IR 05000341/2020002

From kanterella
(Redirected from ML20220A568)
Jump to navigation Jump to search
Integrated Inspection Report 05000341/2020002
ML20220A568
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 08/07/2020
From: Nestor Feliz-Adorno
Reactor Projects Region 3 Branch 4
To: Peter Dietrich
DTE Electric Company
References
IR 2020002
Download: ML20220A568 (18)


Text

August 7, 2020

SUBJECT:

FERMI POWER PLANT, UNIT 2 - INTEGRATED INSPECTION REPORT 05000341/2020002

Dear Mr. Dietrich:

On June 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Fermi Power Plant, Unit 2. On July 21, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Fermi Power Plant, Unit 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Néstor J. Feliz Adorno, Chief Branch 4 Division of Reactor Projects Docket No. 05000341 License No. NPF-43

Enclosure:

As stated

Inspection Report

Docket Number:

05000341

License Number:

NPF-43

Report Number:

05000341/2020002

Enterprise Identifier: I-2020-002-0030

Licensee:

DTE Electric Company

Facility:

Fermi Power Plant, Unit 2

Location:

Newport, MI

Inspection Dates:

April 1, 2020 to June 30, 2020

Inspectors:

T. Briley, Senior Resident Inspector

V. Myers, Senior Health Physicist

R. Ng, Project Engineer

A. Shaikh, Senior Reactor Inspector

T. Taylor, Resident Inspector

Approved By:

Néstor J. Feliz Adorno, Chief

Branch 4

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Fermi Power Plant, Unit 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71124.0

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 2 remained shut down for a planned refueling outage during the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities, and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated summer readiness for extreme weather conditions during the week ending June 20, 2020

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensee's readiness to cope with external flooding under the following conditions:
  • Elevated Lake Erie water levels during the week ending May 30, 2020

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Division 1 core spray as protected inventory control equipment during the week ending April 11, 2020
(2) Division 1 emergency diesel generators (EDGs) 11 and 12 during Division 2 EDGs 13 and 14 planned maintenance during the week ending April 18, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Turbine building basement condenser pump bay during the week ending May 30, 2020
(2) Turbine building first floor pipe chase during the week ending May 30, 2020

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

(1) The inspectors verified the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary were appropriately monitored for degradation and repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from March 23 to April 10, 2020:

03.01.a - Nondestructive Examination and Welding Activities.

Nondestructive Examinations:

  • B31-Reactor Recirculation Loop A Circumferential Weld (FW-RD-2-A9)

Ultrasonic Examination (UT)

Nondestructive Examinations with Indications from Previous Outage:

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Division 1 and Division 2 low pressure coolant injection (LPCI) testable check valves (E1100F050A and E1100F050B) during the week ending June 20, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed;

(1) Emergent work on west station air compressor following loss of station air during the week ending April 18, 2020
(2) Emergent work on visual annunciator system (VAS) following a loss of VAS during the week ending April 18, 2020
(3) Emergent work on Division 1 and Division 2 130/260 volt batteries following low specific gravity measurements during the weeks ending May 9, 2020 and May 16, 2020
(4) Emergent work on torus structural indications identified during structures monitoring and ASME [American Society of Mechanical Engineers] section XI visual examinations during the week ending June 6, 2020
(5) Emergent work on drips and drains piping from steam lines and main turbine piping following identification of a through wall leak during the week ending June 6, 2020
(6) Planned shutdown cooling system valve maintenance with shutdown cooling out of service during the week ending June 27, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Legacy issues in calculations for surveillances affected by license amendment request for 24-month fuel cycle
(2) Operability and functionality of Division 2 LPCI testable check valve (E1100F050B)stuck open, as documented in CARD 20-24104
(3) Operability and functionality of EDG 14 following identification of pole actuator cracking during planned maintenance, as documented in CARD 20-24715
(4) Operability and functionality of the reactor recirculation pump B discharge motor operated valve (B2105F031B) following identification of stem and stem nut damage, as documented in CARD 20-24896

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Draining of torus, using temporary water transfer system and storage

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) Reactor protection system motor generator set 'A' output breaker troubleshooting and component replacements following abnormal operation during the week ending April 18, 2020
(2) Division 1 residual heat removal service water (RHRSW) piping replacement following identification of piping degradation during the week ending May 9, 2020
(3) EDG 13 cylinder liner adapter gasket replacement following unsatisfactory borescope inspections during the week ending June 13, 2020
(4) Core reload alignment verification during the week ending June 27, 2020
(5) Control rod exercising following planned maintenance during the week ending June 27, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial)

The inspectors evaluated refueling outage 20 activities throughout the inspection period. The inspectors completed inspection procedure section 03.01.c.11.

