ML19281C941

From kanterella
Jump to navigation Jump to search
Regulatory Audit in Support of Confirmation of a Plants' Implementation of Nuclear Energy Institute 19-02, Guidance for Assessing Open Phase Condition Implementation Using Risk Insights
ML19281C941
Person / Time
Site: Ginna Constellation icon.png
Issue date: 10/10/2019
From: Alexander Schwab
NRC/NRR/DRA/APOB
To: Antonios Zoulis
NRC/NRR/DRA/APOB
Alexander Schwab
References
NEI 19-02
Download: ML19281C941 (6)


Text

October 10, 2019 MEMORANDUM TO: Antonios Zoulis, Acting Chief Probabilistic Risk Assessment (PRA) Oversight Branch Division of Risk Assessment Office of Nuclear Reactor Regulation FROM: Alexander Schwab, Reliability and Risk Analyst /RA/

PRA Oversight Branch Division of Risk Assessment Office of Nuclear Reactor Regulation

SUBJECT:

REGULATORY AUDIT IN SUPPORT OF CONFIRMATION OF A PLANTS IMPLEMENTATION OF NUCLEAR ENERGY INSTITUTE 19-02, GUIDANCE FOR ASSESSING OPEN PHASE CONDITION IMPLEMENTATION USING RISK INSIGHTS The Office of Nuclear Reactor Regulation, Division of Risk Assessment (DRA) staff plans to conduct an audit of the implementation of Nuclear Energy Institute 19-02, Guidance for Assessing Open Phase Condition Implementation Using Risk Insights The audit will be conducted at Ginna, a site which has decided to use the guidance document to risk-inform the decision of whether to implement the Open Phase Isolation System to provide alarm and indication to the control room operators as opposed to automatic actuation mode in response to an Open Phase Condition. The audit plan is provided in the enclosure to this memorandum.

The audit will take place during the week of October 14th. A member of the DRA staff from the PRA Oversight Branch and a Region I Senior Reactor Analyst will perform the audit.

Enclosure:

Audit Plan CONTACT: Alexander Schwab, NRR/DRA 301-415-8539

ML19281C941 *via email NRR-106 OFFICE NRR/DRA/APOB NRR/DRA/APOB*

NAME ASchwab AZoulis DATE 10/10/2019 10/07/2019 REGULATORY AUDIT IN SUPPORT OF CONFIRMATION OF A PLANTS IMPLEMENTATION OF NUCLEAR ENERGY INSTITUTE 19-02, GUIDANCE FOR ASSESSING OPEN PHASE CONDITION IMPLEMENTATION USING RISK INSIGHTS

1.0 BACKGROUND

An Open Phase Condition (OPC) is when there is a loss of one or two of the three phases of the high-voltage side of a transformer that connects an offsite power circuit to the transmission system. An OPC can be coincident with or without a high-impedance ground fault, can originate from circuit breakers and disconnect switches poles not opening or closing, or can be the failure of transformer bushings or line insulators leading to a loss of circuit continuity. This condition can cause voltage and current imbalances in the alternating current (AC) electrical distribution system for both safety and non-safety related electrical systems that may be detrimental to operating equipment. Inadequate protection from an OPC may result in station blackout conditions and challenge plant safety. Specifically, it may lead to a condition in which neither the offsite power system nor the onsite power system is able to support the safety function(s).

An OPC that affects the safety function(s), if not detected and disconnected promptly, represents a design vulnerability for nuclear power plants. Operating experience in different countries has shown that the currently installed instrumentation and protective schemes have not been adequate to detect this condition and take appropriate action.

On January 30, 2012, Byron Station, Unit 2 experienced an event in which the 4.16 kV engineered safety feature buses were not energized by an operable power source for eight minutes. The event was initiated by a mechanical failure of an electrical insulator in the 345 kV switchyard. The failed insulator caused the loss of one of three electrical phases (Phase C) supplying 345 kV offsite power to the Unit 2 station auxiliary transformers. Following the insulator failure, the reactor automatically tripped from full power and additional complications resulted from the OPC. U.S. Nuclear Regulatory Commission (NRC)Bulletin 2012-01, Design Vulnerability In Electric Power System (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12074A115) was issued in response to this event and contains additional details. The event demonstrated that electrical power systems of nuclear power plants have and may be adversely impacted from such an OPC design vulnerability.

As a result of this event, industry committed, through a Voluntary Industry Initiative (VII), to address OPCs. This initiative was communicated to the NRC by Nuclear Energy Institute (NEI) in a letter dated October 9, 2013 (ADAMS Accession No. ML13333A147) and acknowledged in the NRC letter dated December 19, 2013 (ADAMS Accession No. ML13340329). This NEI letter further indicated that this approved initiative commits each licensee to develop a proactive plan and schedule for addressing the potential design vulnerabilities associated with OPCs. In response to the VII, industry had developed a plan for implementing a system which would automatically actuate and protect against OPC called the Open Phase Isolation System (OPIS).

During the monitoring period established for the use of this system, the industry observed several alarms that would have resulted in spurious automatic actuations of OPIS if the systems had been enabled for automatic actuation at the time of the events. Review of the data resulted in some uncertainty that all existing and potentially new plant/ grid configurations can be reliably Enclosure

handled by the various OPIS designs without inducing spurious actuations. In September 2018, NEI issued Revision 2 to the VII to provide for an extended monitoring period to allow for the collection and application, including completion of any design adjustments, of station-specific Operating Experience such that industry-wide Operating Experience can be evaluated and applied. During a public meeting held on February 20, 2019, NEI indicated that, due to the OE indicating that the OPIS circuitry may be sensitive to electric plant transients resulting from circuit breaker switching, there was a potential for spurious actuation that could lead to an inadvertent loss of offsite power. Therefore, NEI decided to develop Revision 3 to the VII and create a guidance document (NEI 19-02) that enables licensees to use a risk-informed approach to implement the OPIS to provide alarm and indication to the control room operator and rely on operator action to diagnose and respond to the presence of an OPC as opposed to an automatic actuation mode. Revision 3 to the VII was communicated to NRC by NEI in a letter dated June 6, 2019 and NEI 19-02 was provided to the NRC on June 20, 2019.

NEI indicated to the NRC on June 28, 2019 of certain stations that are planning to implement the risk-informed approach discussed above. As a result, the NRC is conducting this audit to verify that Ginna has appropriately implemented the guidance in NEI 19-02 and to verify that implementation of NEI 19-02 is an appropriate alternate approach consistent with the revised VII.

The objectives of this regulatory audit are to:

  • Identify how the methodology described in NEI 19-02 was implemented;
  • The team will review the application (or temporary changes) of the plant specific PRA model of record within the context of applying the 19-02 methodology; and
  • Identify the training conducted and procedures required to address OPC to help verify the Human Reliability Analysis (HRA) and plant configuration described in the licensees assessment and PRA model.

2.0 REGULATORY AUDIT BASIS The Commission directed the staff in SRM-SECY-16-0068 to verify that licensees have appropriately implemented the voluntary industry initiative. The industry has since revised the VII and created the guidance document NEI 19-02 to enable licensees to use a risk-informed approach to implement the OPIS to provide alarm and indication to the control room operator and rely on operator action to diagnose and respond to the presence of an OPC as opposed to automatic actuation mode. The basis for this audit is to verify that the selected plants have appropriately implemented the guidance in NEI 19-02 and the revised VII, per the Commissions direction.

3.0 REGULATORY AUDIT SCOPE OR METHOD The team will review the resulting documentation from implementing NEI 19-02 (i.e., the filled in template specified in Appendix A (Analysis File Template) of NEI 19-02). The team will also review the application (or temporary changes) of the plant specific PRA model of record within the context of applying the 19-02 methodology. In addition, the audit team will review the training conducted and procedures required to address OPC, to help verify the HRA and plant configuration described in the licensees assessment and PRA model.

