| issue date = 04/09/1980
| issue date = 04/09/1980
| title = Proposed Changes to Fire Protection Tech Specs.Changes Reflect Mods Made to Plant Per Requirements of 790731 Fire Protection Safety Evaluation
| title = Proposed Changes to Fire Protection Tech Specs.Changes Reflect Mods Made to Plant Per Requirements of 790731 Fire Protection Safety Evaluation
| author name = HUNTER R S
| author name = Hunter R
| author affiliation = INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
| author affiliation = INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
| addressee name =  
| addressee name =  

Revision as of 16:33, 18 June 2019

Proposed Changes to Fire Protection Tech Specs.Changes Reflect Mods Made to Plant Per Requirements of 790731 Fire Protection Safety Evaluation
ML17326A660
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 04/09/1980
From: Hunter R
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
Shared Package
ML17326A658 List:
References
NUDOCS 8004150510
Download: ML17326A660 (15)


Text

ATTACHMENT 1 TO AEP:NRC:00286 DONALD C.COOK NUCLEAR PLANT UNIT 1'PPENDIX'A'ECHNICAL SPECIFICATIONS CHANGE NO.1 Revisions to Table 3.3-10"Fire Protection Instrumentation" These changes, involve revisions to Table 3.3-10 entitled,"Fire Detection Instrumentation" on pages 3/4 3-52 and 3-53.(a)The minimum number of thermistor detectors specified for the Containment

-quadrants 1, 2, 3 and 4 do not agree with the as built installation of the thermistor detection system for the containment cable trays.This change has been discussed with members of the NRC staff and is consistent with the requirements of the fire protection program fo r the Donald C.Cook Nuclear Plant.This change was previously submitted via our December 22, 1978 letter (AEP:NRC:00109) and is resubmitted here for completeness since other changes to this table are necessary.(b)This change updates the smoke (ionization) detection requirements to reflect the addition of detectors to certain plant areas in accordance

~with fire protection modifications made to the Cook Plant.The upgraded detection capability is described in the fire protection SER and is consistent with our submittals referenced therein.(c)This change reflects the optical (infrared) detection instrumentation added to certain areas of Cook Plant and is in accordance with the requirements of the fire protection SER and is consistent with our previous submittals referenced therein.This change consists of an additional column of instruments listed on Table 3.3-10.The revised pages are attached.These changes will not adversely affect the health and'safety of the public.CHANGE NO.2.Revision to Table 3.7-5"S ra and or S rinkler S stems" This change reflects the closed head sprinkler type water suppression systems added to certain plant areas in accordance with the requirements of the fire protection SER and is consistent with our previous submittals referenced therein.The new sprinkler systems were added to the auxiliary building on elevations 587 feet and 609 feet.These systems provide sprinkler pro-'ection to the corridors, charging pump rooms, safety injection pump rooms and laundry area, and are shared systems with Cook Unit 2.This change also reflects the sprinkler systems added to the reactor coolant pumps.The revised page is attached.These changes will not adversely affect the health (and safety of the, public.

