Letter Sequence Meeting |
---|
|
Results
Other: L-02-010, Independent Spent Fuel Storage Installation Submittal of License Application Amendment 1 (TAC L23399), ML020980082, ML020980126, ML022950286, ML022950304, ML032320119, ML040350009, ML052370264, ML052380142, ML052510118, ML062980229
|
MONTHYEARML0203505932002-02-0101 February 2002 Memo to C. L. Miller from: T. J. Kobetz Subject: Summary of the January 24, 2002, Meeting Between the Nuclear Regulatory Commission Staff and Pacific Gas and Electric, Co. Enclosures: 1.) Attendance List; and 2) PG&E Project Slides Project stage: Meeting ML0208401812002-03-25025 March 2002 Ltr to L. Womack, Diablo Canyon Power Plant, Acceptance Review for the Diablo Canyon Independent Spent Fuel Storage Installation Application Project stage: Acceptance Review ML0209800822002-04-0505 April 2002 Ltr to L. Womack, Diablo Canyon Power Plant, Public Disclosure Determination Project stage: Other ML0209801262002-04-0505 April 2002 Ltr to L. Womack, Pg&E, Public Disclosure Determination Project stage: Other ML0210701182002-04-17017 April 2002 Meeting Summary Between the NRC Staff and Pacific Gas and Electric Company to Discuss Pg&G'S Geology, Round Motion & Other Geotechnical Studies Project stage: Meeting ML0224700252002-09-0404 September 2002 Meeting with Pacific Gas & Electric to Discuss NRC Staff'S Request for Additional Information 10 CFR Part 72 License Application for Independent Spent Fuel Storage Installation at Diablo Canyon Project stage: RAI ML0226805842002-09-26026 September 2002 Summary of Meeting with Pacific Gas & Electric Co Re Diablo Canyon Independent Spent Fuel Storage Installation - 09/26/02 Memo to C.L. Miller from J.R. Hall Project stage: Meeting L-02-010, Independent Spent Fuel Storage Installation Submittal of License Application Amendment 1 (TAC L23399)2002-10-15015 October 2002 Independent Spent Fuel Storage Installation Submittal of License Application Amendment 1 (TAC L23399) Project stage: Other ML0229502862002-10-15015 October 2002 ISFSI Safety Analysis Report - Amendment 1 to Diablo Canyon Independent Spent Fuel Storage Installation Submittal of License Application Amendment 1, List of Current Pages - Section 4.7.6 Project stage: Other ML0229503042002-10-15015 October 2002 ISFSI Safety Analysis Report - Amendment 1 to Diablo Canyon Independent Spent Fuel Storage Installation Submittal of License Application Amendment 1, Table 4.3-1 - Section 8.2.2 Project stage: Other ML0300305682003-01-0303 January 2003 Closed Meeting Notice for Pacific Gas and Electric from 9 Am to 11am at the Us Nuclear Regulatory Commission, Conference Room O13B-2, Rockville, MD 20852 to Discuss NRC Staff'S 12/06/2002 Request for Additional Information Project stage: RAI DCL-03-007, Response to Request for Additional Information for Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI) Physical Security Program and Associated Revised Request for Exemption to Two 10 CFR 73.55 Requirements2003-01-31031 January 2003 Response to Request for Additional Information for Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI) Physical Security Program and Associated Revised Request for Exemption to Two 10 CFR 73.55 Requirements Project stage: Response to RAI L-03-007, Supplemental Slope Stability Design Mitigation Features Information to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application2003-05-0606 May 2003 Supplemental Slope Stability Design Mitigation Features Information to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application Project stage: Supplement ML0315606872003-05-0606 May 2003 Supplemental Slope Stability Design Mitigation Features Information to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application, Enclosure 2 Project stage: Supplement ML0315606902003-05-0606 May 2003 Supplemental Slope Stability Design Mitigation Features Information to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application, Crsp Input File Through References Project stage: Supplement L-03-008, Additional Questions Related to Supplemental Blasts & Explosions Responses to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application2003-06-13013 June 2003 Additional Questions Related to Supplemental Blasts & Explosions Responses to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application Project stage: Supplement ML0323201192003-08-20020 August 2003 Memo to J. Monninger from J.R. Hall - California State Historic Preservation Officer Concurrence in NRC Determination of Effects on Historic Properties for the Proposed Diablo Canyon Independent Spent Fuel Storage Installation (TAC No. L233 Project stage: Other ML0327600222003-10-0202 October 2003 10/02 03 Ltr to L. F. Womack from J. R. Hall - Federal Register Notice Publishing an Environmental Assessment and Finding of No Significant Impact for an Exemption from 10 CFR 72.72 (D) Project stage: Approval ML0403500092004-02-0303 February 2004 Letter to L.F. Womack - Diablo Canyon Independent Spent Fuel Storage Installation Application - Physical Security Program Changes TAC No. L23399) Project stage: Other ML0404302502004-02-11011 February 2004 Attachment (Tech Specs B) to Encl 1 (Preliminary License) to 02/11/04 Ltr to L Womack, Diablo Canyon Power Plant, Re Preliminary License and Safety Evaluation Report (SER) for Diablo Canyon Independent Spent Fuel Storage Installation Project stage: Approval ML0407809532004-03-22022 March 2004 Encl 2 (SER Ch 4) to 03/22/04 - Ltr L Womack Diablo Canyon Power Plant, Issuance of Materials License No. SNM-2511 for the Diablo Canyon ISFSI (72-26) (50-275, -323) Project stage: Approval ML0420501822004-07-22022 July 2004 Ltr to L. Womack (Homboldt Bay Power Plant) from J. Hall - Request for Additional Information for the Humboldt Bay Independent Spent Fuel Storage Installation Application Project stage: RAI ML0420503102004-07-22022 July 2004 Request for Additional Information on License Application and Safety Analyses Report Project stage: RAI ML0435800642004-12-21021 December 2004 Notice of Meeting with Pacific Gas & Electric Company to Discuss Status of NRC Staff Reviews of Pg&E'S 10 CFR Part 72 License Application for Independent Spent Fuel Storage Installation & Related Amendment Request for 10 CFR Part 50 License Project stage: Approval ML0503303912005-02-0202 February 2005 Summary of Meeting with Pacific Gas and Electric Company to Discuss the Application for the Humboldt Bay ISFSI (Tac No. L23683) Project stage: Meeting ML0523702642005-08-25025 August 2005 Ltr J Hall to D Jacobs (Diablo Canyon Power Plant) Public Disclosure Determination for Information Related to the Humboldt Bay ISFSI (Tac. No. L23683) Project stage: Other ML0523801422005-08-31031 August 2005 Preliminary SER Chapter 12 - Quality Assurance Evaluation Project stage: Other ML0525101182005-09-0202 September 2005 Ltr J Hall to D Jacobs (Diablo Canyon Power Plant) Humboldt Bay ISFSI Application - Physical Security Plan (Tac. No. L23683) Project stage: Other ML0629802292006-09-14014 September 2006 Modification No. 241 to Contract No. NRC-02-02-012 Project stage: Other 2003-06-13
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML23268A4072023-09-27027 September 2023 Summary of September 19, 2023, Closed Public Meeting with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML23265A1902023-09-26026 September 2023 Meeting Summary: September 13, 2023 Diablo Canyon, Units 1 and 2 License Renewal Application Pre-Application Meeting ML23143A2262023-06-0101 June 2023 May 3, 2023, Summary of Public Meeting to Discuss the End of Cycle Assessment and Pre-Submittal License Renewal Process Overview for Diablo Canyon Power Plant, Units 1 and 2 ML22272A5072022-09-29029 September 2022 Summary of September 27, 2022, Closed Meeting with Pacific Gas and Electric Company Regarding Planned Security Plan Changes for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22126A0162022-05-0909 May 2022 Summary of April 27, 2022, Closed Teleconference with Pacific Gas and Electric Company Regarding Alternative Security Measures for Early Warning System License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML21300A0272021-10-28028 October 2021 Clarification Call, Summary of October 21, 2021, Clarification Call with Pacific Gas and Electric Company Regarding Final Status Survey Report