Refueling outage and associated inspection activities continued during the next inspection period.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) EDG 14 emergency core cooling system start test and logic functional tests of bus 65F breakers during the week ending July 4, 2020

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Main steam isolation valves local leak rate testing during the week ending May 30,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (1 Sample)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) Torus

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 2 (April 1, 2019 - March 31, 2020)

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1) Unit 2 (April 1, 2019 - March 31, 2020)

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) Unit 2 (April 1, 2019 - March 31, 2020)

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71124.01 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Technical Specification (TS) 5.7.2 states, in part, that areas accessible to individuals with radiation levels such that an individual could receive in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, a dose equivalent > 1000 mrems but < 500 rads at one meter from sources of radioactivity shall be provided with locked doors to prevent unauthorized entry, and the keys shall be maintained under the administrative control of the Nuclear Shift Supervisor on duty and/or the radiation protection supervision.

Technical Specification 5.7.3 states, in part, that for individual areas accessible to individuals with radiation levels such that a major portion of the individual's body could receive in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, a dose > 1000 mrems with measurement made at 30 centimeters from the source of radioactivity, but < 500 rads at one meter from the source of radioactivity that that are located within large areas such as reactor containment, where no enclosure exists for purposes of locking, and where no enclosure can be reasonably constructed around the individual area, that individual area shall be roped off and conspicuously posted, and a flashing light shall be activated as a warning device.

Contrary to the above, on April 11, 2020, the licensee failed either to provide locked doors to prevent unauthorized entry or to activate a flashing light as a warning device for an area accessible to individuals with radiation levels such that a major portion of the individuals body could receive in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> a dose > 1000 mrems with measurement made at 30 centimeters from the source of radioactivity. Specifically, individual areas of the torus (with accumulated coating chips) had measured radiation levels up to about 2500 mrem in any one hour; however, the torus was roped off and conspicuously posted as a High Radiation Area but was not locked nor was there a flashing light as a warning device.

Significance/Severity: Green. Specifically, the inspectors determined that this finding is of very low safety significance (Green) because the performance deficiency did not involve ALARA planning or work controls, there was no overexposure or substantial potential for an overexposure, and the ability to assess dose was not compromised.

Corrective Action References: CARD 20-24300, LHRA Conditions Identified in the Torus Proper

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 21, 2020, the inspectors presented the integrated inspection results to Mr. P. Dietrich, Senior VP and Chief Nuclear Officer and other members of the licensee staff.
  • On April 29, 2020, the inspectors presented the radiation protection inspection results to Mr. R. LaBurn, Radiation Protection Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

