=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:Dominion Resources Services, Inc. | ||
Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 | Innsbrook Technical Center 5000 Dominion Boulevard, 2SE, Glen Allen, VA 23060 May 2, 2016 | ||
'*' U. S. Nuclear Regulatory Commission Serial No.: 16-023 Attention: Document Control Desk NLOS/MLW: R4 One White Flint North Docket Nos.: 50-336/423 11555 Rockville Pike 50-338/339 Rockville, MD 20852-2738 50-280/281 License Nos.: DPR-65 NPF-49 NPF-4/7 DPR-32/37 DOMINION NUCLEAR CONNECTICUT, INC. (DNC) | |||
VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION) | |||
MILLSTONE POWER STATION UNITS 2 AND 3 NORTH ANNA POWER STATION UNITS 1AND2 SURRY POWER STATION UNITS 1 AND 2 NRC REGULATORY ISSUE | MILLSTONE POWER STATION UNITS 2 AND 3 NORTH ANNA POWER STATION UNITS 1AND2 SURRY POWER STATION UNITS 1 AND 2 NRC REGULATORY ISSUE | ||
==SUMMARY== | ==SUMMARY== | ||
2015-16 PLANNED LICENSING ACTION SUBMITTALS | 2015-16 PLANNED LICENSING ACTION SUBMITTALS In response to Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-16, Revision 1, "Planned Licensing Actions Submittals for All Power Reactor Licensees," Attachments 1 through 3 provide the requested information on proposed planned licensing action submittals for the next three calendar years for Millstone (MPS), North Anna (NAPS) and Surry (SPS) Power Stations. Neither DNC nor Dominion currently have power uprates planned in the nextfive years. | ||
Neither DNC nor Dominion currently have power uprates planned in the nextfive years. The information in the attachments is being voluntarily provided to assist the NRC in planning for the necessary resources during the budget process. Alterations to the planned licensing actions in Attachments 1 through 3 will be communicated to the appropriate NRC Project Managers as they occur. If you have any questions concerning this information, please contact Michael Whitlock at (804) 273-3123. | The information in the attachments is being voluntarily provided to assist the NRC in planning for the necessary resources during the budget process. | ||
Sincerely, Mark D. Sartain Vice President | Alterations to the planned licensing actions in Attachments 1 through 3 will be communicated to the appropriate NRC Project Managers as they occur. | ||
-Nuclear Engineering Dominion Nuclear Connecticut, Inc. Virginia Electric and Power Company Attachment 1: Table of Estimated Licensing Actions for Millstone Power Station Attachment 2: Table of Estimated Licensing Actions for North Anna Power Station Attachment 3: Table of Estimated Licensing Actions for Surry Power Station Commitments made in this letter: None cc: U. S. Nuclear Regulatory Commission Region I 2100 Renaissance Blvd. Suite 100 King of Prussia, 19406-2713 U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 R. V. Guzman U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 K. R. Cotton-Gross U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station NRC Senior Resident Inspector North Anna Power Station NRC Senior Resident Inspector Surry Power Station Serial No. 16-023 Docket Nos.: 50-336/423 | If you have any questions concerning this information, please contact Michael Whitlock at (804) 273-3123. | ||
*./ ATTACHMENT 1 | Sincerely, Mark D. Sartain Vice President - Nuclear Engineering Dominion Nuclear Connecticut, Inc. | ||
Table of Estimated Licensing Actions Millstone Power Station Units 2 and 3 Docket Nos: 50-336/50-423 TSTF Number , If Projected Submittal Outage Outage Related | Virginia Electric and Power Company Attachment 1: Table of Estimated Licensing Actions for Millstone Power Station Attachment 2: Table of Estimated Licensing Actions for North Anna Power Station Attachment 3: Table of Estimated Licensing Actions for Surry Power Station Commitments made in this letter: None | ||