HBL-21-010, Survey Unit OOL01-03 ML21287A2512021-10-26026 October 2021 Meeting Summary 2021-10-13 Humboldt Bay Independent Spent Fuel Storage Installation (ISFSI) ML21246A0202021-09-0808 September 2021 Summary of August 30, 2021, Pre-Submittal Teleconference with Pacific Gas and Electric Company Regarding a Post-Shutdown Emergency Plan License Amendment Request for Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML21217A0702021-08-0505 August 2021 Summary of Clarification Call with Pacific Gas and Electric Company Regarding Trailer City Final Status Survey Report ML21158A1132021-06-28028 June 2021 License Amendment Application - Revision of the License Termination Plan - May 3, 2021 Request for Additional Information Response Clarification Call ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML20332A1802020-12-0101 December 2020 Summary of November 24, 2020, Pre-Submittal Teleconference with Pacific Gas and Electric Company a Permanently Defueled Technical Specification License Amendment Request ML20231A6522020-08-24024 August 2020 Summary of Teleconference with Pacific Gas & Electric Company Regarding an Exigent Amendment Request to Modify Diablo Canyon Power Plant, Units 1 & 2, Technical Specification 3.7.5, Auxiliary Feedwater (AFW) System EPID L-2020-LLA-017 ML20189A2832020-07-0707 July 2020 Summary of Region IV Annual Assessment Public Meeting ML19318F5272019-11-15015 November 2019 Summary of the August 27, 2019, Public Meeting Near the Diablo Canyon Nuclear Power Plant Regarding the Establishment and Operation of Community Advisory Boards ML19296A0952019-10-28028 October 2019 Summary of the August 26, 2019, Public Meeting Near the Humboldt Bay Power Plant Regarding the Establishment and Operation of Community Advisory Boards ML19196A0742019-07-22022 July 2019 Summary of Meeting with Pacific Gas and Electric Company Regarding Forthcoming Activities Associated with Diablo Canyon Nuclear Power Plant, Units 1 and 2 Planned Decommissioning ML19064B2652019-03-14014 March 2019 Summary of February 28, 2019, Public Meeting with Pacific Gas and Electric Company to Discuss the Proposed Relief Request Concerning Reactor Vessel Internal Visual Examination for the Diablo Canyon Nuclear Power Plant, Units 1 & 2 ML18348A4202018-12-31031 December 2018 Summary of Meeting with Pacific Gas & Electric Co. to Discuss Exemption Request to Withdraw Funds from the Nuclear Decommissioning Trusts to Fund Decommissioning Planning Activities at Diablo Canyon Nuclear Power Plant ML18207A7332018-08-10010 August 2018 Summary of Pre-Licensing Meeting with PG&E Co. to Discuss the Proposed LAR to Implement WCAP-16996-A, Revision 1, Realistic LOCA Evaluation Methodology Applied to the Full Spectrum of Break Sizes at Diablo Canyon ML17198A6032017-07-17017 July 2017 Summary of Annual Assessment Meeting Regarding Diablo Canyon Power Plant 2016 Performance ML16190A1782016-07-0808 July 2016 Summary of Annual Assessment Town Hall Meeting and Public Outreach Regarding Diablo Canyon Power Plant 2015 Performance ML16011A2042016-01-14014 January 2016 Summary of Conference Call on January 7, 2016, Between the U.S. NRC and Pacific Gas and Electric Co. Concerning the Responses to RAI for the Review of the Diablo Canyon Power Plant, Units 1 and 2, License Renewal Application (CAC Nos. MF401 ML15343A1272015-12-24024 December 2015 Summary of Meeting with Pacific Gas and Electric to Discuss Diablo Canyon, Units 1 and 2 Amendment Request to Revise UFSAR for Beacon Power Distribution Monitoring System Methodology and TS 5.6.5 (COLR) Paragon and Nexus Methodologies ML15348A1702015-12-17017 December 2015 Summary of Telephone Conference Call Held Between NRC and Pacific Gas and Electric Co., Concerning the RAI Responses Pertaining to the Diablo Canyon Power Plant LRA Environmental Review ML15280A2842015-10-20020 October 2015 Summary of Meeting with Pacific Gas & Electric to Discuss Diablo Canyon, Units 1 and 2 Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition), ML15279A4222015-10-0909 October 2015 Summary of 8/25/15 Meeting with Pacific Gas and Electric to Discuss Diablo Canyon Units 1 and 2 Amendment Request to Adopt