September 16, 2020 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Nuclear LaSalle County Station 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

LASALLE COUNTY STATION, UNITS 1 AND 2 CORRECTION TO REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO ADOPT TSTF-505, REVISION 2, PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF INITIATIVE 4B (EPID L-2020-LLA-0018)

Dear Mr. Hanson:

By letter dated September 3, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20240A019), the U.S. Nuclear Regulatory Commission (NRC) staff issued a request for additional information (RAI) regarding your license amendment request dated January 31, 2020 (ADAMS Accession No. ML20035E577). The amendment would revise the technical specification requirements to adopt Technical Specifications Task Force (TSTF)

Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.

The NRC staff has identified that due to inadvertent error, the third paragraph in the NRCs letter stated that The draft request for additional information (RAI) is enclosed. It should read The request for additional information (RAI) is enclosed.

Additionally, the last sentence in the fourth paragraph stated that By e-mail dated August 26, 2020, you committed to provide the responses to this request no later than September 30, 2020. It should read, By e-mail dated August 26, 2020, you committed to provide the responses to this request no later than 30 calendar days from the date of this letter.

The correction does not change any of the RAIs. Based on the above changes, the response date for the RAIs would be October 3, 2020.

B. Hanson If you have any questions, please contact me at 301-415-3308 or via e-mail at Bhalchandra.Vaidya@nrc.gov.

Sincerely,

/RA/

Bhalchandra K. Vaidya, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374 cc: Listserv