| {{#Wiki_filter:UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 January 11, 2013 Tennessee Valley Authority Watts Bar Nuclear Plant, Unit 1 and Sequoyah Nuclear Plant, Units 1 and 2 | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 11, 2013 LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Plant, Unit 1 and Sequoyah Nuclear Plant, Units 1 and 2 |
| | |
| | ==SUBJECT:== |
|
| |
|
| ==SUMMARY== | | ==SUMMARY== |
| OF DECEMBER 13, 2012, MANAGEMENT MEETING WITH TENNESSEE VALLEY AUTHORITY ON THE STATUS OF HYDROLOGY On December 13,2012, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11545 Rockville Pike, Rockville, Maryland. | | OF DECEMBER 13, 2012, MANAGEMENT MEETING WITH TENNESSEE VALLEY AUTHORITY ON THE STATUS OF HYDROLOGY On December 13,2012, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11545 Rockville Pike, Rockville, Maryland. |
| The purpose of the meeting was to discuss: status of TVA efforts to build a new hydrology model based on current hydrology software and the resulted probable maximum flood levels, results of recent analysis of the HESCO temporary flood barrier's vulnerability to postulated barge impact and the simulations to close the traffic access gaps upon notification, update on learning from Fukushima flooding walkdowns, and status of commitments made to the June 25, 2012 Confirmatory Action Letter. An agenda was provided with the meeting notice (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12319A172). | | The purpose of the meeting was to discuss: |
| A list of attendees is enclosed. | | * status of TVA efforts to build a new hydrology model based on current hydrology software and the resulted probable maximum flood levels, |
| Mr. Joseph Shea discussed TVA's slide presentation (ADAMS Accession No. ML12348A208) with support from TVA staff, and answered questions from the NRC staff. TVA plans to submit a supplement to the July 19, 2012, license amendment request (LAR) for Watts Bar Unit 1 to include the main control room emergency ventilation chiller circulating water pump and clarify h,Ow it is credited in the design bases of the plant. However, TVA does not expect, in the near future, to update the July 19, 2013 LAR to include the methodology and the new probable maximum flood level based on the recent analysis discussed and requests the current staff review be continued. | | * results of recent analysis of the HESCO temporary flood barrier's vulnerability to postulated barge impact and the simulations to close the traffic access gaps upon notification, |
| TVA plans to submit a report in January 2013 documenting the results of the recent analyses and exercises, including the following: The results of the HESCO temporary flood barrier gap closing simulation exercises recently performed. River traffic management plan. Results of the recently performed computational fluid dynamics (CFD) computer model simulation of a runaway barge, including the description of the model, velocity profile along the depth of the water, and the choice of projectile shape to represent a barge. | | * update on learning from Fukushima flooding walkdowns, and |
| -2 For future additional CFD modeling considerations, include wind effects and the feasibility of modeling an assumed barge impact on the HESCO barrier and work backward for a credible starting point. No regulatory decisions were made at the meeting. Members of the public were in attendance by telephone. | | * status of commitments made to the June 25, 2012 Confirmatory Action Letter. |
| No public meeting feedback forms were received.