'0 TABLE 3.3-10 FIRE DETECTION INSTRUMENTATION

.INS:F RUMENT ,LOCATION E MINIMUM INSTRUMENTS OPERABLE'I SMOKE.HEAT OPTICAL IONIZATION THERMISTOR INFRARED 1.Containment Zone 6, quadrant 1 Cable Tunnel Zone 7, quadrant 2 Cable Tunnel Zone B,.quadrant 3N Cable Tunnel Zone.9, quadrant 3'able Tunnel Zone 10, quadrant 35 Cable Tunnel Zone 11, (}uadrant 4 Cable Tunnel: quadrant1,..quadrant 2 quadrant 3 quadrant 4 1;HV-'CFT-1 Charcoal Filters 1-HV-CFT-2 Charcoal Filters 2.'ontrol Room~Zone: 22, Control Room 3.Cable Spreading Room'Zone 15, Switchgear Cable Vault Zone 16, Auxiliary Cable Vault Zone 17, Control Room Cable Vault Zone 18, Control Room Cable Vault 4.Diesel Generator::-'."Diesel Generator Room lAB Diesel Generator Room lCD 5.Diesel Fuel Oil Room 3 5 3 3 2 5.24 10 5 24 25 143 18!.11 1 2 3 2 2 2 4 D.C.COOK-UNIT 1 3/4 3-52 Amendment No.

~~~~~I y~TABLE 3.3-10 (Cont'd)FIRE DETECTION INSTRUMENTATION INSTRUMENT LOCATION MINIMUM INSTRUMENTS OPERABLE 6.Auxiliary Building SMOKE (IONIZATION)

HEAT THERMISTOR OPTICAL INFMREO Zone 1, Zone 2, Zone 3, Zone 4, Zone 5, Elevation 573 ft.Elevation 587 ft.Elevation 609 ft.Elevation 633 ft.Elevation 650 ft.5 42 22 , 31 26 Zone 12, 4 kv Switchgear 3 Zone 13, Engineered Sa fety Swi tchgear 7 Zone 14, CRD Switchgear 6 1-HV-AES-1 Charcoal Filters 1-HV-AES-2 Charcoal Filters 12-HV-AFX Charcoal Filters 1-HV-CPR Charcoal Filters 1-HV-CIPX Charcoal Filters 1-HV-ACRF Charcoal Filters 7.Fuel Storage Zone 19, New Fuel Storage Room 1'1 1 1 1 5 4 0.C.COOK-UNIT 1 3/4 3-53 Amendment No.

'TABLE 3.7-5 SPRAY AND/OR SPRINKLER SYSTEMS~~~r I I r I~e~, l A OPEN HEAD DELUGE TYPE WATER SYSTEMS LOCATION'-HV-ASS-I Charcoal Filters 1-HV-AES-2 Charcoal Filters 12-HV-AFX Charcoal Filters 1-HV-CPR-1

'Charcoal Filters 1-HV-CIPX-1 Charcoal, Filters 1-HV-ACRF-1 Charcoal Filters ACTUATION Electric-heat Electric-heat Electr fc-heat Electric-heat Electric-heat Electric-heat I~s~(a I I I B.CLOSED HEAD SPRINKLER TYPE MATER SYSTEMS LOCATION Auxil fary Bldg.Cask Handling Area" Auxiliary Bldg.Drumming Area*Auxiliary Bldg.Elev.587 8.609*(corridors, charging, safety fnj.pump rooms, laundry area)Reactor Coolant Pumps (4')TYPE SYSTEM Preaction Sprinkler Pr eactfon Sprinkler Preaction Sprinkler Preaction Sprink'ler ACTUATION Ory Pilot Ory Pi1ot Dry Pilot Manual Shared system with D.C.COOK-UNIT 2.0.C.COOK-UNIT 1 3l4 7-~6 Amendment No.

ATTACHMENT 2 TO AEP:NRC'00286 DONALD C.COOK NUCLEAR.PLANT UNIT 2 APPENDIX'A'ECHNICAL SPECIFICATIONS

<;1~~CHANGE NO.1 Revisions to Table 3.3-11;"Fire'Protection Instrumentation" These changes involve revisions to Table 3,3-.11 entitled,"Five Detection-Instrumentation" on pages 3/4 3-51 and 3-52.4 (a)The minimum number of thermistor detectors specified for the Containment quadrants 1, 2, 3 and 4 dog not agree with the as built installation of the thermistor detection system for the containment cable trays.This change has been discussed with members of the NRC staff and is consis-tent with the requirements of the fire protection program for the Donald C.Cook Nuclear Plant.This change was previously submitted via our February 13, 1979 letter (AEP:NRC:00111) and is resubmitted here for completeness since other changes to this table are necessary.