10-25389

Overall Condition of Construction Sub #2 Evaluation/Repair

06/28/2010

18-29193

Received Annunciator 11D44, Transformer 1 Trouble

11/09/2018

20-23111

Lake Erie Water Levels Approaching Starting Point of

Design Basis Flood Event

03/23/2020

20-23667

Lake Level Elevation

04/01/2020

20-24215

Lake Level Above PMME Starting Elevation

04/10/2020

20-24689

CB Disconnect Rollers Showing Signs of Degradation

04/17/2020

20-26217

M-WARM20 Work will not be Completed Before 6/1/20

05/28/2020

Miscellaneous

ACMP 20-0004

Adverse Condition Monitoring Plan - Lake Erie Water Level

Elevation

03/30/2020

71111.04

Corrective Action

Documents

03-11894

RFI #111 NRC SSDI EECW

06/05/2003

Drawings

6M721-5707

Core Spray System Functional Operating Sketch

AG

6M721-5734

Emergency Diesel Generator System Functional Operating

Sketch

BK

Engineering

Evaluations

TE-E11-07-032

RBCCW Cooling Instead of EECW for RHR-SDC

Miscellaneous

VMR1-69.2

Triclad Vertical Induction Motor Vendor Manual

F

Procedures

ODE-20

Protected Equipment

71111.05

Fire Plans

FP-TB

Turbine Building

Miscellaneous

MOP 11

Fire Protection

MOP11-100

Fire Protection Implementation

71111.08G Corrective Action

Documents

18-28122

Reactor Pressure Vessel Longitudinal Shell Weld 15-308D

has Reportable Ultrasonic Examination Construction Flaws

10/10/2018

NDE Reports

PT-F20-004

CRDH Tube-to-Tube Weld Liquid Penetrant Examination

04/04/2020

RFO-12-10

Reactor Pressure Vessel Shell Weld 15-308D Ultrasonic

Examination

10/31/2007

UT-F19-002

Standby Liquid Control Nozzle-to-Safe End Butt Weld

Ultrasonic Examination

10/02/2018

UT-F20-005

B31-Reactor Recirculation-Loop A Circumferential Weld

03/31/2020

VE-F19-006

RPV Longitudinal Shell Weld 15-308D Ultrasonic

Examination

10/11/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

VT-F20-017

RHR Integral Attachment Weld G.20 Visual Examination

04/02/2020

Work Orders

2189217

Repair/Replace Pipe Downstream of E1150F605A

10/25/2018

71111.12

Corrective Action

Documents

15-28948

Div 2 LPCI Testable Check Valve Remained in Open

Position Following Full Stroke Test

11/13/2015

17-22684

E1100F050B Failed Pressure Isolation Valve Leakage Test

03/28/2017

20-24104

E1100F050B Failed Pressure Isolation Valve Leakage Test

04/09/2020

20-24790

E1100F050B Internal Damage

04/19/2020

20-25005

E1100F050B Indicator Shaft Bushing and Stuffing Box

Packing and Follower as Found was Unsatisfactory

04/22/2020

20-27145

E1100F050A Indicates Dual in the MCR when it Should

Indicate Closed

06/22/2020

71111.13

Corrective Action

Documents

18-24343

Procedure and Required M&TE Inconsistency

05/31/2018

20-23741

Low Margin Specific Gravity Values Found on Division 1

Battery

04/02/2020

20-24159

Corrected Specific Gravity Passes at Low End of

Acceptance Range

04/09/2020

20-24502

Visual Annunciator System Total System Failure

04/14/2020

20-24698

West Station Air Compressor Tripped

04/17/2020

20-25590

Division 1 Batteries Meet Acceptance Criteria One Pilot Cell

at Minimum Value for Corrected Specific Gravity

05/07/2020

20-25786

The M&TE Used to Measure the Specific Gravity of the

Divisional Batteries is Not Appropriate

05/15/2020

20-25795

Inappropriate Procedure Revision

05/15/2020

20-26283

Leak in South Reactor Feedwater Pump Drip and Drains

Piping

05/29/2020

20-26297

RF20 ASME Section XI Torus Visual Examination Indication

05/29/2020

20-26312

VAS Clock Signal Distortion Cause and Remediation

05/30/2020

20-26349

RF20 ASME Section XI Torus Visual Examination

Unacceptable Indication

05/30/2020

20-26350

RF20 ASME Section XI Torus Visual Examination

Unacceptable Indication

05/30/2020

20-26415

RF20 ASME Section XI Torus Visual Examination

Indications

06/01/2020

20-26717

Roll up CARD for Torus Structural Repairs Past Operability

