Revised Ro:Operability Date of 910830 for Electric Motor Driven Fire Water Pump P-4501 Not Met.Pump Not Actually Declared Operable Until 911025.Caused by Unforseen Matl & Testing Problems.Equivalent Pump Available
ML20085N145
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 11/05/1991
From: Warembourg D
PUBLIC SERVICE CO. OF COLORADO
To: Weiss S
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
References
P-91389, NUDOCS 9111140143
Download: ML20085N145 (2)


Text

- - - - - - - - - - - - - .

~

i I

C"A

$ Public Service' 16805 WCR 19-1/2, Platteville, Colorado 80651 November 5, 1991 Fort St. Vrain Unit No.'l P-91389 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Attention: Dr. Seymour H. Weiss, Director

-Non-Power Reactor, Decommissioning and Environmental Project Directorate

-Docket No. 50-267

SUBJECT:

FIREWATER. PUMP INOPERABILITY

REFERENCE:

PSC. Letter, Fulier to Weiss, dated August 15, 1991 (P-91270)

Dear Dr. Weiss:

This: letter.-provides a revised report on the inoperability of the electric motor driven firewater pump (P-4501) at Fort St. 'Vrain

( FSV) . ._ .Public._ Service -Company of _ Colorado (PSC) had previously; reported the inoperability of firewater. pump P-4501 in the referenced

-letter. At that time, PSC indicated that we were planning to restore the pump to operable status by August 30,.1991. This olanned date

-was _ overly optimistic and firewater pump P-4501 sas not actually declared operable _until October _2F, 1991.

Completion _ of repairs and testing on firewater prmp P-4501 was idelayed beyond August 30, 1991, due to unforseen material and testing-problems. -Replacement parts were not available for installation-

.untii Sept *mber 10, 1991. Also, the pos+ maintenance testing efforts identified problems -that required additional disassembly of-the pump.

and-repair of other system components.

The extended outage of-firewater pump P-4501 did not adversely affect PSC's-ability to maintain the plant in a safe shutdown condition. In fire ' protection; cooldown Train 1, firewater pump-P-4501 is utilized to supply. cooling water to the prestressed concrete reactor vessel

. liner. During the entire outage'of this pump, an equivalent pump, diesel engine driven firewater pump P-45015, was available to supply water to Train 1 and to firefighting equipment. In addition, the '

redundant fire protection cooldown train, Train 2, remained operable.

[ > 2/

9111140143 911105 DDR ADOCK 05000267 t A0 cg PDR 1\

. . . . . . - . . - - . - . - . - . ~ _- - . . - . . . . . - - . -

P-91389 Page 2 November S, 1991 PSC regrets any concerns that were raised by the extended outage of

-firewater pump P-4501. We thoroughly understand the need to maintain essential equipment during the permanent shutdown condition of Fort St. Vrain, and we have numerous administrative controls in effect to ensure this. PSC will continue to emphasize the need for timely restoration of equipment that is needed for the safe defueling of-the FSV reactor.

If you have any questions regarding the inoperability of firewater pump P-4501, please contact Mr, M. H. Holmes at (303) 480-6960. .

Sincerely,

$ )J'kitj+~lnu }

D. W. Warembourg Manager, Nuclear ProductMn and Station Manager DW/SWC/Img cc: Regional Administrator, Region IV Mr. J. B. Baird-Senior Resident Inspector Fort St. Vrain

. - . .