| title = Vogtle, Units 1 and 2, Updated Inspection Plan NRC Inspection Report 05000424/2017005 and 05000425/2017005
| title = Updated Inspection Plan NRC Inspection Report 05000424/2017005 and 05000425/2017005
| author name = Sandal S R
| author name = Sandal S
| author affiliation = NRC/RGN-II/DRP/RPB2
| author affiliation = NRC/RGN-II/DRP/RPB2
| addressee name = Myers D J
| addressee name = Myers D
| addressee affiliation = Southern Nuclear Operating Co, Inc
| addressee affiliation = Southern Nuclear Operating Co, Inc
| docket = 05000424, 05000425
| docket = 05000424, 05000425
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION ust 28, 2017
[[Issue date::August 28, 2017]]


Mr. Darin Site Vice President Southern Nuclear Operating Company, Inc. Vogtle Electric Generating Plant 7821 River Road Waynesboro, GA 30830
==SUBJECT:==
UPDATED INSPECTION PLAN FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 1 AND 2 - NRC REPORT 05000424/2017005 AND 05000425/2017005


SUBJECT: UPDATED INSPECTION PLAN FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 1 AND 2 - NRC REPORT 05000424/2017005 AND 05000425/2017005
==Dear Mr. Myers:==
The enclosed inspection plan lists the inspections scheduled through June 30, 2019 for Vogtle Electric Generating Plant, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.


==Dear Mr. Myers:==
Also, on August 28, 2017, the NRC began the Supplemental Inspection (IP 95001) for a White finding associated with the failure to maintain a standard emergency classification scheme.
The enclosed inspection plan lists the inspections scheduled through June 30, 2019 for Vogtle Electric Generating Plant, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence. Also, on August 28, 2017, the NRC began the Supplemental Inspection (IP 95001) for a White finding associated with the failure to maintain a standard emergency classification scheme. Specifically, the emergency classifications RG1 & RS1 contained effluent radiation monitor threshold values significantly different than appropriate.
 
Specifically, the emergency classifications RG1 & RS1 contained effluent radiation monitor threshold values significantly different than appropriate.
 
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (404) 997-4513 with any questions you have regarding this letter.
 
Sincerely,
/RA/
Shane R. Sandal, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-424, 50-425 License Nos.: NPF-68 and NPF-81 Enclosure:
Vogtle Inspection/Activity Plan 08/01/2017-06/30/2019 Distribution via Listserv SUBJECT: UPDATED INSPECTION PLAN FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 1 AND 2 - NRC REPORT 05000424/2017005 AND 05000425/2017005 August 28, 2017 DISTRIBUTION:
M. Kowal, RII K. Sloan, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMVogtleResource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
ADAMS Accession Number: ML17240A082 OFFICE RII:DRP RII:DRP NAME DMas SSandal DATE 8/23/2017 8/25/2017 OFFICIAL AGENCY RECORD


