| issue date = 06/16/2010
| issue date = 06/16/2010
| title = Letter Change in Schedule for Review of the Kewaunee Power Station License Renewal Application Safety Evaluation (TAC No. MD9408)
| title = Letter Change in Schedule for Review of the Kewaunee Power Station License Renewal Application Safety Evaluation
| author name = Daily J W
| author name = Daily J W
| author affiliation = NRC/NRR/DLR/RPOB
| author affiliation = NRC/NRR/DLR/RPOB

Revision as of 09:44, 9 February 2019

Letter Change in Schedule for Review of the Kewaunee Power Station License Renewal Application Safety Evaluation
ML101600324
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 06/16/2010
From: Daily J W
NRC/NRR/DLR/RPOB
To: Heacock D A
Dominion Energy Kewaunee
References
TAC MD9408
Download: ML101600324 (5)


Text

June 16, 2010 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc. Innsbrook Technical Center - 2SW 5000 Dominion Blvd. Glen Allen, VA 23060-6711

SUBJECT:

CHANGE IN SCHEDULE FOR REVIEW OF THE KEWAUNEE POWER STATION LICENSE RENEWAL APPLICATION SAFETY EVALUATION (TAC NO. MD9408)

Dear Mr. Heacock:

By letter dated August 12, 2008, Dominion Energy Kewaunee, Inc. (Dominion) submitted an application for renewal of operating license DPR-43 for the Kewaunee Power Station. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, "Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants."

Due to request from the Advisory Committee on Reactor Safeguards (ACRS), a schedule change must be made to the ACRS Subcommittee meeting for review of the Safety Evaluation Report (SER) of the Kewaunee Power Station, License Renewal Application. This change also affects certain other milestone dates in the staff's schedule for reviewing this application. The dates for issuing the final SER and for the final decision, Director License Renewal, remain unchanged. Enclosed is a table of affected milestones, along with the old and new dates.

These schedule changes were discussed with Paul Aitken, of your staff. If you have any questions, please contact me by telephone at 301-415-3873 or by e-mail at John.Daily@nrc.gov. Sincerely, /RA/ John Daily, Sr. Project Manager Project Operations Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-305

Enclosure:

Revised Milestone Schedule cc w/encl: See next page June 16, 2010 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc. Innsbrook Technical Center - 2SW 5000 Dominion Blvd. Glen Allen, VA 23060-6711

SUBJECT:

CHANGE IN SCHEDULE FOR REVIEW OF THE KEWAUNEE POWER STATION LICENSE RENEWAL APPLICATION SAFETY EVALUATION (TAC NO. MD9408)

Dear Mr. Heacock:

By letter dated August 12, 2008, Dominion Energy Kewaunee, Inc. (Dominion) submitted an application for renewal of operating license DPR-43 for the Kewaunee Power Station. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, "Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants."

Due to request from the Advisory Committee on Reactor Safeguards (ACRS), a schedule change must be made to the ACRS Subcommittee meeting for review of the Safety Evaluation Report (SER) of the Kewaunee Power Station, License Renewal Application. This change also affects certain other milestone dates in the staff's schedule for reviewing this application. The dates for issuing the final SER and for the final decision, Director License Renewal, remain unchanged. Enclosed is a table of affected milestones, along with the old and new dates.

These schedule changes were discussed with Paul Aitken, of your staff. If you have any questions, please contact me by telephone at 301-415-3873 or by e-mail at John.Daily@nrc.gov. Sincerely, /RA/ John Daily, Sr. Project Manager Project Operations Branch Division of License Renewal Office of Nuclear Reactor Regulation

Docket No. 50-305

Enclosure:

Revised Milestone Schedule cc w/encl: See next page DISTRIBUTION: See next page ADAMS Accession Number: ML101600324 OFFICE PM:DLR:RPOB LA:DLR BC:DLR:RPOB PM:DLR:RPOB NAME JDaily SFigueroa JRobinson JDaily DATE 06/16/10 06/14/10 06/16/10 06/16/10 OFFICIAL RECORD COPY Letter to D. Heacock from J. Daily dated June 16, 2010

SUBJECT:

CHANGE IN SCHEDULE FOR REVIEW OF THE KEWAUNEE POWER STATION LICENSE RENEWAL APPLICATION SAFETY EVALUATION (TAC NO. MD9408)

DISTRIBUTION

HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDraAfpb Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource _ _ _ _ _ _ _ _

J. Daily D. Doyle P. Tam S. Burton, RIII K. Barclay, RIII M. Kunowski, RIII V. Mitlyng, RIII I. Couret, OPA S. Uttal, OGC J. Medoff J. Dozier ENCLOSURE KEWAUNEE POWER STATION LICENSE RENEWAL APPLICATION REVISED MILESTONE SCHEDULE Milestone Old Date New Date Issue Safety Evaluation Report with Open Items 6/4/2010 7/16/2010 ACRS Subcommittee Meeting 7/13/2010 8/18/2010 SER with Open Items - responses received 8/11/2010 9/17/2010 ACRS Full Committee Meeting on SER 12/6/2010 12/2/2010

Kewaunee Power Station cc: Resident Inspectors Office U.S. Nuclear Regulatory Commission N490 Hwy 42 Kewaunee, WI 54216-9510 Mr. Chris L. Funderburk Director, Nuclear Licensing and Operations Support Dominion Resources Services, Inc. Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Thomas L. Breene Dominion Energy Kewaunee, Inc. Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216

Mr. Michael J. Wilson, Director Nuclear Safety & Licensing Dominion Energy Kewaunee, Inc. Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. Daniel G. Stoddard Senior Vice President - Nuclear Operations Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Alan J. Price Vice President - Nuclear Engineering Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. William D. Corbin Director - Nuclear Engineering Innsbrook Technical Center - 3NE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Paul C. Aitken Supervisor - License Renewal Project Innsbrook Technical Center - 3NE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. David A. Sommers Supervisor - Nuclear Engineering Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Ms. Lillian M. Cuoco, Esq. Senior Counsel Dominion Resources Services, Inc. 120 Tredegar Street Riverside 2 Richmond, VA 23219

Mr. Stephen E. Scace Site Vice President Dominion Energy Kewaunee, Inc. Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. David R. Lewis Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, N.W.

Washington, DC 20037-1122 Mr. Ken Paplham E 4095 Sandy Bay Rd. Kewaunee, WI 54216

Mr. Jeff Kitsembel, P.E. Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854