. b. Determine that the corrective actions have been prioritized with consideration of significance and regulatory compliance

. The licensee

's corrective actions have been prioritized with consideration of significance and regulatory compliance. All corrective actions for the White finding RCE 50886801 are completed.

There is one remaining corrective action planned for the undetected failure

RCE 50870357. This action is to implement a design change to remove the external limit switches associated with the ECCS MOV interlocks.

Plans to modify the system to remove the external limit switches will take until Spring 2019

to analyze and implement

in order to ensure the modification is conducted in accordance with 10 CFR 50.59 and

9 50.90. In the interim, the licensee added test requirements to electrically verify the condition of the

ECCS interlock when valves are stroked quarterly for surveillance testing. During the

quarterly stroke tests, the licensee also added visual field inspections of the valve stroke by qualified

MOV engineers. As the actions were implemented at the first reasonable opportunity following

the White

finding, the inspector concluded that the actions were

prioritized.

No deficiencies were noted in this area, however further revisions of the RCEs could introduce additional corrective action items that would require NRC review to assess

prioritization. This 95001 inspection requirement will remain remain open.

c. Determine that corrective actions taken to address and preclude repetition of significant performance issues are prompt and effective

. Corrective actions to prevent recurrence (CAPR) of the White finding RCE 50886801 included the following

(1) Establishment

of supervisory observation signoffs for maintenance verification testing on NamcoŽ external limit switches.

(2) Revision of the Nuclear Procedure Writer's Manual to include specific guidance for establishing maintenance verification testing in electrical procedures.

(3) Revision of MOV maintenance procedures that set and test external limit switches to provide explicit instructions for switch figure configuratio

n control and switch travel setting and testing.

Corrective actions to prevent recurrence of

the undetected failure RCE 50870357 included the following

actions: (1) Development of a routine check to verify interlock circuit continuity for the

RHR 8700A/B valves and their associated external limit switches on a quarterly basis; which was performed concurrent with the quarterly

valve stroke surveillance.

(2) Revision of applicable maintenance procedures t

o specify direction as appropriate:

(a) Inclusion of external limit switch operation data

. (b) Specific evaluation of external limit switch and geared limit switch settings

. (c) Provide instructions for standardized assembly, configuration, and adjustment of external limit switches.

The corrective actions taken to address and preclude repetition of significant performance issues were prompt and effective. All but one CAPR is completed, and that

action has a corresponiding

interim CAPR to monitor the interlock directly. The CAPRs implemented

have restored regulatory compliance and demonstrated

operability for the affected ECCS interlocks.

No deficiencies were noted in this area, however further

revisions of the RCEs could introduce additional CAPR items that would require NRC review to assess effectiveness. This 95001 inspection requirement will remain remain open.

10 d. Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed, either in corrective actions taken or planned

. Corrective actions taken thus far have restored compliance with Technical Specification 5.4.1.a., "Procedures

." The licensee has made applicable and appropriate revisions to the maintenance procedures pertaining to VIO 05000323/2016010

-01. The licensee has taken steps to ensure that there are no additional failures in the extent of condition valve population

. As outlined above, surveillance testing of the affected valves has been enhanced to provide additional means of verification

, including

visual testing of proper external limit switch operation and electrical circuit verification

of the associated ECCS interlock function.

This 95001 inspection requirement

is closed. 02.04 Corrective Action Plans

a. Determine that appropriate corrective action plans are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary. Determine that the corrective action plans have been prioritized with consideration of significance and regulatory compliance

. All corrective actions for the White finding RCE 50886801

are completed.

There is one remaining

corrective action planned for the undetected failure

RCE 50870357. This action is to implement a design change to remove the external limit switches associated with the ECCS MOV interlocks. This design change is expected to be implemented during the respective

unit refueling outages in the spring 2018 and the spring

2019. Corrective actions taken thus far have been

appropriate. Corrective

actions taken and planned have been prioritized with consideration of safety significance and regulatory compliance.

The interim actions to verify the design basis of the ECCS interlocks and NamcoŽ external limit switches provide a reliable means of maintaining safety and regulatory compliance.