In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (404) 997-4513 with any questions you have regarding this letter.
Page 1 of 2      Vogtle 08/23/2017 10:31:50    Inspection / Activity Plan Report 22 08/01/2017 - 06/30/2019 Unit Planned Dates        No. of Staff Number Start End Inspection Activity    Title   on Site 95001 - VOGTLE 95001 INSPECTION      4 1, 2 08/28/2017 09/01/2017 IP 95001  Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area ISI - UNIT 2 IN-SERVICE INSPECTION      1 2 09/25/2017 09/29/2017 IP 7111108P Inservice Inspection Activities - PWR RP - RP PUBLIC INSPECTION      2 1, 2 09/25/2017 09/29/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/25/2017 09/29/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation OL EXAM - INITIAL LICENSE EXAM      4 1 10/06/2017 10/17/2017 V23491 VOGTLE/UNIT 1 APRIL 2017 INITIAL EXAM AT POWER FACILITIES EQI - DESIGN BASES ASSURANCE INSPECTION (PROGR      4 1, 2 11/06/2017 11/10/2017 IP 7111121N Design Bases Assurance Inspection (Programs)
1, 2 11/27/2017 12/01/2017 IP 7111121N Design Bases Assurance Inspection (Programs)
1, 2 12/11/2017 12/15/2017 IP 7111121N Design Bases Assurance Inspection (Programs)
TI-191 - MITIGATING STRATEGIES      4 1, 2 11/13/2017 11/17/2017 IP 2515/191 Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 RP - RP PUBLIC INSPECTION      2 1, 2 12/04/2017 12/08/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 12/04/2017 12/08/2017 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 12/04/2017 12/08/2017 IP 71151  Performance Indicator Verification EP - EP EXERCISE        6 1, 2 05/14/2018 05/18/2018 IP 7111401 Exercise Evaluation 1, 2 05/14/2018 05/18/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 05/14/2018 05/18/2018 IP 7111408 Exercise Evaluation - Scenario Review 1, 2 05/14/2018 05/18/2018 IP 71151-EP02 ERO Readiness MODS - PLANT MODIFICATIONS INSPECTION      3 1, 2 08/27/2018 08/31/2018 IP 7111117T Evaluations of Changes, Tests, and Experiments ISI - UNIT 1 IN-SERVICE INSPECTION      1 1 09/24/2018 09/28/2018 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL - WEEK 1      2 1, 2 09/24/2018 09/28/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/24/2018 09/28/2018 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 09/24/2018 09/28/2018 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 09/24/2018 09/28/2018 IP 71124.04 Occupational Dose Assessment This report does not include INPO and OUTAGE activities.


Sincerely,/RA/
This report shows only on-site and announced inspection procedures. Enclosure
Shane R. Sandal, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-424, 50-425 License Nos.: NPF-68 and NPF-81


