ML20217N89115 October 1999Forwards Rept of Changes,Tests & Experiments at Pilgrim Nuclear Power Station for Period of 970422-990621,IAW 10CFR50.59(b).List of Changes Effecting Fsar,Encl
ML20217F58413 October 1999Requests Revocation of License OP-11038-1 for GE Kingsley. Individual Has Been Reassigned to Position within Naesco
ML20217F58113 October 1999Forwards Insp Data & Naesco Evaluation of a EDG Exhaust Insp Conducted on 990407.Insp Ensured That Unacceptable Wall Thinning Will Not Occur During 40-year Design Lifetime of Sys
ML20217F12612 October 1999Forwards Update to Previously Submitted RELAP5 Analytical Assumptions for App R,Re RAI of 961104Safe Shutdown
BVY-99-130, Provides Clarification of Method for Determining MSIV Maximum & Minimum Pathway at Vermont Yankee Nuclear Power Station8 October 1999Provides Clarification of Method for Determining MSIV Maximum & Minimum Pathway at Vermont Yankee Nuclear Power Station
BVY-99-128, Submits Listed Addl Info in Support of 990414 Request for Clarification to SER Confirming Adequacy of Space Cooling for HPCI & RCIC Sys,Re Item II.K.3.24 of NUREG-0737.Copy of NEDE-24955,encl6 October 1999Submits Listed Addl Info in Support of 990414 Request for Clarification to SER Confirming Adequacy of Space Cooling for HPCI & RCIC Sys,Re Item II.K.3.24 of NUREG-0737.Copy of NEDE-24955,encl
ML20217C3156 October 1999Forwards Scenario Package for Pilgrim Nuclear Power Station Nrc/Fema Evaluated Exercise Scheduled for 991207.Without Encl
ML20217D5595 October 1999Documents Pilgrim Nuclear Power Station Five Yr Survey of Main Breakwater.Survey Has Determined That Pilgrim Main Breakwater Is Intact & Remains Adequately Constructed to Perform Designed Safety Function
ML20217C8055 October 1999Forwards Proprietary Results of Audiologic Evaluations for Jp Giar,License SOP-10061-3.Attachment Clearly Shows Requirements for Operator Hearing Ability Are Met. Proprietary Info Withheld,Per 10CFR2.790(a)(6)
ML20217B8625 October 1999Forwards Rev 28,change 1 to EPIP Er 1.1, Classification & Emergencies, Per 10CFR50.54(q).Rev to Procedure Does Not Decrease Effectiveness of Seabrook Station Radiological Emergency Plan
ML20217B7471 October 1999Provides Notification of Change in PCT of More than 50 F,Per Requirements of 10CFR50.46(a)(3)(i),(ii).Tabulation of Large Break LOCA PCT Margin Utilization Applicable to Seabrook Station,Encl
ML20216J35329 September 1999Responds to NRC Re Violations Noted in Insp Rept 50-271/99-12 on 990628-0811.Corrective Actions:Based on RFO 20 Maint Rule Outage Performance Review,Task Was Generated to Clarify & Enhance SD Monitoring ProcessMaintenance Rule Program
ML20216J99629 September 1999Forwards Resume of Person Identified as Acting RPM in Licensee to NRC Re Notification That Person Named in License Condition 11 of 20-07626-02,is No Longer Employed at Pilgrim Station.Resume Withheld,Per 10CFR2.790
BVY-99-122, Notifies of Intention to Reinstate Original Version of App F in FSAR & Correct Docket Re Assumption That Electrical Power Sys Are Designed IAW Requirements of GDC-1728 September 1999Notifies of Intention to Reinstate Original Version of App F in FSAR & Correct Docket Re Assumption That Electrical Power Sys Are Designed IAW Requirements of GDC-17
ML20212H13823 September 1999Submits Info in Support of Request Filed on 990730 to Grant one-time Exemption from 10CFR50,App E,Authorizing Biennial Full Participation Emergency Preparedness Exercise to Be Conducted in 2002 Instead of 2001
ML20212H14423 September 1999Withdraws 990121 Request for License Change Re Emergency Core Cooling Sys Net Positive Suction Head,Due to Incorrect Datum Preparation
BVY-99-114, Provides Notification That Licensee Completed Y2K Remediation Efforts Described in Util 990608 Response to NRC GL 98-01,Suppl 121 September 1999Provides Notification That Licensee Completed Y2K Remediation Efforts Described in Util 990608 Response to NRC GL 98-01,Suppl 1