This 95001 inspection requirement will remain remain open

pending completion of a re

-assessment of the licensee's root cause to satisfy Section 02.02.b, above

. b. Determine that corrective plans direct prompt actions to effectively address and preclude repetition of significant performance issue

. All corrective actions to prevent recurrence under White finding RCE 50886801 are completed.

The remaining

actions planned for the undetected failure RCE 50870357 to modify the system by removing the external limit switches have corresponding

interim actions in place to verify the ECCS interlocks associated with the

NamcoŽ external limit switches are functioning properly

. This 95001 inspection requirement will remain remain open

pending completion of a re

-assessment of the licensee's root cause to satisfy Section 02.02.b, above

.

11 c. Determine that appropriate quantitative or qualitative measures of success have been

developed for determining the effectiveness of planned and completed corrective actions. The White finding RCE 50886801 specified the following effectiveness evaluations:

(1) Procedure use and adherence

- Targeted supervisory observations during outages

and online; review of station and department level events for procedure use and adherence as a causal factor; and quick hit self-assessments

. (2) Procedure writers guide changes

- 100 percent review of maintenance procedure revisions

, as well as interviews with

maintenance procedure writers to confirm understanding of the writers guide changes. The undetected failure RCE 50870357 specified the following effectiveness evaluations:

(1) Design verification testing and return to service following the design change modification to remove the external limit switches from the ECCS interlocks.

(2) During outages 1R20 and 2R20

, satisfactory

verifications of the setting, testing, and adjustment

of affected Namco

Ž external limit switches

. (3) Satisfactory testing of the interlock circuit continuity testing during the quarterly surveillance testing.

The success measures for RCE 50886801

were appropriate and provide

qualitative measures of success

of the corrective actions taken. RCE 50870357

effectiveness measures are satisfactory; the second and third criteria provide appropriate effectiveness measures until the modifications associated with the first criteria are implemented

. This 95001 inspection requirement will remain remain open

pending completion of a re

-assessment of the licensee's root cause to satisfy Section 02.02.b, above

. d. Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed in corrective actions taken or planned

. As discussed in Section 02.03.d (above), the corrective actions have restored compliance with Technical Specification 5.4.1.a., "Procedures

." for which the NOV was issued associated with the White finding.

This 95001 inspection requirement

is closed. 02.05 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues. Not applicable

the performance deficiency associated with the White finding does not warrant treatment as an old design issue

. This 95001 inspection requirement

is closed.

12 03.00 Inspection Results

Summary The NRC determined that the licensee's cause evaluations were not performed to the depth and breadth

described in Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column

2 Inputs."

The licensee did not perform root cause evaluations to a level of detail commensurate with the significance of the problem (White finding). In particular, the questioning process concluded prior to the causes identified being beyond the licensee's control as described in Section 03.03.b of Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column

2 Inputs." Had continued questioning occurred, additional organizational and

programmatic causes associated with the failure to provide supervisory oversight and

the failure to provide adequate guidance for developing work instructions would likely have been identified. The additional organizational and programmatic causes would also require the development of corrective actions and effectiveness measures. Therefore, the adequacy of the extent of cause, extent of condition, and corrective actions required to prevent recurrence cannot be assessed until the depth and breadth of the root cause evaluation is fully developed.

The status of the

inspection requirements of

Inspection

Procedure 95001 have been categorized below. Requirement

s held open in entirety by this inspection will require a full re-evaluation by NRC inspectors at a later date.

Requirement

s held open for changes only

are those for which

no deficiencies were noted

during this inspection but may be impacted, and therefore require additional review, as a result of revisions to the

licensee's RCEs. In this instance, only the changes added by future revisions of the RCEs will have to be evaluated by NRC inspectors at a later date. Requirements

closed by this inspection effort will require no

additional

inspection effort.