Risk-Informed Completion Times, TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times-RITSTF Initiati ML15275A0942015-10-0707 October 2015 Summary of the Severe Accident Mitigation Alternatives Site Audit Related to the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Review ML15275A1302015-10-0707 October 2015 Summary of the Site Audit Related to the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Environmental Review ML15233A0062015-09-10010 September 2015 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML15233A0052015-09-0909 September 2015 Summary of Meeting with Pacific Gas and Electric to Discuss Diablo Canyon, Units 1 & 2 License Amendment Request to Adopt Risk-Informed Completion Times, TSTF-505, Revision 1, Provide Risk-Informed Extended Completion Times-RITSTF. Initiati ML15233A4912015-09-0101 September 2015 August 5, 2015, Public Scoping Meetings for the Environmental Review of the Diablo Canyon Power Plant, Units 1 and 2 License Renewal Application ML15209A9442015-07-28028 July 2015 June 24, 2015, Summary of Annual Assessment Meeting with Pacific Gas and Electric and Public Open House Regarding Diablo Canyon Power Plant 2014 Performance ML15125A1862015-05-27027 May 2015 April 28, 2015, Summary of Category 1 Public Meeting with Pacific Gas and Electric Company to Discuss Diablo Canyon'S Seismic Hazard Reevaluation Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2. ML15134A2572015-05-18018 May 2015 5/7/15 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML15092A0792015-04-16016 April 2015 July 14-17, 2014 - Summary of Diablo Canyon, Units 1 and 2, Audit to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition) ML15069A0952015-03-24024 March 2015 Summary of Telephone Conference Call Held on March 4, 2015 Between the U.S. Nuclear Regulatory Commission and Pacific Gas and Electric Company Concerning the Diablo Canyon Power Plant, Units 1 and 2, License Renewal Application ML15043A1992015-02-19019 February 2015 2/3/2015 Summary of Meeting with Pacific Gas and Electric Regarding Presubmittal Discussion on Alternate Source Term License Amendment Request for Diablo Canyon Power Plant, Units 1 and 2 ML15037A2482015-02-0505 February 2015 Summary of Regulatory Conference to Discuss Safety Significance of Diablo Canyon Power Plant Protective Action Recommendations for Areas of the Ocean Finding ML14350A2712014-12-22022 December 2014 Summary of 12/11/14 Preapplication Meeting with Pacific Gas and Electric Company to Discuss License Amendment Request to Support Installation of 500 Kilovolt Output Generator Breakers at Diablo Canyon, Units 1 and 2 ML14029A4502014-12-10010 December 2014 Summary of 12/18/13 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14295A7332014-11-17017 November 2014 9/24/14 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14197A3522014-07-22022 July 2014 7/9/14 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14157A0912014-06-17017 June 2014 Summary of 5/21/14 Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14155A3742014-06-0404 June 2014 May 22, 2014, Summary of Annual Assessment Meeting with Pacific Gas and Electric Regarding Diablo Canyon Power Plant 2013 Performance ML14113A4932014-05-0606 May 2014 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML14113A4222014-04-23023 April 2014 Public Meeting with Pacific Gas & Electric (Pg&E)To Discuss the Operating Performance for Diablo Canyon Power Plant for the Period January 1 - December 31, 2013 ML13329A4172013-12-30030 December 2013 Summary of Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13357A7952013-12-24024 December 2013 B. Watson Memo Meeting Summary of December 5, 2013 Meeting with PG&E on Humboldt Bay Emergency Plan 2023-09-27
[Table view] Category:Memoranda