Licensing Action Type Licensing Action Description/Title make the lnfonnallon C-ta any Date Related? Date public? | |||
Table of Estimated Licensing Actions North Anna Power Station Unit 1 and Unit 2 Docket Nos: 50-338/339 | Serial No. 16-023 Docket Nos.: 50-336/423 50-338/339 50-280/281 Page 2 of 2 cc: U. S. Nuclear Regulatory Commission Region I 2100 Renaissance Blvd. | ||
Suite 100 King of Prussia, Penn~ylvania 19406-2713 U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 R. V. Guzman U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 K. R. Cotton-Gross U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station NRC Senior Resident Inspector North Anna Power Station NRC Senior Resident Inspector Surry Power Station | |||
Surry Power Station Units 1 and 2 Surry Power Station Units 1 and 2 | Serial No. 16-023 Docket Nos.: 50-336/423 | ||
*./ | |||
ATTACHMENT 1 Table of Estimated Licensing Actions for Millstone Power Station MILLSTONE POWER STATION - UNITS 2 & 3 DOMINION NUCLEA.R CONNECTICUT, INC. | |||
Table of Estimated Licensing Actions Millstone Power Station Units 2 and 3 Docket Nos : 50-336/50-423 Can the NRC staff TSTF Number, If Projected Submittal Outage Outage Related Proprietary Plant Name and Unit Number(*) Licensing Action Type Licensing Action Description/Title make the lnfonnallon C-ta any Date Related? Date lnfonnatlon public? | |||
Millstone Power Station Unit 2 and 3 Relief Request Relief Requests RR-04-23 and IR-03-28 to use UT in lieu of RT. 04/2016 Yes 102017 Yes No Millstone Power Station Unit 2 License Amendment LAR for Large Break LOCA Reanalysis 05/2016 Yes 402016 Yes Yes Millstone Power Station Unit 3 Exemptions Exemption for AXIOM Lead Test Assembly 07/2016 Yes 402017 Yes No LAR to Revise MPS2 TS 3.8.1.1 to add a required ACTION that Millstone Power Station Unit 2 License Amendment 09/2016 Yes 402017 Yes No would reduce shutdown risk at MPS3. (RSST) | |||
LAR to Add New TS 3/4.7.15 for Main Feedwater Isolation , | |||
Millstone Power Station Unit 3 License Amendment 12/2016 No Yes No Regulating, and Bypass Valves Extension of Type A ILRT Interval to 15 Years. Revise TS for Millstone Power Station Unit 2 License Amendment 10/2017 Yes 402018 Yes No Containment Leakage Rate Testing Requirements Millstone Power Station Units 2 and 3 License Amendment LAR for Electrical Cross-Tie Connection 2017 No Yes No LAR for Resolution of Open Phase Condition Bulletin 2012 Millstone Power Station Unit 3 License Amendment TSTF-556 2017 No Yes No Design Vulnerability in electric power system LAR to Revise SR 4.6.2.1.2.b to Increase RBCCW Minimum Millstone Power Station Unit 2 License Amendment 2017 No Yes No Flow Rate to CAR Coolers from >500 gpm to >1700 gpm Millstone Power Station Unit 3 License Amendment TSTF-374 Modify TS requirements for EDG fuel oil testing 2017 No Yes No Diesel Generator Frequency and Voltage Surveillance Millstone Power Station Units 2 and 3 License Amendment TSTF-552 2018 No Yes No Requirements. WCAP-17308-NP . | |||
Measurement Uncertainty Recapture (MUR) - Recovery of a Millstone Power Station Unit 2 License Amendment portion of the 2% measurements Uncertainty Required by 2018 No Yes No Rono 1~1;nnc Delete Item 8 (Containment Water Level Narrow Range) from Millstone Power Station Un it 2 License Amendment 2018 No Yes No Table 3.3-11 of TS 3.3.3.8 Extension of Type A ILRT Interval to 15 Years. Revise TS for Millstone Power Station Unit 3 License Amendment 10/2019 Yes 402020 Yes No Containment Leakage Rate Testing Requirements Page 1of1 | |||
Serial No. 16-023 Docket Nos.: 50-338/339 ATTACHMENT 2 Table of Estimated Licensing Actions for North Anna Power Station NORTH ANNA POWER STATION-UNITS 1 & 2 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION) | |||
