| number = ML12345A371
| number = ML12345A371
| issue date = 12/21/2012
| issue date = 12/21/2012
| title = Kewaunee Power Station - Suspension of Review Effort Related to Request for Review of Reactor Vessel Internal Components Inspection Plan (TAC ME7727)
| title = Suspension of Review Effort Related to Request for Review of Reactor Vessel Internal Components Inspection Plan
| author name = Feintuch K D
| author name = Feintuch K
| author affiliation = NRC/NRR/DORL/LPLIII-1
| author affiliation = NRC/NRR/DORL/LPLIII-1
| addressee name = Heacock D A
| addressee name = Heacock D
| addressee affiliation = Dominion Energy Kewaunee, Inc
| addressee affiliation = Dominion Energy Kewaunee, Inc
| docket = 05000305
| docket = 05000305
| license number = DPR-043
| license number = DPR-043
| contact person = Feintuch K D
| contact person = Feintuch K
| case reference number = TAC ME7727
| case reference number = TAC ME7727
| document type = Letter
| document type = Letter
| page count = 3
| page count = 3
| project = TAC:ME7727
| project = TAC:ME7727
| stage = Approval
}}
}}


=Text=
=Text=
{{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 December 21, 2012 Mr. David A. Heacock Dominion Energy Kewaunee, Innsbrook Technical SOOO Dominion Glen Allen, VA SUBJECT: KEWAUNEE POWER STATION -SUSPENSION OF REVIEW EFFORT RELATED TO REQUEST FOR REVIEW OF REACTOR VESSEL INTERNAL COMPONENTS INSPECTION PLAN (TAC NO. ME7727) Dear Mr. Heacock: By letter dated December 12, 2011, Dominion Energy Kewaunee, Inc. (DEK, the licensee), submitted an inspection plan (the Inspection Plan) for the reactor vessel internals (RVI) components at Kewaunee Power Station (KPS). Pursuant to the license renewal commitments items 1 and 2 in USAR, Chapter 1S, Table 1S.7-1, "License Renewal Commitments," as reproduced from Appendix A of NUREG-19S8, "Safety Evaluation Report Related to the Kewaunee Power Station," dated January 2011, the licensee requested that the staff review and approve the Inspection Plan. By letter dated November 2, 2012, pursuant to Title 10, Code Federal Regulation, Part SO.82(a)(1 )(i), the licensee submitted a letter to the NRC stating its decision to permanently cease power operation of KPS. The license letter further stated that they expected operations to cease in the second quarter of 2013, with a specific date to be determined after the completion of a grid stability review by the Midwest Independent Transmission System Operator, Inc. (MISO). Upon completion of the MISO review, they stated their intention to provide a specific date for permanent cessation of operations to fulfill requirements for a Certification of permanent cessation of operations, as expressed in 10 CFR S0.4(b)(8). Based on this recent development, the NRC has decided to suspend the review of the licensee's December 12, 2011, submittal because the proposed Inspection Plan is no longer applicable for the reactor vessel that is scheduled to be decommissioned. If this situation should change in the future, NRC would restart this review under a new TAC.
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 21, 2012 Mr. David A. Heacock Dominion Energy Kewaunee, Inc.
D. Heacock -2 If you should have any questions on this matter, please contact me at Sincerely, Karl Feintuch, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 20-305 and 50-305 cc: Distribution via ListServ D. Heacock -If you should have any questions on this matter, please contact me at 301-415-3079. . . . Sincerely, IRAJ Karl Feintuch, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 20-305 50-305 cc: Distribution via ListServ DISTRIBUTION: Public LPL3-1 r/f RidsRgn3Mailcenter Resource RidsNrrDeEVIB Resource RidsNrrDorlLpl3-1 Resource RidsOgcRp Resource GCheruvenki, NRRlDE/EVIB RidsAcrsAcnw_MailCTR Resource RidsNrrDeEVIB Resource SKennedy, EDO R-III RidsNrrPMKewaunee Resource RidsNrrDorlDpr Resource ADAMS Accession No.: ML 12345A371 OFFICE LPL3-1/PM LPL3-1/LAit LPL3-2/LA DE/EVIB/BC NAME KFeintuch ELee SRohrer SRosenberg DATE 12/11/12 12/11/12 12/17/12 12/17112 OFFICE LPL3-1/BC LPL3-1/PM NAME RCarlson KFeintuch DATE 12/21/12 12/21/12 OFFICIAL RECORD COpy
Innsbrook Technical Center SOOO Dominion Blvd.
}}
Glen Allen, VA 23060-6711
 
==SUBJECT:==
KEWAUNEE POWER STATION - SUSPENSION OF REVIEW EFFORT RELATED TO REQUEST FOR REVIEW OF REACTOR VESSEL INTERNAL COMPONENTS INSPECTION PLAN (TAC NO. ME7727)
 
==Dear Mr. Heacock:==
 
By letter dated December 12, 2011, Dominion Energy Kewaunee, Inc. (DEK, the licensee),
submitted an inspection plan (the Inspection Plan) for the reactor vessel internals (RVI) components at Kewaunee Power Station (KPS). Pursuant to the license renewal commitments items 1 and 2 in USAR, Chapter 1S, Table 1S.7-1, "License Renewal Commitments," as reproduced from Appendix A of NUREG-19S8, "Safety Evaluation Report Related to the Kewaunee Power Station," dated January 2011, the licensee requested that the staff review and approve the Inspection Plan.
By letter dated November 2, 2012, pursuant to Title 10, Code Federal Regulation, Part SO.82(a)(1 )(i), the licensee submitted a letter to the NRC stating its decision to permanently cease power operation of KPS. The license letter further stated that they expected operations to cease in the second quarter of 2013, with a specific date to be determined after the completion of a grid stability review by the Midwest Independent Transmission System Operator, Inc. (MISO).
Upon completion of the MISO review, they stated their intention to provide a specific date for permanent cessation of operations to fulfill requirements for a Certification of permanent cessation of operations, as expressed in 10 CFR S0.4(b)(8).
Based on this recent development, the NRC has decided to suspend the review of the licensee's December 12, 2011, submittal because the proposed Inspection Plan is no longer applicable for the reactor vessel that is scheduled to be decommissioned. If this situation should change in the future, NRC would restart this review under a new TAC.
 
