Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML20212G08220 August 1999Rev 4 to Augmented Inservice Insp Plan for Cpses,Unit 1Non-Destructive Examination
Control of Heavy Loads
Flow Induced Vibration
ML20212H07720 August 1999Rev 6 to CPSES Glen Rose,Tx ASME Section XI ISI Program Plan for 1st Interval on 990820. Page 119 in Unit 1 ASME Section XI of Incoming Submittal Not Included
ML20211M0045 August 1999Rev 31 to Technical Requirements Manual
ML20211G74027 July 1999Revs 29 & 30 to Technical Requirements Manual (TRM) for Cpses,Units 1 & 2Safe Shutdown
Boric Acid
Shutdown Margin
High Radiation Area
Ultimate heat sink
Offsite Dose Calculation Manual
Tornado Missile
Hydrostatic
Earthquake
ML20206Q03116 April 1999Rev 28 to CPSES Technical Requirements Manual
ML20205Q16814 April 1999Rev 27 to CPSES Technical Requirements Manual
ML20203B00125 January 1999Rev 10 to Security Training & Qualification Plan
ML20211C10715 January 1999Rev 3 to ASME Section XI ISI Program Plan,Unit 2 - 1st Interval
ML20236T99320 July 19981RF06 ISI Summary Rept First Interval,Third Period,First Outage for CPSES Unit 1, Commerical Operating Date 900830
ML20154C45120 July 1998Interim Change Request ISI-1R5-01, Unit 1 ISI Plan,Rev 5VT-2
Liquid penetrant
Dissimilar Metal Weld
ML20216B28124 April 1998Rev 13 to Cpses,Units 1 & 2,IST Plan for Pumps & Valves First Interval
ML20203J61524 February 1998Rev 26 to Technical Requirements Manual
ML20217P15312 February 1998Rev 2 to ISI-2R2-01, Unit 2 ISI Plan
ML20217P29630 January 1998Rev 5 to Unit 1 ISI Program Plan
ML20202E59825 November 1997Rev 12 to CPSES Units 1 & 2 IST Testing Plan for Pumps & Valves,First Interval
ML20212E9816 October 1997Rev 11 to CPSES Units 1 & 2 IST Plan for Pumps & Valves First Interval
ML20210S3913 September 1997Rev 10 to CPSES Units 1 & 2 Inservice Testing Plan for Pumps & Valves in First Interval
ML20151L13931 July 19975 to Technical Requirements Manual, for Plant
ML20141E62026 June 1997Rev 24 of CPSES Units 1 & 2 Technical Requirements Manual
ML20141F84726 June 1997Rev 9 to IST Plan for Pumps & Valves First Interval
ML20136G43613 March 1997Rev 23 to CPSES Units 1 & 2 Technical Requirements Manual
ML20135A82424 February 1997Rev 22 to CPSES Units 1 & 2 Technical Requirements Manual
ML20134C68331 January 1997Rev 8 to Comanche Peak Steam Electric Station Units 1 & 2 Inservice Testing Plan for Pumps & Valves First IntervalBoric Acid
Stroke time
Power Operated Valves
ML20134M43713 November 1996Self Assessment Guide Program Guidelines
ML20129A59916 October 1996Rev 7 to CPSES Unit 1 & 2 IST Plan for Pumps & Valves First Interval
ML20128G7662 October 1996CPSES Unit 1 & 2 Inservice Testing Plan for Pumps & Valves First Interval
ML20138B5181 October 1996Rev 14 to ODCM for TU Electric CPSES Units 1 & 2Grab sample
Offsite Dose Calculation Manual
Annual Radioactive Effluent Release Report
Annual Radiological Environmental Operating Report
Process Control Program
Power change
ML20117C84619 July 1996Glen Rose,Tx ASME Section XI ISI Program Plan,Unit 1 - 1st Interval Rev 4Boric Acid
Non-Destructive Examination
VT-2
Liquid penetrant
ML20217M16924 May 1996Rev 3 to STA-750, Check Valve Reliability Program
ML20117C6183 May 1996Rev 1 to Unit 2 ISI Plan
ML20117C61414 April 1996Rev 1 to Unit 2 ISI PlanHydrostatic
VT-2
ML20107J0942 April 1996Rev 1 to Interim Change Request ISI-2, CPSES Unit 2 ASME Section XI ISI Program PlanVT-2
ML20107E4479 February 1996Rev 1 of CPSES ASME XI ISI Program Plan Unit 2
ML20100B94724 January 1996Rev 21 of CPSES Units 1 & 2 Technical Requirements ManualStroke time
ML20086C54930 June 1995Rev 20 to Technical Requirements ManualOffsite Dose Calculation Manual
Earthquake
ML20091L19429 March 1995Interim Change Request ISI-IR3-003, Unit 1 ISI PlanVT-2
ML20081F11312 March 1995Interim Change Request ISI-1R3-02 to Rev 3 to Unit 1 ISI Plan
ML20080Q33524 February 1995Rev 17 to CPSES Technical Requirements Manual
ML20078R63715 February 1995Rev 5 to CPSES Unit 1 & 2 IST Plan for Pumps & Valves First IntervalBoric Acid
Stroke time
Power Operated Valves
ML20078H85030 November 1994CPSES Odmc Rev Change SheetSafe Shutdown
Grab sample
Offsite Dose Calculation Manual
ML20073L6596 October 1994Rev 4 to CPSES Unit 1 & 2 IST Plan for Pumps & Valves First Interval
ML20072C70824 July 1994Rev 16 to Simulator Operations/Maint Instruction - 010, Simulator Certification Testing
ML20069E51717 May 1994Interim Change Request ISI-2RO-001, Comanche Peak Ses Unit 2 ISI Program Plan
ML20029D07111 May 1994Rev 16 to Technical Requirements Manual.
ML20065K17215 April 1994Rev 15 to CPSES Units 1 & 2 Technical Requirements Manual
ML20058E38430 November 1993Rev 14 to Technical Requirements Manual, Page 2-27, Clarifying Discussion in Table 2.1.1 Notations for Local Test Connections,Vent & Drain Valves & Revising List of Effective Pages EPL-1 Through EPL-4
ML20058C44423 November 1993IST Plan for Pumps & Valves First Interval, Rev 3
ML20058B57919 November 1993Rev 14 to Comanche Peak Steam Electric Station Technical Requirements Manual
ML20058J97119 November 1993Interim Change Request ISI-1R2-005 to Rev 2 to Unit 1 ISI PlanHydrostatic
ML20056D81611 August 1993Salp,Directive 8.6Systematic Assessment of Licensee Performance