Issue date | Title | Topic | |
---|---|---|---|
ML18107A529 | 10 September 1999 | Revised Event Classification Guide,Including Rev 18 to Table of Contents,Rev 10 to Attachments 6 & 7 & Rev 11 to Attachment 9 | Unanalyzed Condition Fitness for Duty High winds |
ML20216E620 | 10 September 1999 | Revised Event Classification Guide,Including Rev 14 to Table of Contents & Rev 10 to Attachments 6,7 & 9 | Unanalyzed Condition Fitness for Duty High winds Fatality |
ML20211Q877 | 27 August 1999 | Rev 0 to Inservice Testing Manual for Pumps & Valves Program | Stroke time Incorporated by reference Cold shutdown justification Power Operated Valves |
ML18107A512 | 23 August 1999 | Procedure 71151, Performance Indicator Verification. | Significance Determination Process |
ML18107A509 | 23 August 1999 | Attachment 21 to Procedure 71111, Safety Sys Design & Performance Capability. | Significance Determination Process |
ML20206T894 | 12 May 1999 | Revised Event Classification Guide,Including Rev 12 to Table of Contents,Rev 8 to Attachment 8,Rev 8 to Attachment 7 & Rev 8 to Attachment 9 | Unanalyzed Condition Fitness for Duty High winds Fatality |
ML18107A296 | 12 May 1999 | Revised Event Classification Guide,Including Rev 16 to Table of Contents,Rev 8 to Attachment 6,rev 8 to Attachment 7 & Rev 9 to Attachment 9 | Unanalyzed Condition Fitness for Duty High winds |
ML20206G228 | 31 March 1999 | Rev 18 to ODCM for Hope Creek Generating Station | Grab sample Offsite Dose Calculation Manual Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program Power change |
ML20216B064 | 1 May 1998 | Rev 1 to ECG-ATT 14, Four Hour Rept - NRC Operations & Rev 7 to ECG-HECG-TOC, Hope Creek Event Classification Guide Table of Contents/Signature Page | Unanalyzed Condition Fitness for Duty High winds Fatality |
ML18106A557 | 16 April 1998 | Rev 21 to EOP-CFST-1, Shutdown Margin Status Tree & Rev 10 to Table of Contents | Unanalyzed Condition Fitness for Duty High winds Shutdown Margin |
ML20239A125 | 31 March 1998 | Rev 11 to Salem Nuclear Generating Station Odcm | Grab sample Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report |
ML18106A392 | 13 March 1998 | Rev 9 to ECG-SECG-TOC & Rev 2 to ECG-ATT.04, General Emergency. | Unanalyzed Condition Fitness for Duty High winds |
ML18106A828 | 4 March 1998 | Rev 1 to Reactivity Manipulations Documentation Guide. | Power change |
ML20197H851 | 8 December 1997 | Rev 0 to IST Program Submittal Interval 2,Dec 21,1997 Through Dec 20,2006 | Safe Shutdown Ultimate heat sink Stroke time Squib Incorporated by reference Locked High Radiation Area Scram Discharge Volume Cold shutdown justification Power-Operated Valves Power Operated Valves |
ML20198J643 | 10 October 1997 | Rev 0 to 55-WP3/F43TB3-05, Weld Procedure | |
ML18102B668 | 1 October 1997 | Rev 8 to Inservice Testing Manual for Pumps & Valves Program. | Safe Shutdown Boric Acid Stroke time Incorporated by reference Cold shutdown justification Power Operated Valves |
ML18106A829 | 4 September 1997 | Rev 2 to Reactivity Manipulations Documentation Guide. Page to Training Manual NC.TQ-TP.ZZ-0302,encl | |
ML20198J650 | 20 August 1997 | Rev 5 to WP3/F43TB3-05, Welding Procedure Specification | |
ML20198J654 | 20 August 1997 | Rev 3 to 55-PQ7001-03, Procedure Qualification Record | Weld Overlay |
ML18102A794 | 21 January 1997 | Event Classification Guide,Technical Basis, for Hope Creek Generating Station & Salem | |
ML18102A793 | 21 January 1997 | Event Classification Guide,Technical Basis, Salem Generating Station | Safe Shutdown Unanalyzed Condition Boric Acid Time of Discovery Fitness for Duty High winds Shutdown Margin Reactor Vessel Water Level Ultimate heat sink Offsite Dose Calculation Manual Safe Shutdown Earthquake Internal Flooding Met Tower NJPDES Operating Basis Earthquake Design basis earthquake Earthquake Deep Dose Equivalent Pressure Boundary Leakage Stolen |
ML18102A666 | 19 November 1996 | Rev 2 to Pse&G Simulation Facility Certification Program. | Stroke time Power change |
ML20115B779 | 3 July 1996 | Final Draft, Hope Creek Event Classification Guide, Sections 1-9 | Safe Shutdown Unanalyzed Condition Time of Discovery High winds Shutdown Margin Packing leak Ultimate heat sink Grab sample Offsite Dose Calculation Manual Internal Flooding Met Tower Operating Basis Earthquake Design basis earthquake Earthquake Fuel cladding Pressure Boundary Leakage Pressure boundary leak Power change |
