Letter Sequence Request |
---|
|
|
MONTHYEARML16041A3412016-02-29029 February 2016 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54(f) Information Request - Flood-Causing Mechanism Reevaluation Project stage: Other ML16049A5422016-03-0101 March 2016 Tables 1 and 2 Project stage: Request ML16183A0212016-08-12012 August 2016 NRC Report for the Audit of Virginia Electric and Power Company'S Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for Surry Power Station, Units 1 and 2 Project stage: Other ML16355A1722016-12-20020 December 2016 Storm Surge Technical Evaluation Report Surry Power Station Hazard Reevaluation Review Project stage: Request ML16323A1852016-12-21021 December 2016 Staff Assessment of Response to 10 CFR 50.54(f) Information Request - Flood-Causing Mechanism Reevaluation Project stage: Acceptance Review 2016-02-29
[Table View] |
Similar Documents at Surry |
---|
Category:Graphics incl Charts and Tables
MONTHYEARML20332A1592020-12-0707 December 2020 Documentation of Completion of Required Actions Taken in Response to Lessons Learned from the Fukushima Dai-Ichi Accident ML20203M1602020-07-20020 July 2020 VA Elec. & Power Co., Dominion Energy Nuclear Co. Inc., Dominion Energy Sc Inc., Millstone Power Station 2, N. Anna & Surry Power Stations 1 & 2, Virgil C. Summer Station 1, Updated Anchor Darling Double Disc Gate Valve Information & Status ML17213A0802017-07-28028 July 2017 Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules ML16130A5642016-05-0202 May 2016 NRC Regulatory Issue Summary 2015-16 Planned Licensing Action Submittals ML16056A1392016-03-11011 March 2016 Correction to the U.S. Nuclear Regulatory Commission Analysis of Licensees' Decommissioning Funding Status Reports ML16049A5422016-03-0101 March 2016 Tables 1 and 2 ML12124A2972010-03-11011 March 2010 Soarca Documents Review/Approval Process ML0806406572008-02-22022 February 2008 Inservice Inspection Owner'S Activity Report (Form OAR-1), Refueling Outage S1R21, Second Period of the Fourth Ten-Year ISI Interval ML0728203072007-10-11011 October 2007 Electronic Distribtion Initiative Letter, Licensee List, Electronic Distribution Input Information, Division Plant Mailing Lists ML0722801962007-08-10010 August 2007 Response to Request for Additional Information 2006 Steam Generator Inservice Inspection Reports ML0609500942006-04-0303 April 2006 North Anna Units 1 and 2, and Surry Units 1 and 2, Response to Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power ML0508804122005-03-23023 March 2005 Virginia Electric and Power Company Surry Power Station Unit 2, ASME Section XI Fourth Inservice Inspection (ISI) Interval Update, Risk Informed Inservice Inspection (RI-ISI) Program, Response to NRC Request for Additional Information ML0501802572005-01-13013 January 2005 Stations Units 1 & 2, Millstone Power Station Units 2 & 3, Request for Approval of Appendix B of Topical Report DOM-NAF-2, Qualification of Westinghouse WRB-1 CHF Correlation in the Dominion VIPRE-D Computer Code. ML0501202612005-01-12012 January 2005 December Monthly Report on the Status of Open TIAs Assigned to NRR ML0434802422004-12-29029 December 2004 November Monthly Report on the Status of Open TIAs Assigned to NRR ML0501903172004-12-17017 December 2004 Virginia Electric and Power Company Surry Power Station Units 1 and 2 - Proposed Technical Specifications Change Request for Reactor Coolant System Pressure/Temperature Limits. Ltops Setpoint, and Ltops Enable Temperature with Exemption. ML0424700192004-08-24024 August 2004 Attachment 4 - Table of Where ANSI N18.7 Requirements Are Addressed by NQA-1-1994 Standards And/Or the New QA Topical Report ML0312902322003-05-0808 May 2003 Graph Emergency Diesel Fuel Oil Consumption ML19093B1121978-07-14014 July 1978 Response to Concerns Use of a Certain Type Cable Manufactured by the Continental Wire and Cable Company ML19093B0681978-04-28028 April 1978 Response to Letter of 03/16/1978 Which Requested Certain Information Regarding 11/22/1977 Submittal for Permanent Solution of Low Head Safety Injection & Recirculation Spray Pumps Net Positive Suction Head Problems ML19093B0691978-04-26026 April 1978 Purpose of Letter to Present the Surry Unit No.1 Steam Generator Surveillance Program for the Outage Which Began on 04/22/1978 ML19093B0721978-04-17017 April 1978 Vepco Is Pleased to Provide Attached Responses to Request for Additional Information Dated March 16, 1978. Submittal Contains Program Description for Monitoring Fish Populations in James River Near Power Station ML19093B0201978-02-22022 February 1978 Response to 02/02/78 Letter Possibility That Reactor Cavity Annulus Seal Ring or Associated Biological Shielding Could Become Missiles in Event of