03.01 Inspection Requirements Held Open in Entirety

02.02b Determine that the root cause evaluation was conducted to a level of detail commensurate with the significance of the problem

02.02d Determine that the root cause evaluation addressed the extent of condition and the extent of cause of the problem

03.02 Inspection Requirements Held Open for Changes Only

02.02c Determine that the root cause evaluation included a consideration of prio

r occurrences of the problem and knowledge of prior operating experience

02.02e Determine that the root cause, extent of condition, and extent of cause evaluation appropriately considered the safety culture traits in NUREG

-2165, "Safety Culture Common Language," referenced in IMC 0310, "Aspects within Cross

-Cutting Areas

" 02.03a Determine that appropriate corrective actions are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary

02.03b Determine that the corrective actions have been prioritized with consideration of significance and regulatory compliance

13 02.03c Determine that corrective actions taken to address and preclude repetition of significant performance issues are prompt and effective

02.04a Determine that appropriate corrective action plans are specified for each root and contributing cause or that the licensee has an adequate evaluation for why no corrective actions are necessary. Determine that the corrective action plans have been prioritized with consideration of significance and

regulatory compliance

02.04b Determine that corrective plans direct prompt actions to effectively address and preclude repetition of significant performance issue

02.04c Determine that appropriate quantitative or qualitative measures of success have been developed for determining the effectiveness of planned and completed corrective actions

03.03 Inspection Requirements Closed

02.01a Determine that the evaluation documented who identified the issue and under what conditions the issue was identified

02.01b Determine the evaluation documented how long the issue existed and prior opportunities for identification

02.01c Determine that the evaluation documented significant plant

-specific consequence, as applicable, and compliance concerns associated with the

issue 02.02a Determine that the problem was evaluated using a systematic methodology to identify the root and contributing causes

02.02f Examine the common cause analyses for potential programmatic weaknesses in performance when a licensee has a second white input in the same cornerstone

02.03d Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed, either in corrective actions taken or planned 02.04d Determine that each Notice of Violation (NOV) related to the supplemental inspection is adequately addressed in corrective actions taken or planned

02.05 Evaluation of IMC 0305 Criteria for Treatment of Old Design Issues

14 4OA6 Meetings, Including Exit

Exit Meeting Summary

On September 21, 2017, the inspectors presented the inspection results to Mr. J. Welsch

, Site Vice President,

and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.

Attachment SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel T. Baldwin, Director, Nuclear Site Services

J. Cheek, MOV Program Engineer D. Evans, Director, Security & Emergency Services

M. Fraunheim, Manager Nuclear Performance Improvement

P. Gerfen, Senior Director Plant Manager

M. Ginn, Manager, Emergency Planning

E. Halpin, Sr. Vice President, Chief Nuclear Officer Generation

H. Hamzehee, Manager, Regulatory Services

A. Heffner, NRC Interface, Regulatory Services

J. Hinds, Director, Quality Verification

L. Hopson, Director Maintenance Services

T. Irving, Manager, Radiation Protection

K. Johnston, Director of Operations

M. McCoy, NRC Interface, Regulatory Services

J. Morris, Senior Advising Engineer

C. Murry, Director Nuclear Work Management

J. Nimick, Senior Director Nuclear Services

A. Peck, Director, Nuclear Engineering

R. Walthos, Nuclear Engineering Specialist, Principal

J. Welsch, Site Vice President

NRC Personnel

C. Newport, Senior Resident Inspector

J. Reynoso, R

esident Inspector

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Discussed

05000323/2016010

-01 VIO Failure to Establish Adequate Work Instructions for Installation

of NamcoŽ Snap Lock Limit Switches (Section 4OA4)

LIST OF DOCUMENTS REVIEWED

Section 4OA

4: Supplemental Inspection (95001)

Procedures

Number Title Revision AD1 Administrative Controls Program

17 AD1.ID1 Nuclear Generation Procedure Writer's Manual

30

A-2 Procedures

Number Title Revision AD7.ID12 Work Management Process

6 AD7.ID15 On-Line Maintenance Outrage Window Execution

3 AD7.ID16 Tool Pouch and Minor Maintenance

4 AD7.ID2 Daily Notification Review Team (DRT) & Standard Plant Priority Assignment Scheme

27 AD7.ID4 On-line Maintenance Scheduling

25 AWP E-027 Motor Operated Valve Sizing, Switch Setpoint Determination and Test evaluation

4 MA1.DC58 Troubleshooting Evidence Preservation and Forensic Analysis 1 MP E-53.10A Preventive Maintenance of Limitorque Motor Operators