06/09/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Drawings

6WM-N30-5021-1

Piping Isometric Drips and Drains From Main and Reheat

Steam to Reactor Feedwater Pump Turbine

H

6WM-N30-5022-1

Piping Isometric Drips and Drains From Main and Reheat

Steam to Reactor Feedwater Pump Turbine South Turbine

Building

L

M-2985-1

Diagram Drips and Drains From Steam Lines and Main

Turbine

Q

Miscellaneous

Fermi 2, Plan of the Day

06/22/2020

Fermi 2, RF20 Outage Nuclear Safety Review

03/16/2020

MOP05-100

Protected Equipment

2C

Procedures

20.129.01

Loss of Station and/or Control Air

23.129

Station and Control Air System

20

23.621

Main Control Room Annunciator and Sequence Recorder

3D19

Annunciator System Trouble

2.309.01

Division 1/2 Weekly 130/260VDC Battery Check

2.309.02

Division 1/2 Quarterly 130/260 VDC Battery Check

QCP-9.1.6-

NUC2019138

Torus Class MC Metal Containment Examination-RF20 Prior

to Recoat

01/29/2020

Work Orders

57509039

Leak in SRFP Drip and Drains Piping Downstream of

P9500F621

06/01/2020

57524622

Extent of Condition UT Inspection on North Train

06/11/2020

71111.15

Corrective Action

Documents

19-23374

DC-4550-A-01

05/01/2019

19-23497

DC-4535 Calibrating Instrument Errors

05/06/2019

19-28317

44.030.156 Tables 7 and 14 do not Match DC-4534 Volume

Revision J Issued 9/18/17

10/31/2019

19-29099

Procedure 44.110.001 has Required Test Gauge Tolerance

Specified as +/- 4.8 PSIG. DC-4556 Volume 1 Revision H

Issued 11/3/2011 Requires an Accuracy of +/- 0.75 PSIG

11/26/2019

19-29754

DC-4573 Volume 1 Revision B Issued 8/13/2019 has

Multiple Changes with no Revision Bars, Some of Which

may Affect Current Configuration

2/19/2019

20-24104

E1100F050B Failed Pressure Isolation Valve Leakage Test

04/09/2020

20-24715

Pole Actuator for EDG 14 Breaker Aux Switches in ED2,

ED3, ED4 and ED5 Damaged

04/17/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

20-24896

Score Identified on B3105F031B Stem

04/21/2020

20-25056

2S/H Aux Switch Rod Head Cracks

04/23/2020

20-25071

Request WO to Schedule Inspections

04/23/2020

20-26588

B3105F031B Foreign Material Found in Actuator

Compensator Housing

06/05/2020

Corrective Action

Documents

Resulting from

Inspection

20-26620

NRC Identified - Arc Strike Outboard Ring Girder 14/15

06/06/2020

20-26629

NRC Identified - Indication on Torus Shell Bay #6

06/07/2020

20-26997

Past Operability Reviews Need a Process Developed to

Drive Consistency and Accuracy

06/18/2020

Procedures

24.204.05

Div 1 and Div 2 RHR Valve Position Indication Verification

Test

44.030.156

ECCS - HPCI Torus Level Calibration

71111.18

Corrective Action

Documents

20-24055

Torus Water Activity in Bladder Bags is Higher than

Expected

04/08/2020

Engineering

Changes

19-0019

Confidential: Torus Dewatering and Water Storage

Temporary Modification to the Support the Torus Recoating

Project

71111.19

Corrective Action

Documents

19-00081

RPS East MG Set 'A' Noise Coming from Outboard Flywheel

Bearing

06/29/2019

20-23266

Corrosion of RHRSW Pipe at MDCT Penetration MK-151

03/26/2020

20-23410

Document Trend for RHRSW Internal Pipe Condition

03/28/2020

20-23625

RPS Output Breaker Failed Acceptance Criteria

04/01/2020

20-23627

RPS MG Set 'A' Motor Internals Dirty

04/01/2020

20-23906

While Performing 42.610.02 EPA Channel acl and

Functional, MG Set Gen Output Breaker Tripped

04/05/2020

20-23963

Walkdown Photos Appear to Show Tapecoat Stopping Just

Short of Penetration Seal at MK151

04/06/2020

Drawings

I-2151-01

Reactor Protection System Motor-Generator Set A

AI

I-2155-01

Reactor Protection System Power Distribution Notes and

References

T

Engineering

Evaluations

ACMP 19-014

RPS A MG Set

07/03/2019

Miscellaneous

Cycle 21 Master Core Loading Pattern

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

Design Equivalent

Change Package

266

