September 3, 2004 MEMORANDUM TO: Richard J. Laufer, Chief, Section 1 Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Robert Clark, Project Manager, Section 1 /RA/

Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF MEETING HELD ON AUGUST 18, 2004, WITH CONSTELLATION ENERGY GROUP REGARDING PROPOSED EXTENDED POWER UPRATE (TAC NO. MC4033)

On August 18, 2004, the licensee for the R.E. Ginna Nuclear Power Plant (Ginna) met with the members of the Nuclear Regulatory Commission (NRC) staff in Rockville, Maryland. The purpose of the meeting was to exchange information with the NRC regarding their proposed extended power uprate for Ginna. A formal license amendment request is scheduled to be submitted to the NRC for approval in May of 2005.

The presentation given by the licensee covered: plant modifications, analytical methods, license amendments, conformance with RS-100, probability risk analysis and startup test and vibration monitoring requirements. Meeting slides were used to provide an overview of the proposed power uprate program. The licensee believed that they are in a unique position to safely accomplish an extended power uprate of 17% thermal power for the following reasons:

Ginna replaced the steam generators in 1996 with an oversized design that is fully capable of transferring the required heat load, they replaced the reactor vessel head in 2003 to resolve the Alloy 600 pressurized water stress corrosion cracking issue, and they plan to use the same fuel assemblies at Kewaunee Nuclear Power Plant to produce an equivalent thermal power. is a list of attendees and a copy of the handout provided by Ginna is given in .

Robert Clark, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosures:

As stated cc w/encls: See next page

September 3, 2004 MEMORANDUM TO: Richard J. Laufer, Chief, Section 1 Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Robert Clark, Project Manager, Section 1 /RA/

Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF MEETING HELD ON AUGUST 18, 2004, WITH CONSTELLATION ENERGY GROUP REGARDING PROPOSED EXTENDED POWER UPRATE (TAC NO. MC4033)

On August 18, 2004, the licensee for the R.E. Ginna Nuclear Power Plant (Ginna) met with the members of the Nuclear Regulatory Commission (NRC) staff in Rockville, Maryland. The purpose of the meeting was to exchange information with the NRC regarding their proposed extended power uprate for Ginna. A formal license amendment request is scheduled to be submitted to the NRC for approval in May of 2005.

The presentation given by the licensee covered: plant modifications, analytical methods, license amendments, conformance with RS-100, probability risk analysis and startup test and vibration monitoring requirements. Meeting slides were used to provide an overview of the proposed power uprate program. The licensee believed that they are in a unique position to safely accomplish an extended power uprate of 17% thermal power for the following reasons:

Ginna replaced the steam generators in 1996 with an oversized design that is fully capable of transferring the required heat load, they replaced the reactor vessel head in 2003 to resolve the Alloy 600 pressurized water stress corrosion cracking issue, and they plan to use the same fuel assemblies at Kewaunee Nuclear Power Plant to produce an equivalent thermal power. is a list of attendees and a copy of the handout provided by Ginna is given in .

Robert Clark, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosures:

As stated cc w/encls: See next page DISTRIBUTION PUBLIC PDI-1 R/F WLyon ACRS/ACNW JUhle WBateman SLittle RClark RLaufer JStang JHardy PPrescott BElliot RLobel RPettis PClifford NIqbal EImbro TBergman CHolden TMarsh/JLyons GMatakas, RI LRaghavan OGC JLamb SShang CLiang FOrr SMiranda RDennig TMensah CMiller Accession No.: ML042450626 OFFICE PDI-1/PM PDI-1/LA PDI-1/SC NAME RClark SLittle RLaufer DATE 9/1/04 9/1/04 9/2/04 OFFICIAL RECORD COPY

R.E. Ginna Nuclear Power Plant cc:

Mr. Michael J. Wallace Daniel F. Stenger President Ballard Spahr Andrews & Ingersoll, LLP R.E. Ginna Nuclear Power Plant, LLC 601 13th Street, N.W., Suite 1000 South c/o Constellation Energy Washington, DC 20005 750 East Pratt Street Baltimore, MD 21202 Ms. Thelma Wideman, Director Wayne County Emergency Management Mr. John M. Heffley Office Senior Vice President and Wayne County Emergency Operations Chief Nuclear Officer Center Constellation Generation Group 7336 Route 31 1997 Annapolis Exchange Parkway Lyons, NY 14489 Suite 500 Annapolis, MD 21401 Ms. Mary Louise Meisenzahl Administrator, Monroe County Kenneth Kolaczyk, Sr. Resident Inspector Office of Emergency Preparedness R.E. Ginna Nuclear Power Plant 1190 Scottsville Road, Suite 200 U.S. Nuclear Regulatory Commission Rochester, NY 14624 1503 Lake Road Ontario, NY 14519 Mr. Paul Eddy New York State Department of Regional Administrator, Region I Public Service U.S. Nuclear Regulatory Commission 3 Empire State Plaza, 10th Floor 475 Allendale Road Albany, NY 12223 King of Prussia, PA 19406 Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 James M. Petro, r., Esquire Counsel Constellation Energy 750 East Pratt Street, 5th Floor Baltimore, MD 21202 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271

MEETING BETWEEN NRC AND CONSTELLATION ENERGY GROUP (CEG)

ATTENDANCE LIST AUGUST 18, 2004 NRC INDUSTRY R. Clark, NRR M. Finley, CEG J. Stang, NRR J. Nicholson, Stone & Webster B. Elliot, NRR D. Dominicis, Westinghouse R. Lobel, NRR D. Sklarsky, Westinghouse R. Pettis, NRR R. Cavedo, CEG P. Clifford, NRR G. Wrobel, CEG N. Iqbal, NRR J. Dunne, CEG C. Holden, NRR G. Verdin, CEG L. Raghavan, NRR J. Lamb, NRR S. Shang, NRR C. Liang, NRR F. Orr, NRR S. Miranda, NRR C. Liang, NRR J. Hardy, NRR P. Prescott, NRR Enclosure 1