MONTHYEARML23265A1902023-09-26026 September 2023 Meeting Summary: September 13, 2023 Diablo Canyon, Units 1 and 2 License Renewal Application Pre-Application Meeting ML23143A2262023-06-0101 June 2023 May 3, 2023, Summary of Public Meeting to Discuss the End of Cycle Assessment and Pre-Submittal License Renewal Process Overview for Diablo Canyon Power Plant, Units 1 and 2 ML23046A0292023-02-23023 February 2023 Timely Renewal Exemption 5 Day Memorandum ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22131A1592022-05-11011 May 2022 Reply to the Nrc'S Response to the Office of the Inspector General'S (OIG) Event Inquiry Into the Nrc'S Oversight of the Auxiliary Feedwater System at Diablo Canyon Nuclear Power Plant, OIG Case No. 20-025 ML22108A1672022-05-0303 May 2022 Staff Assessment of OIG Event Inquiry Into the Nrc'S Oversight AFW at Diablo Canyon (OIG Case No. 20-025) ML22109A1792022-05-0303 May 2022 Response OIG Special Inquiry Into Nrc'S Oversight AFW at Diablo Canyon (OIG Case No. 20-025) ML21158A1132021-06-28028 June 2021 License Amendment Application - Revision of the License Termination Plan - May 3, 2021 Request for Additional Information Response Clarification Call ML21146A1852021-06-28028 June 2021 DC RFI 2021401 ML21146A185 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21060B1822021-03-0101 March 2021 Memorandum: 1-26-21 Diablo Canyon Renewal Pre-Application Meeting Summary ML19318F5272019-11-15015 November 2019 Summary of the August 27, 2019, Public Meeting Near the Diablo Canyon Nuclear Power Plant Regarding the Establishment and Operation of Community Advisory Boards ML19296A0952019-10-28028 October 2019 Summary of the August 26, 2019, Public Meeting Near the Humboldt Bay Power Plant Regarding the Establishment and Operation of Community Advisory Boards ML19182A3562019-07-23023 July 2019 Quarterly Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206 - April 1 to June 30, 2019 ML19120A2172019-04-26026 April 2019 Memo to File Environmental Assessment and Finding of No Significant Impact for Energy Northwest Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72,30(b) and 72.30(c) for Humboldt Bay ISFSI ML18298A0762018-10-26026 October 2018 Notice of Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss Security-Related Information for Diablo Canyon Power Plant, Units 1 and 2 ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers ML18131A0482018-05-11011 May 2018 Memorandum to File Environmental Assessment and Finding of No Significant Impact for Pacific Gas and Electric Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) for the Diablo Canyon Independent Spent Fuel S ML18022A1512018-01-16016 January 2018 Memo to A. Hsia Summary of December 12, 2017, Meeting with Pacific Gas & Electric Company to Discuss the Upcoming Submittal of the Application for Renewal of the Humboldt Bay Independent Spent Fuel Storage Installation License ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning ML16119A5002016-04-29029 April 2016 Notice of Forthcoming Closed Meeting with Pacific Gas & Electric Company to Discuss Proposed Change to Defensive Strategy and 10 CFR 50.54(p) Documentation for Reduction in Minimum Staffing Requirements at Diablo Canyon ML16106A1212016-04-26026 April 2016 Notice of Availability of Environmental Assessment and Finding of No Significant Impact for the License Termination Plan for Humboldt Bay Power Plant, Unit 3 ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16029A2322016-03-16016 March 2016 LTR-15-0337-1 - Diablo Canyon Power Plant, Units 1 and 2 - Closure of 10 CFR 2.206 Petition from Bullard High School Students (CAC Nos. MF6515 and MF6516) ML15125A1862015-05-27027 May 2015 April 28, 2015, Summary of Category 1 Public Meeting with Pacific Gas and Electric Company to Discuss Diablo Canyon'S Seismic Hazard Reevaluation Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2. ML14344A6302014-12-15015 December 2014 Close-out letter-California Facilities Preemption Safety Evaluation ML14206A9492014-07-28028 July 2014 Memo to Anderson, Work Request for Humboldt Bay Emergency Plan ML14167A4922014-07-0303 July 2014 Summary of June 5, 2014, Conference Call to Discuss the Status of the License Renewal Application Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2 ML14022A1202014-06-23023 June 2014 Memorandum to File, Review of Revision 21 of Final Safety Analysis Report Update ML14162A4582014-06-12012 June 2014 Pacific Gas and Electric Company Diablo Canyon Power Plant Units 1 and 2, Regulatory Audit in Support of the License Amendment Request