Table of Estimated Licensing Actions North Anna Power Station Unit 1 and Unit 2 Docket Nos: 50-338/339 Can the NRC staff Licensing Action Projected Submittal Outage Outage Proprietary Plant Name and Unit Number(s) TSTF Number, If any Licensing Action Description/Title make the lnfonnatlon Comments Type Date Related? Related Data Information public? Yes or No EAL Revision - Fuel clad degradation and North Anna Power Station, Units 1 and 2 License Amendment 07/2016 No Yes No fuel clad barrier loss North Anna Power Station , Units 1 and 2 License Amendment ISFSI License Renewal (for Pad 1 TN-32) 05/2016 No Yes No Fuel Independent SBLOCA Analysis (TS Supports compliance North Anna Power Station, Units 1 and 2 License Amendment 08/2016 No Yes Yes Reference Change/COLR Mod) with 10CFR50.46(c) | |||
Revision to Spent Fuel Criticality Analysis North Anna Power Station, Units 1 and 2 License Amendment - updated fuel design w/ 5% fuel 09/2016 No Ye s Yes enrichment LAR for PAD 5.0 and FSLOCA [Large Supports compliance North Anna Power Station, Units 1 and 2 License Amendment 2018 No Yes Yes Break] with 10CFR50.46(c) | |||
Adds Open Phase Condition (OPC) 2nd Otr 2018 Isolation System operability and (NAPS1) | |||
North Anna Power Station, Units 1 and 2 License Amendment 01/2017 Yes Yes No surveillance requirements for mitigation of 4th Otr 2020 an OPC (NAPS2) | |||
Revise the Environmental Protection Plan North Anna Power Station , Units 1 and 2 License Amendment 2017 No Yes No to Correct CFR References Revise the surveillance requirements for TS 3.7.10 and 3.7.12 for the PREACS and MCR/ESGR Filters to operate them for greater than or equal to 15 minutes. | |||
North Anna Power Station, Units 1 and 2 License Amendment TSTF-522 Revise TS 5.5.10 to incorporate the 09/2016 No Yes No requirements of Regulatory Guide 1.52, revision 3, which requires In-Place Filter Testing/Laboratory Testing to be extended to 24 months. | |||
Second Period Limited Examination Relief North Anna Power Station , Unit 1 Relief Request 2017 No Yes No Request - N1-14-LMT-002 Request to extend the reactor vessel weld examinations by ten years. The PWR North Anna Power Station, Units 1 and 2 Relief Request Owner's Group analysis by Westinghouse 07/2016 Yes 102018 Yes No has already been started. N1-14-NDE-008 I N2-14-NDE-003 North Anna Unit 1 Fifth Interval ISi North Anna Power Station, Unit 1 Relief Request 2018 Yes 302019 Yes No Program Relief Requests LAR to rely on off-site EMT's rather than North Anna Power Station , Units 1 and 2 License Amendment 2017 No Yes No on-site EMT's LAR to move the Local Emergency North Anna Power Station, Units 1 and 2 License Amendment Operations Facility (LEOF) to an EOF 2017 No Yes No located at Innsbrook Page 1of1 | |||
Serial No. 16-023 Docket Nos. : 50-280/281 ATTACHMENT 3 Table of Estimated Licensing Actions for Surry Power Station SURRY POWER STATION- UNITS 1 & 2 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION) | |||
Table of Estimated Licensing Actions Surry Power Station Unit 1 and Unit 2 Docket Nos: 50-280/281 Can the NRC staff Projected Submittal Outage Outage Related Proprietary Plant Name and Unit Number(*) Licensing Action Type TSTF Number, If any Licensing Action Description/Title make the Information Comments Date Related? Date Information public? Yea or No Alternate monitoring of rod position with one Surry Power Station Units 1 and 2 License Amendment TSTF-547 inoperable rod position indicator 05/2016 No Yes No Revises Residual Heat Removal (RHR) and Surry Power Station Units 1 and 2 License Amendment Component Cooling (CC) Systems' TS 05/2016 No Yes No Requirements and adds an RHR Surveillance Revises the Fuel Cladding Barrier Degradation and Surry Power Station Units 1 and 2 License Amendment Loss Emergency Action Level Thresholds 06/2016 No Yes No Extends the Charging Pump Service Water and Surry Power Station Units 1 and 2 License Amendment MCR/ESGR AC Subsystems Flowpath Allowed 05/2016 No Yes No Outage Time from 24 to 72 hrs Expands the Primary Grade (PG) Water Lockout TS Surry Power Station Units 1 and 2 License Amendment Requirements 05/2016 No Yes No Extends the Emergency Service Water Pump Surry Power Station Units 1 and 2 License Amendment Allowed Outage Time from 7 to 14 days 06/2016 No Yes No Adds Open Phase Condition (OPC) Isolation Surry Power Station Units 1 and 2 License Amendment System operability and surveillance requirements 01 /2017 Yes 2nd Qtr 2018 (SPS1 ) Yes No for mitigation of an OPC 4th Qtr 2018 (S PS2) | |||