(b)This change updates the smoke (ionization)detection requirements to reflect the addition of detectors to certain plant areas in accordance with fire protection modifications made to the Cook Plant.The upgraded detection capability is described in the fire protection SER and is consistent with our submittals referenced therein.(c)This change reflects the optical (infrared) detection instrumentation added to certain areas of Cook Plant and is in accordance with the requirements of the fire protection SER,and is consistent of an additional column of instruments listed on Table 3.3-11.The revised pages are attached.These changes will not adversely affect the health and safety of the public.CHANGE NO.2 Revision to Table 3.7-5"S ra and or S r inkier S stems" This changes reflects the closed head sprinkler type water suppression systems added to certain plant areas in accordance with the requirements of the fire protection SER and is consistent with our previous submittals referenced therein.The new sprinkler systems were added to the auxiliary building on elevations 587 feet and 609 feet.These systems provide sprinkler protection to the corridors, charging pump rooms, safety injection pump.rooms laundry area and are shared systems with Cook Unit 1.This change also reflects the spri.nkler systems added to the reactor coolant pumps.The revised page is attached.These changes will not adversely affect the health and safety of the public.

TABLE 3.3-11 FIRE DETECTION Ii'INSTRUMENTATION I t P INSTRUYiENT LOCATION 1 Containment MINIMiUM INSTRUMEiNTS OPERABLE SMOKE HEAT t'PTICAL IONIZATION THERMISTOR

~IN RAREO\Zone 1, Quadrant 1 Cable Tunnel Zone 2, Quadrant 2 Cable Tunnel Zone 3, Quadrant 3N Cable Tunnel Zone 4, Quadrant 3M Cable Tunnel Zone 5, Quadrant 3S Cable Tunnel Zone 6, Quadrant 4 Cable Tunn 1 Quadrant 1 Quadrant 2 Quadrant 3 Quadrant 4 2-HV-CFT-1 Charcoal Filters 2-HV-CFT-2 Charcoal Filters 2.Control Room , Zone 16, Control Room 3;Cable Spreading Room Zone 10, Switchgear Cable Vault Zone ll, Auxiliary Cable Vault Zone 12, Con.rol Room Cable Vault Zone 13, Control Room Cable Vault 4.Diesel Generator Diesel Generator Room 2AB Diesel Generator Room ZCD 5.Diesel Fuel Oil Room 3 5 3'2 5 22 8 5 24 25 12 5:23~'I 2 3 2 i Il2 2 D.C.COOK-UNIT 2 3/4 3-51

3~TABI E 3.3-11 (Cont'd)FIRE OETECTION INSTRUMENTATION INSTRUMENT LOCATION MINIMUM INSTRUMENTS OPEPABLE T 6.Auxiliary Building SMOKE IONIZATION)

HEAT OPTICAL THERMISTOR (INFRAREO)

Elevation 573 Elevation 587 Elevation 609 Elevation 633'Elevation 650 ft*ft*ft.*ft.*ft*5 42 22 31, 26 Zone 7, 4 Kv Switchgear Zone 8, Engineered Safety Switchgear Zona 9, CRD Switchgear 2-HV-AES-1 Char coal Fil ters 2-HV-AES-2 Charcoal Filters 12-HY-AFX Charcoal Fi1ters'2-HY-CPR Charcoal Filters 2-HY-CIPX Charcoal Filters 2-HV-ACRF Charcoal Filters 7.Fuel Storage New Fuel Storage Room*3 7 6 5 4~TT.i T 0.T.TTTK-IIIITT 0.C.COOK-UNIT 2 3/4 3-52

r~~M~~>.t~~4 E a V PLANT SYSTEMS SURVEILLANCE RE UIREHENTS Continued 2.By inspection of deluge and preaction type system spray headers, to verify their integrity.

