Letter Sequence Approval |
---|
|
|
MONTHYEARML20063M5941982-09-10010 September 1982 Responds to 820813 Request for Addl Info Re Adequacy of Electrical Distribution Sys Voltages.Theoretical & Actual Voltages for safety-related Buses Listed Project stage: Request ML20065T5841982-10-29029 October 1982 Responds to NRC Re Adequacy of Station Electrical Distribution.Failure of Both Low Voltage Station Auxiliary Transformers Is Condition Described in Fsar,Chapter 7, Electrical Sys Project stage: Other ML20077K6701983-02-0909 February 1983 Adequacy of Electric Distribution Sys Voltages for Point Beach Nuclear Plant,Units 1 & 2, Technical Evaluation Rept Project stage: Other ML20069E6501983-03-14014 March 1983 Suppls 791012 & 810601 Responses to Requests for Addl Info Re Offsite Power Distribution Sys.Nrc Safety Analysis Concluded That Ac Auxiliary Power Sys Adequate & Physical & Electrical Separation of Power Sys Acceptable Project stage: Other ML20072J6891983-03-23023 March 1983 Application for Amend to Licenses DPR-24 & DPR-27,modifying 820427 Tech Spec Change Request 77 Re Loss of Voltage Protective Relays Project stage: Request ML20204F5381983-04-25025 April 1983 Safety Evaluation of Util Preferred Ac Power Sys Conformance GDC 17.Proximity of Low Voltage Transformers Does Not Fully Meet GDC 17 Requirements for Physical Separation,But Deluge Sprinkler Sys Adequate Project stage: Approval ML20204F5251983-04-25025 April 1983 Forwards Safety Evaluation of Util Preferred Ac Power Sys Conformance to GDC 17.Power Sys Do Not Fully Meet Intent of GDC 17 Since Sys Could Be Automatically Disconnected from 4,160-volt Safeguards Buses in Worst Case Accident Loads Project stage: Approval ML20085A7491983-06-30030 June 1983 Informs of No Significant Changes to Electrical Distribution Sys Described in FSAR Which Would Affect Degree of Conformance w/GDC-17.Available Info Adequate to Determine Intent of GDC-17 Re Offsite Power Distribution Sys Project stage: Other 1983-03-14
[Table View] |
|
---|
Category:SAFETY EVALUATION REPORT--LICENSING & RELATED ISSUES
MONTHYEARML20212D5961999-09-15015 September 1999 Safety Evaluation Supporting Licensee IPEEE Process.Plant Has Met Intent of Suppl 4 to GL 88-20 ML20196J4251999-06-30030 June 1999 Safety Evaluation Authorizing Proposed Alternatives Described in Relief Requests VRR-01,ROJ-16,PRR-01 & VRR-02 ML20207D6751999-02-22022 February 1999 Assessment of Design Info on Piping Restraints for Point Beach Nuclear Plant,Units 1 & 2.Staff Concludes That Licensee Unable to Retrieve Original Analyses That May Have Been Performed to Justify Removal of Shim Collars ML20206R9001999-01-13013 January 1999 SER Accepting Nuclear Quality Assurance Program Changes for Point Beach Nuclear Plant,Units 1 & 2 ML20198C7671998-12-10010 December 1998 Safety Evaluation Accepting Licensee Proposed Alternative to ASME BPV Code,1986 Edition,Section XI Requirement IWA-2232, to Use Performance Demonstration Initiative Program During RPV Third 10-yr ISI for Plant,Unit 2 ML20236Q3161998-07-10010 July 1998 Safety Evaluation Accepting Licensee Proposed Alternative to ASME Code Requirements PTP-3-01 & PTP-3-02 ML20236L6771998-07-0707 July 1998 Safety Evaluation Approving Wepco Implementation Program to Resolve USI A-46 at Point Beach NPP Units 1 & 2 ML20217F3131998-04-17017 April 1998 Safety Evaluation Accepting Proposed Alternative to ASME Code for Surface Exam of Nonstructural Seal Welds,For Plant, Unit 1 ML20217A8501998-03-19019 March 1998 SER Accepting Proposed Changes Submitted on 980226 by Wiep to Pbnp Final SAR Section 1.8 Which Will Impact Commitments Made in Pbnp QA Program Description.Changes Concern Approval Authority for Procedures & Interviewing Authority ML20216J0101998-03-17017 March 1998 Safety Evaluation Accepting Third 10-yr Inservice Insp Interval Relief Request RR-1-18 for Plant ML20198L1151998-01-0808 January 1998 SER Accepting Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Point Beach Nuclear Plant,Units 1 & 2 ML20198L4671998-01-0202 January 1998 SER Approving Request for Relief VRR-4B to Inservice Testing Program Wisconsin Electric Power Co,Point Beach Nuclear Plant,Units 1 & 2 ML20197J9341997-12-12012 December 1997 Safety Evaluation Accepting Licensee Request for Relief from Performing Inservice Volmetric Exam of Inaccessible Portions of RPV Lower Shell to Lower Head Ring Weld During 10-yr ISI Interval of Plant,Unit 2 ML20137U4991997-04-10010 April 1997 Safety Evaluation Accepting Proposed Alternatives Contained in Requests for Relief RR-1-17 & RR-2-21 ML20129G6901996-10-0303 October 1996 SER Accepting Request for Relief from ASME Code Repair Requirements for ASME Code Class Three Piping at Plant ML20062J4991993-10-28028 October 1993 Safety Evaluation Granting IST Relief Requests Per 10CFR50.55a(a)(3)(ii) & 10CFR50.55a(f)(4)(iv) ML20062F1361990-09-25025 September 1990 SE Accepting Util Responses to Generic Ltr 83-28,Item 1.2, Post-Trip Review - Data & Info Capability ML20248A0101989-09-18018 September 1989 Safety Evaluation Re Containment Liner Leak Chase Channel Venting.Concurs W/Licensee That Plant Does Not Need to Vent Containment Liner Weld Leak Chase Channels During Test ML20246H0121989-07-0707 July 1989 Safety Evaluation Accepting Util 880325 & 1117 Responses to NRC Bulletin 88-002, Rapidly Propagating Fatigue Cracks in Steam Generator Tubes ML20245B0311989-06-14014 June 1989 Safety Evaluation Supporting Util Response to Generic Ltr 83-28,Item 4.5.3 Re on-line Functional Testing of Reactor Trip Sys.Existing Intervals for on-line Functional Testing Consistent W/High Reactor Trip Sys Availability ML20207E4191988-08-0404 August 1988 Safety Evaluation Supporting Compliance W/Atws Rule 10CFR50.62, Requirements for Reduction of Risk from ATWS Events for Light Water Cooled Nuclear Power Plants ML20151R6771988-08-0202 August 1988 Safety Evaluation Granting Request for Relief from ASME Code,Section XI Evaluation Requirements ML20151N2191988-07-27027 July 1988 Safety Evaluation Supporting Util Proposal Re Design of Switchgear Room,Per Sections Iii.G & Iii.L of App R to 10CFR50 ML20150C1311988-06-21021 June 1988 Safety Evaluation Accepting Responses to Generic Ltr 83-28, Item 2.1,confirming That Program Exists for Identifying, Classifying & Treating Components Required for Performance of Reactor Trip Function as safety-related ML20154H5791988-05-12012 May 1988 Safety Evaluation Supporting Conclusions That Rev 1 to Offsite Dose Calculation Manual (ODCM) Uses Methods Consistent W/Staff Requirements,However Some Discrepancies Identified.Odcm & Environ Manual Should Be Revised ML20148H4551988-03-24024 March 1988 Safety Evaluation Accepting Util 840405 Response to Generic Ltr 83-28,Item 2.1,(Part 2) Re Vendor Interface Programs & Reactor Trip Sys Components ML20235K9241987-07-0909 July 1987 Safety Evaluation Re Reactor Pressure Vessel Flaw.Flaw Conditionally Acceptable Per Subarticle IWB-3123 of Section XI of ASME Code & Therefore Requires Augmented Inservice Insps Based on 10CFR50.55(g)(4) ML20213G5801987-05-0707 May 1987 Safety Evaluation Re Util 861027 Request for Relief from Exam Requirements of Section XI of ASME Boiler & Pressure Vessel Code for Shell & Nozzle Welds in Regenerative Hxs. Request Granted ML20206K6011987-04-10010 April 1987 SER Supporting Util 860513 Proposed Replacement of Hydraulic Snubbers W/Energy Absorbers on Main Steam Bypass Line ML20210P2781987-02-0505 February 1987 Safety Evaluation Supporting Util 831107 & 860411 Responses to Generic Ltr 83-28,Item 4.5.2 Re Reactor Trip Sys Reliability on-line Testing.Plant Designed to Permit on-line Functional Testing of Diverse Trip Features of Breakers ML20214U6081986-11-26026 November 1986 Safety Evaluation Supporting Util 850516 Capsule T Summary Rept Re Use of Reactor Vessel Pressure Temp Limits Specified in Figures 15.3.1-1 & 15.3.1-2 of Tech Specs.Temp Limits Valid & May Continue to Be Used ML20206S7091986-09-16016 September 1986 Safety Evaluation on Util 850426 Response to Open Items Re Generic Ltr 81-14, Seismic Qualification of Auxiliary Feedwater Sys (Afws). Reasonable Assurance Exists That Afws Will Perform Required Safety Function Following SSE ML20214L9311986-09-0404 September 1986 Corrected Safety Evaluation Re Projected Values of Matl Properties for Fracture Toughness Requirements for