ML20095K975

From kanterella
Jump to navigation Jump to search
Fort St Vrain Project Update Presentation to NRC, on 951207 & 15
ML20095K975
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 12/15/1995
From:
PUBLIC SERVICE CO. OF COLORADO
To:
References
NUDOCS 9512290351
Download: ML20095K975 (24)


Text

ENCLOSURE 2 FORT ST. VRAIN PROJECT UPDATE Presentation to tite Nna6lee?

= Rem,a c kba r .

LrrSTitM 4 4 LiS S?O M 4 i:

290026 O Public m s.,*,c - Service-y,c.,.

w Jy 0 1 f0A"%8S!dM$$$jg7

I l

FORT ST. VRAIN UPDATE l

PUBLIC SERVICE COMPANY OF COLORADO PRESENTATION TO THE ,

s NUCLEAR REGULATORY COMMISSION December 7,1995 (Washington)

December 15,1995 (Region IV)

L____________________________________ __ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _

AGENDA

  • Decommissioning Status Safety and Radiological Performance

- Final Release Survey

  • Spent Fuel Status -- DOE Agreement
  • PSCo Corporate Merger
  • Repowering Status
  • Present Concerns l
  • Conclusions 1

l l

  • Supplemental Information Page 1

DECOMMISSIONING STATUS Page 2

PRESTRESSED CONCRETE REACTOR VESSEL (PCRV)

~

/

49 CLN y , .y L g ge C.

r p

Wy:~P7 s ,Nd - .-

- CONTROL R00 DRIVES

/,/g) 5 P

!, I

, ACTWATED CONCRETE l- g e

D% $ l l

A  !. .

l '

fl i

- 880E REFLECTOR BLOCKS

~

. . ~ FUS, ELEMENTS

. ~ i I pg,,N 111 d ..

~

CORE SUPPORT H

h -

- SNM GMMAM MODULES l FLOOR --- , /

Pwl /

i M w '

l

[ / HEUUM CIRCULATORS l u '

'/

/

UNER '

31' die.

hY '

l

,- - i N/

%- BOTTOM HEAD PENETRATIONS G/

\.

Page 3

+ ,

r k I

&y/

'*E

!/ pt. iI

Y \T Y >

  • A SERIES OF VERTICAL k5 E <

j \

CONCRETE CUTS ARE Y) , .yi '

' MADE USING THE

  • VERTICAL TENDON

'd ,

l n TUBES AS CONDUlTS l, ,% \ < FOR THE DIAMOND

, m AA 4> '

WIRE SA W.

V P ~~~

/ ,Q THE CONCRETE SLABS

' \\l 9 ARE REMOVED AND

\

\

TTI PACKAGED FOR I

, SHIPMENT.

I i

i I l I l io i N I

f i

i ces q o

l g j h

%f nn Y

PCRV ACTIVATED CONCRETE REMOVAL Page 4

l WW g<j fft? j 1

.J t.

l' ,4 M

V -

h Q 'a 8 y h 0

  • j, l AFTER FINAL
sJ CLEAN-UP THE jl* 'sur PCRV WILL BE l

,% \ LEFT AS SHOWN

$' &@ p_

q , STEEL PLA TE h : CLOSURES WILL

~

~x

, BE MADE FOR

& i 'Y i THE TOP HEAD h3 '

J AND THEPCRV

\ WILL BE LEFT

,G

' G '

. (;

FOR LONG ' TERM STORAGE FOR

~

, \ DISMANTLEMENT i

IN THE FUTURE.

M N, b,'ck '

,y -

,,9 && . i

\,,

PCRV FINAL DISPOSITION Page 5 L.___. . . . . _ . _ . . . _

DECOMMISSIONING STATUS PROGRESS SINCE MAY 1995:

  • Removal of Activated Upper Beltline Concrete Complete
  • Removal of Fuel Storage Wells Complete
  • Removal of Shield Water System Complete, Release of Shield Water Complete
  • Final Survey of Buildings Outside Restricted Area Complete
  • PCRV and BOP Dismantlement, Decontamination Activities Are Approximately 90% Complete
  • Characterization Surveys and Decontamination of Reactor Building Structures and Systems Are in Progress Page 6