Revises RCS Activity Limits and Dose Surry Power Station Units 1 and 2 License Amendment Consequences for FHA, SGTR, MSLB and LRA 06/2016 No Yes No TS change to extend ACT to permit replacement of Surry Power Station Units 1 and 2 License Amendment the Reserve Statio n Service Transformer C and and 03/2017 Yes Yes No cable/bus replacement 3rd Qtr 2018 ISi Alternative Request to permit use of CFRP Surry Power Station Units 1 and 2 Relief Request application in buried safety related SW Piping as 07/2016 Yes Yes No pressure boundary 2nd Qtr 2017 Administrative change deletes temporary/one-time Surry Power Station Units 1 and 2 License Amendment TS AOTs/Requirements for previously completed 08/2016 No Yes No chilled water pipe replacement project, and other Surry Power Station Units 1 and 2 License Amendment Revised UFSAR Dose Analyses 09/2016 No Yes No Surry Power Station Units 1 and 2 License Amendment Fuel Independent SBLOCA Analysis 09/2016 No Yes Yes Topical Report DOM-NAF-2 Appendix E (AGORA Surry Power Station Units 1 and 2 License Amendment CHF Correlation) 12/2016 No Yes TBD Surry Power Station Units 1 and 2 License Amendment RLBLOCA for Vendor Qualification Program 04/2017 No Yes TBD Surry Power Station Units 1 and 2 License Amendment AGORA Vendor Qualification Program Submittal 04/201 7 No Yes TBD Surry Power Station Units 1 and 2 License Amendment Spent Fuel Poot Criticality Analysis 2018 No Yes Yes Surry Power Station Units 1 and 2 License Amendment Full Spectrum LOCA Analysis 2018 No Yes Yes Relocation of Leak Testing of Miscellaneous Surry Power Station Units 1 and 2 License Amendment Rad ioactive Materail s to TRM 2018 No Yes No LAR to rely on off-site EMrs rather than on-site Surry Power Station Units 1 and 2 License Amendment EMrs 2017 No Yes No LAR to move the Local Emergency Operations Surry Power Station Units 1 and 2 License Amendment Facility (LEOF) to an EOF located at Innsbrook 2017 No Yes No Page 1of1}} |
Latest revision as of 19:20, 30 October 2019
ML16130A564 | |
Person / Time | |
---|---|
Site: | Millstone, Surry, North Anna |
Issue date: | 05/02/2016 |
From: | Mark D. Sartain Dominion Nuclear Connecticut, Virginia Electric & Power Co (VEPCO) |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
RIS-15-016, SN 16-023 | |
Download: ML16130A564 (8) | |
Text
Dominion Resources Services, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard, 2SE, Glen Allen, VA 23060 May 2, 2016
'*' U. S. Nuclear Regulatory Commission Serial No.: 16-023 Attention: Document Control Desk NLOS/MLW: R4 One White Flint North Docket Nos.: 50-336/423 11555 Rockville Pike 50-338/339 Rockville, MD 20852-2738 50-280/281 License Nos.: DPR-65 NPF-49 NPF-4/7 DPR-32/37 DOMINION NUCLEAR CONNECTICUT, INC. (DNC)
VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
MILLSTONE POWER STATION UNITS 2 AND 3 NORTH ANNA POWER STATION UNITS 1AND2 SURRY POWER STATION UNITS 1 AND 2 NRC REGULATORY ISSUE
SUMMARY
2015-16 PLANNED LICENSING ACTION SUBMITTALS In response to Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-16, Revision 1, "Planned Licensing Actions Submittals for All Power Reactor Licensees," Attachments 1 through 3 provide the requested information on proposed planned licensing action submittals for the next three calendar years for Millstone (MPS), North Anna (NAPS) and Surry (SPS) Power Stations. Neither DNC nor Dominion currently have power uprates planned in the nextfive years.