Protection Against Pressurized Thermal Shock Events.Licensee Projections Acceptable ML20207D6781986-07-11011 July 1986 Safety Evaluation Accepting Util Responses to Generic Ltr 82-33 Re post-accident Monitoring Instrumentation Compliance W/Guidelines of Reg Guide 1.97,Rev 2,subj to Listed Condition.Portions of Rev 1 to EGG-EA-6771 Encl ML20138N7801985-10-31031 October 1985 Safety Evaluation Granting Util 840706 Relief Requests for Second 10-yr Inservice Insp Interval.Review of Requests for Relief from ASME Code Section XI Requirements Summarized in Encl Tables ML20134A4821985-10-24024 October 1985 Safety Evaluation Supporting Util Response to Generic Ltr 83-28,Items 3.1.1,3.1.2,4.1 & 4.5.1 Re post-maint Testing (Reactor Trip Sys Components) & Reactor Trip Sys Reliability.Programs Outlined in Acceptable ML20134A6051985-10-22022 October 1985 Safety Evaluation Re Util 831107 & 850910 Responses to Generic Ltr 83-28,Item 1.1, Post-Trip Review Program Description & Procedures. Program & Procedures Acceptable ML20138H1721985-10-18018 October 1985 Safety Evaluation Accepting Util 831107 Response to Generic Ltr 83-28,Items 3.1.3 & 3.2.3 Re post-maint Testing ML20133G4171985-07-29029 July 1985 Safety Evaluation Accepting Util 831108 Response to Generic Ltr 83-28,Item 1.1 Re post-trip Review.Response to Listed Deficiencies,Including Development of Systematic Safety Assessment Program for Unscheduled Reactor Trips Required ML20129H7871985-05-16016 May 1985 Safety Evaluation Supporting Licensee Response to Generic Ltr 83-28,Items 4.2.1 & 4.2.2 Re Reactor Trip Sys Reliability,Provided Corrective Action Taken If Higher than Normal Valves Observed in Trip Force & Response Time Values ML20205H2171984-09-10010 September 1984 Supplemental Safety Evaluation Re Util 820820 & 860113 Requests for Relief from Inservice Insp Requirements. Volumetric Exam Acceptable Method for Detecting O.D. Initiated Flaws.Relief from Surface Exams Should Be Granted ML20204F5381983-04-25025 April 1983 Safety Evaluation of Util Preferred Ac Power Sys Conformance GDC 17.Proximity of Low Voltage Transformers Does Not Fully Meet GDC 17 Requirements for Physical Separation,But Deluge Sprinkler Sys Adequate 1999-09-15
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARNPL-99-0569, Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Pbnp,Units 1 & 2. with ML20212D5961999-09-15015 September 1999 Safety Evaluation Supporting Licensee IPEEE Process.Plant Has Met Intent of Suppl 4 to GL 88-20 NPL-99-0051, Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Pbnp,Units 1 & 2. with NPL-99-0449, Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Pbnp,Units 1 & 2. with ML20196J4251999-06-30030 June 1999 Safety Evaluation Authorizing Proposed Alternatives Described in Relief Requests VRR-01,ROJ-16,PRR-01 & VRR-02 ML20209D2691999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Pbnps,Units 1 & 2 ML20196F3341999-06-22022 June 1999 Safety Evaluation for Implementation of 422V+ Fuel Assemblies at Pbnp Units 1 & 2 ML20195F9781999-06-10010 June 1999 Unit 2 Refueling 23 Inservice Insp Summary Rept for Form NIS-1 ML20209D2751999-05-31031 May 1999 Revised MORs for May 1999 for Pbnps,Units 1 & 2 NPL-99-0328, Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Pbnp,Units 1 & 2. with NPL-99-0273, Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Point Beach Nuclear Plant,Units 1 & 2.With ML20196F3521999-04-30030 April 1999 Non-proprietary WCAP-14788, W Revised Thermal Design Procedure Instrument Uncertainty Methodology for Wepc Point Beach Units 1 & 2 (Fuel Upgrade & Uprate to 1656 Mwt - NSSS Power) NPL-99-0193, Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Pbnp,Units 1 & 2. with NPL-99-0134, Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Pbnp,Units 1 & 2. with ML20207D6751999-02-22022 February 1999 Assessment of Design Info on Piping Restraints for Point Beach Nuclear Plant,Units 1 & 2.Staff Concludes That Licensee Unable to Retrieve Original Analyses That May Have Been Performed to Justify Removal of Shim Collars ML20206R9001999-01-13013 January 1999 SER Accepting Nuclear Quality Assurance Program Changes for Point Beach Nuclear Plant,Units 1 & 2 NPL-99-0008, Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Pbnp,Units 1 & 2. with NPL-99-0091, 1998 Annual Results & Data Rept for Pbnps,Units 1 & 2. with1998-12-31031 December 1998 1998 Annual Results & Data Rept for Pbnps,Units 1 & 2. with ML20198C7671998-12-10010 December 1998 Safety Evaluation Accepting Licensee Proposed Alternative to ASME BPV Code,1986 Edition,Section XI Requirement IWA-2232, to Use Performance Demonstration Initiative Program During RPV Third 10-yr ISI for Plant,Unit 2 NPL-98-1006, Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Point Beach Nuclear Plant,Units 1 & 2.With ML20195J5101998-11-16016 November 1998 Proposed Revs to Section 1.3 of FSAR for Pbnp QA Program ML20198J5941998-11-0303 November 1998 1998 Graded Exercise,Conducted on 981103 NPL-98-0948, Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Point Beach Nuclear Plant,Units 1 & 2.With NPL-98-0880, Special Rept:On 980913,fire Alarm Control Panels Inoperable for More That Fourteen Days.Troubleshooting of D-401 Panel Following Installation of Replacement Batteries Revealed No Apparent Cause for Spurious Alarms.Panel D-401 Restored1998-10-21021 October 1998 Special Rept:On 980913,fire Alarm Control Panels Inoperable for More That Fourteen Days.Troubleshooting of D-401 Panel Following Installation of Replacement Batteries Revealed No Apparent Cause for Spurious Alarms.Panel D-401 Restored ML20154M9121998-10-14014 October 1998 Unit 1 Refueling 24 Repair/Replacement Summary Rept for Form NIS-2 ML20154L6751998-10-14014 October 1998 Unit 1 Refueling 24 ISI Summary Rept for Form NIS-1 NPL-98-0826, Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Point Beach Nuclear Plant,Units 1 & 2.With ML20151W3851998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Pbnp Units 1 & 2 NPL-98-0653, Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W4471998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 2 ML20151W4541998-07-31031 July 1998 Corrected Page to MOR for July 1998 for Pbnp Unit 1 ML20236Q3161998-07-10010 July 1998 Safety Evaluation Accepting Licensee Proposed Alternative to ASME Code Requirements PTP-3-01 & PTP-3-02 ML20236L6771998-07-0707 July 1998 Safety Evaluation Approving Wepco Implementation Program to Resolve USI A-46 at Point Beach NPP Units 1 & 2 NPL-98-0558, Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Pbnp,Units 1 & 2 ML20151W4261998-06-30030 June 1998 Corrected Page to MOR for June 1998 for Pbnp Unit 2 ML20151W4221998-05-31031 May 1998 Corrected Page to MOR for May 1998 for Pbnp Unit 2 NPL-98-0481, Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W4011998-04-30030 April 1998 Corrected Page to MOR for April 1998 for Pbnp Unit 2 NPL-98-0356, Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for April 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20217F3131998-04-17017 April 1998 Safety Evaluation Accepting Proposed Alternative to ASME Code for Surface Exam of Nonstructural Seal Welds,For Plant, Unit 1 ML20216D7071998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3981998-03-31031 March 1998 Corrected Page to MOR for March for Pbnp Unit 2 NPL-98-0209, Special Rept Re Fire Barrier Inoperable for Greater than Seven Days.Compensatory Measures Implemented in Accordance W/Fire Protection Program Requirements During Time That Barriers Were Inoperable1998-03-30030 March 1998 Special Rept Re Fire Barrier Inoperable for Greater than Seven Days.Compensatory Measures Implemented in Accordance W/Fire Protection Program Requirements During Time That Barriers Were Inoperable ML20217A8501998-03-19019 March 1998 SER Accepting Proposed Changes Submitted on 980226 by Wiep to Pbnp Final SAR Section 1.8 Which Will Impact Commitments Made in Pbnp QA Program Description.Changes Concern Approval Authority for Procedures & Interviewing Authority ML20216J0101998-03-17017 March 1998 Safety Evaluation Accepting Third 10-yr Inservice Insp Interval Relief Request RR-1-18 for Plant NPL-98-0159, Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20151W3891998-02-28028 February 1998 Corrected Page to MOR for Feb 1998 for Pbnp Unit 2 ML20216D7121998-02-28028 February 1998 Revised Corrected MOR for Feb 1998 for Point Beach Nuclear Plant,Unit 2 NPL-98-0084, Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 21998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Point Beach Nuclear Plant,Units 1 & 2 ML20198L1151998-01-0808 January 1998 SER Accepting Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves, for Point Beach Nuclear Plant,Units 1 & 2 1999-09-30
[Table view] |
Text
-_- .- _ .- .
Safety Evaluation of the Preferred Power Systems Conformance to General Design Criteria 17 Point Beach Nuclear Power Plant Docket Nos. 50-266 and 50-301 Introduction Following the issuance of a letter to all licensees, on August 8, 1979, concerning the adequacy of station electrical distribution system voltages, Region III management requested the resident inspectors to perform onsite followup inspections of the licensee's actions required by the letter.
During the course of these inspections at Point Beach Nuclear Plant (PBNP) the resident inspector identified two concerns relative to General Design Criteria (GDC) 17 of Appendix A to 10 CFR Part 50 (Reference 1).
These concerns were identified as:
- 1. A single fa tlure of the primary winding or a catastrophic failure of either secondary windings of the low voltage station auxiliary trans-formers 1-X04 or 2-X04 could render the entire transformer inoperable thus removing normal power availability from both trains of safeguards equipment.
- 2. The proximity of the 1-X04 and 2-X04 low voltage auxiliary transformers (approximately 16 feet apart) could conceivably render both inoperable if one were to have a catastrophic failure, thus eliminating all off-site power to the safeguards trains of both units.
This safety evaluation addresses only these two specific concerns of the resident inspector.
Evaluation General Design Criteria 17, which was first published on February 20, 1971, and became effective on May 21, 1971, states in part:
- "An onsite electric power system and an offsite electrical power l system shall be provided to permit functioning of structures , systems ,
and components important to safety.---
l
---Electric power from the transmission network to the onsite electric distribution system shall be supplied by two physically independent circuits (not necessarily on separate rights of way) designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions. A switchyard common to both circuits is acceptable.-- "
l 8305020137 B30425 PDR ADOCK 05000266 P PDR l
4 The PBNP Safety Analysis Report (SAR) states that the design bases for the auxiliary electrical systems is as follows:
"The function of the auxiliary electrical system is to provide reliable ,
power to those auxiliaries required during any normal or emergency mode '
? of plant operation.
The design of the system is such that sufficient independence or f
isolation between the various sources of electrical power is provided in order to guard against concurrent loss of all auxiliary power."
Auxiliary power required during unit startup, shutdown, and after a reactor
- trip, and power for auxillaries associated with safeguards is supplied from the 345KV switchyard via the units high and low voltage station auxiliary transformers (see attached figure). The 345KV switchyard is served by four separate and independent lines. The 345KV system is the normal or preferred power supply for the auxiliary loads associated with plant engineered safe-guards. The two high voltage transformers (1-X03 and 2-X03) supply 13,800 volts to buses 1-HX04 for Unit No. I and 2-HX04 for Unit No. 2. A tie bus, H01, can be manually connected to intertie these buses and also the gas turbine generator to either low voltage transformer. Closing of the tie bus breakers into a common fault is prevented by trip and lockout, pre-venting automatic closure operations.
With the above described arrangement, either of the high voltage station auxiliary transformers may be removed from service and its associated low voltage station auxiliary transformer served via the tie bus from the opposite high voltage station auxiliary transformer and/or the 20 Mw gas turbine generator, thus permitting both units to operate.
With only one low voltage station auxiliary transformer operable, Section 4 15.3.7 of the Technical Specifications requires that only the reactor associated with the operable transformer shall be made critical or main-tained critical.
The 4160 volt system is divided into six buses per unit. Two buses for Unit No. 1, numbers 1-A03 and 1-A04 are connected to the 13,800 volt system via bus main breakers and the low voltage station auxiliary transformer Number 1-X04. These buses are used solely as switching buses. Buses 1-A03 and 1-A04 can be cross connected by manually switching to similar buses of Unit 2 (2-A03 and 2-A04). Thus, one low voltage transformer can feed the switching buses of the other unit as well as its own, supplying 4160 volt service to the safeguards buses and the 4160-480 volt safeguards transformers.
Buses 1-A05 and 1-A06 are connected to buses 1-A03 and 1-A04 using manually closed tie breakers.
i Buses 1-A05 and 1-A06 each serve one of the two 4160-480 volt station service I transformers for the unit's 480 volt safeguards equipment and one of the two safety injection pumps. No transfer is required for the safeguards equipment in the event of a turbine generator trip. .In addition to being served by buses 1-A03 and 1-A04, buses 1-A05 and 1-A06 are directly served by emergency diesel generators G01 and G02, respectively. Each emergency diesel generator 2
- - - - - ,-w--,r-.- - - - . , e-m,----e,,. -w,., .,,.e,,.m .,-c.,.---.r-e ,
-- - - - , - . - - - - - . , , . . , - - ---,-mm- . - - - - ---.----w - - - p y--- - .-- - ,-
will be automatically started and placed on the line upon undervoltage on the 4160 volt buses to which it is associated. One diesel will handle both the loads of one reactor in an accident mode and the other in hot shutdown mode.
The six 4160 volt buses for Unit No. 2 have the same arrangement as described for Unit No. 1.
The preferred power systems at PBNP are shared in that the two independent systems can be used for either unit upon failure of one component. Although present standards and guides do not address the sharing of offsite preferred power systems, the sharing of onsite standby safety-related systems is per-mitted, with certain restrictiors, for facilities constructed prior to 1973.
Standard Review Plan (SRP) NUREG-0800, Section 8.2, Offsite Power Systems, covers the review of the preferred power system (normal offsite external commercial power). The acceptance criteria states in part:
"In general, the preferred power system is acceptable when it can be concluded that two separate circuits from the transmission network to the onsite Class IE power distribution system are provided adequate physical and electrical separation, and the system has the capacity to supply power to all safety loads and other required equipment."
The Power Systems Branch's acceptance criteria for the preferred power system are based on meeting'the relevant requirements and guidelines of GDC-17 as it relates to the preferred power system's (i) capacity and capability to permit functioning of structures, systems, and components important to safety; (ii) provisions to minimize the probability.of losing electric power from any of the remaining supplies as a result of, or coin-cident with, the loss of power generated by the nuclear power unit or loss of power from the onsite electric power supplies; (iii) physical independence; (iv) availability; and the guidelines of Regulatory Guide 1.32 (see also IEEE 308-1974) as related to the availability and number of immediate access circuits from the transmission network.
Regulatory Guide 1.32 gives guidance only on the availability of offsite power within a few seconds following a loss-of-coolant accident. The Standard concerns only standby onsite safety-related power systems. Other electrical RG's and standards referred to in the SRP are silent on what is acceptable for a preferred power system's physical independence.
We have reviewed the two concerns using these acceptance criteria and guidance.
The first concern was that one failure in one of the low voltage auxiliary transformers (1-X04 or 2-X04) could remove preferred power from both trains of safeguards equipment; therefore, the preferred power supply was not independent or redundant as required by GDC-17.
The electrical independence of the two preferred systems as described above gives the flexibility to switch A.C. power around a failed low voltage 3
1
transformer via the associated unit's transformer. This can be accomplished manually in a few seconds meeting the guidance of R.G. 1.32.
In the above case, Technical Specifications (TSs) require that the reactor associated with the failed transformer be in or placed in the hot shutdown condition. If preferred power is not restored immediately, the diesel generators automatically start and one can carry the vital loads for about 13 days without replentishing onsite fuel.
Calculations by the licensee (Reference 2) indicate that in the instance of one unit in hot shutdown, the other in an accident situation, and only one low voltage transformer in service, the voltage on the 4160 volt safe-guards buses would be 3714 volts, below the present degraded voltage trip setpoint of 3762 volts + 2% and the proposed setpoint of 3875 volts + 2%
(Reference 3). In this case, both preferred power systems would be auto-matica11y disconnected from the buses and unavailable until loads were reduced, one to two hours later. During this period, no offsite preferred power would be available contrary to the requirements of GDC-17. The short duration power disconnection was found to be acceptable in the Technical Evaluation Report and NRR Safety Evaluation (Reference 7).
The second concern of the resident inspector was that the proximity of the 1-X04 and 2-X04 transformers did not meet the requirements of GDC-17, e.g.
"two physically independant circuits be designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions."
The two low voltage station auxiliary transformers are Westinghouse 13.8 KV to 4.16 KV 3 phase, 60 cycle, Class OA/FA and each use 4406 gallons of oil (140 C Flash Point) as the cooling medium. The transformers are located outside and about 12 feet away from the Gas Turbine Building (sheetmetal construction). The four output breaker cabinets are located between the transformers which are separated by about 16 feet. The breaker cabinets are standard weather proof metal outdoor cabinets. The inlet and outlet leads to the transformers and breakers are underground and with the excep-tion of the Gas Turbine Building wall there are no overhead towers or cables that could fall and damage the transformers. An automatic deluge sprinkler system with pneumatic rate-of-rise detection is provided for oil fire suppression. The transformers are mounted on concrete bases about 2 to 4 inches above grade. The ground has a slight slope away from the Gas Turbine Building and the transformers.
The Fire Protection Handbook states that, "Although transformer failures
, appear to be common, percentage wise they are few. A study of all trans-former failures over a 5-year period showed a fire developing in 64 of 430 losses caused by lightening, electrical breakdown and fire"; and
" Transformer containing appreciable quantities of flammable, inhibited mineral insulating oils with flash point ranging from 130C to 135C are placed at least 25 ft away from windows or other important structures or placed in a vault of the type specified in the National Electric Code (NEC)".
NEC, Article 450-27 (1981), Oil-insulated Transformers Installed Outdoors, states in part " Space separations, fire-resistant barriers, automatic water 4
spray systems, and enclosurcs that confine the oil of a ruptured transformer tank are recognized safeguards. One or more of these safeguards shall be applied according to the degree of hazard involved in cases where the transformer installation presents a fire hazard."
The effect of one transformer failure on another adjacent transformer cannot be reliably predicated. Projectiles from a transformer rupture failure are not likely to damage the adjacent transformer; however, fire from expelled hot oil could cause damage if the burning oil is not contained or extinguished.
The NRR fire protection safety evaluation of the PBNP (Reference 4) found that building walls adjacent to the transformers were adequately protected by automatic deluge sprinkler systems and the existing yard fire protection systems were adequate to protect equipment required for safe shutdown.
Other causes of both transformers being damaged simultaneously can be postulated; such as lightning, windstorm, tornado, earthquake, falling aircraft, etc. Further separation distance between the transformers could reduce, to a certain extent, the probability of both transformers being incapacitated by a single event; but, it would not entirely eliminate the possiblity.
The probability of the above events occurring and deactivating both trans-formers simultaneously is small, but real and the proximity of the trans-formers and outlet breakers do not meet the intent of GDC-17 for physical separation.
The licensee correctly points out (References 5 and 6) that the PBNP was designed and constructed before GDC-17 was promulgated and that the preferred and emergency standby systems are as described in the Final Safety Analysis Report (FSAR). He also states that they have adequately considered the potential consequence of the loss of both transformers; however, aside from having ample diesel fuel available, no formal plans or procedures are in place to restore offsite A.C. power to the facilities in such an emergency as simultaneous failure of both low voltage transformers.
Since they are unique and require some months to construct, the licensee is considering the procurement of a spare low voltage transformer which could be installed in a few days. The licensee is also studying the possibility of backfeeding offsite power through the main power transformer, which if possible, could take a few hours to accomplish. If these pre-cautions are taken, we feel the safety of the PBNP is not reduced to an unacceptable level.
Conclusion We have determined that the PBNP preferred offsite A.C. power systems do not fully meet the requirements of GDC-17, since with the failure of one low voltage transformer in the worst case situation, voltage on the 4160 volt safeguards buses could drop below the degraded voltage set point, disconnecting the offsite power from the buses for a short period of time.
The NRR safety evaluation considered this departure from GDC-17 requirements to be acceptable (Reference 7).
5
We have also determined that the proximity of the low voltage transformers do not fully meet the intent of GDC-17 requirements for' physical separation.
However, the NRR Fire Prevention Safety Evaluation found the deluge sprinkler system adequate to protect the transformers and the Gas Turbine Building from fire (Reference 4). Other' simultaneous failures by interactive causes or natural events would not be substantially reduced by further separation of the transformers, i
The following NRC personnel have contributed to this Safety Evaluation.
- K. R. Ridgway P. A. Barrett i
I i
6
-]
i i
REFERENCES
- 1. Memorandum from W. G. Guldemond, Senior Resident Inspector, PBNP, to T. Colburn, Licensing Project Manager, PBNP, Office of Nuclear Reactor Regulation, NRC, June 11, 1981.
- 2. Lettar from C. W. Fay, Assistant Vice President, Wisconsin Electric Power Company (WEPC) to H. R. Denton, Director, NRR, September 10, 1982.
- 3. Letter from C. W. Fay, Assistant Vice President, WEPC, to H. R. Denton, Director, NRR, June 1, 1982.
- 4. -Letter from A. Schwencer, Chief of Operating Reactor Branch No. 1, NRR, to S. Burstein, Executive Vice President, WEPC, August 2, 1979 (Amendment Nos. 39 and 44 to Facility Operating License Nos. DPR-24 and 27).
- 5. Letter from C. W. Fay, Assistant Vice President, WEPC, to H. R. Denton, Director, NRR, October 29, 1982.
- 6. Letter from C. W. Fay, Assistant Vice President, WEPC, to H. R. Denton, Director, NRR, March 14, 1983.
- 7. Memorandum from L. S. Rubenstein, Assistant Director for Core and Plant Systems, NRR, to G. C. Lainas, Assistant Director for Operating Reactors, March 2, 1983.
7
lJll' '
, lil { , ! i
, s
.s u s o
- 3. -a ? _ s
_. E , 2 a- J. 2. "' o T N CR $ s
V E
3
^ 3 M^
[
S T # ^
L C %
A C
4 3
E N ^
^
t N J.
o J h
T C
T E
L U
B 2 M. W 2 > ^
P . A R * ] A }
E f L
P =
T T.
c [
3 '. bo t o E A. Rv ZX A. J. X a s
2 P -
N E n CU C.
$ 2 5
o AVM loWg XA L 2 X T. 8 Y3 xOl/
- P V 28
- T R)
T u N 2 Us 2NI s U E
A.V/ A 4 R
U AE d n 3 G n" T 5 I
3 4 F V. 2 H 3 s
.E 3
O A
3 0
S.
S. 2 0a s o
4
- CN$ -
T 2 2 LT) i C
E h
o h M" Q 3
S ^^
U /
S A, 3 A
b r
, r .
WnP X
.eK n 8
Ut4 M^ )
c4J h n" c A. g /
A Y . v O
A o
A
- 3. at v
o J. E "'eo CS J. 2. M 2 -
4 2 L 2 V. R LT J
I 2. /
R 2 T E s.
3 N N N E E C . E T S G C E
C D S M E R L L E D U U E9 R R
' E A J. T S E A 3
W s t C E U u 3 i l NG E s A D O IE K G GFS NAU V ESS 4 t K 1 M A.
U44 C4 8
4 o
s o
5S.A 4 o
C-1R S'o
A AV /
A A s m c T 1 K I
e L7) v" s
3.
V. R 3 4 )
LT8
/
u" I 2
A. 6 b A 'e N T. n" n A C W3e I E D S 3]
A C
R J
. [
h a" )b E
A U S O 6 o Sh S
s Yo o A - Cu$ Ss -
e
- s L$e.
R /
I 8
T M V T. K n K 4 1 UJ 1 R A. / T 8 3AV RV R 2 0 7M E n T.
l 1 33 We .A b V4 s X 2 J8 - o m E ( M3 tPv o/ LUA o A
s.
CR$
s o
L C n LI eN h '-
e LT) -
nl S u. T V
N l
]
- A 4 .
- N I
y^ 3 e
A s IuJ g
U 6 v^ [
R T. M /
G V
C E wm A.
A h
N J. A 3
4 S
U wM A L
h q 3 S 6 3 l
f E
N E
o s
s 5 8uM o s
G - 3. 6N Ve s e Ct $
Li l *
, l.' I ll i 1,