DECOMMISSIONING STATUS REMAINING ACTIVITIES:

  • Removal of Lower Beltline Concrete from PCRV
  • Removal of Lower Plenum insulation
  • Decontamination of Embedded Piping and PCRV Internal Surfaces
  • Characterization and Decontamination of Reactor Building Surfaces and Systems
  • Final Radiological Survey l

Turbine Building Surfaces Buildings and Areas inside Restricted Areo Unaffected Systems Effluent Pathways Reactor Building Surfaces Affected Systems

- Open Land Areas l

l Fr Je 7

, D NTE: 12-06-95 i PCRV n

N B7 B8 M ..- . R 8 .. M

... '0'b b &-6? '

' ~

B5 6:j-5') ~'

' j_jR

, B10

. l b

, -4 ;-

~

. . . . . .. g41:

B4 lL .'.???.., {

') 1.: ... B11 m.

Aip - j,jd.,.=.

Q-3iu 41 -3 } 0

...s. ..~.

. ..; - i h g

83 b 312 3 (1-2 '.). . .

... ,.. $ .2 jti R23-1 : :2-1 ;,at i

B2 s.. g1 NOTE: RADIAL CONCRETE CUT Bi3 B1 14 R2 IS IN PROGRESS AND BACK CUT B4 IS ALSO IN PROGRESS.

% CUT COMPLETE PREPARED BY BOB GUNNERSON

.___ .e

l ilil\I!i l  !

N ,

D O l

C N E a I D g ,

0 E R N

S O x -

x I

I E

e T T l

E R

A L

x 6

4 J S E

C U i x C

1 J I R

6 0 N' x x

I I C A

M i

M M I

D E U x A R P

T A

N E x M R V

I I

P ,

x l O T

T C R x I

F A R

A d0 x J E L

x N

E U v D

I G

I E

V  : L i N M A

O M .

l E E 0 T R I S . 4 5 O

& P i

E A S R l

C' .

L 5 J R 4 I Y 9 C E 1 J V mHe R l -

N U I S A . L A

M e N m I i

m F F E m a

l R T J O E S O L H m D

Y F

C E N l

K T O N C

(

0 S

R E

T U

D R)

M U

S D

E I M I

t E A R l

.S O 4

4 J mKC C 9 O V 1 J mL R C

I M

.G

. P l .R

.OI A C E

_ M L l f m

_ l F .tR m.

J I m u

D

.N

.EN S l

.A E N .M G l R N E A 0 E P H S IT C

F E E S H I R E l

F R C P

/ N A W A O l D O P C 3 S N C U S J O -

4 R D

-P 9 O C A D 1 J T E A E S E E i

C H E L S M R V E mI L P C l O R U F T C O G A E A P I &

R t F

E h f N E L 0 _

N L v 1 E _

l E I u I F G F H A E I

E L J M R -Nl U A i )

L E A E D m. I H I

S mN C N K .O S l C mC L 2 0 O L .E A 4

4

.D (

5 sP 1 9

l .O G B .B I A R S O A

l J

2 jll f l

OL eDed a!!!!!!!!!!

= MMMGMM%\\\\\\N i

~

a M@@MMM\\Mx\\\N i

- x MM@MMEMNNW i a

e MMM@MENNNNNNNY MMMMME\\\\\\\\ i N

$l m

e 8@MMMMh\\\\\\\N 5 g

a x MMM&\\\\\\\\\%\\\1 ! <

Sa MMMMENNNNNNNN\\\\\\\N e to !

