ML20125A324

From kanterella
Jump to navigation Jump to search

Pre-Submittal Meeting Slides for License Amendment Request - Main Control Room Chiller Completion Time Extension
ML20125A324
Person / Time
Site: Watts Bar  Tennessee Valley Authority icon.png
Issue date: 05/05/2020
From: Jim Barstow
Tennessee Valley Authority
To: Kimberly Green
Plant Licensing Branch II
Green K
References
Download: ML20125A324 (34)


Text

Watts Bar Nuclear Plant (WBN)

Pre-Submittal Meeting for License Amendment Request Main Control Room Chiller Completion Time Extension May 5, 2020

Opening Remarks

Background

Control Room Emergency Air Temperature Control System (CREATCS) Design CREATCS Modification TS 3.7.11, Required Action A.1 Main Control Room (MCR) Cooling Temporary Chilled Water Equipment TS 3.7.11, Required Action E.1 Summary of Compensatory Actions Precedent Schedule Milestones Closing Remarks Agenda l 2

Opening Remarks The purpose of this meeting is to discuss a proposed license amendment for WBN Units 1 and 2.

TVA is requesting a license amendment for a one-time change to WBN Units 1 and 2 Technical Specification (TS) 3.7.11, Control Room Emergency Air Temperature Control System (CREATCS), Required Actions A.1 and E.1 to support modifications to the CREATCS chillers.

This presentation will discuss the basis for the proposed TS changes and the modifications that are planned to be made to the CREATCS chillers and proposed compensatory measures.

l 3

=

Background===

The CREATCS chiller units are scheduled to be replaced to improve their efficiency.

The CREATCS provides cooling to the common MCR, therefore, inoperability of the CREATCS affects operation of both Units.

The Nuclear Regulatory Commission (NRC) previously issued a similar license amendment for WBN Unit 1 on February 8, 2011 (ML110190280) to allow one CREATCS train to be inoperable for up to 60 days while performing the modifications to the CREATCS chillers.

However, the modifications to the WBN Unit 1 CREATCS chillers were not performed due to issues with the seismic qualification of the replacement chiller units.

Documented in NRC Inspection Report 390/2014005 and 390/2014501 (ML15040A425).

The new chillers will be nuclear grade safety-related which addresses the corrective actions and lessons learned from the previous modification.

l 4

CREATCS Design The CREATCS provides temperature control for the MCR during normal operation and following isolation of the MCR.

The CREATCS consists of two independent and redundant trains that provide cooling of recirculated MCR air. Fresh air is also introduced into the MCR through the CREATCS.

Each train consists of an air-handling unit (AHU), water chiller, chilled water pump, and associated piping, ductwork, instrumentation, and controls to provide for MCR temperature control.

WBN has a common MCR for Units 1 and 2 located in the Control Building.

The design basis of the CREATCS is to maintain the MCR temperature for 30 days of continuous occupancy.

l 5

CREATCS Design l 6 AHU AHU

CREATCS Modification The proposed permanent modifications are limited to replacement of each of the CREATCS chiller packages.

The CREATCS AHUs, chilled water pumps and chilled water piping will not be changed during this modification.

During CREATCS chiller replacement, the affected CREATCS train will be inoperable.

l 7

Train A Chiller Replacement Duration l 8

  • Activity performed in parallel with chiller replacement activities
    • Activity performed in parallel with piping re-installation activities

Train B Chiller Replacement Duration l 9

  • Activity performed in parallel with chiller replacement activities
    • Activity performed in parallel with piping re-installation activities

Figure of Train A CREATCS Orientation l 10

TS 3.7.11, Required Action A.1 TS 3.7.11, Required Action A.1 provides a 30 day Completion Time to restore a CREATCS train to operable status if one train has been declared inoperable.

To accomplish these chiller replacements, TVA proposes that the TS 3.7.11 Required Action A.1 Completion Time for restoration of one inoperable CREATCS train be extended from 30 days to 60 days.

l 11

Proposed Technical Specification Change l 12 Units 1 and 2 - TS 3.7.11 Footnote for Action A.1

MCR Cooling During CREATCS chiller replacement, the affected CREATCS train is inoperable. However, train components remain functional with the exception of the chilled water pump and the chiller unit.

To provide defense in depth for cooling the MCR, a temporary chiller unit will be installed and connected to the functional CREATCS AHU.

The temporary chiller unit will operate during the modification to maintain the MCR temperature below limits.

If the temporary chiller unit fails, the Operable CREATCS train will automatically start on high AHU temperature, or may be manually started to maintain the MCR temperature.

l 13

MCR Cooling The Operable CREATCS train (in standby) will automatically start after a 30-second delay for the following occurrences:

(1) high air inlet temperature to the operating AHU, (2) low discharge airflow from the operating AHU, or (3) low differential pressure across the operating chilled water pump.

Failure of the operating train for any of these cases is alarmed in the MCR.

During the CREATCS chiller replacement modification, the low differential pressure start signal from the inoperable CREATCS train will be defeated to allow the temporary chiller system to provide the chilled water to that train.