4.0 INFORMATION AND OTHER MATERIAL NECESSARY FOR THE AUDIT The NRC audit team will require access to personnel knowledgeable regarding the implementation of NEI 19-02, application (or temporary changes) of the plant specific PRA model of record within the context of applying the 19-02 methodology, and the training and procedure changes made regarding OPC. The NRC audit team will need access to hardcopies and/or electronic copies of the following documentation:

  • The resulting documentation from implementing NEI 19-02 (i.e., the filled in template specified in Appendix A of NEI 19-02);
  • Documentation for the application (or temporary changes) of the plant specific PRA model of record within the context of applying the 19-02 methodology;
  • Any procedures related to the operator actions required to address an OPC; and
  • Any documentation of the training conducted to address an OPC.

5.0 TEAM ASSIGNMENTS The audit will be conducted by NRC staff from the Office of Nuclear Reactor Regulation (NRR)

Division of Risk Assessment. NRC staff from other organizations may be assigned to the team as appropriate and others may participate as observers.

The NRC Audit Team Leader will be Alexander Schwab. The audit team leader will conduct daily briefings on the status of the review and coordinate audit activities while on site. The tables below show (1) audit milestones and schedule, and (2) planned audit team composition and their assigned areas for review during the audit.

Audit Milestones and Schedule Activity Time Frame Comments Audit Teleconference to provide clarification of audit Scheduling/Clarification 10/03/209 questions.

Call NRC will present a brief team introduction and Onsite Audit Kick-Off discuss the scope of the audit. The licensee 10/15/2019 Meeting representatives should introduce team members and give logistics for the week.

End of Day Summary Meet with licensee representatives to provide a 10/17/2019 Briefing summary of any significant audit results 10/16- Facilitate discussion between licensee Provide Break-out Areas 1017/2019 representatives and NRC staff.

Onsite Audit Exit NRC staff will hold a brief exit meeting, with 10/18/2019 Meeting licensee staff to conclude audit activities.

90 days after To document the audit.

Audit Summary exit

Assigned Area Lead Review licensee documentation resulting from A. Schwab, F.

1 implementing NEI 19-02 Arner Review changes to the licensees PRA model A. Schwab, F.

2 made as a result of the implementation of NEI Arner 19-02 3 Review procedures related to the actions A. Schwab, F.

required to address an OPC Arner Review documentation of the training A. Schwab, F.

4 conducted to address an OPC Arner 6.0 LOGISTICS This regulatory audit is planned for the week of October 14th, and will last approximately 4 days.

A conference call will be scheduled one to two weeks prior to the audit to discuss the details of the audit plan. The dates in the milestone chart are subject to change based on agreement between the licensee and the NRC. An entrance meeting for this audit will be held the first day at 3:00 PM and an exit meeting will be held the final audit day at 12:00 noon, or based on a mutually agreed upon time after receipt of this audit plan. The NRC audit team leader will provide daily progress to licensee personnel on the second day of the audit.

The audit will take place at a location agreed upon by the licensee and NRC audit leader where (1) the necessary reference material and (2) appropriate analysts will be available to support the review. Unescorted access will be requested for the entire audit team. We recommend that security paperwork and processing be handled upon arrival on the first day of the audit week.

7.0 SPECIAL REQUESTS The regulatory audit team will require the following to support the regulatory audit:

  • Unescorted access will be needed for all team members participating in the audit.
  • Phone line with teleconference capabilities
  • Two computers with internet access and printing capability in the NRC room and wired or wireless internet access.
  • A private conference room should be made available.

8.0 DELIVERABLES A regulatory audit summary will be issued within approximately 90 days after the completion of the audit. The summary will use the guidance of NRR Office Instruction LIC-111 for content.

The audit summary will be placed ADAMS.

It is understood that the results of the audit will be of interest to the industry including other stations considering implementation of NEI 19-02. The staff should consider alternate methods for communicating the audit results in advance of the issuance of the summary.