to Implement Risk-Informed, Performance-Based, Fire Protection Program as Allowed by Title 10 of the Code ML13339A4282014-04-28028 April 2014 Transmittal Memorandum for Regulatory Audit Report for the August 6, 2013 Through August 8, 2013 Cyber Security Pilot Study at Dcnpp Avila Beach, CA ML14099A4862014-04-14014 April 2014 Memo to Gene Carpenter, NRR Requesting Technical Assistance on Review of Financial Information for the Humboldt Bay License Termination Plan ML13357A7952013-12-24024 December 2013 B. Watson Memo Meeting Summary of December 5, 2013 Meeting with PG&E on Humboldt Bay Emergency Plan ML13357A8082013-12-24024 December 2013 B. Watson Memo Meeting Summary of December 5, 2013 Humboldt Bay on License Termination Plan ML13312A6462013-11-25025 November 2013 Meeting Notice with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13319A8952013-11-19019 November 2013 Public Meeting Notice to Discuss the Proposed Submittal of Humboldt Bay Emergency Plan Changes Requiring Prior NRC Approval ML13319A9202013-11-19019 November 2013 Notice of Public Meeting on Humboldt Bay License Termination Plan ML13290A2272013-10-18018 October 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13274A0572013-10-0202 October 2013 August 20, 2013 Summary of Meeting for Humboldt Bay ML13263A1922013-09-24024 September 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13260A0052013-09-18018 September 2013 10/2/13 Notice of Pre-Application Meeting with Pacific Gas and Electric Company to Discuss Upcoming Structural Weld Overlay Relief Request to Use an Alternative to Disposition Detected Laminar Indications at Diablo Canyon, Unit 2 ML13246A4162013-09-0505 September 2013 9/24/13 - Notice of Pre-Application Meeting to Discuss License Amendment Request for Technical Specification 3.8.1 Diesel Generator Surveillance Requirements at Diablo Canyon, Units 1 and 2 ML13246A4072013-09-0505 September 2013 9/25/13 Notice of Forthcoming Pre-Application Meeting to Discuss Emergency Core Cooling System Evaluations for License Amendment Request at Diablo Canyon, Units 1 and 2 ML13246A4262013-09-0505 September 2013 Notice of Meeting to Discuss Amendment Request to Adopt Technical Specifications Task Force TSTF-505, Provide Risk-Informed Extended Completion Times, RITSTF Initiative 4B at Diablo Canyon, Units 1 and 2 ML13246A2622013-09-0404 September 2013 9/18/13 Notice of Forthcoming Closed Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13191A1842013-07-30030 July 2013 Memo to Cindy Bladey Humboldt Bay Power Plant Unit 3- Notice of Public Meeting on License Termination Plan ML13198A5442013-07-18018 July 2013 August 20, 2013 Meeting Notice to Discuss Humboldt Bay Decommissioning Process, License Termination Plan and Obtain Public Comments ML13179A0622013-07-0909 July 2013 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 ML13163A0242013-06-12012 June 2013 6/26/13 Notice of Forthcoming Meeting with Pacific Gas and Electric Company to Discuss Digital Replacement of Process Protection System at Diablo Canyon Power Plant, Units 1 and 2 2023-09-26
[Table view] |
Text
February 1, 2002 MEMORANDUM TO: Charles L. Miller, Deputy Director Licensing and Inspection Directorate Spent Fuel Project Office, NMSS FROM: Timothy Kobetz, Project Manager /RA/
Licensing Section Spent Fuel Project Office, NMSS
SUBJECT:
SUMMARY
OF THE JANUARY 24, 2002, MEETING BETWEEN THE NUCLEAR REGULATORY COMMISSION STAFF AND PACIFIC GAS AND ELECTRIC COMPANY (TAC NO. L23399)
On January 24, 2002, a meeting was held between the Nuclear Regulatory Commission (NRC) staff and representatives of Pacific Gas and Electric Company (PG&E) to discuss PG&Es plans for licensing an independent spent fuel storage installation (ISFSI) at the Diablo Canyon Nuclear Plant. This meeting was conducted at the Center for Nuclear Waste Regulatory Analysis (CNWRA) in San Antonio, TX. The CNWRA will assist NRC with the site specific technical review of the application. The purpose of this meeting was for PG&E to discuss the format and content of the 10 CFR Part 72 application for an ISFSI at Diablo Canyon. is an attendance list. This meeting was noticed on January 11, 2002.