ML20096F474 | 13 January 1996 | Revised Hope Creek Generating Station Event Classification Guide, Including Rev 45 to Table of Contents,Rev 39 to Attachments Signature Page,Rev 26 to Attachment 6,Rev 26 to Attachment 7 & Rev 26 to Attachment 9 | Earthquake Fatality |
ML20096C223 | 19 December 1995 | Rev 0 to HC.SA-AP.ZZ-0005(Z), Operational Readiness Self Assessment Program | Scaffolding |
ML20096C215 | 26 November 1995 | Rev 0 to Hope Creek RF06 Outage Completion Plan | Temporary Modification |
ML20094P115 | 14 November 1995 | Revised Hope Creek Event Classification Guide, Including Rev 44 to Table of Contents,Rev 38 to Attachments Signature Page & Rev 25 to Attachments 6,7 & 9 | Earthquake |
ML18101B114 | 14 November 1995 | Revised Salem Generating Station Event Classification Guide, Including Rev 46 to Table of Contents,Rev 37 to Attachments Signature Page,Rev 26 to Attachment 6,Rev 25 to Attachment 7 & Rev 24 to Attachment 9 | |
ML20091M991 | 15 October 1995 | Event Classification Guide HCGS, Including Revised Eals, Technical Basis Document & NUMARC EAL-to-Hope Creek Comparison Summary | Safe Shutdown Unanalyzed Condition Time of Discovery Fitness for Duty High winds Shutdown Margin Reactor Vessel Water Level Packing leak Ultimate heat sink Grab sample Offsite Dose Calculation Manual Internal Flooding Met Tower Operating Basis Earthquake Design basis earthquake Earthquake Fuel cladding Pressure Boundary Leakage Pressure boundary leak Stolen Power change Fatality |
ML20086G134 | 21 July 1995 | Rev 42 to Hope Creek Generating Station Event Classification Guide | Safe Shutdown Earthquake |
ML18101A691 | 31 May 1995 | Nbu Issue Mgt & Prioritized Action Plan, Dtd May 1995 | NJPDES Temporary Modification Missed surveillance Foreign Material Exclusion Systematic Assessment of Licensee Performance Power change |
ML18101A771 | 11 May 1995 | Rev 1A to Vol a of Salem Generating Station Unit 2 Second 10-Yr Insp Interval ISI Program Plan. | Liquid penetrant |
ML20134K083 | 27 February 1995 | Pse&G/Nuclear Business Unit Organizational Effectiveness Assessment Plan, | |
ML18101A676 | 16 February 1995 | Rev 12 to EOP 1-EOP-TRIP-2, Reactor Trip Response. | |
ML18101A675 | 16 February 1995 | Rev 11 to EOP 1-EOP-TRIP-1, Reactor Trip or Safety Injection. | |
ML18101A538 | 27 January 1995 | Revised Salem Generating Station Event Classification Guide. | Earthquake |
ML20076F902 | 14 October 1994 | Event Classification Guide | Earthquake |
ML20073D367 | 20 September 1994 | Rev 3 to IST Program,Including Review Sheets to Add 17 Valves,Three Revised Pump Review Sheets,Reflecting Testing Requirements of Relief Request P3 & Review Sheets for Two Valves Which Had Testing Requirements Changed | Stroke time Hydrostatic Probabilistic Risk Assessment Fast acting solenoid valve Cold shutdown justification Power Operated Valves |
ML18101A211 | 17 August 1994 | Revised Salem Event Classification Guide. | Earthquake |
ML20071J980 | 15 July 1994 | Revised Hope Creek Event Classification Guide | Met Tower Operating Basis Earthquake Design basis earthquake Earthquake Fuel cladding Fatality |
ML18101A677 | 11 July 1994 | Rev 10 to EOP 1-EOP-TRIP-3, Safety Injection Termination. | |
ML20069N207 | 9 June 1994 | Revised Hope Creek Generating Station Event Classification Guide,Including Rev 33 to Table of Contents,Rev 12 to Attachment 1,Page 5 & Rev 7 to Attachment 2,Page 4 | |
ML20069D296 | 21 May 1994 | Revised Event Classification Guide,Including Rev 33 to Table of Contents,Rev 28 to Attachments Signature Page,Rev 12 to Attachment 1,Rev 7 to Attachment 2,Rev 7 to Attachment 3,Rev 6 to Attachment 4 & Rev 18 to Attachment 6 | Safe Shutdown Earthquake |
ML20147B160 | 23 April 1994 | Rev 3 to S1.OP-SO.CW-0001(Z), Circulating Water Pump Operation | |
ML18100A808 | 7 January 1994 | Rev 30 to Salem Generating Station Event Classification Guide. | Safe Shutdown Unanalyzed Condition Fire Barrier Met Tower Annual Radiological Environmental Operating Report Earthquake Fatality |
ML20147B094 | 13 December 1993 | Rev 10 to Procedure HC.IC-GP.ZZ-0008(Q), Maint Troubleshooting & Known Component Problems | Half scram Temporary Modification |
ML20147B149 | 2 November 1993 | Rev 2 to Procedure S1.OP-SO.CW-0001(Z), Circulating Water Pump Operation | NJPDES |
ML20046D331 | 9 August 1993 | Rev 3 to Section 7,Page 3 of Hope Creek Event Classification Guide, Rev 28 | |
ML18100A420 | 15 June 1993 | Justification for Sgs Units 1 & 2 Restart & Operation Rod Control Sys Failures. | |
ML18100A377 | 5 May 1993 | Rev 27 to Salem Generating Station Event Classification Guide. | Safe Shutdown Earthquake |