Loss of Coolant Accident Pipe... ML19093B0241978-01-23023 January 1978 Response to a Request of 05/18/1977 for Additional Information on the Reactor Vessel Material Surveillance Program ML19093A1511977-12-31031 December 1977 Annual Operating Report 1977, Volume 4 ML19093B0661977-12-14014 December 1977 Forwarding Table 4.3-2, Which Was Omitted from Revision 1 to Steam Generator Program, Surry Power Station, Unit Nos. 1 & 2, Submitted on 12/2/1977, Serial No. 532 ML19093B0671977-12-14014 December 1977 Letter to Inform of a Delay in Final Installation of Reactor Coolant System Overpressure Protection System ML19093B0331977-11-30030 November 1977 Enclosed Justification for Tube Inspection Program & Plugging Criteria, Results of Completed Surry Unit No. 1 Inspection Program with Small Change in Denting ML19093A9811977-10-31031 October 1977 Purpose of the Letter Is to Present the Surry Unit No. 1 Steam Generator Surveillance Program for the Forthcoming Outage ML19094A5601977-09-26026 September 1977 09/26/1977 Letter Proposed Design Change to Allow the Lhsi Discharge Valves to Be Remotely Throttled from the Control Room ML19093A9871977-09-26026 September 1977 a Submission of a Proposed Design Change Which Allows the Lhsi Discharge Valves to Be Remotely Throttled from Control Room. Provides Completed Description of Tests Along with Evaluation of Results ML19093B0081977-08-29029 August 1977 Informs of Necessary Change to Operating Procedures to Require Throttling Lhsi Pump Discharge Valves During Recirculation Mode of Pump Operation in Order to Assure That Lhsi Pump Cavitation Does Not Occur During ... ML19098B4841977-07-0808 July 1977 Forwarding Corrected Pages to 1976 Annual Operating Report ML19098B4441977-06-28028 June 1977 Provide Requested Information Relative to Site Settlement to Close Previously Unresolved Item Identified as 76-15/1, Site Settlement Surveillance ML19098B4411977-06-0202 June 1977 Response to Letter of 4/13/1977, Provide Requested Information Regarding Iodine Spiking ML19098B4241977-04-15015 April 1977 Furnishing Information to Present Unit 1 Steam Generator Surveillance Program for Present Outage ML19094A7491976-07-0101 July 1976 Submits a Copy of the Supplement to Surry Unit Nos. 1 & 2 Startup Reports Dated 05/01 & 07/31/1973 Respectively ML19093B3531975-08-12012 August 1975 Response to Requested for Reasons of Surry Power Technical Specification TS 4.14.A.1 Be Waived on an Interim Basis Until 12:00 PM 09/20/1975 ML19098B3051975-07-23023 July 1975 5/13/1975 Summary of Meeting with NRC Staff, VEPCO, & Stone & Webster Corp to Discuss Possibility of Differential Settlement for Major Safety Related Structures ML19098B3071975-07-18018 July 1975 Confirming Vepco'S Plan to Conduct Large Load Reduction Test on Unit 2, on Tentative Date of 8/2/1975, as Discussed in Meeting of 7/9/1975 ML19093B3351975-05-16016 May 1975 Refers to Letter of 01/17/1975 Which Advised Replacement of Certain Water Temperature Monitoring Equipment at Station & Informing VEPCO of a Purchased & Installed New Monitoring System to Comply with Provisions ML19093B3361975-02-0303 February 1975 Confirms a Report of a Fish Impingement Incident Which Occurred on 01/28/1975 Reported to Paul Leech of Staff by John White of VEPCO on 01/19/1975 2020-07-20
[Table view] |
Text
SurryPowerStation,Units1&2 Table 1. Current Design Basis Flood Hazards for Use in the MSA Mechanism Stillwater Waves/ Design Basis Reference Elevation Runup Hazard Elevation Local Intense Precipitation Not included Not included Not included FHRR Table 3.0-1 in DB in DB in DB Streams and Rivers No Impact No Impact No Impact FHRR Table 3.0-1 on the Site on the Site on the Site Identified Identified Identified Failure of Dams and Onsite Water Control/Storage Structures No Impact No Impact No Impact FHRR Table 3.0-1 on the Site on the Site on the Site Identified Identified Identified Storm Surge PMH Flooding West Side 22.7 MSL 1.3 ft 24.0 MSL FHRR Section 3.9 PMH Flooding East Side 22.7 MSL 5.9 ft 28.6 MSL FHRR Section 3.9 Seiche No Impact No Impact No Impact FHRR Table 3.0-1 on the Site on the Site on the Site Identified Identified Identified Tsunami No Impact No Impact No Impact FHRR Table 3.0-1 on the Site on the Site on the Site Identified Identified Identified Ice-Induced Flooding Not included Not included Not included FHRR Table 3.0-1 in DB in DB in DB
SurryPowerStation,Units1&2 Table 1. Current Design Basis Flood Hazards for Use in the MSA Mechanism Stillwater Waves/ Design Basis Reference Elevation Runup Hazard Elevation Channel Migrations/Diversions Not included Not included Not included FHRR Table 3.0-1 in DB in DB in DB Note 1: Reported values are rounded to the nearest one-tenth of a foot.