3.By inspection of each open head de1uge nozzle to verify no blockage.c.At least once per 3 years.by performing an air flow test through each open head deluge header and verifying each open head deluge nozzIe is unobstructed.

D.C.COOK-UNi'T 1 3(4 7-45 Amendment'No.22 C.~'~-I Nk~~e TABLE 3.T-5 SPRAY AND/OR SPRINKLER SYSTEiMS A OPEN HEAD DELUGE TYPE WATER SYSTEMS h h LOCATION 2-HV-AES-1 Charcoal Fil te ACTUATION rs Hectric-heat 2-HV-AES-2 Char coal Fil ters 12-HV-AFX Charcoal-Fi1 ters 2-HV-CPR-1 Charcoal Filters 2-HV-CIPX-1 Charcoal Filters 2-HV-ACRF-1 Charcoal Filter Electri c-heat ETectric-heat Electric-heat Hectric-heat Gectric-heat C B.CLOSED HEAD SPRIiNKLER TYPE MATER SYSTEMS LOCATION Auxiliary Bldg.Cask Handling Ar ea*Auxiliary Bldg.Drumming Ar'ea*Auxiliary Bldg.Elev.587&609*/Corridors, charging, safety Inj.pump rooms, laundry are/Reactor Coolant Pumps (4)TYPE SYSTEM Preaction Sprinkler Preaction Sprinkler Preaction Sprinkler Preaction Sprinkler ACTUATION Ory Pilot Ory Pilot Dry Pilot Manual Shared system with O.C.COOK-UNIT T.Q.C.COOK-UNIT 2 3/4 7-41

<p.R REC>0 p+c/y++*++80O50V<SS p~UNITED STATES NUCLEAR REGULATORY COMMISSION SVASHINGTON, D.C.20555'pss 0 g 1990 Docket No.50-316 P fir.John E.Dolan, Vice President.Indiana and Michigan Electric Company P.0.Box 18 Bowling Green Station Hew York, New York 10004

Dear Hr.Dolan:

On March 18, 1980 you provided information by letter which supports our'eview'of your proposed Technical Speci fication changes to the power peaking limits of the Donald C.Cook Unit No.2.With this submittal, we find that I<CAP-9566 Westinghouse proprietary report is not a necessary basis for our r'eview of your proposed change.Therefore, MCAP 9566 is hereby returned as you requested in your letter dated February 12, 1980.Sincerely,

Enclosure:

As stated A.Schwencer, Chief Operating Reactors Branch dl Division of Operating Reactors cc: See next page tao~eat t o+Abli o be pLthhegd Xo DXsol osme:~

".".C.N.Dunn Duquesne Light Company cc: Gerald Charnoff, Esquire Jay E.Silberg, Esquire Shaw, P ittman, Potts and Trowbridge 1800 i+i Street, H.W.Washington, D.C.20036 Mr.James A.Werling Plant Superintendent Beaver Valley Power Station P.0.Box 4 Shi ppi ngp ort, P ennsy 1 va ni a 15077 Karin Carter, Esquire Special Assistant Attorney General Bureau of Administrative Enforcement 5 h Floor, Executive House Harri sburg, P ennsyl vani a 17120 Mr.Roger Tapan Stone and Webster Engineering Corporation P.0.Box 2325 Boston, Massachusetts 021 07 Mr.F.l)oon R 8 0 Center Westinghouse Electric Corporation Building 7-303 Pi tts burgh, P ennsyl va ni a 15230 B.F.Jones Memorial Libra'ry 663 Franklin Avenue.Aliquippa, Pennsylvania 15001 Mr.John Carey, Dir ctor Nuclear Operations Duquesne Light, Company 435 Sixth Avenue P it ts burgh, P ennsy1 va ni a 15219 Mr.R.E, Martin Duquesne Light Company 435 Sixth Avenue Pittsburgh, Pennsylvania 15219 Mr.John A.Levin Public Utility Coranission P.0.Box 3265 Harri sburg, P ennsy1 vani a 17120 Mr.J.D.Sieber, Superintendent of Licensing and Compliance Duquesne Light Company Post Office Box 4 Shippingport, Pennsylvania 15077 Marvin Fein Utility Counsel City of Pittsburgh 313 City-County Building Pittsburgh, Pennsylvania 15219