ML20212G50721 September 1999Submits Complaint to NRC Re NRC Failure to Cite Seabrook Station NPP Operators for Failing to Periodically Calibrate & Establish Adequate Measures to Insure That Relay Equipment Met All Required Calibration Settings Prior to Installation
BVY-99-116, Informs of Determination That Wh Schulze,License SOP-10528-1,will No Longer Maintain License at Facility. Termination of License Requested21 September 1999Informs of Determination That Wh Schulze,License SOP-10528-1,will No Longer Maintain License at Facility. Termination of License Requested
BVY-99-113, Requests Approval to Perform Alternative Testing to That Specified by ASME Boiler & Pressure Vessel Code,Section XI & Asme/Ansi OM, Operation & Maint of Nuclear Power Plants. Attachment 1 Provides Justification for Alternative Testing21 September 1999Requests Approval to Perform Alternative Testing to That Specified by ASME Boiler & Pressure Vessel Code,Section XI & Asme/Ansi OM, Operation & Maint of Nuclear Power Plants. Attachment 1 Provides Justification for Alternative Testing
BVY-99-121, Requests Extension Until 990929 to Respond to Violations Noted in Insp Rept 50-271/99-12,dtd 990819.Licensee Did Not Receive Rept Until 990830 & Addl Time Is Needed to Prepare & Allow for Adequate Review of Violation Response Submittal20 September 1999Requests Extension Until 990929 to Respond to Violations Noted in Insp Rept 50-271/99-12,dtd 990819.Licensee Did Not Receive Rept Until 990830 & Addl Time Is Needed to Prepare & Allow for Adequate Review of Violation Response Submittal
ML20212B95117 September 1999Forwards NRC Form 396 for MG Sketchley,License SOP-10685, Along with Supporting Medical Exam Info.Nrc Form 396 Has Been Superceded by Revised Version Dtd 971222,which Was Previously Submitted to NRC on 990812.Encl Withheld
BVY-99-115, Forwards non-proprietary & Proprietary Responses to 990714 RAI Re Civil & Mechanical Engineering Considerations for Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355.Proprietary Encls Withheld16 September 1999Forwards non-proprietary & Proprietary Responses to 990714 RAI Re Civil & Mechanical Engineering Considerations for Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355.Proprietary Encls WithheldSafe Shutdown Earthquake
Hydrostatic
Operating Basis Earthquake
Earthquake
BVY-99-118, Responds to RAI Concerning GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions16 September 1999Responds to RAI Concerning GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions
ML20216F34516 September 1999Forwards Summary Rept Providing Results of ISI Conducted at PNPS on-line & Refueling Outage (RFO 12)
ML20212C36215 September 1999Forwards Rev 34 to Seabrook Station Radiological Emergency Plan & Rev 85 to Seabrook Station Emergency Response Manual, Per 10CFR50,App E & 10CFR50.4
ML20216E7119 September 1999Forwards License Renewal Application Including Form NRC-398 & Form NRC-396 for Jp Giar,License SOP-10061-3.Without Encls
ML20211Q8528 September 1999Informs That Rl Couture,License SOP-11027,terminated Employment at Naesco on 990907.Revocation of License Requested
ML20216E5897 September 1999Forwards Copy of Pilgrim Station Organization Structure. Encl Refelcts Changes in Upper Mgt Level Structure.Changes Were Effective 990901
ML20211M4503 September 1999Informs That Pilgrim Nuclear Power Station Plans to Conduct Full Participation Emergency Preparedness Exercise with Commonwealth of Ma on 991207,IAW 10CFR50,App E,Section IV.F.2
ML20211N8783 September 1999Forwards Response to 990820 RFI Re NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing ExamsGeneric Fundamentals Examination
ML20211J9293 September 1999Forwards mark-ups & Retypes of Proposed Conforming License Changes Required in Connection with Transfers Being Sought in 990615 Application of Montaup Electric Co & New England Power Co for Transfer of Licenses & Ownership InterestsSafe Shutdown
Fire Protection Program