Contingency Pipe Replacement for RHRSW Penetration

Inspection for MK 1-4

Procedures

24.106.02

Control Rod Drive Coupling Integrity Verification

27.106.03

Control Rod Drive Insert and Withdrawal Stall Flow

Measurement

27.106.05

Control Rod Drive Timing and Adjustment

35.307.008

Emergency Diesel Generator - Engine General Maintenance

35.316.001

20 VAC Reactor Protection MG Set

35.317.003

RPS MG Set General Maintenance

Work Orders

2177931

Perform Electrical-Mechanical Checks and Lubrication of

RPS MG Set A

03/30/2020

2180058

Replace RPS MG Set Voltage Reg Module and Voltage

Control Rheostat

03/30/2020

2180190

Perform 42.610.02 Div 1, Normal Feed, EPAs A and C,

Cal/Functional

04/06/2020

235174

RHR Return Piping Seals not Designed as Water Barriers

10/26/2018

55667627

Contingency - DECP 70266 - Replace Div 1 RHRSW Piping

at Penetration MK-104

09/06/2019

57410471

Replace EDG Adapter Gaskets

05/18/2020

71111.20

Corrective Action

Documents

20-24463

Recirc Loop B Jet Pump Plugs not Holding

04/14/2020

Corrective Action

Documents

Resulting from

Inspection

20-23940

NRC Resident Observation and Feedback; Lifting and

Rigging at RHR Complex

04/06/2020

20-25570

NRC Identified : Technical Specification 5.1.2 Uses

Outdated Title for Shift Manager

05/06/2020

20-25651

NRC Identified - Lack of No Mode (Defueled) Requirements

Specified in Fermi Tech Specs and MOP01

05/11/2020

Drawings

M-2083

Residual Heat Removal Division 2

CB

M-2084

Residual Heat Removal Division 1

BP

Engineering

Evaluations

TE-E-11-20-007

RF20 Decay Heat Evaluation

Miscellaneous

RF 20 Core Verification Video

06/23/2020

MOP05-200

RPV Water Inventory Control

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MOP13

Conduct of Refueling and Core Alterations

MWC13

Outage Nuclear Safety

Procedures

20.205.01

Loss of Shutdown Cooling

35.710.016

Installation and Removal of the Jet Pump Nozzle Plugs

MWC13

Outage Nuclear Safety

ODE-20

Protected Equipment

71111.22

Drawings

64721-2205-O6

RHR Relay Logic B Circuit - Part 2

M

6SD721-2500-01

One Line Diagram Plant 416V & 480V System Service

CD

Procedures

24.137.01

Main Steam Line Isolation Channel Functional Test

24.137.03

Main Steam Line Valve Operability Test

43.401.500

Local Leakage Rate Testing for Penetration X-7A, X-7B, X-

7C, and X-7D

38C

Work Orders

47453964

Perform 24.307.13 EDG No. 14 ECCS Start and Load

Rejection Test and LF of Bus 65F

05/16/2020

29304

Final 43.401.500 LLRT for X-7D B2103F022D & F028D

05/27/2020

71124.01

Corrective Action

Documents

20-24300

LHRA Conditions Identified in the Torus Proper

04/11/2020

Miscellaneous

WI-RPO-057

Work Instruction for RP Playbook for Torus Recoat Project

(RFO-20)

Radiation

Surveys

286-R20

Torus Radiological Survey

04/11/2020

Radiation Work

Permits (RWPs)

2040

Torus Recoat Project - Overall Diving, Decontamination,

Wash Down, Water Management and Associated Work

and 02

2042

Torus Recoat Project - Grit Blasting, Painting, Demob,

Shipping and Associated Work

71151

Engineering

Evaluations

19-24737

EDG 14 Surging in Idle During Surveillance Run

Miscellaneous

RCS Leakage Data

2019

RCS Leakage Data

20

EDG MSPI and WANO Performance Indicators Table

Various

MSPI Derivation Report - Emergency AC Power System

Unavailability Index

03/2020

MSPI Derivation Report - Emergency AC Power System

03/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Unreliability Index

MSPI Derivation Report - High Pressure Injection System

Unavailability Index

03/2020

MSPI Derivation Report - High Pressure Injection System

Unreliability Index

03/2020

HPCI Performance Indicators Table

Various

Operators' Narrative Log

Various

Procedures

24.000.02

Eight Hour - Mode 1, 2, 3 -- Control Room

Various

Work Orders

51059475

Perform 24.202.01 HPCI Pump / Flow Test & Valve Stroke

at 1025 PSIG

11/21/2019