MONTHYEARML0208701212002-03-29029 March 2002 Conference Call (Meeting) with Rg&E Rg&E Response to NRC Bulletin 2002-01 Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity Project stage: Meeting ML0209405052002-04-0303 April 2002 Conference Call Regarding Rg&E Post-Inspection Results of the Reactor Pressure Vessel Head Project stage: Other ML0209500102002-04-0505 April 2002 R. E. Ginna Nuclear Power Plant - Summary of 03/29/2002 Conference Call Rg&E Post-Inspection Results of the Reactor Pressure Vessel Head Project stage: Other ML0214303112002-05-24024 May 2002 Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, 15-Day Response (Tac No. MB4548) Project stage: Other ML0217006932002-06-12012 June 2002 R. E. Ginna Withdrawal of Request for Application for Amendment to Facility Operating License Regarding Proposed Change to Plant Staff Qualification Project stage: Withdrawal ML0232600672002-11-22022 November 2002 RAI, Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity. Project stage: RAI 2002-04-03
[Table View] |
Similar Documents at Ginna |
---|
Category:Memoranda
MONTHYEARML21277A2472021-11-0505 November 2021 Notification of Significant Licensing Action - Proposed Issuance of Order Approving the Transfer of Licenses for Which a Hearing Has Been Requested - Exelon Generation Company, LLC; Et. Al ML20213C5322020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Constellation Energy Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for R.E. Ginna ML19281C9412019-10-10010 October 2019 Regulatory Audit in Support of Confirmation of a Plants' Implementation of Nuclear Energy Institute 19-02, Guidance for Assessing Open Phase Condition Implementation Using Risk Insights ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations ML13122A0082013-05-22022 May 2013 Notice of Impending Public Release of Technical Letter Report (Tlr) on Summary of Aging Management Program Effectiveness Audits to Inform Subsequent License Renewal: R.E. Ginna Nuclear Power Plant and Nine Mile Point Nuclear Station, Unit 1 ML12136A5672012-05-17017 May 2012 Summary of Meeting with Constellation Energy to Discuss the Constellation Apparent Violation of NRC Regulations at Title 10 of the Code of Federal Regulations Part 50.9 ML12107A5052012-04-16016 April 2012 Forthcoming Category 1 Public Meeting with Constellation Energy Nuclear Group, LLC to Discuss Preliminary Enforcement ML11354A1182011-12-22022 December 2011 12/8/2011 Summary of Meeting Between NRC Staff and the Nuclear Energy Institute to Discuss Current License Renewal Topics ML1110104272010-12-0606 December 2010 Written Retake - Draft - Outlines (Facility Letter Dated 12/6/10) (Folder 2) ML1028503942010-10-0707 October 2010 S. Wastler Memo Technical Assistance Request - Review of Proposed Amendment to the R. E. Ginna Nuclear Power Plant Physical Security Plan (TAC L24479) ML1001101702010-01-13013 January 2010 Notice of Forthcoming Conference Call with R. E. Ginna Nuclear Power Plant, LLC to Discuss R. E. Ginna Nuclear Power Plant Generic Letter 2004-02 Supplemental Responses ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0613601522006-05-12012 May 2006 Summary of May 9, 2006, Annual Assessment Meeting with Constellation Energy, R. E. Ginna Nuclear Power Plant, LLC ML0609503542006-04-0404 April 2006 FRN - Power Uprates, April 27, 2006 ML0607901132006-03-20020 March 2006 Cancellation - Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC Regarding Extended Power Uprate Amendment Application ML0605500922006-02-24024 February 2006 FRN - Power Uprates, March 15-16, 2006 ML0600300802006-02-17017 February 2006 Transmittal of Final ASP Analyses (August 14, 2003 Grid Disturbance Events) ML0602403072006-01-20020 January 2006 Inspection-Related Information Provided to Licensee ML0524500902005-09-0202 September 2005 Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC (Ginna, Llc), Regarding Extended Power Uprate Amendment Application ML0524102782005-08-24024 August 2005 R. E. Ginna Partial Site Release Application - Request for Additional Information ML0516602662005-08-0303 August 2005 Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0504901422005-02-17017 February 2005 Summary of January 13, 2005, Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Nuclear Energy Institute (NEI) on Updating the License Renewal Guidance Documents ML0500602092004-11-17017 November 2004 Canceled - 11/30/2004 Meeting with R. E. Ginna Nuclear Power Plant, LLC Regarding Proposed Extended Power Uprate ML0432203022004-11-17017 November 2004 Notice of Meeting with R. E. Ginna Nuclear Power Plant, LLC Regarding Proposed Extended Power Uprate ML0424506262004-09-0303 September 2004 Summary of Meeting with Constellation Energy Group Regarding Proposed Extended Power Uprate ML0417002292004-06-30030 June 2004 May Monthly Report on the Status of Open TIAs Assigned