SurryPowerStation,Units1&2 Table 2. Reevaluated Flood Hazards for Flood-Causing Mechanisms for Use in the MSA Mechanism Stillwater Waves/ Reevaluated Reference Elevation Runup Hazard Elevation Local Intense Precipitation Site-specific PMP 29.4 MSL Minimal 29.4 MSL FHRR Table 3.0-1 and Section 2.1.4 Failure of Dams and Onsite Water Control/Storage Structures
[Redacted] [Redacted] [Redacted] [Redacted] [Redacted]
Storm Surge Deterministic PMSS with James 24.2 MSL 14.6 ft 38.8 MSL FHRR Section 2.9-7 River 25-year Flood, East Side of Plant, Low Level Intake Structure Deterministic PMSS with James 24.2 MSL Minimal 24.2 MSL FHRR Table 2.9-4, FHRR Section River 25-year Flood, West Side 2.9.2.2, and FHRR Section 2.9.1.1 of Plant Note 1: The licensee is expected to develop flood event duration parameters and applicable flood associated effects to conduct the MSA. The staff will evaluate the flood event duration parameters (including warning time and period of inundation) and flood associated effects during its review of the MSA.
Note 2: Reevaluated hazard mechanisms bounded by the current design basis (see Table 1) are not included in this table Note 3: Reported values are rounded to the nearest one-tenth of a foot.
Note 4: Onsite Structure Failure flood causing mechanism elevations are reported as the highest elevations at specific door locations; it appears from the FHRR that the licensee may intend to specify a different flood elevation for each door, based on model output.
SurryPowerStation,Units1&2 Table 1. Current Design Basis Flood Hazards for Use in the MSA Mechanism Stillwater Waves/ Design Basis Reference Elevation Runup Hazard Elevation Local Intense Precipitation Not included Not included Not included FHRR Table 3.0-1 in DB in DB in DB Streams and Rivers No Impact No Impact No Impact FHRR Table 3.0-1 on the Site on the Site on the Site Identified Identified Identified Failure of Dams and Onsite Water Control/Storage Structures No Impact No Impact No Impact FHRR Table 3.0-1 on the Site on the Site on the Site Identified Identified Identified Storm Surge PMH Flooding West Side 22.7 MSL 1.3 ft 24.0 MSL FHRR Section 3.9 PMH Flooding East Side 22.7 MSL 5.9 ft 28.6 MSL FHRR Section 3.9 Seiche No Impact No Impact No Impact FHRR Table 3.0-1 on the Site on the Site on the Site Identified Identified Identified Tsunami No Impact No Impact No Impact FHRR Table 3.0-1 on the Site on the Site on the Site Identified Identified Identified Ice-Induced Flooding Not included Not included Not included FHRR Table 3.0-1 in DB in DB in DB
SurryPowerStation,Units1&2 Table 1. Current Design Basis Flood Hazards for Use in the MSA Mechanism Stillwater Waves/ Design Basis Reference Elevation Runup Hazard Elevation Channel Migrations/Diversions Not included Not included Not included FHRR Table 3.0-1 in DB in DB in DB Note 1: Reported values are rounded to the nearest one-tenth of a foot.
SurryPowerStation,Units1&2 Table 2. Reevaluated Flood Hazards for Flood-Causing Mechanisms for Use in the MSA Mechanism Stillwater Waves/ Reevaluated Reference Elevation Runup Hazard Elevation Local Intense Precipitation Site-specific PMP 29.4 MSL Minimal 29.4 MSL FHRR Table 3.0-1 and Section 2.1.4 Failure of Dams and Onsite Water Control/Storage Structures
[Redacted] [Redacted] [Redacted] [Redacted] [Redacted]
Storm Surge Deterministic PMSS with James 24.2 MSL 14.6 ft 38.8 MSL FHRR Section 2.9-7 River 25-year Flood, East Side of Plant, Low Level Intake Structure Deterministic PMSS with James 24.2 MSL Minimal 24.2 MSL FHRR Table 2.9-4, FHRR Section River 25-year Flood, West Side 2.9.2.2, and FHRR Section 2.9.1.1 of Plant Note 1: The licensee is expected to develop flood event duration parameters and applicable flood associated effects to conduct the MSA. The staff will evaluate the flood event duration parameters (including warning time and period of inundation) and flood associated effects during its review of the MSA.
Note 2: Reevaluated hazard mechanisms bounded by the current design basis (see Table 1) are not included in this table Note 3: Reported values are rounded to the nearest one-tenth of a foot.
Note 4: Onsite Structure Failure flood causing mechanism elevations are reported as the highest elevations at specific door locations; it appears from the FHRR that the licensee may intend to specify a different flood elevation for each door, based on model output.