| | An agenda was provided with the meeting notice (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12319A172). A list of attendees is enclosed. |
| Please direct any inquiries to me by phone at 301-415-8480, or e-mail at Andrew.Hon@nrc.gov. Andrew Hon, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-390,50-327, and List of cc w/encl: Distribution via LIST OF A MANAGEMENT MEETING WITH TENNESSEE VALLEY AUTHORITY ON THE LICENSING BASIS FOR FLOODING/HYDROLOGY WAITS BAR NUCLEAR PLANT, UNIT 1 SEQUOYAH NUCLEAR PLANT. UNITS 1 AND 2 THURSDAY, DECEMBER 13, 2012 Tennessee Valley Authority J. Shea J. Williams P. Selman B. Wetzel T. Spink R. Golden Nuclear Regulatory Commission (from NRR unless otherwise noted)
| | Mr. Joseph Shea discussed TVA's slide presentation (ADAMS Accession No. ML12348A208) with support from TVA staff, and answered questions from the NRC staff. TVA plans to submit a supplement to the July 19, 2012, license amendment request (LAR) for Watts Bar Unit 1 to include the main control room emergency ventilation chiller circulating water pump and clarify h,Ow it is credited in the design bases of the plant. However, TVA does not expect, in the near future, to update the July 19, 2013 LAR to include the methodology and the new probable maximum flood level based on the recent analysis discussed and requests the current staff review be continued. TVA plans to submit a report in January 2013 documenting the results of the recent analyses and exercises, including the following: |
| M. Evans P. Hiland J. Monninger M. Cheok R. Taylor E. Miller* A. Hon J. Poole F. Ferrante J. Uribe N. DiFrancesco J. Mitman S. Flanders, NRO C. Cook, NRO S. Shaeffer, RII* R. Monk, RII* T. Nicholson, RES PUBLIC J. Riley* J. Gasper* J. Bellini* *by teleconference Enclosure
| | : 1. The results of the HESCO temporary flood barrier gap closing simulation exercises recently performed. |
| -For future additional CFD modeling considerations, include wind effects and the feasibility of modeling an assumed barge impact on the HESCO barrier and work backward for a credible starting point. No regulatory decisions were made at the meeting. Members of the public were in attendance by telephone.
| | : 2. River traffic management plan. |
| No public meeting feedback forms were received. | | : 3. Results of the recently performed computational fluid dynamics (CFD) computer model simulation of a runaway barge, including the description of the model, velocity profile along the depth of the water, and the choice of projectile shape to represent a barge. |
| | |
| | -2 |
| | : 4. For future additional CFD modeling considerations, include wind effects and the feasibility of modeling an assumed barge impact on the HESCO barrier and work backward for a credible starting point. |
| | No regulatory decisions were made at the meeting. Members of the public were in attendance by telephone. No public meeting feedback forms were received. |
| Please direct any inquiries to me by phone at 301-415-8480, or e-mail at Andrew.Hon@nrc.gov. | | Please direct any inquiries to me by phone at 301-415-8480, or e-mail at Andrew.Hon@nrc.gov. |
| IRA! Andrew Hon, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-390, 50-327, and List of cc w/encl: Distribution via DISTRIBUTION:
| | Andrew Hon, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-390,50-327, and 50-328 |
| PUBLIC RidsNrrDorlLpl2-2 F. Ferrante LPL2-2 rlf M. Evans J. Uribe RidsAcrsAcnw_MailCTR Resource P. Hiland N. DiFrancesco RidsNrrPMSequoyah J. Monninger J. Mitman RidsNrrPMWattsBar1 Resource M. Cheok S. Flanders, NRO RidsNrrLABClayton Resource R. Taylor C. Cook, NRO RidsRgn2MailCenter Resource E. Miller S. Shaeffer, RII RidsOgcRp Resource A. Hon R. Monk, RII RidsNrrOd Resource J. Poole T. Nicholson, RES ADAMS Accession Nos.: Package ML13010A117 Notice ML12319A172 SlidesML12348A208 Summary ML13010A137 i,OFFICE NRRlLPL2-2/PM NRRlLPL2-2/LA(ln NRRlLPL2*2/LA NRRlLPL2*2IBC NRRlLPL2*21PM II NAME AHon FKeith BClayton JQuichocho AHon II DATE 1110/13 1/10/13 1/10/13 1/11/13 1/11113 OFFICIAL RECORD COPY}}
| | |
| | ==Enclosure:== |
