Text

...

Mc

/

'o UNITED STAYES y"

NUCLEAR REGULATORY COMMISSION

{,

E W ASHINGTON,0.C. 20555 8

'% * * * *

  • J F

June 15, 1982 OFflCE OF THE SECRETARY 4

s MEMORANDUM FOR:

William J. Dircks, Executive Director for Operations 1

(b FROM:

Samuel J. Chilk, Secreta 2

/ I T )

SUBJECT:

STAFF REQUIREMENTS - BRI JG ON STATUS OF ZIMMER INVESTIGATION, 9:40 A.M.,

MONDAY, JUNE 7, 1982, COMMISSIONERS' CONFERENCE ROOM, D.C. OFFICE (OPEN TO PUBLIC ATTENDANCE)

The Commission in open session was briefed by staff on the results of the Zimmer investigation.

The Commission requested information on the number of QA/ QC employees at all plants currently under construction; including the number of quality assurance persons and the number of quality control persons employed by the utility and by the constructor and architect.

(Constructor and architect employees should be shown individually, if possible.)

(EDO)

(SECY Suspense:

6/25/82)

(Subsequent to the open portion of this meeting, the Commission noted that the July 2nd letter from the Department of Justice referred to at the meetir.g (see transcript, page 59) as a public document had actually not been released to the public.)

The Commission held the final portion of this meeting in closed session.

cc:

Chairman Palladino Commissioner Gilinsky Commissioner Ahearne Commissioner Roberts Commissioner Asselstine Commission Staff Offices PDR (Advance) f DCS - 016 Phillips J 8206220134 820615 l

PDR 10CFR PT9.7 PDR