The information in the attachments is being voluntarily provided to assist the NRC in planning for the necessary resources during the budget process.
Alterations to the planned licensing actions in Attachments 1 through 3 will be communicated to the appropriate NRC Project Managers as they occur.
If you have any questions concerning this information, please contact Michael Whitlock at (804) 273-3123.
Sincerely, Mark D. Sartain Vice President - Nuclear Engineering Dominion Nuclear Connecticut, Inc.
Virginia Electric and Power Company Attachment 1: Table of Estimated Licensing Actions for Millstone Power Station Attachment 2: Table of Estimated Licensing Actions for North Anna Power Station Attachment 3: Table of Estimated Licensing Actions for Surry Power Station Commitments made in this letter: None
Serial No.16-023 Docket Nos.: 50-336/423 50-338/339 50-280/281 Page 2 of 2 cc: U. S. Nuclear Regulatory Commission Region I 2100 Renaissance Blvd.
Suite 100 King of Prussia, Penn~ylvania 19406-2713 U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 R. V. Guzman U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 K. R. Cotton-Gross U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station NRC Senior Resident Inspector North Anna Power Station NRC Senior Resident Inspector Surry Power Station
Serial No.16-023 Docket Nos.: 50-336/423
- ./
ATTACHMENT 1 Table of Estimated Licensing Actions for Millstone Power Station MILLSTONE POWER STATION - UNITS 2 & 3 DOMINION NUCLEA.R CONNECTICUT, INC.
Table of Estimated Licensing Actions Millstone Power Station Units 2 and 3 Docket Nos : 50-336/50-423 Can the NRC staff TSTF Number, If Projected Submittal Outage Outage Related Proprietary Plant Name and Unit Number(*) Licensing Action Type Licensing Action Description/Title make the lnfonnallon C-ta any Date Related? Date lnfonnatlon public?
Millstone Power Station Unit 2 and 3 Relief Request Relief Requests RR-04-23 and IR-03-28 to use UT in lieu of RT. 04/2016 Yes 102017 Yes No Millstone Power Station Unit 2 License Amendment LAR for Large Break LOCA Reanalysis 05/2016 Yes 402016 Yes Yes Millstone Power Station Unit 3 Exemptions Exemption for AXIOM Lead Test Assembly 07/2016 Yes 402017 Yes No LAR to Revise MPS2 TS 3.8.1.1 to add a required ACTION that Millstone Power Station Unit 2 License Amendment 09/2016 Yes 402017 Yes No would reduce shutdown risk at MPS3. (RSST)
LAR to Add New TS 3/4.7.15 for Main Feedwater Isolation ,
Millstone Power Station Unit 3 License Amendment 12/2016 No Yes No Regulating, and Bypass Valves Extension of Type A ILRT Interval to 15 Years. Revise TS for Millstone Power Station Unit 2 License Amendment 10/2017 Yes 402018 Yes No Containment Leakage Rate Testing Requirements Millstone Power Station Units 2 and 3 License Amendment LAR for Electrical Cross-Tie Connection 2017 No Yes No LAR for Resolution of Open Phase Condition Bulletin 2012 Millstone Power Station Unit 3 License Amendment TSTF-556 2017 No Yes No Design Vulnerability in electric power system LAR to Revise SR 4.6.2.1.2.b to Increase RBCCW Minimum Millstone Power Station Unit 2 License Amendment 2017 No Yes No Flow Rate to CAR Coolers from >500 gpm to >1700 gpm Millstone Power Station Unit 3 License Amendment TSTF-374 Modify TS requirements for EDG fuel oil testing 2017 No Yes No Diesel Generator Frequency and Voltage Surveillance Millstone Power Station Units 2 and 3 License Amendment TSTF-552 2018 No Yes No Requirements. WCAP-17308-NP .