| | |
| | List of Attendees cc w/encl: Distribution via Listserv |
| | |
| | LIST OF AITENDEES MANAGEMENT MEETING WITH TENNESSEE VALLEY AUTHORITY ON THE LICENSING BASIS FOR FLOODING/HYDROLOGY WAITS BAR NUCLEAR PLANT, UNIT 1 SEQUOYAH NUCLEAR PLANT. UNITS 1 AND 2 THURSDAY, DECEMBER 13, 2012 Tennessee Valley Authority J. Shea J. Williams P. Selman B. Wetzel T. Spink R. Golden Nuclear Regulatory Commission (from NRR unless otherwise noted) |
| | M. Evans P. Hiland J. Monninger M. Cheok R. Taylor E. Miller* |
| | A. Hon J. Poole F. Ferrante J. Uribe N. DiFrancesco J. Mitman S. Flanders, NRO C. Cook, NRO S. Shaeffer, RII* R. Monk, RII* |
| | T. Nicholson, RES PUBLIC J. Riley* J. Gasper* |
| | J. Bellini* |
| | *by teleconference Enclosure |
| | |
| | Package ML13010A117 Notice ML12319A172 SlidesML12348A208 Summary ML13010A137 i,OFFICE NRRlLPL2-2/PM NRRlLPL2-2/LA(ln NRRlLPL2*2/LA NRRlLPL2*2IBC NRRlLPL2*21PM II NAME AHon FKeith BClayton JQuichocho AHon II DATE 1110/13 1/10/13 1/10/13 1/11/13 1/11113}} |
Letter Sequence Request |
---|
|
|
MONTHYEARML1207501092012-03-15015 March 2012 Notice of Meeting with Tennessee Valley Authority to Discuss Pre-submittal Planning for Licensing Basis Change Regarding Hydrology for Watts Bar Nuclear Plant, Unit 1 Project stage: Request ML12097A3122012-03-29029 March 2012 3/29/2012 Meeting Slides - Pre-Submittal Meeting Regarding Watts Bar Unit 1 Hydrology Licensing Basis Change Project stage: Meeting ML12097A3062012-04-11011 April 2012 3/29/2012 Summary of Pre-Application Meeting with Tennessee Valley Authority on Changing the Licensing Basis for Hydrologic Engineering Project stage: Meeting ML12236A1672012-07-19019 July 2012 Application to Revise Watts Bar Nuclear Plant, Unit 1 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01) Project stage: Request ML12226A5612012-08-10010 August 2012 Application to Revise Sequoyah Nuclear Plant Units I and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (SQN-TS-12-02) Project stage: Request ML12226A5622012-08-10010 August 2012 Enclosure 1, Evaluation of Proposed Changes Attachment 1 Proposed SQN Units 1 and 2 UFSAR Text Changes (Markups), Page 2.4-1 Through 2.4-41 Project stage: Request ML12226A5632012-08-10010 August 2012 Enclosure 1, Evaluation of Proposed Changes Attachment 1 Proposed SQN Units 1 and 2 UFSAR Text Changes (Markups), Page 2.4-42 Through Enclosure 2 Project stage: Request ML12276A3752012-10-0101 October 2012 Notification of Completion of Review of Updated Hydrologic Analysis Results for Impact on Watts Bar Nuclear Plant (WBN) Units 1 and 2 Final Environmental Statements Project stage: Other ML12292A3962012-10-19019 October 2012 Forthcoming Meeting with Tennessee Valley Authority Regarding Hydrology Issues Project stage: Request ML12319A1722012-11-14014 November 2012 Meeting Notice with Tennessee Valley Authority to Discuss Hydrology Issues at Watts Bar Nuclear Plant, Unit 1 Project stage: Request ML12348A2082012-12-13013 December 2012 Meeting Slides Re TVA Hydrology Update Slides Project stage: Request ML13010A1372013-01-11011 January 2013 Summary of Meeting with TVA Regarding Hydrology Updates Project stage: Request ML13037A3262013-01-31031 January 2013 Submittal Date for Supplement to Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis (WBN-UFSAR-12-01) Project stage: Supplement CNL-14-026, Transmittal of Supplemental Clarification Information for the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01)2014-02-28028 February 2014 Transmittal of Supplemental Clarification Information for the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, TAC No. ME8200 (WBN-UFSAR-12-01) Project stage: Supplement 2012-03-29