The meeting was separated into two discussions. First, PG&E staff discussed what documents were contained in the application, how the documents were formatted, and how the documents incorporated other information, previously docketed by NRC. Previously docketed information includes the Holtec HI-STORM 100 Safety Analysis Report, as amended through December 2001, and past seismic evaluations performed for the Diablo Canyon Power Plant. PG&E also discussed changes required to its 10 CFR Part 50 reactor license to accommodate the use of the Holtec HI-STORM System. Attachment 2 contains slides presented by PG&E during this portion of the meeting. The NRC staff is currently performing an acceptance review of the application. If NRC staff finds the application acceptable, a Notice of Docketing, a Notice of Consideration of Issuance, and a Notice of Opportunity for a Hearing will be posted in the Federal Register.
The second discussion focused on seismic evaluations that support the ISFSI application.
These evaluations include both previous evaluations performed for the Diablo Canyon Power Plant and new evaluations performed specifically for the ISFSI application. Attachment 2 also provides slides presented by PG&E during this portion of the meeting.
No proprietary information was disseminated or presented at this meeting. No regulatory decisions were requested or made.
Docket Nos. 72-26 (50-275, -323) 72-27 (50-133)
Attachments: 1. Attendance List
- 2. PG&E Project Slides cc: Mailing List
February 1, 2002 MEMORANDUM TO: Charles L. Miller, Deputy Director Licensing and Inspection Directorate Spent Fuel Project Office, NMSS FROM: Timothy Kobetz, Project Manager (Original Signed by:)
Licensing Section Spent Fuel Project Office, NMSS
SUBJECT:
SUMMARY
OF THE JANUARY 24, 2002, MEETING BETWEEN THE NUCLEAR REGULATORY COMMISSION STAFF AND PACIFIC GAS AND ELECTRIC COMPANY (TAC NO. L23399)
On January 24, 2002, a meeting was held between the Nuclear Regulatory Commission (NRC) staff and representatives of Pacific Gas and Electric Company (PG&E) to discuss PG&Es plans for licensing an independent spent fuel storage installation (ISFSI) at the Diablo Canyon Nuclear Plant. This meeting was conducted at the Center for Nuclear Waste Regulatory Analysis (CNWRA) in San Antonio, TX. The CNWRA will assist NRC with the site specific technical review of the application. The purpose of this meeting was for PG&E to discuss the format and content of the 10 CFR Part 72 application for an ISFSI at Diablo Canyon. is an attendance list. This meeting was noticed on January 11, 2002.
The meeting was separated into two discussions. First, PG&E staff discussed what documents were contained in the application, how the documents were formatted, and how the documents incorporated other information, previously docketed by NRC. Previously docketed information includes the Holtec HI-STORM 100 Safety Analysis Report, as amended through December 2001, and past seismic evaluations performed for the Diablo Canyon Power Plant. PG&E also discussed changes required to its 10 CFR Part 50 reactor license to accommodate the use of the Holtec HI-STORM System. Attachment 2 contains slides presented by PG&E during this portion of the meeting. The NRC staff is currently performing an acceptance review of the application. If NRC staff finds the application acceptable, a Notice of Docketing, a Notice of Consideration of Issuance, and a Notice of Opportunity for a Hearing will be posted in the Federal Register.
The second discussion focused on seismic evaluations that support the ISFSI application.
These evaluations include both previous evaluations performed for the Diablo Canyon Power Plant and new evaluations performed specifically for the ISFSI application. Attachment 2 also provides slides presented by PG&E during this portion of the meeting.
No proprietary information was disseminated or presented at this meeting. No regulatory decisions were requested or made.