Measurement Uncertainty Recapture (MUR) - Recovery of a Millstone Power Station Unit 2 License Amendment portion of the 2% measurements Uncertainty Required by 2018 No Yes No Rono 1~1;nnc Delete Item 8 (Containment Water Level Narrow Range) from Millstone Power Station Un it 2 License Amendment 2018 No Yes No Table 3.3-11 of TS 3.3.3.8 Extension of Type A ILRT Interval to 15 Years. Revise TS for Millstone Power Station Unit 3 License Amendment 10/2019 Yes 402020 Yes No Containment Leakage Rate Testing Requirements Page 1of1
Serial No.16-023 Docket Nos.: 50-338/339 ATTACHMENT 2 Table of Estimated Licensing Actions for North Anna Power Station NORTH ANNA POWER STATION-UNITS 1 & 2 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
Table of Estimated Licensing Actions North Anna Power Station Unit 1 and Unit 2 Docket Nos: 50-338/339 Can the NRC staff Licensing Action Projected Submittal Outage Outage Proprietary Plant Name and Unit Number(s) TSTF Number, If any Licensing Action Description/Title make the lnfonnatlon Comments Type Date Related? Related Data Information public? Yes or No EAL Revision - Fuel clad degradation and North Anna Power Station, Units 1 and 2 License Amendment 07/2016 No Yes No fuel clad barrier loss North Anna Power Station , Units 1 and 2 License Amendment ISFSI License Renewal (for Pad 1 TN-32) 05/2016 No Yes No Fuel Independent SBLOCA Analysis (TS Supports compliance North Anna Power Station, Units 1 and 2 License Amendment 08/2016 No Yes Yes Reference Change/COLR Mod) with 10CFR50.46(c)
Revision to Spent Fuel Criticality Analysis North Anna Power Station, Units 1 and 2 License Amendment - updated fuel design w/ 5% fuel 09/2016 No Ye s Yes enrichment LAR for PAD 5.0 and FSLOCA [Large Supports compliance North Anna Power Station, Units 1 and 2 License Amendment 2018 No Yes Yes Break] with 10CFR50.46(c)
Adds Open Phase Condition (OPC) 2nd Otr 2018 Isolation System operability and (NAPS1)
North Anna Power Station, Units 1 and 2 License Amendment 01/2017 Yes Yes No surveillance requirements for mitigation of 4th Otr 2020 an OPC (NAPS2)
Revise the Environmental Protection Plan North Anna Power Station , Units 1 and 2 License Amendment 2017 No Yes No to Correct CFR References Revise the surveillance requirements for TS 3.7.10 and 3.7.12 for the PREACS and MCR/ESGR Filters to operate them for greater than or equal to 15 minutes.
North Anna Power Station, Units 1 and 2 License Amendment TSTF-522 Revise TS 5.5.10 to incorporate the 09/2016 No Yes No requirements of Regulatory Guide 1.52, revision 3, which requires In-Place Filter Testing/Laboratory Testing to be extended to 24 months.