D. Heacock                                   -2 If you should have any questions on this matter, please contact me at 301-415-3079.
Sincerely, Karl Feintuch, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 20-305 and 50-305 cc: Distribution via ListServ
 
D. Heacock                                   - 2 If you should have any questions on this matter, please contact me at 301-415-3079.
                                                            .         .         . ~
Sincerely, IRAJ Karl Feintuch, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 20-305 50-305 cc: Distribution via ListServ DISTRIBUTION:
Public     LPL3-1 r/f                 RidsRgn3Mailcenter Resource       RidsNrrDeEVIB Resource RidsNrrDorlLpl3-1 Resource             RidsOgcRp Resource               GCheruvenki, NRRlDE/EVIB RidsAcrsAcnw_MailCTR Resource         RidsNrrDeEVIB Resource           SKennedy, EDO R-III RidsNrrPMKewaunee Resource             RidsNrrDorlDpr Resource ADAMS Accession No.: ML12345A371 OFFICE LPL3-1/PM               LPL3-1/LAit       LPL3-2/LA           DE/EVIB/BC NAME       KFeintuch         ELee             SRohrer             SRosenberg DATE       12/11/12           12/11/12         12/17/12           12/17112 OFFICE LPL3-1/BC               LPL3-1/PM NAME       RCarlson           KFeintuch DATE       12/21/12           12/21/12 OFFICIAL RECORD COpy}}

Latest revision as of 19:02, 11 November 2019

Suspension of Review Effort Related to Request for Review of Reactor Vessel Internal Components Inspection Plan
ML12345A371
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 12/21/2012
From: Feintuch K
Plant Licensing Branch III
To: Heacock D
Dominion Energy Kewaunee
Feintuch K
References
TAC ME7727
Download: ML12345A371 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 21, 2012 Mr. David A. Heacock Dominion Energy Kewaunee, Inc.

Innsbrook Technical Center SOOO Dominion Blvd.

Glen Allen, VA 23060-6711

SUBJECT:

KEWAUNEE POWER STATION - SUSPENSION OF REVIEW EFFORT RELATED TO REQUEST FOR REVIEW OF REACTOR VESSEL INTERNAL COMPONENTS INSPECTION PLAN (TAC NO. ME7727)

Dear Mr. Heacock:

By letter dated December 12, 2011, Dominion Energy Kewaunee, Inc. (DEK, the licensee),

submitted an inspection plan (the Inspection Plan) for the reactor vessel internals (RVI) components at Kewaunee Power Station (KPS). Pursuant to the license renewal commitments items 1 and 2 in USAR, Chapter 1S, Table 1S.7-1, "License Renewal Commitments," as reproduced from Appendix A of NUREG-19S8, "Safety Evaluation Report Related to the Kewaunee Power Station," dated January 2011, the licensee requested that the staff review and approve the Inspection Plan.

By letter dated November 2, 2012, pursuant to Title 10, Code Federal Regulation, Part SO.82(a)(1 )(i), the licensee submitted a letter to the NRC stating its decision to permanently cease power operation of KPS. The license letter further stated that they expected operations to cease in the second quarter of 2013, with a specific date to be determined after the completion of a grid stability review by the Midwest Independent Transmission System Operator, Inc. (MISO).

Upon completion of the MISO review, they stated their intention to provide a specific date for permanent cessation of operations to fulfill requirements for a Certification of permanent cessation of operations, as expressed in 10 CFR S0.4(b)(8).

Based on this recent development, the NRC has decided to suspend the review of the licensee's December 12, 2011, submittal because the proposed Inspection Plan is no longer applicable for the reactor vessel that is scheduled to be decommissioned. If this situation should change in the future, NRC would restart this review under a new TAC.

D. Heacock -2 If you should have any questions on this matter, please contact me at 301-415-3079.

Sincerely, Karl Feintuch, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 20-305 and 50-305 cc: Distribution via ListServ

D. Heacock - 2 If you should have any questions on this matter, please contact me at 301-415-3079.

. . . ~

Sincerely, IRAJ Karl Feintuch, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 20-305 50-305 cc: Distribution via ListServ DISTRIBUTION:

Public LPL3-1 r/f RidsRgn3Mailcenter Resource RidsNrrDeEVIB Resource RidsNrrDorlLpl3-1 Resource RidsOgcRp Resource GCheruvenki, NRRlDE/EVIB RidsAcrsAcnw_MailCTR Resource RidsNrrDeEVIB Resource SKennedy, EDO R-III RidsNrrPMKewaunee Resource RidsNrrDorlDpr Resource ADAMS Accession No.: ML12345A371 OFFICE LPL3-1/PM LPL3-1/LAit LPL3-2/LA DE/EVIB/BC NAME KFeintuch ELee SRohrer SRosenberg DATE 12/11/12 12/11/12 12/17/12 12/17112 OFFICE LPL3-1/BC LPL3-1/PM NAME RCarlson KFeintuch DATE 12/21/12 12/21/12 OFFICIAL RECORD COpy