Urenco 2021 Inspection Schedule Letter Rev 1
ML20203M062
Person / Time
Site: 07003103
Issue date: 07/20/2020
From: Robert Williams
NRC/RGN-II/DFFI
To: Cowne S
URENCO USA
References
Download: ML20203M062 (4)


Text

July 20, 2020 Stephen Cowne, Chief Nuclear Officer and Compliance Manager URENCO USA P.O. Box 1789 Eunice, NM 88231

SUBJECT:

LOUISIANA ENERGY SERVICES, LLC (LES), dba URENCO USA (UUSA) -

CALENDAR YEAR 2021 INSPECTION SCHEDULE

Dear Mr. Cowne:

Enclosed is the schedule of inspections to be performed by the U.S. Nuclear Regulatory Commission (NRC) inspectors at URENCO USA (UUSA) for calendar year 2021. The inspection schedule is provided in advance to minimize the resource impact on your staff and allow for the resolution of any scheduling conflicts and personnel availability issues, well in advance of inspector arrival onsite.

Please note that any regional initiative or other reactive inspection is not included in the schedule. If circumstances arise which cause the NRC inspectors to change the dates of the planned inspections, we will contact you to discuss the change as early as possible. Please contact Brannen Adkins at (404) 997-4620 with any questions or concerns you may have regarding this letter or the inspection schedule.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).

S. Cowne 2 ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Robert E. Williams Jr., Chief Projects Branch 1 Division of Fuel Facility Inspection Docket No. 70-3103 License No. SNM-2010

Enclosure:

URENCO USA CALENDAR YEAR 2021 INSPECTION SCHEDULE (See page 2) cc: w/ encl: Distribution via LISTSERV

ML20203M062 SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DFFI/PB1 RII:DFFIPB1 NAME B. Adkins R. Williams DATE 07/17/2020 07/20/2020 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO URENCO USA CALENDAR YEAR 2021 INSPECTION SCHEDULE OPS1 Dates 02/08/21 - 02/12/21 Number of Inspectors 2 Inspection Procedures (IPs) 88020 - Operational Safety NCS1/RP Dates 04/05/21 - 04/09/21 Number of Inspectors 2 88015 - Nuclear Criticality Safety Inspection Procedures (IPs) 88030 - Radiation Protection PHYSEC Dates 06/14/21 - 06/18/21 Number of Inspectors 2 Inspection Procedures (IPs) 81431, 81810, 81340 OPS2/FP Dates 08/09/21 - 08/13/21 Number of Inspectors 2 88020 - Operational Safety Inspection Procedure (IP) 88055 - Fire Protection NCS2/TRANS Dates 09/13/21 - 09/17/21 Number of Inspectors 2 88015 - Nuclear Criticality Safety Inspection Procedure (IP) 86740 - Inspection of Transportation Activities EPX Dates 10/18/21 - 10/22/21 (Placeholder)

Number of Inspectors 3 Inspection Procedure (IP) 88051 - Evaluation of Exercises and Drills Enclosure