MONTHYEARML11355A1562011-12-12012 December 2011 Reactor Vessel Internals Inspection Plan Review Request Project stage: Request ML12011A1232012-01-0505 January 2012 NRR E-mail Capture - TAC ME7727 Conference Call Project stage: Other ML12065A0042012-03-0202 March 2012 NRR E-mail Capture - ME7727 - Kewaunee - Reactor Vessel Internals Inspection Plan Review - an Aging Management Program Report Is Needed to Prepare RAI Items Project stage: RAI ML12101A0612012-04-0202 April 2012 Response to Request for Additional Information Reactor Vessel Internals Inspection Plan Review Request Project stage: Response to RAI ML12101A2312012-04-0202 April 2012 Response to Request for Additional Information, Reactor Vessel Internals Inspection Plan Review Request Project stage: Response to RAI ML12107A1492012-04-13013 April 2012 NRR E-mail Capture - ME7727 - RAI Clarification Conference Call - Planning for Continuation of the Call Project stage: RAI ML12138A0072012-05-15015 May 2012 NRR E-mail Capture - ME7110 Scvb Draft RAI Set Adoption of TSTF-51 & TSTF- 448, as Part of Chi-over-Q Action Project stage: Draft RAI ML12139A0502012-05-17017 May 2012 NRR E-mail Capture - FW: ME7727 - Kewaunee - Request for Additional Information Rvi Components Inspection Plan Project stage: RAI ML12188A0042012-06-28028 June 2012 Reactor Vessel Internals Inspection Plan Review Request Supplement and Response to Request for Additional Information Project stage: Supplement ML12199A1312012-07-16016 July 2012 NRR E-mail Capture - ME7727 Reactor Vessel Internals Inspection Plan Review - Draft Record of Conference Call on 6/25/2012 Project stage: Draft Other ML12200A0012012-07-17017 July 2012 NRR E-mail Capture - ME7727 - Kewaunee - Request for Additional Information Rvi Components Inspection Plan - Follow-up RAI to Response Provided for RAI Item Cher-006 Project stage: RAI ML12206A0782012-07-23023 July 2012 NRR E-mail Capture - FW: ME7727 - KPS Reactor Vessel Internals Inspection Plan Review - 7/23/2012 Conference Call Record - Discussion of Raii EVIB-Cher-017 Project stage: Other ML12215A3292012-08-0202 August 2012 NRR E-mail Capture - FW: ME7727 - Kewaunee - Draft Request for Additional Information Rvi Components Inspection Plan - RAII-Cher-018 to -020 Project stage: Draft RAI ML12236A0092012-08-21021 August 2012 NRR E-mail Capture - ME7727 - Kewaunee - Draft Request for Additional Information Rvi Components Inspection Plan - RAII-Cher-021 to -022 Project stage: Draft RAI ML12214A5832012-08-23023 August 2012 Exemption Project stage: Other NRC-2012-0197, Exemption2012-08-23023 August 2012 Exemption Project stage: Other ML12268A0262012-09-21021 September 2012 NRR E-mail Capture - ME7727 - Kewaunee Rvi Inspection Plan Review - Enclosed Table for Submitted Information Project stage: Other ML12345A3712012-12-21021 December 2012 Suspension of Review Effort Related to Request for Review of Reactor Vessel Internal Components Inspection Plan Project stage: Approval 2012-05-17
[Table View] |
Text
From:
Feintuch, Karl To:
Feintuch, Karl Cc:
Cheruvenki, Ganesh; Sheng, Simon
Subject:
ME7727 conference call.
Date:
Thursday, January 05, 2012 4:45:00 PM The conference call started at 3:30 PM and concluded at approximately 3:45 PM ET.
Attending were:
For NRC: Karl Feintuch, Ganesh Cheruvenki, Simon Sheng For Kewaunee: Jack Gadzala, Craig Sly, Brian Koehler, Chuck Tomes, Phil Bukes
The discussion centered on the topic below to qualitatively understand the impact of the overall NRC review schedule on licensee activities. The information provides a perspective in establishing work schedules for planning multiple Technical Branch review activities. No decisions were discussed or made.
Agenda Topic:. Be prepared to discuss how the forthcoming outage depends on the timing of the NRC response requested in the application document of December 12, 2011 (ADAMS Accession Number ML11355A156)