to NRR ML0413402552004-05-21021 May 2004 Renewal of Full-Power Operating License for the R. E. Ginna Nuclear Power Plant - Memo to the Commission from Travers ML0405806902004-02-27027 February 2004 Transmittal of Preliminary ASP Analyses for Peer Review (August 14, 2003 Grid Event) ML0401405602004-01-22022 January 2004 Correction of License Authority Files ML0326811302003-09-25025 September 2003 Summary of the U.S. Nuclear Regulatory Commission (NRC) Staff'S Review of the R.R. Ginna Nuclear Power Plant (Ginna) Steam Generator Tube Inspection Report Dated July 2002 ML0235703982002-12-31031 December 2002 TIA, Response to the Task Interface Agreement Regarding the Minimum on-shift and Augmentation Staffing for Radiological Emergencies at R.E. Ginna Nuclear Power Plant ML0231700712002-11-13013 November 2002 Report on the Status of Open TIAs Assigned to NRR ML0229703632002-10-23023 October 2002 Meeting with NEI, Surry & North Anna Units 1 & 2, McGuire & Catawba Units 1 & 2, Peach Bottom Units 2 & 3, St. Lucie Units 1 & 2, Fort Calhoun, H. B. Robinson Unit 2, R.E. Ginna, and Virgil C. Summer. the Proposed Agenda Is Attached ML0226002922002-09-17017 September 2002 Memorandum Regarding Report on the Status of Open TIAs Assigned to NRR ML0214103572002-05-22022 May 2002 Rochester Gas & Electric License Amendment Pre-Application Meeting Future Modifications to the Control Room Ventilation System ML0209500102002-04-0505 April 2002 R. E. Ginna Nuclear Power Plant - Summary of 03/29/2002 Conference Call Rg&E Post-Inspection Results of the Reactor Pressure Vessel Head ML0120002552001-07-18018 July 2001 E-mail Correspondence Between NRC and Rge from June 12 to June 29, 2001 NRC Generic Letter 1989-111989-06-30030 June 1989 NRC Generic Letter 1989-011: Resolution of Generic Issue 101 Boiling Water Reactor Water Level Redundancy ML18143A2041980-05-0606 May 1980 R. E. Ginna - Administrative Measures Taken to Detect End of Life in Ginna Station Electrical Components ML18143A6171976-03-23023 March 1976 Technical Assistance Request No. ORB-1-230, Request Review of 2/27/1976 Submittal to Determine That It Meets Listed Requirements IR 05000244/19750011975-03-28028 March 1975 Letter Regarding Inspection Report No. 05000244/75-01 ML18143A6421975-03-19019 March 1975 Technical Assistance Request No. ORB-1-135, Informing That Licensee'S Submittal Was Delivered to Mr. Hazelton on March 17, 1975 ML18143A2621971-08-12012 August 1971 R. E. Ginna - Questions Relating to Instrumentation and Emergency Power. Requests Additional Information in Area of Testing ML18142B6661969-07-0808 July 1969 R. E. Ginna, Unit 1 - 07/08/1969 Memo Inspection Report 05000244/1969009 ML18143A0651969-04-21021 April 1969 R. E. Ginna - Special Quality Control Inspection Report 244/69-1, on 04/21/1969, Inspections of Four Safety-Oriented Reactor Systems, Three Mechanical and One Electrical 2021-11-05
[Table view] |
Text
April 5, 2002 MEMORANDUM TO: Joel T. Munday, Acting Chief, Section 1 /RA by PTam for JMunday/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Robert Clark, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF MARCH 29, 2002, CONFERENCE CALL REGARDING RG&E POST-INSPECTION RESULTS OF THE REACTOR PRESSURE VESSEL HEAD (TAC NO. MB4548)
On March 29, 2002, a conference call was held with members of the U.S. Nuclear Regulatory Commission (NRC) staff and representatives from Rochester Gas and Electric Corporation, the licensee for Ginna Nuclear Power Plant. The purpose of this call was to discuss the licensees preliminary results of their inspection of the reactor pressure vessel head. This conference call summary supersedes the summary issued on April 3, 2002. A correction was made to the information in the last paragraph. Thus, the April 3 summary should be discarded.
The reactor pressure vessel head inspection consisted of: 1) a 100% visual inspection of the block insulation located on top of the reactor pressure vessel head inside the shroud support ring; 2) ultrasonic testing to verify the thickness of the head around the center control rod drive mechanism (CRDM) penetration nozzle; and 3) ultrasonic testing of that portion of the head located outside the shroud support ring where four nearby instrument ports had previously experienced boric acid leakage. The licensee asserted that a potential through-wall crack in a penetration nozzle, J-groove weld or leakage from above the reactor pressure vessel head would lead to accumulation of boric acid and corrosion products at the head/insulation interface, in the annulus between insulation and nozzle, and above the insulation. The licensee also postulated that if the boric acid deposits and corrosion products were to accumulate at the head/insulation interface, the accumulation would eventually exert sufficient force on the insulation to cause displacement or cracking.