41 MP E-53.10A1 Low Impact External Inspections of Limitorque Motor Operators

2 MP E-53.10R Augmented Stem Lubrication for Limitorque Operated Valves 9 MP E-53.10S Limitorque Swap

-Out and Switch Settings

14 MP-E-53.10V1 MOV Diagnostic Testing

18 OM15.ID8 Human Performance Error Prevention Tools

7 OM7.ID1 Problem Identification and Resolution

49A OM7.ID3 Root Cause Evaluation

45 OM7.ID4 Cause Determinations

36 OM7.ID7 Emerging Issue and Event Investigations

18A OP1.DC18 Authorization of Test Equipment Operation, Maintenance, and Testing

11 OP2.ID1 Clearances

39 PEP V-7B Test of ECCS Valve Interlocks

10 PRA 17-02 Probabilistic

Risk Assessment

1 STP V-2B2 Exercising and Position Verification of Valves

9003A and 9003B Unit 2 0 STP V-2B2 Exercising and Position Verification of Valves

9003A and 9003B Unit 1 16 STP V-2D2A Exercising and Position Verification of Valve

8700A Unit 2 0 STP V-2D2A Exercising and Position Verification of Valve

8700A Unit 1 3

A-3 Procedures

Number Title Revision STP V-2D2B Exercising and Position Verification of Valve 8700B Unit 2 0 STP V-2D2B Exercising and Position Verification of Valve

8700B Unit 1 3 STP V-2O6 Exercising and Position Verification of Valves

8982A and 8982B Unit 2 1 STP V-2O6 Exercising and Position Verification of Valves

8982A and 8982B Unit 1 10 STP V-2V1 Exercising and Position Verification of Valves

8804A and 8804B Unit 2 0 STP V-2V1 Exercising and Position Verification of Valves

8804A and 8804B Unit 1 11 TP V-3M5 Exercising Valves RHR

-8701 and RHR

-8702, Reactor Coolant Loop 4 to RHR Pump Suction 16 Notifications

50852345 50870357 50923338 50923339 50857553 50874911 50886801 50871499 50910294 50908100 50915340 50891772 50906150 50906119 50915775 50893249 50874463 50875300 50866497 50872919 50913951 50891005 50910293 50891005 Miscellaneous Documents

Number Title Revision / Date Cause Determination Manual

May 18, 2017

2016 Maintenance Audit

November 7, 2016

HUJITDC055

JITT Validating Assumptions

April 20, 2017 HUJITDC050 Confined Space DLA

February

16, 2017 HUJITIS041 Human Performance Training

March 29, 2016 JITTEM1604 JITT Pre-Outage MOV Training

April 19, 2017 1R20 Supervisor Stand Down

May 1, 2017 R165C11 Task Training: Nuclear Operators

0 Program and Process Codes

May 2, 2013 Cause Codes

A-4 Miscellaneous Documents

Number Title Revision / Date Site Standards Handbook

WG-24 NRC Administrative Support

7 WG-7 Reportability Reviews

8 2017-S009-001 Undetected ECCS Interlock Failure

April 18, 2017 50870357 Root Cause Evaluation Report Undetected ECCS Interlock Failure

2 50886801 Root Cause Evaluation Report DCPP Inadequate NAMCO Procedure

1A 50913375 95-001 Pre-Inspection Assessment

May 3, 2017 130100011

Work Order Preparation

January 28, 2013 150360043

Assessment of

1Y19 February

5, 2015 163620001

2017 Fire Protection Audit

1 9000035423

Motor Operated Valve Sizing

and Switch Setting Calculations

September

30, 2013 Work Order

s 60098575 60098576 60098577 60098578 60094730 60094731 60090383 64090172 60100131 64065079 LIST OF ACRONYMS

ADAMS Agencywide

Document Access and Management System

CAPR corrective action to prevent recurrence

CFR Code of Federal Regulations

ECCS emergency core cooling system

ESFAS engineered safety features actuation system

MOV motor-operated valve

PRA probabilistic risk assessment

RCE Root Cause Evaluation

RCS reactor coolant syste

m RHR residual heat removal