ML20211M3222 September 1999Responds to NRC Re Violations Noted in Insp of License NPF-86 & Proposed Imposition of Civil Penalty. Corrective Actions:Conducted Prompt Review of Layoff Decision to Determine Relevant Facts
ML20211J8411 September 1999Forwards Updated NRC Form 396 for E Decosta,Nrc License OP-10655-1.Without Encl
ML20211J8811 September 1999Forwards Comments on Seabrook Station Review of Reactor Vessel Integrity Database (Rvid)(Version 2).Minor Discrepancies Were Noted.Proposed Changes Are Encl in Order to Correct Discrepancies
BVY-99-111, Informs That Encl TS Bases Page 91 Has Been Revised to Allow Reactivity Anomaly BOC Steady State Core Reactivity to Be Normalized Between off-line Uncorrected Solution & on-line 3D-Monicore Exposure Corrected Solution31 August 1999Informs That Encl TS Bases Page 91 Has Been Revised to Allow Reactivity Anomaly BOC Steady State Core Reactivity to Be Normalized Between off-line Uncorrected Solution & on-line 3D-Monicore Exposure Corrected Solution
BVY-99-110, Informs of Util Intent to Replace Commitments Made in Licensee & Subsequently Ack in NRC with Containment Insp Criteria Defined in 10CFR50.55a(b)(2)(vi),per Drywell Coating Insp31 August 1999Informs of Util Intent to Replace Commitments Made in Licensee & Subsequently Ack in NRC with Containment Insp Criteria Defined in 10CFR50.55a(b)(2)(vi),per Drywell Coating Insp
ML20211M91631 August 1999Submits Review & Correction of Info in Reactor Vessel Integrity Database (Rvid),Version 2,re Pilgrim Station
ML20211J83930 August 1999Forwards Rev 1 to Provisional Decommissioning Trust Agreement for Plant,Changing Portions of Agreement to Permit Up to Two Distributions & Clarify Formula for Distribution
ML20211G91927 August 1999Informs NRC That Name of New Company, Ref in Order Approving Application Re Corporate Merger Is Nstar Which Is Massachusetts Business Trust
BVY-99-107, Submits Response to NRC RAI Re Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355 Fuel Assemblies26 August 1999Submits Response to NRC RAI Re Proposed Change to TS to Increase Spent Fuel Storage Capacity from 2,870 to 3,355 Fuel AssembliesUltimate heat sink
ML20211G77624 August 1999Expresses Great Concern Re Lack of Enforcement Actions Against Seabrook Station Despite Citations NRC Has Issued for Violations of Seabrook Operating License
ML20211J21723 August 1999Expresses Disappointment with Lack of Enforcement Action Against Seabrook Station Despite Repeated Safety Violations
ML20211J49721 August 1999Submits Comments Re Violations Cited in Early Mar & 990509 Insps
ML20211H83619 August 1999Submits Concerns Re Violations at Seabrook Station
BVY-99-108, Requests That Gv Bogue,Bj Croke,Vs Ferrizzi,Me French, Bk Mcnutt,Jf Meyer & DM Navarro Take BWR Gfes of OL Exam Administered on 991006.DA Daigler & ST Brown Will Have Access to Exams Before Tests Administered19 August 1999Requests That Gv Bogue,Bj Croke,Vs Ferrizzi,Me French, Bk Mcnutt,Jf Meyer & DM Navarro Take BWR Gfes of OL Exam Administered on 991006.DA Daigler & ST Brown Will Have Access to Exams Before Tests AdministeredGeneric Fundamentals Examination
ML20211C33819 August 1999Provides semi-annual LTP Update,Including Schedule, Commitment Descriptions,Progress Since Last Update & Summary of Changes.Rev Bars Indicate Changes in Status Since Last SubmittalSafe Shutdown
Ultimate heat sink
Coatings
Foreign Material Exclusion
Severe Accident Management Guideline
Maintenance Rule Program
BVY-99-103, Informs That Util Expects to Submit Approx Twenty Licensing Actions in FY00 & FY01,in Response to Administrative Ltr 99-0218 August 1999Informs That Util Expects to Submit Approx Twenty Licensing Actions in FY00 & FY01,in Response to Administrative Ltr 99-02
ML20211B38416 August 1999Forwards Response to NRC Second RAI Re Pressure Locking & Thermal Binding of SR power-operated Gate ValvesStroke time
Weak link
ML20211J32415 August 1999Expresses Disappointment in Apparent Failure of NRC to Cite Seabrook Station NPP for Recent Violations of Safety Regulations Uncovered During Recent Insps in Mar & May