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24292A1832024-10-30030 October 2024 Summary of Meeting with Tennessee Valley Authority, October 16, 2024, to Discuss Proposed License Amendment Regarding Implementation of an Online Monitoring Methodology ML24269A0062024-10-0303 October 2024 Correction to Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the TVA Nuclear Quality Assurance Plan ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24228A2652024-08-20020 August 2024 Summary of Public Pre-Submittal Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant and Watts Bar Nuclear Plant LAR Related to TS 3.5.2. ECCS - Operating ML24221A0132024-08-19019 August 2024 July 10, 2024, Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24218A2182024-08-15015 August 2024 Summary of July 16, 2024, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Sequoyah Nuclear Plant LAR Related to Containment Penetrations and Fuel Handling ML24173A2122024-06-27027 June 2024 Summary of Public Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding Adoption of TSTF-276-A, Revision 2 to Clarify Requirements for Diesel Generator Testing ML24158A3002024-06-11011 June 2024 Summary of May 6, 2024, Public Meeting with Tennessee Valley Authority to Discuss the Potential for a License Amendment Request Regarding the Control Room Envelope and Selective Use of an Alternative Source Term ML24136A2242024-05-15015 May 2024 1B EDG NRC Regulatory Conference Meeting Summary May 2, 2024 ML24102A1212024-04-18018 April 2024 Summary of Conference Call with Tennessee Valley Authority Regarding Sequoyah Nuclear Plant, Unit 1 Spring 2024 Steam Generator Tube Inspections ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24082A2532024-03-26026 March 2024 Summary of March 18, 2024, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Fuel Handling and Fuel Decay Time ML24057A3792024-03-0808 March 2024 Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Fuel Handling and Fuel Decay Time ML24065A0262024-03-0101 March 2024 LAR Pre-Application Meeting TS 3.9.8 (Decay Time) and FHA Dose Analysis Meteorological Monitoring and Dispersion Modeling Topics ML24057A0582024-02-27027 February 2024 Summary of February 15, 2024, Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML24044A0372024-02-15015 February 2024 February 8, 2024, Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future License Amendment Request Related to Technical Specification Surveillance Requirement 3.1.1.8 ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23304A0682023-11-0606 November 2023 Summary of October 24, 2023, Public Mtg W/Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, and Sequoyah Nuclear Plant, Units 1 and 2 to Revise Function 5, Turbine Trip and F ML23265A1512023-09-28028 September 2023 Summary of September 12, 2023, Partially Closed Meeting with Tennessee Valley Authority to Discuss Proposed License Amendment Request ML23198A3102023-07-20020 July 2023 July 10, 2023, Summary of Public Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML23068A1532023-03-16016 March 2023 Summary of February 22, 2023, Meeting with Tennessee Valley Authority Regarding Proposed License Amendment Request to Increase Allowable Number of Tritium Producing Burnable Absorber Rods at Watts Bar Nuclear Plant, Units 1 and 2 ML23055A4562023-03-0909 March 2023 Summary of February 15, 2023, Public Meeting with Tennessee Valley Authority Regarding Proposed Expedited License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2 ML22329A1382022-12-0505 December 2022 Summary of Meeting with Tennessee Valley Authority Related to Planned Alternative Request WBN-2-ISI-01 for Watts Bar Nuclear Plant, Unit 2 ML22312A3522022-12-0101 December 2022 – Revised - Summary of Regulatory Audit for Alternative Request RV-02 ML22207B8302022-07-28028 July 2022 Summary of July 20, 2022, Observation Public Meeting with the Tennessee Valley Authority to Discuss Planned Alternative Request RP-12 to ASME OM Code Testing for the 1B-B Centrifugal Charging Pump at Sequoyah Nuclear Plant, Unit 1 ML22168A1642022-06-27027 June 2022 Summary of June 9, 2022, Meeting with TVA Regarding a Proposed License Amendment Request Related to Low Temperature Overpressure System and Cold Overpressure Mitigation System for Sequoyah and Watts Bar Nuclear Plants ML22109A0042022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Alternative Request Related to Testing of the Motor-Driven Auxiliary Feedwater Pumps at Sequoyah and Watts Bar Nuclear Plants ML22104A2252022-04-20020 