Second Period Limited Examination Relief North Anna Power Station , Unit 1 Relief Request 2017 No Yes No Request - N1-14-LMT-002 Request to extend the reactor vessel weld examinations by ten years. The PWR North Anna Power Station, Units 1 and 2 Relief Request Owner's Group analysis by Westinghouse 07/2016 Yes 102018 Yes No has already been started. N1-14-NDE-008 I N2-14-NDE-003 North Anna Unit 1 Fifth Interval ISi North Anna Power Station, Unit 1 Relief Request 2018 Yes 302019 Yes No Program Relief Requests LAR to rely on off-site EMT's rather than North Anna Power Station , Units 1 and 2 License Amendment 2017 No Yes No on-site EMT's LAR to move the Local Emergency North Anna Power Station, Units 1 and 2 License Amendment Operations Facility (LEOF) to an EOF 2017 No Yes No located at Innsbrook Page 1of1
Serial No.16-023 Docket Nos. : 50-280/281 ATTACHMENT 3 Table of Estimated Licensing Actions for Surry Power Station SURRY POWER STATION- UNITS 1 & 2 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
Table of Estimated Licensing Actions Surry Power Station Unit 1 and Unit 2 Docket Nos: 50-280/281 Can the NRC staff Projected Submittal Outage Outage Related Proprietary Plant Name and Unit Number(*) Licensing Action Type TSTF Number, If any Licensing Action Description/Title make the Information Comments Date Related? Date Information public? Yea or No Alternate monitoring of rod position with one Surry Power Station Units 1 and 2 License Amendment TSTF-547 inoperable rod position indicator 05/2016 No Yes No Revises Residual Heat Removal (RHR) and Surry Power Station Units 1 and 2 License Amendment Component Cooling (CC) Systems' TS 05/2016 No Yes No Requirements and adds an RHR Surveillance Revises the Fuel Cladding Barrier Degradation and Surry Power Station Units 1 and 2 License Amendment Loss Emergency Action Level Thresholds 06/2016 No Yes No Extends the Charging Pump Service Water and Surry Power Station Units 1 and 2 License Amendment MCR/ESGR AC Subsystems Flowpath Allowed 05/2016 No Yes No Outage Time from 24 to 72 hrs Expands the Primary Grade (PG) Water Lockout TS Surry Power Station Units 1 and 2 License Amendment Requirements 05/2016 No Yes No Extends the Emergency Service Water Pump Surry Power Station Units 1 and 2 License Amendment Allowed Outage Time from 7 to 14 days 06/2016 No Yes No Adds Open Phase Condition (OPC) Isolation Surry Power Station Units 1 and 2 License Amendment System operability and surveillance requirements 01 /2017 Yes 2nd Qtr 2018 (SPS1 ) Yes No for mitigation of an OPC 4th Qtr 2018 (S PS2)
Revises RCS Activity Limits and Dose Surry Power Station Units 1 and 2 License Amendment Consequences for FHA, SGTR, MSLB and LRA 06/2016 No Yes No TS change to extend ACT to permit replacement of Surry Power Station Units 1 and 2 License Amendment the Reserve Statio n Service Transformer C and and 03/2017 Yes Yes No cable/bus replacement 3rd Qtr 2018 ISi Alternative Request to permit use of CFRP Surry Power Station Units 1 and 2 Relief Request application in buried safety related SW Piping as 07/2016 Yes Yes No pressure boundary 2nd Qtr 2017 Administrative change deletes temporary/one-time Surry Power Station Units 1 and 2 License Amendment TS AOTs/Requirements for previously completed 08/2016 No Yes No chilled water pipe replacement project, and other Surry Power Station Units 1 and 2 License Amendment Revised UFSAR Dose Analyses 09/2016 No Yes No Surry Power Station Units 1 and 2 License Amendment Fuel Independent SBLOCA Analysis 09/2016 No Yes Yes Topical Report DOM-NAF-2 Appendix E (AGORA Surry Power Station Units 1 and 2 License Amendment CHF Correlation) 12/2016 No Yes TBD Surry Power Station Units 1 and 2 License Amendment RLBLOCA for Vendor Qualification Program 04/2017 No Yes TBD Surry Power Station Units 1 and 2 License Amendment AGORA Vendor Qualification Program Submittal 04/201 7 No Yes TBD Surry Power Station Units 1 and 2 License Amendment Spent Fuel Poot Criticality Analysis 2018 No Yes Yes Surry Power Station Units 1 and 2 License Amendment Full Spectrum LOCA Analysis 2018 No Yes Yes Relocation of Leak Testing of Miscellaneous Surry Power Station Units 1 and 2 License Amendment Rad ioactive Materail s to TRM 2018 No Yes No LAR to rely on off-site EMrs rather than on-site Surry Power Station Units 1 and 2 License Amendment EMrs 2017 No Yes No LAR to move the Local Emergency Operations Surry Power Station Units 1 and 2 License Amendment Facility (LEOF) to an EOF located at Innsbrook 2017 No Yes No Page 1of1