ML20253A227: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:September 16, 2020 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Nuclear LaSalle County Station 4300 Winfield Road Warrenville, IL 60555
 
==SUBJECT:==
LASALLE COUNTY STATION, UNITS 1 AND 2  CORRECTION TO REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO ADOPT TSTF-505, REVISION 2, PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF INITIATIVE 4B (EPID L-2020-LLA-0018)
 
==Dear Mr. Hanson:==
 
By letter dated September 3, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20240A019), the U.S. Nuclear Regulatory Commission (NRC) staff issued a request for additional information (RAI) regarding your license amendment request dated January 31, 2020 (ADAMS Accession No. ML20035E577). The amendment would revise the technical specification requirements to adopt Technical Specifications Task Force (TSTF)
Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.
The NRC staff has identified that due to inadvertent error, the third paragraph in the NRCs letter stated that The draft request for additional information (RAI) is enclosed. It should read The request for additional information (RAI) is enclosed.
Additionally, the last sentence in the fourth paragraph stated that By e-mail dated August 26, 2020, you committed to provide the responses to this request no later than September 30, 2020. It should read, By e-mail dated August 26, 2020, you committed to provide the responses to this request no later than 30 calendar days from the date of this letter.
The correction does not change any of the RAIs. Based on the above changes, the response date for the RAIs would be October 3, 2020.
 
B. Hanson                                    If you have any questions, please contact me at 301-415-3308 or via e-mail at Bhalchandra.Vaidya@nrc.gov.
Sincerely,
                                          /RA/
Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374 cc: Listserv
 
ML20253A227                                                *via e-mail OFFICE  NRR/DORL/LPL3/PM*  NRR/DORL/LPL3/LA*        NRR/DORL/LPL3/BC* NRR/DORL/LPL3/PM*
NAME    BVaidya            SRohrer (JBurkhardt for) NSalgado          BVaidya DATE    09/14/2020          09/11/2020              09/16/2020        09/16/2020}}

Revision as of 00:56, 25 September 2020

Correction to Request for Additional Information Application to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b
ML20253A227
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 09/16/2020
From: Bhalchandra Vaidya
Plant Licensing Branch III
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Vaidya B
References
EPID L-2020-LLA-0018
Download: ML20253A227 (3)


Text

September 16, 2020 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Nuclear LaSalle County Station 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

LASALLE COUNTY STATION, UNITS 1 AND 2 CORRECTION TO REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO ADOPT TSTF-505, REVISION 2, PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF INITIATIVE 4B (EPID L-2020-LLA-0018)

Dear Mr. Hanson:

By letter dated September 3, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20240A019), the U.S. Nuclear Regulatory Commission (NRC) staff issued a request for additional information (RAI) regarding your license amendment request dated January 31, 2020 (ADAMS Accession No. ML20035E577). The amendment would revise the technical specification requirements to adopt Technical Specifications Task Force (TSTF)

Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.

The NRC staff has identified that due to inadvertent error, the third paragraph in the NRCs letter stated that The draft request for additional information (RAI) is enclosed. It should read The request for additional information (RAI) is enclosed.

Additionally, the last sentence in the fourth paragraph stated that By e-mail dated August 26, 2020, you committed to provide the responses to this request no later than September 30, 2020. It should read, By e-mail dated August 26, 2020, you committed to provide the responses to this request no later than 30 calendar days from the date of this letter.

The correction does not change any of the RAIs. Based on the above changes, the response date for the RAIs would be October 3, 2020.

B. Hanson If you have any questions, please contact me at 301-415-3308 or via e-mail at Bhalchandra.Vaidya@nrc.gov.

Sincerely,

/RA/

Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374 cc: Listserv

ML20253A227 *via e-mail OFFICE NRR/DORL/LPL3/PM* NRR/DORL/LPL3/LA* NRR/DORL/LPL3/BC* NRR/DORL/LPL3/PM*

NAME BVaidya SRohrer (JBurkhardt for) NSalgado BVaidya DATE 09/14/2020 09/11/2020 09/16/2020 09/16/2020