April 2022 Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Exemption Request for Watts Bar Nuclear Plant, Unit 2 ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22048B7852022-03-0202 March 2022 Summary of February 16, 2022, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a Request for an Alternative to Requirements for Addressing Pressure Isolation Valve Leakage ML22042B3262022-02-14014 February 2022 Summary of February 8, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed License Amendment Request to Revise the Allowable Value for Trip of Turbine-Driven Main Feedwater Pump at Watts Bar Nuclear Plant, Unit 1 ML22025A3112022-02-0909 February 2022 Summary of January 19, 2022, Meeting with Tennessee Valley Authority Regarding a Proposed Schedule for Development of a License Amendment Request for Increased Tritium Production ML21349A3642022-01-0404 January 2022 Summary of December 14, 2021, Teleconference with Tennessee Valley Authority Regarding a Proposed Change to the Capsule Withdrawal Schedule for Watts Bar Nuclear Plant, Unit 2 ML21313A3482021-11-18018 November 2021 Summary of Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a License Amendment Request Regarding Seismic and Fire Probabilistic Risk Assessment (PRA) Modifications to 10 CFR 50.69 ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21279A0902021-11-0303 November 2021 Summary of Conference Calls Regarding the Fall 2021, Mid-Cycle Steam Generator Tube Inspections ML21265A5142021-10-12012 October 2021 Summary of September 15, 2021, Public Preapplication Meeting with Tennessee Valley Authority Regarding a Future Submittal of a License Amendment Request Regarding Elimination of the High Negative Flux Rate Trip ML21253A0872021-09-15015 September 2021 Summary of August 19, 2021, Partially Closed Meeting with Tennessee Valley Authority to Discuss Mid-Cycle Outage Contingencies for Watts Bar Nuclear Plant, Unit 2 ML21245A4252021-09-15015 September 2021 Summary of August 19, 2021, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to the Watts Bar Nuclear Plant, Units 1 and 2 ML21218A1472021-08-11011 August 2021 August 5, 2021 N-769 Relief Pre-Submittal Meeting Summary ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21152A1252021-06-0202 June 2021 Summary of Verbal Authorization of Alternative Request RP-10 for the 1B-B Motor Driven Auxiliary Feedwater Pump ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML21120A2192021-05-0404 May 2021 April 28,2021, Summary of Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Units 1 and 2, to Remove from Technical Specifications Redundant Units of Measurement for Control ML21112A3262021-04-30030 April 2021 Summary of April 21, 2021, Teleconference with Tennessee Valley Authority to Discuss a Planned License Amendment Request for Sequoyah Nuclear Plant, Units 1 and 2 ML21099A2072021-04-13013 April 2021 Summary of April 7, 2021, Meeting with Tennessee Valley Authority Related to a Planned Relief Request from ASME Code Testing Requirements ML21067A2132021-03-23023 March 2021 Summary of March 2, 2021, Teleconference with Tennessee Valley Authority to Discuss a Planned Alternative Request ML21060B0532021-03-0303 March 2021 Summary of February 11, 2021, Meeting with Tennessee Valley Authority Related to a Planned License Amendment Request for Watts Bar Nuclear Plant, Unit 2, to Apply a Temperature Adjusted Steam Generator Tube Flaw Growth Rate Methodology ML21033A5952021-02-23023 February 2021 Summary of Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Requests Related to the Watts Bar Nuclear Plant, Unit 2 Steam Generator Replacement 2024-09-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 11, 2013 LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Plant, Unit 1 and Sequoyah Nuclear Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF DECEMBER 13, 2012, MANAGEMENT MEETING WITH TENNESSEE VALLEY AUTHORITY ON THE STATUS OF HYDROLOGY On December 13,2012, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of the Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11545 Rockville Pike, Rockville, Maryland.
