IR 05000424/2015005

From kanterella
Jump to navigation Jump to search
Mid-Cycle Assessment Letter for Vogtle Electric Generating Plant Units 1 and 2 (Inspection Report No. 05000424/2015005 and 05000425/2015005
ML15244B046
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 09/01/2015
From: Joel Munday
Division Reactor Projects II
To: Taber B
Southern Nuclear Operating Co
References
IR 2015005
Download: ML15244B046 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION ber 1, 2015

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 1 AND 2 (INSPECTION REPORT NO. 05000424/2015005 AND 05000425/2015005

Dear Mr. Taber:

On August 11, 2015, the NRC completed its mid-cycle performance review of Vogtle Electric Generating Plant Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014, through June 30, 2015. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at Vogtle Units 1 and 2 during the most recent quarter was within the Regulatory Response Column of the NRCs Reactor Oversight Process (ROP)

Action Matrix because of a White violation in the Public Radiation Safety Cornerstone for improper transportation of radioactive waste. The White violation was assessed as an ROP Action Matrix input for Vogtle Units 1 and 2 beginning in the fourth quarter of 2014 (ADAMS Accession Number ML15131A322).

On June 1, 2015, your staff notified the NRC of your readiness for a supplemental inspection to review the actions taken to address this performance issue. Therefore, in addition to ROP baseline inspections, the NRC conducted a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area, during the week of August 17, 2015. The objectives of this supplemental inspection were to provide assurance that the 1) root causes and contributing causes of risk-significant performance issues were understood, 2) extent of condition and extent of cause of risk significant performance issues were identified, and 3) corrective actions for risk-significant performance issues were sufficient to address the root and contributing causes and prevent recurrence. The NRC is finalizing the results of that inspection and will document our conclusions in a subsequent inspection report (05000424/2015009 and 05000425/2015009).

The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. In addition, we will also conduct reactor operator licensing examinations and inspect construction of a second independent spent fuel storage installation pad. Also, we are coordinating with your staff to schedule an inspection of your implementation of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In response to the accident at Fukushima, the NRC is conducting audits of licensee efforts towards compliance with Commission issued Orders EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. This audit has been completed for the first unit at Vogtle and the information gathered will aid the staff in development of the ultimate Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing Temporary Instruction (TI) 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Mr. Shane Sandal at 404-997-4513 or by e-mail at shane.sandal@nrc.gov with any questions you have regarding this letter.

Sincerely,

/RA/

Joel Munday, Director Division of Reactor Projects Docket Nos.: 50-424. 50-425 License Nos.: NPF-68, NPF-81 Enclosure: Inspection/Activity Plan (09/01/2015 - 06/30/2017)

cc: distribution via ListServ

_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP RII:DRP SIGNATURE ELP1 CWR1 SRS5 JTM NAME E. Powell C. Rapp S. Sandal J. Munday DATE 8/17/2015 8/18/2015 8/20/2015 8/31/2015 9/ /2015 9/ /2015 9/ /2015 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO Letter to Brian Taber from Joel Munday dated September 1, 2015 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR VOGTLE ELECTRIC GENERATING PLANT UNITS 1 AND 2 (INSPECTION REPORT NO. 05000424/2015005 AND 05000425/2015005)

DISTRIBUTION:

D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC A. Adams, NRR RidsNrrPMVogtle Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)

Page 1 of 2 Vogtle 09/01/2015 10:34:19 Inspection / Activity Plan Report 22 09/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site OL EXAM - INITIAL LICENSE EXAM 3 1 08/31/2015 09/18/2015 V23458 VOGTLE U1/AUGUST 2015 INITIAL EXAM AT POWER FACILITIES RP - RAD HAZARDS ANALYSIS AND TRANSPORTATION 2 1, 2 09/21/2015 09/25/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 09/21/2015 09/25/2015 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 1, 2 09/21/2015 09/25/2015 IP 71151 Performance Indicator Verification ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 09/28/2015 10/02/2015 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 10/05/2015 10/09/2015 IP 7111108P Inservice Inspection Activities - PWR ISFSI - CONSTRUCTION OF SECOND SMALL ISFSI PAD 1 1, 2 10/26/2015 10/30/2015 IP 60853 On-Site Fabrication Of Components And Construction On An ISFSI RP - RP OCCUPATIONAL INSPECTION WEEK 1 3 1, 2 03/07/2016 03/11/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 03/07/2016 03/11/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 03/07/2016 03/11/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/07/2016 03/11/2016 IP 71124.04 Occupational Dose Assessment 1, 2 03/07/2016 03/11/2016 IP 71151 Performance Indicator Verification ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 03/14/2016 03/18/2016 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL INSPECTION WEEK 2 1 1, 2 03/21/2016 03/25/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 03/21/2016 03/25/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 03/21/2016 03/25/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/21/2016 03/25/2016 IP 71124.04 Occupational Dose Assessment 1, 2 03/21/2016 03/25/2016 IP 71151 Performance Indicator Verification SGISI - UNIT 2 SG IN-SERVICE INSPECTION 1 2 03/21/2016 03/25/2016 IP 7111108P Inservice Inspection Activities - PWR EP - EP EXERCISE INSPECTION 2 1, 2 05/09/2016 05/13/2016 IP 7111401 Exercise Evaluation 1, 2 05/09/2016 05/13/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 05/09/2016 05/13/2016 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 2 Vogtle 09/01/2015 10:34:19 Inspection / Activity Plan Report 22 09/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site CDBI - COMPONENT DESIGN BASES INSPECTION 7 1, 2 09/12/2016 09/16/2016 IP 7111121 Component Design Bases Inspection 1, 2 10/03/2016 10/07/2016 IP 7111121 Component Design Bases Inspection 1, 2 10/17/2016 10/21/2016 IP 7111121 Component Design Bases Inspection 1, 2 10/31/2016 11/04/2016 IP 7111121 Component Design Bases Inspection RP - RP INSTRUMENTS 1 1, 2 11/14/2016 11/18/2016 IP 71124.05 Radiation Monitoring Instrumentation PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 5 1, 2 02/20/2017 02/24/2017 IP 71152B Problem Identification and Resolution 1, 2 03/06/2017 03/10/2017 IP 71152B Problem Identification and Resolution ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 04/03/2017 04/07/2017 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 04/10/2017 04/14/2017 IP 7111108P Inservice Inspection Activities - PWR EP - EP PROGRAM INSPECTION 5 1, 2 05/22/2017 05/26/2017 IP 7111402 Alert and Notification System Testing 1, 2 05/22/2017 05/26/2017 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 05/22/2017 05/26/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 05/22/2017 05/26/2017 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 05/22/2017 05/26/2017 IP 71151 Performance Indicator Verification TFPI - TRIENNIEL FIRE PROTECTION INSPECTION 1 1, 2 06/12/2017 06/16/2017 IP 7111105T Fire Protection [Triennial]

1, 2 06/26/2017 06/30/2017 IP 7111105T Fire Protection [Triennial]

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure