ML20217P206 | 26 October 1999 | Forwards for First Energy Nuclear Operating Co Insp Rept 50-346/99-17 on 990928-1001.Insp Was Exam of Activities Conducted Under License Re Implementation of Physical Security Program.No Violations Identified | |
IR 05000412/1999007 | 21 October 1999 | Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System | Zebra Mussel Biofouling |
ML20217N385 | 20 October 1999 | Forwards RAI Re Licensee 990521 Request for License Amend to Allow Irradiated Fuel to Be Stored in Cask Pit at Davis-Besse,Unit 1.Response Requested within 60 Days from Receipt of Ltr | |
ML20217M159 | 19 October 1999 | Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates | |
ML20217N232 | 15 October 1999 | Requests NRC Approval to Use Alternative to Requirements of 10CFR50.55a(f)(4)(ii).Licensee Requests Extension to Specified Schedule for Implementing Updates to IST Program | Safe Shutdown Stroke time Incorporated by reference Power-Operated Valves |
ML20217G920 | 14 October 1999 | Discusses Utils Request for Approval of Quality Assurance Program Changes | |
PY-CEI-NRR-2438, Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl | 14 October 1999 | Informs That DBNPS & Pnpp Staffs Have Modified or Withdrawn Several of Positions Proposed within Re Request for Approval of Qap.Revised Positions Encl | |
ML20217F390 | 14 October 1999 | Discusses Request That Proprietary Document NEDE-32907P,DRF A22-0084-53, Safety Analysis Rept for Perry NPP 5% Power Uprate, Class III Dtd Sept 1999 Be Withheld.Determined Document Proprietary & Will Be Withheld | |
PY-CEI-NRR-2435, Responds to NRC Re Violations Noted in Insp Rept 50-440/99-13.Corrective Actions:Ts SRs with Incorrect Descriptions Were Annotated to Ensure That CR Operators Are Aware That ACs Are Effect | 13 October 1999 | Responds to NRC Re Violations Noted in Insp Rept 50-440/99-13.Corrective Actions:Ts SRs with Incorrect Descriptions Were Annotated to Ensure That CR Operators Are Aware That ACs Are Effect | |
L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct | 11 October 1999 | Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct | |
L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections | 11 October 1999 | Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections | Boric Acid High Radiation Area VT-2 Scaffolding |
ML20217C674 | 8 October 1999 | Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr | |
ML20217F837 | 8 October 1999 | Forwards Insp Rept 50-346/99-10 on 990802-0913.One Violation Occurred Being Treated as NCV | |
L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program | 7 October 1999 | Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program | Time of Discovery Zebra Mussel |
ML20217E030 | 7 October 1999 | Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling | |
ML20216J962 | 30 September 1999 | Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified | |
ML20212L069 | 30 September 1999 | Forwards,For Review & Comment,Copy of Preliminary ASP Analysis of Operational Condition Discovered at Unit 1 on 981014,as Reported in LER 346/98-011 | |
ML20217A564 | 30 September 1999 | Informs of Completion of mid-cycle PPR of Davis-Besse on 990901.Informs That NRC Plans to Conduct Addl Insps to Address Questions Raised by Issues Re Operator Errors & Failure to Commit to JOG Topical Rept on MOV Verification | |
ML20212K807 | 30 September 1999 | Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility | Biofouling |
ML20212M266 | 30 September 1999 | Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application | |
ML20217E711 | 30 September 1999 | Documents Telcon Conducted on 990929 Between M Underwood of Oh EPA & D Tizzan of Pnpp,Re Request to Operate Pnpp Sws,As Is,Until Resolution Can Be Obtained | |
ML20212J145 | 30 September 1999 | Forwards Order,In Response to 990505 Application PY-CEI/NRR- 2394L.Order Approves Conforming License Amend Which Will Be Issued & Made Effective When Transfer Completed | |
ML20212K927 | 30 September 1999 | Refers to 990927 Meeting Conducted at Perry Nuclear Power Plant to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PSA Staff | |
L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion | 28 September 1999 | Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion | |
L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 | 24 September 1999 | Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 | |
ML20212G416 | 24 September 1999 | Informs of Completion of Licensing Action for Generic Ltr 98-01, Y2K Readiness of Computer Systems at Nuclear Power Plants, for Perry Nuclear Power Plant | |
ML20216J670 | 24 September 1999 | Forwards Post Examination Documentation for Written Operator Initial License Examination Administered at Davis-Besse Nuclear Power Station on 990920.Without Encls | |