===Enclosure:===
Page 2 of 2      Vogtle 08/23/2017 10:31:50    Inspection / Activity Plan Report 22 08/01/2017 - 06/30/2019 Unit Planned Dates      No. of Staff Number Start End Inspection Activity     Title on Site RP - RP OCCUPATIONAL - WEEK 1    2 1, 2 09/24/2018 09/28/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 09/24/2018 09/28/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences SGISI - UNIT 1 SG IN-SERVICE INSPECTION    1 1 09/24/2018 09/28/2018 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL - WEEK 2    2 1, 2 10/15/2018 10/19/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/15/2018 10/19/2018 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/15/2018 10/19/2018 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/15/2018 10/19/2018 IP 71124.04 Occupational Dose Assessment 1, 2 10/15/2018 10/19/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 10/15/2018 10/19/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences OL EXAM - INITIAL LICENSE EXAM PREP    3 1 10/29/2018 11/02/2018 V23520 VOGTLE U1/ DECEMBER 2018 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL LICENSE EXAM    3 1 11/26/2018 12/14/2018 V23520 VOGTLE U1/ DECEMBER 2018 INITIAL EXAM AT POWER FACILITIES RP - RP INSTRUMENTS    1 1, 2 12/03/2018 12/07/2018 IP 71124.05 Radiation Monitoring Instrumentation ISI - UNIT 2 IN-SERVICE INSPECTION    1 2 03/18/2019 03/22/2019 IP 7111108P Inservice Inspection Activities - PWR RP - RP RADHAZARDS    1 1, 2 03/18/2019 03/22/2019 IP 71124.01 Radiological Hazard Assessment and Exposure Controls SGISI - UNIT 2 SG IN-SERVICE INSPECTION    1 2 03/18/2019 03/22/2019 IP 7111108P Inservice Inspection Activities - PWR PI&R - PROBLEM IDENTIFICATION AND RESOLUTION    5 1, 2 04/22/2019 04/26/2019 IP 71152B Problem Identification and Resolution 1, 2 05/06/2019 05/10/2019 IP 71152B Problem Identification and Resolution EP - EP PROGRAM INSPECTION    3 1, 2 05/06/2019 05/10/2019 IP 7111402 Alert and Notification System Testing 1, 2 05/06/2019 05/10/2019 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 05/06/2019 05/10/2019 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 05/06/2019 05/10/2019 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 05/06/2019 05/10/2019 IP 71151  Performance Indicator Verification This report does not include INPO and OUTAGE activities.
Vogtle Inspection/Activity Plan 08/01/2017-06/30/2019 Distribution via Listserv SUBJECT: UPDATED INSPECTION PLAN FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 1 AND 2 - NRC REPORT 05000424/2017005 AND 05000425/2017005 August 28, 2017 DISTRIBUTION: M. Kowal, RII K. Sloan, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMVogtleResource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
ADAMS Accession Number: ML OFFICE RII:DRP RII:DRP NAME DMas SSandal DATE 8/23/2017 8/25/2017 OFFICIAL AGENCY RECORD Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteVogtleInspection / Activity Plan08/01/2017-06/30/2019Page 1 of 208/23/2017 10:31:5095001-VOGTLE 95001 INSPECTION41,2 IPSupplemental Inspection for One or Two White Inputs in a Strategic Performance Area9500108/28/201709/01/2017ISI-UNIT 2 IN-SERVICE INSPECTION1 2 IPInservice Inspection Activities - PWR7111108P09/25/201709/29/2017RP-RP PUBLIC INSPECTION21,2 IPRadiological Hazard Assessment and Exposure Controls71124.0109/25/201709/29/20171,2 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0809/25/201709/29/2017OL EXAM-INITIAL LICENSE EXAM41 VOGTLE/UNIT 1 APRIL 2017 INITIAL EXAM AT POWER FACILITIESV2349110/06/201710/17/2017EQI-DESIGN BASES ASSURANCE INSPECTION (PROGR41,2 IPDesign Bases Assurance Inspection (Programs)7111121N11/06/201711/10/20171,2 IPDesign Bases Assurance Inspection (Programs)7111121N11/27/201712/01/20171,2 IPDesign Bases Assurance Inspection (Programs)7111121N12/11/201712/15/2017TI-191-MITIGATING STRATEGIES41,2 IPInspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 20122515/19111/13/201711/17/2017RP-RP PUBLIC INSPECTION21,2 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0612/04/201712/08/20171,2 IPRadiological Environmental Monitoring Program71124.0712/04/201712/08/20171,2 IPPerformance Indicator Verification7115112/04/201712/08/2017EP-EP EXERCISE61,2 IPExercise Evaluation711140105/14/201805/18/20181,2 IPEmergency Action Level and Emergency Plan Changes711140405/14/201805/18/20181,2 IPExercise Evaluation - Scenario Review711140805/14/201805/18/20181,2 IPERO Readiness71151-EP0205/14/201805/18/2018MODS-PLANT MODIFICATIONS INSPECTION31,2 IPEvaluations of Changes, Tests, and Experiments7111117T08/27/201808/31/2018ISI-UNIT 1 IN-SERVICE INSPECTION11 IPInservice Inspection Activities - PWR7111108P09/24/201809/28/2018RP-RP OCCUPATIONAL - WEEK 121,2 IPRadiological Hazard Assessment and Exposure Controls71124.0109/24/201809/28/20181,2 IPOccupational ALARA Planning and Controls71124.0209/24/201809/28/20181,2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0309/24/201809/28/20181,2 IPOccupational Dose Assessment71124.0409/24/201809/28/2018This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.


