DCL-24-045, Annual Report of Occupational Radiation Exposure for 2023

From kanterella
Jump to navigation Jump to search
Annual Report of Occupational Radiation Exposure for 2023
ML24115A331
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 04/24/2024
From: Sutton C
Pacific Gas & Electric Co
To:
Office of Nuclear Reactor Regulation, Office of Nuclear Regulatory Research, Document Control Desk
References
DCL-24-045
Download: ML24115A331 (1)


Text

Craig D. Sutton Manager, Nuclear Radiation Protection Diablo Canyon Power Plant Mail code 104/5/521 P.O. Box 56 Avila Beach, CA 93424 805.545.4208 Craig.Sutton@pge.com A member of the STARS Alliance Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek PG&E Letter DCL-24-045 REIRS Project Manager 10 CFR 20.2206 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Annual Report of Occupational Radiation Exposure for 2023 REIRS Project Manager:

On April 10, 2024, Pacific Gas and Electric Company (PG&E) submitted the Annual Report of Occupational Radiation Exposure for individuals monitored at Diablo Canyon Power Plant during the 2023 calendar year in accordance with 10 CFR 20.2206(c). The report was created in the electronic format specified in Regulatory Guide 8.7, Revision 4, Instructions for Recording and Reporting Occupational Radiation Dose Data. The data file, NRC20240408.dat, was submitted electronically on the Radiation Exposure Information and Reporting System (REIRS) web page.

PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.

If you have any questions about the report, please contact me at 805-545-4208.

Sincerely, Craig D. Sutton Date armb/50942689 cc:

Diablo Distribution Mahdi O. Hayes, NRC Senior Resident Inspector Samson S. Lee, NRC Project Manager John D. Monninger, NRC Region IV Administrator NRC Document Control Desk 4/24/2024 Pacific Gas and Electric Company*