Docket Nos. 72-26 (50-275, -323) 72-27 (50-133)
Attachments: 1. Attendance List
- 2. PG&E Project Slides cc: Mailing List DISTRIBUTION: (Closes TAC L23399)
Dockets NRC File Center PUBLIC NMSS R/F SFPO R/F SGagner, OPA BSpitzburg, RIV VEverett, RIV BHenderson, RIV NRC attendees Anorris GShukla, NRR C:\Program Files\Adobe\Acrobat 4.0\PDF Output\Public Meeting Summary 01-2~.wpd ADAMS:
ML020350568 OFC: SFPO E SFPO E SFPO E NAME: TKobetz EZiegler JMonninger DATE: 02/ 1 /02 02/ 1 /02 02/ 1 /02
OFFICIAL RECORD COPY Attachment 1 Attendance List
January 24, 2002 Meeting between the Nuclear Regulatory Commission and Pacific Gas and Electric ATTENDANCE LIST Name Affiliation Charles Miller NRC/NMSS/SFPO Wayne Hodges NRC/NMSS/SFPO Tim Kobetz NRC/NMSS/SFPO Henry Lee NRC/NMSS/SFPO Mark Delligatti NRC/NMSS/SFPO Girja Shukla NRC/NRR Terry Grebel PG&E Jearl Strickland PG&E Rich Klimczak PG&E Lloyd Cluff PG&E Greg Heggli PG&E Brian Gutherman Holtec Wesley Patrick CNWRA Asad Chowdhury CNWRA John Stamatokos CNWRA Amitava Ghish CNWRA Pat Mackin CNWRA Doug Gute CNWRA Darius Daruwalla CNWRA Michael Smith CNWRA Oleg Povetko CNWRA Goodluck Ofoegbu CNWRA Biswajit Dasgupta CNWRA Daniel Pomerening SwRI P. A. Cox SwRI Attachment 1
Attachment 2 PG&E Project Slides
Diablo Canyon Power Plant, Units 1 and 2 cc:
NRC Resident Inspector Mr. David H. Oatley, Vice President Diablo Canyon Nuclear Power Plant Diablo Canyon Operations c/o U.S. Nuclear Regulatory Commission Diablo Canyon Nuclear Power Plant P.O. Box 369 P.O. Box 3 Avila Beach, CA 93424 Avila Beach, CA 93424 Dr. Richard Ferguson, Energy Chair Telegram-Tribune Sierra Club California ATTN: Managing Editor 1100 11th Street, Suite 311 1321 Johnson Avenue Sacramento, CA 95814 P.O. Box 112 San Luis Obispo, CA 93406 Ms. Nancy Culver San Luis Obispo Mr. Ed Bailey, Radiation Program Director Mothers for Peace Radiologic Health Branch P.O. Box 164 State Department of Health Services Pismo Beach, CA 93448 P.O. Box 942732 (MS 178)
Sacramento, CA 94327-7320 Chairman San Luis Obispo County Board of Mr. Robert A. Laurie, Commissioner Supervisors California Energy Commission Room 370 1516 Ninth Street (MS 31)
County Government Center Sacramento, CA 95814 San Luis Obispo, CA 93408 Ms. Charlotte Alexander Mr. Truman Burns Vice President, Special Projects Mr. Robert Kinosian Green Car Group California Public Utilities Commission 1241 Johnson Avenue #356 505 Van Ness, Room 4102 San Luis Obispo, CA 93401 San Francisco, CA 94102 Ellen Carroll Mr. Steve Hsu Environmental Coordinator Radiologic Health Branch Department of Planning and Building State Department of Health Services County of San Luis Obispo P.O. Box 942732 County Government Center, Room 310 Sacramento, CA 94327-7320 San Luis Obispo, CA 93408 Diablo Canyon Independent Safety The Honorable Lois Capps Committee Member, United States ATTN: Robert R. Wellington, Esq. House of Representatives Legal Counsel ATTN: Greg Hass, District Representative 857 Cass Street, Suite D 1411 Marsh Street Monterey, CA 93940 San Luis Obispo, CA 93401 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavilion 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Christopher J. Warner, Esq.
Pacific Gas & Electric Company Post Office Box 7442 San Francisco, CA 94120