Based on the results of the visual inspection, the licensee stated that the block insulation within the shroud support ring was in very good condition with only minor cracks or gaps in the insulation. The licensee also stated that some minor staining (brown spots) was present on top of the insulation and that white shading was also observed on certain CRDM nozzles.
However, there was no evidence of boric acid deposits or corrosion products on the outside surface of the insulation and no visible indication of distortion (displacement or cracking) of the block insulation due to boric acid/corrosion product uplifting.
CONTACT: P. Tam, NRR/DLPM 415-1451
J. Munday In areas where the insulation was damaged (stained, missing or cracked), the licensee removed small pieces of the insulation to expose the bare metal of the head. These areas showed no evidence of boric acid deposits nor any evidence of degradation. Upon careful examination of the discolored areas, the licensee determined that the brown coloring on top of the block insulation was due to previous conoseal leaks from instrument ports and was not the result of corrosion products. The white coloring observed on some of the nozzles (near the canopy seal weld) was due to white developer overspread while performing Section XI weld inspections and was not boric acid deposits. The licensee also analyzed block insulation samples (i.e., the ones removed to expose the bare metal of the head) and determined that no significant radioactivity was present (providing some assurance that no significant leakage had occurred).
In addition to the above, bare metal inspections of several penetration nozzles were performed using a video camera to look into the annulus between the block insulation and nozzle. The licensee stated that the video inspection did not reveal any crystalline deposits around the penetration nozzles. The licensee also removed the block insulation from the head outside the shroud support ring to perform bare metal inspection of the head in this region. No boric acid deposits or corrosion products were observed coming out of the shroud support ring from under the insulation.
The ultrasonic testing (UT) examination on the center CRDM penetration nozzle from beneath the head indicated that head thickness was well within design limits and that there was no physical evidence of reactor vessel head corrosion (i.e., no material loss). The licensee also performed UT examination for wall thickness of the reactor pressure vessel head outside the shroud support ring on the downhill side of four instrument ports. The results indicated that the head thickness was well within design limits.
Based on the preliminary findings from Davis-Besse, the inspections performed by the licensee, and the licensees susceptibility to nozzle cracking, the NRC staff did not identify any issues that needed additional follow-up prior to plant restart. The staff will document its formal review after receiving the licenseesBulletin 2002-01 response.
Docket No. 50-244
J. Munday In areas where the insulation was damaged (stained, missing or cracked), the licensee removed small pieces of the insulation to expose the bare metal of the head. These areas showed no evidence of boric acid deposits nor any evidence of degradation. Upon careful examination of the discolored areas, the licensee determined that the brown coloring on top of the block insulation was due to previous conoseal leaks from instrument ports and was not the result of corrosion products. The white coloring observed on some of the nozzles (near the canopy seal weld) was due to white developer overspread while performing Section XI weld inspections and was not boric acid deposits. The licensee also analyzed block insulation samples (i.e., the ones removed to expose the bare metal of the head) and determined that no significant radioactivity was present (providing some assurance that no significant leakage had occurred).
In addition to the above, bare metal inspections of several penetration nozzles were performed using a video camera to look into the annulus between the block insulation and nozzle. The licensee stated that the video inspection did not reveal any crystalline deposits around the penetration nozzles. The licensee also removed the block insulation from the head outside the shroud support ring to perform bare metal inspection of the head in this region. No boric acid deposits or corrosion products were observed coming out of the shroud support ring from under the insulation.
The ultrasonic testing (UT) examination on the center CRDM penetration nozzle from beneath the head indicated that head thickness was well within design limits and that there was no physical evidence of reactor vessel head corrosion (i.e., no material loss). The licensee also performed UT examination for wall thickness of the reactor pressure vessel head outside the shroud support ring on the downhill side of four instrument ports. The results indicated that the head thickness was well within design limits.
Based on the preliminary findings from Davis-Besse, the inspections performed by the licensee, and the licensees susceptibility to nozzle cracking, the NRC staff did not identify any issues that needed additional follow-up prior to plant restart. The staff will document its formal review after receiving the licenseesBulletin 2002-01 response.
Docket No. 50-244 DISTRIBUTION PUBLIC PD1-1 Rdg File J. Zwolinski/T. Marsh W. Bateman R. Clark A. Hiser K. Karwoski J. Munday S. Little S. Bloom D. McCain I. Jung D. Lew, RGI M. Evans, RGI B. Platchek, RGI T. Bergman, RGI W. Lanning, RG1 C. Welch, RGI ACRS OGC J. Collins S. Collins L. Doerflein, RGI B. Borchardt J. Johnson A. Mendiola M. Case B. Kane B. Sheron E. Gray, RGI S. Coffin B. Wetzel Accession No.: ML020950010 *See previous concurrence OFFICE PDI-1/PM PDI-1/LA EMCB/PM PD1-1/(A)SC NAME PTam for RClark SLittle SBloom* PTam for JMunday DATE 4/5/02 4/5/02 4/4/02 4/5/02 OFFICIAL RECORD COPY