Report 22UnitNumberPlanned DatesStart EndInspection ActivityTitleNo. of Staffon SiteVogtleInspection / Activity Plan08/01/2017-06/30/2019Page 2 of 208/23/2017 10:31:50RP-RP OCCUPATIONAL - WEEK 121,2 IPOccupational Exposure Control Effectiveness71151-OR0109/24/201809/28/20181,2 IPRETS/ODCM Radiological Effluent Occurrences71151-PR0109/24/201809/28/2018SGISI-UNIT 1 SG IN-SERVICE INSPECTION11 IPInservice Inspection Activities - PWR7111108P09/24/201809/28/2018RP-RP OCCUPATIONAL - WEEK 221,2 IPRadiological Hazard Assessment and Exposure Controls71124.0110/15/201810/19/20181,2 IPOccupational ALARA Planning and Controls71124.0210/15/201810/19/20181,2 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0310/15/201810/19/20181,2 IPOccupational Dose Assessment71124.0410/15/201810/19/20181,2 IPOccupational Exposure Control Effectiveness71151-OR0110/15/201810/19/20181,2 IPRETS/ODCM Radiological Effluent Occurrences71151-PR0110/15/201810/19/2018OL EXAM-INITIAL LICENSE EXAM PREP31 VOGTLE U1/ DECEMBER 2018 INITIAL EXAM AT POWER FACILITIESV2352010/29/201811/02/2018OL EXAM-INITIAL LICENSE EXAM31 VOGTLE U1/ DECEMBER 2018 INITIAL EXAM AT POWER FACILITIESV2352011/26/201812/14/2018RP-RP INSTRUMENTS11,2 IPRadiation Monitoring Instrumentation71124.0512/03/201812/07/2018ISI-UNIT 2 IN-SERVICE INSPECTION1 2 IPInservice Inspection Activities - PWR7111108P03/18/201903/22/2019RP-RP RADHAZARDS11,2 IPRadiological Hazard Assessment and Exposure Controls71124.0103/18/201903/22/2019SGISI-UNIT 2 SG IN-SERVICE INSPECTION1 2 IPInservice Inspection Activities - PWR7111108P03/18/201903/22/2019PI&R-PROBLEM IDENTIFICATION AND RESOLUTION51,2 IPProblem Identification and Resolution71152B04/22/201904/26/20191,2 IPProblem Identification and Resolution71152B05/06/201905/10/2019EP-EP PROGRAM INSPECTION31,2 IPAlert and Notification System Testing711140205/06/201905/10/20191,2 IPEmergency Preparedness Organization Staffing and Augmentation System711140305/06/201905/10/20191,2 IPEmergency Action Level and Emergency Plan Changes711140405/06/201905/10/20191,2 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140505/06/201905/10/20191,2 IPPerformance Indicator Verification7115105/06/201905/10/2019This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
This report shows only on-site and announced inspection procedures.
}}
}}

Latest revision as of 20:28, 29 October 2019

Updated Inspection Plan NRC Inspection Report 05000424/2017005 and 05000425/2017005
ML17240A082
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 08/28/2017
From: Shane Sandal
NRC/RGN-II/DRP/RPB2
To: Myers D
Southern Nuclear Operating Co
References
IR 2017005
Download: ML17240A082 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION ust 28, 2017

SUBJECT:

UPDATED INSPECTION PLAN FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 1 AND 2 - NRC REPORT 05000424/2017005 AND 05000425/2017005

Dear Mr. Myers:

The enclosed inspection plan lists the inspections scheduled through June 30, 2019 for Vogtle Electric Generating Plant, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.

Also, on August 28, 2017, the NRC began the Supplemental Inspection (IP 95001) for a White finding associated with the failure to maintain a standard emergency classification scheme.

Specifically, the emergency classifications RG1 & RS1 contained effluent radiation monitor threshold values significantly different than appropriate.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (404) 997-4513 with any questions you have regarding this letter.

Sincerely,

/RA/

Shane R. Sandal, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-424, 50-425 License Nos.: NPF-68 and NPF-81 Enclosure:

Vogtle Inspection/Activity Plan 08/01/2017-06/30/2019 Distribution via Listserv SUBJECT: UPDATED INSPECTION PLAN FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 1 AND 2 - NRC REPORT 05000424/2017005 AND 05000425/2017005 August 28, 2017 DISTRIBUTION:

M. Kowal, RII K. Sloan, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMVogtleResource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)

ADAMS Accession Number: ML17240A082 OFFICE RII:DRP RII:DRP NAME DMas SSandal DATE 8/23/2017 8/25/2017 OFFICIAL AGENCY RECORD