The chilled water pump is out of service during the chiller replacement.

l 14

MCR Cooling The remaining two start signals will continue to function as designed, providing a diverse means to automatically start the standby Operable CREATCS train. This adequately supports the design function to ensure that a suitable environment is maintained for personnel and equipment in the MCR.

In addition to the automatic start signals, the temperature in the MCR is monitored every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> per the Technical Requirements Manual Section 3.7.5, Area Temperature Monitoring.

l 15

Temporary Chilled Water Equipment A temporary non-safety related chiller system will be installed and used to support MCR cooling during the CREATCS chiller replacements.

This temporary system is capable of providing adequate cooling to maintain the MCR within its normal temperature band.

The temporary chiller system is robust and reliable as demonstrated by its operation during other maintenance activities.

The major components of the temporary chiller system include:

Air cooled chilled water package Chilled water pump Power supply, cables, and connections Chilled water supply and return hoses Demineralized water source Engineered penetrations with isolation valves Backup diesel generator (DG) with fuel tank l 16

Temporary Chilled Water Equipment l 17

Temporary Chilled Water Equipment The temporary chiller system will use a 150-ton (minimum) capacity portable air-cooled chiller, a 500 gallons per minute (gpm) chilled water pump or pumps, temporary chilled water supply and return hoses, temporary penetration configurations and associated isolation valves, temporary chilled water connections to the appropriate AHU, and a 320kW DG.

TVA performed a calculation that considered operational heat loads, the nominal rating of the temporary chiller unit, and nominal temporary chilled water pump ratings.

The calculation determined that MCR temperatures would remain below 80°F.

These components are on stand-alone skid mounted packages and will be located in the yard west of the Auxiliary Building and in the Control Building Supply and return hoses will be used for routing the chilled water from the temporary chilled water package to the AHUs in the Control Building.

l 18

Temporary Chilled Water Equipment Existing sleeves located on Elevation 755.0 which are part of the MCR boundary will be used for routing the chilled water supply and return hoses to the appropriate MCR AHU located in the Mechanical Equipment Room.

Two manual isolation valves, one for each penetration through the MCR boundary will be provided for isolation purposes.

The valves at the penetrations are qualified for seismic retention to maintain the integrity of the MCR boundary.

The temporary hoses, pipe, and fittings are qualified for adequate pressure to protect against rupture and pipe whip.

A combustible loading evaluation has been performed to ensure the materials associated with this temporary modification do not substantially increase fire risks within the Control Building.

Spill containment will be provided beneath the chiller skid.

l 19

Temporary Chilled Water Equipment The temporary non safety related chiller system and chilled water pump will be powered from non-safety related 480V AC sources located within the station area.

The temporary chilled water system has a temporary 320 kW DG dedicated to it so that it can operate independently of site power.

The temporary chiller is not proposed as a safety related substitute for the permanent CREATCS chillers. Therefore, for this one-time TS extension request, the installation of the temporary chiller system, without the application of all safety related design criteria associated with weather and missile protection, is appropriate.

l 20

Control Room Habitability The CREATCS together with the Main Control Room Habitability System (MCRHS) provides for the safe uninterrupted occupancy of the MCR Habitability Zone (MCRHZ) during an accident and subsequent recovery period The MCRHZ is unaffected by the temporary chilled water system.

No changes to the ductwork, AHU characteristics, or the various system air flows serving the MCRHZ.

No changes to the emergency air cleaning system and no impact to post accident dose analysis.

The temporary chiller system and associated equipment will have no interface with the MCRHZ isolation, and therefore, will not impact the ability to isolate the MCRHZ or the ability of the emergency air cleanup system to function as designed.

Penetrations used for the temporary chiller supply and return hoses are limited in size to remain below the MCR boundary unfiltered inleakage criteria.

l 21

TS 3.7.11, Required Action E.1 TS 3.7.11, Required Action E.1 addresses a condition with two trains of CREATCS inoperable.

It requires immediate entry into Limiting Condition for Operation (LCO) 3.0.3, with subsequent Unit shutdown.

Because WBN has a common MCR for both Units, this would require a dual Unit shutdown.

During CREATCS chiller replacement, the affected CREATCS train will be inoperable.

If the other CREATCS train should be declared inoperable due to a failure or during post modification testing, LCO 3.0.3 is required to be entered immediately.

A four-day delay is requested prior to entering LCO 3.0.3 based on corrective maintenance repair times.

MCR temperature will be monitored hourly to ensure it remains below 90°F.

l 22

Proposed Technical Specification Change l 23 Units 1 and 2 - TS 3.7.11 Footnote for Action E.1

Corrective Maintenance Time for CREATCS l 24 Date Corrective Maintenance Issue Unavailability Time (Hours:Mins)

Unavailability Time (Days) 11/8/19 MCR Chiller A TCV failed 51:19 2.14 11/5/19 MCR Chiller A TCV failed 49:11 2.05 3/31/19 MCR Chiller B Air Handling Unit (AHU) motor failure 70:45 2.95 3/28/19 MCR Chiller B AHU motor failure 74:10 3.09 7/9/18 MCR Chiller B not cooling 88:00 3.67 4/12/17 MCR Chiller A oil temperature issue 77:20 3.22 3/8/16 MCR Chiller A Oil Cooler Temperature Control Valve (TCV) failure 64:43 2.70 10/8/15 MCR Chiller B Essential Raw Cooling Water (ERCW) leak on oil return line (rework from repair made during week) 25:29 1.06 9/30/15 MCR Chiller B ERCW copper pipe rupture 64:52 2.70 3/1/15 MCR Chiller A ERCW TCV failed 31:00 1.29

TS 3.7.11, Required Action E.1 The proposed footnote to TS 3.7.11, Condition E, is based on verifying that the MCR temperature is less than or equal to 90°F.