The purpose of the meeting was to discuss:
- status of TVA efforts to build a new hydrology model based on current hydrology software and the resulted probable maximum flood levels,
- results of recent analysis of the HESCO temporary flood barrier's vulnerability to postulated barge impact and the simulations to close the traffic access gaps upon notification,
- update on learning from Fukushima flooding walkdowns, and
- status of commitments made to the June 25, 2012 Confirmatory Action Letter.
An agenda was provided with the meeting notice (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12319A172). A list of attendees is enclosed.
Mr. Joseph Shea discussed TVA's slide presentation (ADAMS Accession No. ML12348A208) with support from TVA staff, and answered questions from the NRC staff. TVA plans to submit a supplement to the July 19, 2012, license amendment request (LAR) for Watts Bar Unit 1 to include the main control room emergency ventilation chiller circulating water pump and clarify h,Ow it is credited in the design bases of the plant. However, TVA does not expect, in the near future, to update the July 19, 2013 LAR to include the methodology and the new probable maximum flood level based on the recent analysis discussed and requests the current staff review be continued. TVA plans to submit a report in January 2013 documenting the results of the recent analyses and exercises, including the following:
- 1. The results of the HESCO temporary flood barrier gap closing simulation exercises recently performed.
- 2. River traffic management plan.
- 3. Results of the recently performed computational fluid dynamics (CFD) computer model simulation of a runaway barge, including the description of the model, velocity profile along the depth of the water, and the choice of projectile shape to represent a barge.
-2
- 4. For future additional CFD modeling considerations, include wind effects and the feasibility of modeling an assumed barge impact on the HESCO barrier and work backward for a credible starting point.
No regulatory decisions were made at the meeting. Members of the public were in attendance by telephone. No public meeting feedback forms were received.
Please direct any inquiries to me by phone at 301-415-8480, or e-mail at Andrew.Hon@nrc.gov.
Andrew Hon, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-390,50-327, and 50-328
Enclosure:
List of Attendees cc w/encl: Distribution via Listserv
LIST OF AITENDEES MANAGEMENT MEETING WITH TENNESSEE VALLEY AUTHORITY ON THE LICENSING BASIS FOR FLOODING/HYDROLOGY WAITS BAR NUCLEAR PLANT, UNIT 1 SEQUOYAH NUCLEAR PLANT. UNITS 1 AND 2 THURSDAY, DECEMBER 13, 2012 Tennessee Valley Authority J. Shea J. Williams P. Selman B. Wetzel T. Spink R. Golden Nuclear Regulatory Commission (from NRR unless otherwise noted)
M. Evans P. Hiland J. Monninger M. Cheok R. Taylor E. Miller*
A. Hon J. Poole F. Ferrante J. Uribe N. DiFrancesco J. Mitman S. Flanders, NRO C. Cook, NRO S. Shaeffer, RII* R. Monk, RII*
T. Nicholson, RES PUBLIC J. Riley* J. Gasper*
J. Bellini*
- by teleconference Enclosure
Package ML13010A117 Notice ML12319A172 SlidesML12348A208 Summary ML13010A137 i,OFFICE NRRlLPL2-2/PM NRRlLPL2-2/LA(ln NRRlLPL2*2/LA NRRlLPL2*2IBC NRRlLPL2*21PM II NAME AHon FKeith BClayton JQuichocho AHon II DATE 1110/13 1/10/13 1/10/13 1/11/13 1/11113