Page 1 of 2 Vogtle 08/23/2017 10:31:50 Inspection / Activity Plan Report 22 08/01/2017 - 06/30/2019 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 95001 - VOGTLE 95001 INSPECTION 4 1, 2 08/28/2017 09/01/2017 IP 95001 Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 09/25/2017 09/29/2017 IP 7111108P Inservice Inspection Activities - PWR RP - RP PUBLIC INSPECTION 2 1, 2 09/25/2017 09/29/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/25/2017 09/29/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation OL EXAM - INITIAL LICENSE EXAM 4 1 10/06/2017 10/17/2017 V23491 VOGTLE/UNIT 1 APRIL 2017 INITIAL EXAM AT POWER FACILITIES EQI - DESIGN BASES ASSURANCE INSPECTION (PROGR 4 1, 2 11/06/2017 11/10/2017 IP 7111121N Design Bases Assurance Inspection (Programs)

1, 2 11/27/2017 12/01/2017 IP 7111121N Design Bases Assurance Inspection (Programs)

1, 2 12/11/2017 12/15/2017 IP 7111121N Design Bases Assurance Inspection (Programs)

TI-191 - MITIGATING STRATEGIES 4 1, 2 11/13/2017 11/17/2017 IP 2515/191 Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 RP - RP PUBLIC INSPECTION 2 1, 2 12/04/2017 12/08/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 12/04/2017 12/08/2017 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 12/04/2017 12/08/2017 IP 71151 Performance Indicator Verification EP - EP EXERCISE 6 1, 2 05/14/2018 05/18/2018 IP 7111401 Exercise Evaluation 1, 2 05/14/2018 05/18/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 05/14/2018 05/18/2018 IP 7111408 Exercise Evaluation - Scenario Review 1, 2 05/14/2018 05/18/2018 IP 71151-EP02 ERO Readiness MODS - PLANT MODIFICATIONS INSPECTION 3 1, 2 08/27/2018 08/31/2018 IP 7111117T Evaluations of Changes, Tests, and Experiments ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 09/24/2018 09/28/2018 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL - WEEK 1 2 1, 2 09/24/2018 09/28/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/24/2018 09/28/2018 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 09/24/2018 09/28/2018 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 09/24/2018 09/28/2018 IP 71124.04 Occupational Dose Assessment This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 Vogtle 08/23/2017 10:31:50 Inspection / Activity Plan Report 22 08/01/2017 - 06/30/2019 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RP - RP OCCUPATIONAL - WEEK 1 2 1, 2 09/24/2018 09/28/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 09/24/2018 09/28/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 09/24/2018 09/28/2018 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL - WEEK 2 2 1, 2 10/15/2018 10/19/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/15/2018 10/19/2018 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/15/2018 10/19/2018 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/15/2018 10/19/2018 IP 71124.04 Occupational Dose Assessment 1, 2 10/15/2018 10/19/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 10/15/2018 10/19/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences OL EXAM - INITIAL LICENSE EXAM PREP 3 1 10/29/2018 11/02/2018 V23520 VOGTLE U1/ DECEMBER 2018 INITIAL EXAM AT POWER FACILITIES OL EXAM - INITIAL LICENSE EXAM 3 1 11/26/2018 12/14/2018 V23520 VOGTLE U1/ DECEMBER 2018 INITIAL EXAM AT POWER FACILITIES RP - RP INSTRUMENTS 1 1, 2 12/03/2018 12/07/2018 IP 71124.05 Radiation Monitoring Instrumentation ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 03/18/2019 03/22/2019 IP 7111108P Inservice Inspection Activities - PWR RP - RP RADHAZARDS 1 1, 2 03/18/2019 03/22/2019 IP 71124.01 Radiological Hazard Assessment and Exposure Controls SGISI - UNIT 2 SG IN-SERVICE INSPECTION 1 2 03/18/2019 03/22/2019 IP 7111108P Inservice Inspection Activities - PWR PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 5 1, 2 04/22/2019 04/26/2019 IP 71152B Problem Identification and Resolution 1, 2 05/06/2019 05/10/2019 IP 71152B Problem Identification and Resolution EP - EP PROGRAM INSPECTION 3 1, 2 05/06/2019 05/10/2019 IP 7111402 Alert and Notification System Testing 1, 2 05/06/2019 05/10/2019 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 05/06/2019 05/10/2019 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 05/06/2019 05/10/2019 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 05/06/2019 05/10/2019 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.