ML20212G581 | 23 September 1999 | Informs That Licenses for Ta Lentz,License SOP-31449,PJ Arthur,License SOP-30921-1 & Dp Mott,License SOP-31500 Are Considered to Have Expired,Iaw 10CFR50.74(a),10CFR55.5 & 10CFR55.55 | |
ML20212G060 | 23 September 1999 | Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile | |
ML20212C552 | 21 September 1999 | Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers | |
ML20212D350 | 21 September 1999 | Forward Copy of Final Accident Sequence Precursor Analysis of Operational Event at Plant,Unit 1 on 980624,reported in LER 346/98-006 | High winds Probabilistic Risk Assessment Condition Adverse to Quality Tornado Generated Missile Biofouling |
PY-CEI-NRR-2432, Forwards NRC Form 536, Operator Licensing Exam Data, in Response to Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams | 21 September 1999 | Forwards NRC Form 536, Operator Licensing Exam Data, in Response to Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams | Generic Fundamentals Examination |
L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 | 20 September 1999 | Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 | Generic Fundamentals Examination |
PY-CEI-NRR-2428, Submits Resolution to Seventh Question Proposed within NRC 980615 RAI Relating to Cooling Water Sys That Serve Containment Air Coolers & Assessment,Post Accident,Of Potential Water Hammer & two-phase Flow Conditions | 16 September 1999 | Submits Resolution to Seventh Question Proposed within NRC 980615 RAI Relating to Cooling Water Sys That Serve Containment Air Coolers & Assessment,Post Accident,Of Potential Water Hammer & two-phase Flow Conditions | |
ML20212B329 | 16 September 1999 | Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 | |
L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC | 15 September 1999 | Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC | |
ML20212D015 | 14 September 1999 | Requests Cancellation of NPDES Permit 3II00036.Permit Has Been Incorporated in Permit 3IB00016*ED.Discharge Point Sources & Associated Fees Currently Covered Under Permit 3IB00016*ED | |
ML20212A837 | 13 September 1999 | Forwards Insp Rept 50-440/99-13 on 990712-30 & Notice of Violation.Insp Included Evaluation of Engineering Support, Design Change & Modification Activities,Internal Assessment Activities & Corrective Actions | |
ML20217A897 | 9 September 1999 | Forwards Insp Rept 50-440/99-09 on 990709-0825.One Violation of NRC Requirements Occurred & Being Treated as NCV, Consistent with App C of Enforcement Policy | |
PY-CEI-NRR-2431, Forwards Revised Emergency Plan for Perry NPP, IAW 10CFR50.54(q).Changes Constitute Revs,Temporary Changes or Reissued Pages | 9 September 1999 | Forwards Revised Emergency Plan for Perry NPP, IAW 10CFR50.54(q).Changes Constitute Revs,Temporary Changes or Reissued Pages | |
05000346/LER-1998-001, Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached | 9 September 1999 | Forwards Rev 1 for LER 1998-001,which Updates Corrective Actions & Revises Completion Date Re Implementation of Changes to Plant Emergency Operating Procedure.List of Commitments Attached | |
ML20211Q343 | 8 September 1999 | Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 | |
ML20211Q560 | 7 September 1999 | Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys | Biofouling |
ML20216E596 | 7 September 1999 | Forwards Application for Amend to License NPF-3,revising Tech Specs 3/4.3.2.1,safety Features Actuation Sys Instrumentation & Associated Bases 3/4.3.1 & 3/4.3.2,reactor Protection Sys & Safety Sys Instrumentation | |
ML20211P300 | 7 September 1999 | Forwards FEMA Transmitting FEMA Evaluation Rept for 990504 Emergency Preparedness Exercise at Davis-Besse Nuclear Power Plant.No Deficiencies Identified.One Area Requiring C/A & Two Planning Issues Identified | |
ML20211Q691 | 6 September 1999 | Informs That NRC Tentatively Scheduled Initial Licensing Exam for Perry Operator License Applicants During Wks of 010108 & 15.Validation of Exam Will Occur at Station During Wk of 001218 | |
L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) | 3 September 1999 | Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) | |
L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods | 2 September 1999 | Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods | |
L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls | 2 September 1999 | Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls | |
L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl | 31 August 1999 | Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl | Stroke time Cold shutdown justification |