5e MMMMMMM i H e M@MWN: h e M M ANNNNNNNNN M % \\N g e M M M & % \\\\ M M e s' M M E \\\\\\\\ % \\\1 O HVAC SYSTEMS MM'@Mh\\MN\\\\\\3 O

SAFETY AND RADIOLOGICAL PERFORMANCE OCCUPATIONAL RADIATION EXPOSURES:

(Person-REM)

Total Estimate per Decommissioning Plan 433 Expected Total Project Dose 392 Actual Dose to 12/1/95 366 l

l LOW LEVEL RADIOACTIVE WASTE SHIPPING:

l (Cubic Feet Shipped from FSV) l l

l Total Project Estimate 245,000 Shipped to 12/1/95 218,600

  • 71,380 Curies l
  • 442 Shipments l

Page 11

SAFETY AND RADIOLOGICAL PERFORMANCE (Continued)

TIME WORKED IN RADIOLOGICALLY CONTROLLED AREAS (RCA):

(Porson-Hours)

Actual RCA Hours to 12/1/95 573,000 Original Project Estimate 367,100 (per Decommissioning Plan)

PERSONNEL CONTAMINATIONS:

(Contaminations per 10,000 RCA hours)

! FSV 4.5 PWR Outages 6.5 BWR Outages 14.5 l

LOST WORKDAY INDICATORS:

  • Only 3 Lost Time Work injuries
  • Lost Work Day incidence Rate (per 200,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />):

FSV 0.47 l Typical Construction Projects 6.9 (National Bureau of Labor Statistics)

  • Severity Rate (per 200,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />):

l l FSV 45.7 l l i Typical Construction Projects 132 Page 12

FINAL RELEASE SURVEY

1. REMAINS MAJOR CHALLENGE OF PROJECT
2. PROGRAM OVERVIEW:

FSV Buildings, Systems, and Land Areas Divided into 9 Survey Groupings Groups A through I include:

l l

  • 289 Survey Packages 1
  • 100,300 Measurement Locations
  • 390,900 Measurements f

Page 13

l l

l FINAL RELEASE SURVEY (Continued)

3. EMBEDDED PIPING REPRESENTS SIGNIFICANT CHALLENGE
  • 30,000 feet of Small Diameter Piping
  • 5% of Measurements May Exceed Fixed Contamination Site Specific Guideline Values (SGLV)

> FSV SGLVs are 4,000 dpm/100 cm2(Average),

12,000 dpm/100 cm 2(Individual)

> All Measurements Are Expected < 50,000 dpm/100 cm 2After Aggressive Decontamination

  • PSCo/WT Submitted Proposed Treatment on October 12,1995:
  • Aggressive Decontamination

> Fill Piping With Grout That Exceeds SGLVs

> NRC Approval of Measurements That Cannot Be Reduced Below 100,000 dpm/100 cm 2

> Requested Approval By December 31,1995

  • Dose Consequences 2.4 mrem Per Year --

from 2

100,000 dpm/100 cm

  • Cost of Additional Decontamination or Removal Efforts to Meet SGLVs is From $3.1 Million to $33.9 Million

-- Not ALARA Page 14

FINAL RELEASE SURVEY (Continued)

4. BACKGROUND Widely Varying Background Complicates Demonstration That Exposure Rate Meets Release Criteria
  • Release criteria is 5 pR/hr above background
  • Background varies from 5 - 30 pR/hr
  • WT developing methodology including use of in situ gamma spectrometer
  • Need to Ensure NRC's Confirmatory Survey Uses Same Survey Protocol, Groundrules as PSCo l

S. CONCLUSION l

  • NRC Inspected Final Survey Program September 25-28

> Reviewed Procedures and Records

> ORISE Performed independent Field Measurements

> GPU Independent Measurements Were Consistent With SEG, Expect Consistent with ORISE

> NRC Found that Program Was Being implemented l in Sound Manner i > Survey Packages Were Thorough, Although incomplete At Time of Inspection

  • PSCo Appreciates NRC Efforts to Perform Confirmatory Survey in Parallel With PSCo/WT Final Survey --

Significant Savings in Time and Possible Rework

  • Excellent Communications With NRC Staff Page 15

SPENT FUEL STATUS - DOE AGREEMENT PSCO AND DOE HAVE REACHED AGREEMENT IN PRINCIPLE

  • DOE Takes Title to All FSV Fuel in ISFSI
  • DOE Takes Title to 2 New Spent Fuel Shipping Casks
  • DOE Pays PSCo $16 Million of ISFSI Costs
  • DOE Responsible For All Future Costs Before and After Title Transfer, e.g., Maintenance, Defueling, Decommissioning, Regulatory Changes l

l l

Page 16

PSCo CORPORATE MERGER 1

On August 23,1995, PSCo and Southwestern Public Service Company (SPS) of Amarillo, Texas Announced Intent for Merger, Under New Holding Company