The temperature limit for MCR equipment operability is 104°F.

The 90°F temperature limit provides margin between the normal MCR operating temperature of 75°F and a limit that ensures that the equipment operability limit of 104°F is not exceeded.

l 25

TS 3.7.11, Required Action E.1 The proposed footnote for TS 3.7.11, Required Action E.1 requires that operators monitor the MCR temperature every hour and verify the MCR temperature is less than or equal to 90°F.

To support the one-hour frequency for temperature monitoring TVA evaluated the effect of a loss of cooling on the MCR temperature by performing an analysis of the heatup of the MCR and surrounding areas.

Two cases were evaluated Normal operating heat loads, summertime maximum outdoor temperatures, one AHU operating, no chillers in operation LOCA heat loads, summertime maximum outdoor temperatures, no AHUs running, no chillers in operation The calculation demonstrates that the temperature increase from 75°F (normal MCR operating temperature) to 104°F takes approximately 5.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> for the normal operating heat load case and 4.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> for the LOCA heat load case.

l 26

TS 3.7.11, Required Action E.1 The one-hour frequency for temperature monitoring is adequate based on the heat-up calculations for the MCR and the indications available in the MCR.

With hourly temperature monitoring, a degraded condition would be identified before equipment temperature limits were reached and Unit shutdown activities would be initiated.

Additionally, with operators continually stationed in the MCR, temperature increases of this magnitude would most likely be identified before the hourly monitoring requirement.

l 27

TS 3.7.11, Required Action E.1 Maintaining MCR temperatures at or below 104°F will ensure that the safety-related functions are operable.

Since this proposed change maintains the CREATCS function for a limited period of time and supports plant safety functions, there is no adverse impact to nuclear safety.

The proposed change will allow both Units to continue power operation and not be subjected to an unnecessary shutdown when sufficient cooling is available to maintain an acceptable MCR environment.

l 28

TS 3.7.11, Required Action E.1 The proposed delayed entry into LCO 3.0.3 would be used if the operable CREATCS train became inoperable unexpectedly. It is also proposed that the delayed entry into LCO 3.0.3 be used to support post modification testing.

Delayed entry into LCO 3.0.3 is needed to allow stabilization of the water and air flow from the modified CREATCS train during post modification testing. This impact is due to the automatic start signals from the modified train requiring the operable train to start inappropriately and repeatedly.

For example, during testing of the modified train, there may be cooling water flow and air flow anomalies that would signal the operable train to start unnecessarily This type of entry into TS 3.7.11, Condition E would only be used in direct support of post modification testing and only when the potential for anomalous water and/or air flow in the modified CREATCS train is possible.

l 29

Summary of Compensatory Actions A temporary, non-safety related chiller system with a temporary DG to provide power to the temporary chiller system will be installed and operated as described.

Instructions for operation of the temporary cooling equipment will be provided.

During replacement of the CREATCS chillers, TVA will employ a graded approach to defense-in-depth and protected equipment strategies based on the operating status of the affected unit. The risk of the activity will be assessed and managed, including the use of physical barriers as needed.

Additionally, TVA procedures preclude work on or near protected equipment and limit access to the area to emergency situations and non-intrusive monitoring of running equipment per operator rounds.

During replacement of the CREATCS chillers, no elective maintenance will be performed on TS related support equipment for the Operable CREATCS chiller except for any required TS Surveillance Requirements.

l 30

Precedent NRC license amendment for WBN Unit 1 dated February 8, 2011 (ML110190280)

NRC approved a 60-day extension to the TS 3.7.11, Required Action A.1 Completion Time NRC license amendment for Sequoyah Nuclear Plant, Units 1 and 2, dated May 21, 2004 (ML041460534)

NRC approved a 7-day extension to the 3.7.15.b Completion Time NRC license amendment for Surry Power Station, Unit Nos. 1 and 2 dated January 23, 2008 (ML0734800287)

NRC approved a 14 and 45-day extension to the Completion Time for one train of switchgear room air conditioning NRC license amendment for Seabrook Station, Unit No. 1 dated September 17, 1999 (ML011920184)

NRC approved a 60-day extension to the Completion Time for one train of control room air conditioning l 31

Schedule Milestones May 5, 2020 - LAR Pre-Submittal Meeting with NRC May 2020 - LAR Submittal - Request NRC approval within 12 months of submittal with 30-day implementation June 2020 - Telecon or meeting to discuss any NRC questions May 2021 - NRC Approval of LAR (Requested) l 32

Closing Remarks l 33