I POR-oi6 o,
UNIT ED STATES
- [ ? s,g h NUCLE AFI REGULATORY COMMISSION
/. E WASHINGTON D. C. 20555 g[..h h'/ /
,,, *....f a
April 12,1982 ke 5
d' 2(
& g;Ong?' 9 Mr. Warren Liebold 44 Roslyn Avenue IN RESPONS Sea Cliff, NY 11579 TO F01A-82-11 N
Dear Mr. Liebold:
This is in response to your letter dated February 26, 1982, in which you requested, pursuant to the Freedom of Information Act, seven categories of documents concerning the Hayward Tyler Pump Company.
The documents listed on the Appendix to this letter are enclosed with the exceptions noted below.
A home telephone number has been deleted from document 35 pursuant to exemptions (6) and (7)(C) of the Freedom of Information Act (F0IA) (5 U.S.C. 552(b)'(6) and (7)'(C)) and 10 CFR 9.5(a)(6) and (7)(iii) of the Commission's regulations because disclosure of this information would constitute an unwarranted invasion of personal privacy.
The remaining portions of this document are enclosed.
Document 37 consists of investigatory records compiled for law enforcement purposes, and is being) withheld from public disclosure pursuant to exemptions (7.)(A) and (Q of the F0IA~
and 10 CFR 9.5(a).(7)(1) and (iv) because disclosure of the informat. 'n would interfere with an enforcement proceeding and disclose coc.fidemial information furnished by a confidential source.
The review of documents 12,14,15, 21, 29, 30, 31, 32, 33 and 36 has not been completed. -As soon as our review is completed, we will advise you of our disclosure determination.
Pursuant to 10 CFR 9.9 of the Commission's regulations, it has been determined that the information withheld is exempt from production or disclosure, and that its production or disclosure is contrary to the public interest.
The person responsible for the denial of document 35 is the undersigned.
The persons responsible for the denial of document 37 are the undersigned and Mr. Richard C. DeYoung, Director, Office of Inspection and Enforcement.
8205100019 820412 PDR FOIA LIEBOLD82-117 PDR
I l
1 Mr. Warren Liebold !
This denial may be appealed to the Commission's Executive Director for Operations within 30 days from the receipt of this letter. As provided in 10 CFR 9.11, any such appeal must be in writing, addressed to the Executive Director for Operations, U.S. Nuclear Regulatory Commission, Washington, DC 20555, and should clearly state on the envelope and in the letter that it is an " Appeal from an Initial F0IA Decision."
Sincerely, f
'~
y
/,
_ci d 'cP: W
/
J.' M. Felton, Director
/ /
Division of Rules and Records Office of Administration
Enclosures:
As stated
~
..i._..........-.
_u_-_-_
Appendix 7^.
l '.
December 11, 1981 Letter from Rep. Markey to Chairman Palladino with 5 affidavits.
2.
December 15, 1981 Letter from Cong. Jeffords to Chairman Palladino regarding' progress of investigation.
.3.
December 16, 1981 Memo from Com. Ahearne to ED0 requesting update on Markey request.
4.
December 22, 1981 Memo to Rehm from Collins regarding 12/11/81 Markey letter.
5.
December 22, 1981 Memo to Rehm from Collins regarding 12/16/81 Ahearne memo.
6.
December 23, 1981 Memo from Com. Bradford to EDO requesting investigation.
7.
January 18, 1982 Letter to Rep. Markey from OCA responding to December 11 request.
8.
January 18, 1982 Memo to Bradford from EDO preliminary response to December 23 memo.
9.
January 21, 1982 Letter to Cong. Jeffords from EDO responding to December 15 letter.
I 10.
January 25, 1982 Memo to EDO from Bradford forwarding newspaper article, i
11.
January 26, 1982 Memo to Ahearne from EDO in response to December 16 Ahearne memo.
12.
February 18, 1982 briefing outline from John Collins.
13.
February 12, 1982 Memo to Bradford from EDO final response to December 23 Bradford memo.
14.
Undated draft investigator's and inspector's reports and NOV provided in IE:HQ review on February 18, 1982, 15.
February 19, 1982 Memo from Karl Seyfrit to Roger Fortuna transmitting a February 19, 1982 letter to HTPC from Karl Seyfrit regarding " Final" Report of Investigation No. 99900345/82-01 (Statements and administrative page have been deleted from Report) (See Item 37),
16.
February 23, 1982 Memo to Cummings from Collins reouesting OIA review of reports.
17.
March 5,1982 Memo to Commission from Cummings reporting release of report to vendor.
18.
March 5, 1982 Memo to Chairman from ED0 announcing OIA investigation.
19.
March 5,1982 Memo to EDO from Collins chronology.
20.
March 5,1982 Memo to Cummings from EDO requesting OIA audit.
2 21.
March 5.1982 Memo to Commission from ED0 reporting release of draft reports to HTPC and including copies of documents released.
- 22. March 5,1982 Memo to File by W. J. Ward documenting transmittal of draft reports to Commission and EDO.
23.
March 9,1982 Memo from Cummings to Chairman advising of invitation of investigation.
- 24. March 10,1982 Letter from HTPC to DeYoung advising of Field inspection program.
- 25. March 20,1980 Letter from Uldis Potapovas to HTPC regarding QA Program Inspection conducted on February 25-27, 1980.
- 26. January 21, 1982 Memo from John Collins to Ed Jordan regarding listing of pumps manufactured by Hayward Tyler Pump Company fer the period 1977-1981.
- 27. Jar,uary 28, 1982 Informal note from David Reiff to G. Bagchi regarding investigation of defective Hayward Tyler pumps.
28.
Februa ry 25, 1982 Memo from ED0 to Commissioner Ahearne regarding Region IV Report delay.
29.
Undated / Unsigned draft Investigation Report No. 99900345/82-01.
- 30. Undated / Unsigned draft Investigation Report No. 99900345/82-01.
- 31. Undated / Unsigned draft letter to HTPC fran John Collins regarding Inspection R. port No.99900345/82-02.
32.
Undated / Unsigned draft letter to HTPC from John Collins regarding Inspection Report No. 99900345/82-02.
33.
February 19, 1982 Letter to HTPC from John Collins regarding Inspection Report No. 99900345/82-02 34.
Chronology of Contact Between NRC and HTPC.
- 35. October 30, 1981 Note to W. Reinmuth from J. Sniezek regarding 10 CFR Part 21 Reports / Allegation.
36.
flarch 22, 1982 Memo from John Collins to R. DeYoung transmitting final draft investigation and inspection reports.
- 37. Written statements and Reports of Interview (with names included) and a key which reveals the identities of those not mentioned by name in the report.
38.
Porch 24, 1982 Note to Jim Cummings from Jim Sniezek transmitting above Document #36 (enclosure not repeated here).
3 r
.39.
March 19,1982 Memo from James Sniezek to' Roger Fortuna regarding continued investigation and enforcement activities regarding HTPC.
- 40. March 10,.1982 Letter from Rep. Markey to Chairman Palladino regarding hearing on circumstances sur.ounding release of draft reports.
}
}
T S*