  • PSCo Will Remain an Entity Under New Holding Company, and Will Retain Existing Licenses
  • Current Financial Assurance Provisions Unchanged
  • SPS Has Substantial Generating Capacity with Primarily Coal and Natural Gas -- No Nuclear Involvement
  • PSCo Will Own 61.9 % of Common Equity of New Holding Company: SPS Will Own 38.1 %

l l

l Page 17

l REPOWERING STATUS l

l PROJECT CONSTRUCTION IS PROCEEDING ON SCHEDULE

  • Combustion Turbine and Generator Arrived On-site By ,

Rail On September 6,1995

  • Installation 45% Complete
  • Natural Gas Pipe Installation in Progress

> NRC Approval Received July 31,1995

  • First Ignition Startup Test Scheduled for February 2, 1996 a

r e>

4,~'

Page 18

l PRESENT DECOMMISSIONING CONCERNS

  • Completion of Final Survey for Site Release
  • Approval of Embedded Piping Treatment
  • Confirmation That Established FSV Site Release Criteria Will Not Be Subject to Change
  • Final License Termination Process l
  • Successful Completion of ISFSI License Transfer to DOE Page 19 l

CONCLUSION

  • FORT ST. VRAIN DECOMMISSIONING IS PROGRESSING WELL
  • RADIOLOGICAL AND INDUSTRIAL SAFETY PERFORMANCE IS EXCELLENT
  • THE PROJECT WILL BE COMPLETED AHEAD OF PROGRAM SCHEDULE AND UNDER BUDGET 1

!

  • PSCo APPRECIATES NRC'S PROFESSIONALISM AND l DEDICATION DURING FSV DECOMMISSIONING PROJECT I

l Page 21

1 SUPPLEMENTAL INFORMATION

  • STAFFING CHART e

l Page 22

FORT ST. VRAIN 1

l DECOMMISSIONING STAFF LEVELS l Legend W WESTINGHOUSE TEAM CONTRACT EMPLOYEES PSC EMPLOYEES soo 700 k k i

~ ~

g _. . i 3004 :.

CD tttt, w 4%.: ..  :..

W  ??-MI4 c

>- :TM$g+g O 4m -ti::T-7T- h"--i 'l .

3

.,,,,J 9 O- NN "

ti <$': ..w 2  : Jif 4.,j CONELACT EMPLOYEES W zoo _ :pp _ .grity -

e j g(ggt g i

  • MF5 NMs iI![ ++r.r

+

ml,
k ,

&,-A. ,<+M,:::i:z::: :m p 7 __ ._. _. n, , .

g;  ;  ;  ; ,

,y,  ; ,, . M,,a i::

% 4:  :  ::  :::,:0, 1 ,. :o m ,:::

',::52::

": :i::  :::i:-  :: 2::

i 200-- .

i::  ::  :: MMMB:%:'i% :M2::  : :i::  :::i::  :: i::  ::%k 7 'i u _.. _ m.__,_. _

i k M:::i%  %:i  :  :':i ::i%%:'::i:'  ; :-:!O%  : :50 .::2:: , :: ':::

' v-r , ]+ -

={ - T*"::: 2:::i:: .

[

M PSCEMPLOYEES i  : [ hjjj,.j [

WESTINGilOUSETEAM r'4T+ 5 -- /

e 2:::i:::i:: .::m,,,,..,.. y _ _, _ ,-,, . .,,. .

o  :. m I E? U'i M' ,'

M 100 - +

5  ? '

'-' i IS E_l'.kM k iMEE:2 r% E i  :

+ ~

Yi"-M """"

-Y.D# M@ SiFJd Nhjhkgh.fh -h[: 23 ((_N$f $'$$ 55  : s

_m

'I...

7.

,gd '

1. --o. l b i' s 4

.s,

_ .p.. .

3 .-

. .s .

l l .I

. hl L i

f l- ;j Z!~ -

Ti ( h f h

,, e ,A. e e ,- e e e ,e ., ., e ,e e A - . A e e . e ,e e